IS THE DUTCH ROUNDABOUT READY?NO NEW WORK, ALL PROJECTS FINISHED?

Enno FreeseDirector Projects

IPLOCA's Regional Meeting for Europe North-West

15 March 2012

Gasunie: gas infrastructure & gas transport

Gas roundabout is a success

Gas roundabout strategy of Dutch authorities is a success Important contribution to the economy Positive effect on competition and security of supply Gasunie contribution by means of gas infrastructure projects

Make sure that the gas roundabout continues to be a success!

First LNG tanker to dock in Rotterdam

Activities 2012

Pipeline Odiliapeel-Melick (65 km 48"), OS 2012

Connection Hommelhof-Schinnen, at Hommelhof and CS Schinnen, OS 2012

Relocation M&R Wijngaarden, OS 2005

IOS Netherlands

IOS Germany

Maintenance projects Operations (Opex/Capex)

New connections / new clients

Pigging

Stuart and Lloyds replacement project

Zuidwending

Heiligerlee

Gasunie Engineering

Masterplan Renovation

- Pressure regulating stations

- Gas receiving stations

- Valve locations regional pipelines

Scope and budget IOS Netherlands

Pipelines:– Pipeline Beverwijk – Wijngaarden– Pipeline Westerschelde West – Cambron

Facilities:– Connection of Jemgum cavernes at Oude Statenzijl– a.o. Beverwijk, Schinnen and Anna Paulowna

Netnorm increase:– N2 injection and MS OLT– Modification gas appliances at large large consumers

Total budget P-90: € 495 mln.

Pipeline Beverwijk - Wijngaarden

• 8 motorways• 7 railway lines• 3 rivers• 2 canals• Schiphol landing strip • Difficult terrain (peat bog)• HDD in total 15 km

Activities 2012 Germany

CS Achim

CS Folmhusen

M&R Heidenau

Engineering and Feasibility Studies

(Fockbek-Ellund, Quarnstedt)

Total budget P-90: € 235 mln.

IOS Investments in Germany

Overview Project Portfolio (work to be executed)

Answers / Conclusions

1. Question: Is the Dutch roundabout ready?

Answer: No, the grid is still expanding, there is market demand for transport capacity, storage and flexibility.

2. Question: No new work, all projects finished?

Answer: See answer 1, NO.We see change from large diameter pipelinesand compressor stations to more maintenanceprojects because of ageing of the system andenvironmental legislation.