introduction to leed building commissioning

Post on 31-Jan-2016

83 Views

Category:

Documents

2 Downloads

Preview:

Click to see full reader

DESCRIPTION

Introduction to LEED Building Commissioning. Presented by Bob Alpers, PE TESTMARCx Commissioning Solutions. Agenda. Benefits Introduction to LEED Commissioning Requirements and Deliverables Process Questions. Commissioning Purpose. - PowerPoint PPT Presentation

TRANSCRIPT

Introduction toLEED

Building Commissioning Presented by Bob Alpers, PE

TESTMARCx Commissioning Solutions

Agenda

Benefits Introduction to LEED Commissioning Requirements and Deliverables Process Questions

How does the building function relative to the Owners Project Requirements?

Commissioning Purpose

Benefits & Cost Savings Cost to Change

Concept Design Construction Acceptance Occupancy

$

Time

When should we start Commissioning?

What is systems are impacted most?

Control System Problems Comfort Problems Air Quality Problems Building Maintenance Costs Operations Staff

understanding

LEED Objective – Get Certified

LEED Rating Points Required

Certified 26-32 points

Silver 33-38 points

Gold 39-51 points

Platinum 52-69 points

Buildings Certified Under USGBC Guidelines

LEED- EA Prerequisite 1

Water

Efficiency

8%Energy &

Atmosphere

27%

Materials &

Resources

20%

Sustainable

Sites

22%

Indoor

Environmental

Quality

23%

Commissioning underEnergy and Atmosphere

WHAT ARE THE LEED Commissioning ACTIVITIES?

Energy and Atmosphere Credit Category

EA Prerequisite 1 ( required, must be completed) Fundamental Commissioning

EA Credit 3 ( additional available point) Enhanced Commissioning

Fundamental Commissioning

Pre-Requisite 1 Overview:

1. Designate a third party Cx

2. Review OPR and BOD Document

3. Specify Commissioning in CD

Fundamental Commissioning

Prerequisite Overview (Cont’d)

4. Develop a Cx Plan.

5. Verify installation meets BOD

6. Verify performance of systems

7. Summary report

8. Certify Commissioned

Fundamental CommissioningEA Prereq. 1

The Process Under LEED

Project Milestones in Construction Schedule

Project Timeline

PLAN DESIGN CONSTRUCT ACCEPT OCCUPANCY

Review Owners Functional

Requirements

& Basis of Design

Functional Testing

Final CxReport

Commissioning Plan

ScopingMeetings

Verify InstallationPre-Functional

Checklist

Collect Start-upCheck sheets

Incorporate

Commissioning

Specification

Owners Project Requirements Workshops

Small groups to work out concepts

Commissioning Plan

The commissioning plan must contain: Overview & goals Project information Systems to be commissioned Team’s roles & protocol Describe Deliverables List Key Milestones and schedule.

What Systems does LEED require Commission? Systems and Assemblies having to do with

operational efficiencies: HVAC Systems Building Automation Lighting Controls Domestic Heating Renewable Energy

Contract Divisions 1, 15 and 16

Commissioning Specifications

Installation Verification

Focus is O&M

Master Deficiency List

Date

Item

#

EQUIP #

/Spec

Section

DATE

REVIEWEDFIV/ FPT/O&M DEFICIENCY RESP. ACTION TAKEN

DATE Cx

VERIFIED

1 Panel HCR2 8/9/2004 FIVThe electrical working clearance for Panel HCR2 is not per NEC 110. Panel LCR2 blocks the right portion of the panel width within the 42" reqmt.

CEC

2 Panel LCR2 8/9/2004 FIV

The electrical working clearance for Panel LCR2 is not per NEC 110. The conduits at the floor in front of the panel, penetrate the floor in front of the plane of the panel can.

CEC

3 Panel HN3 8/9/2004 FIV

The electrical working clearance for Panel HN3 may not be per NEC 110. The transformer and flexible conduits @ the floor must be 42" from the panel (exposed live parts).

CEC

4 Panel LCR5 8/9/2004 FIVThe electrical working clearance for Panel LCR5 is not per NEC 110. The adjacent panel can blocks the right portion of the panel width within the 36" reqmt.

CEC

5 AHU 1 8/9/2004 FIVThe chilled water coil pull is blocked by the header at the coil.

B&KFlanged connections have been provided in the piping above the coil for piping removal for coil pull.

JAH9/20/04

6 RF 5A 8/9/2004 FIVThe relief duct is tapped into the back of the 90 degree silencer.

B&KPCA

Relief duct tap into 90o silencer approved and designed by M&I Systems.

JAH9/20/04

7 RF 5A and B 8/9/2004 FIV

The FSDs at the floor entering the return (see sheet M406) are not accessible without dismantling a section of the fabricated return plenum. An access door is not shown to be installed.

B&KPCA

Removable access panels have been provided in the return plenum for access to FSDs.

JAH9/20/04

Master Deficiency List

February 3, 2005(latest deficiencies in bold text)

Verify System Performance

Functional Testing of Systems: Observe Startup Activities Functionally Test Equipment and Systems

Final Commissioning Report

Must be presented to the owner within reasonable time and must include: Executive summary Testing results Deficiency List and History Outstanding Issues BOD review.

Enhanced CommissioningEA Credit 3

The Process Under LEED

Enhanced Cx

EA Credit 3 ( additional credit 1 point) Design Review Contractor Submittals Review Verify Training 10th Month Warranty & Operations Review Systems manual

Fundamental & Enhanced

Project Timeline

PLAN DESIGN CONSTRUCT ACCEPT OCCUPANCY

Owners Functional

Requirements

& Basis of Design

Functional Performance

Testing

CxReport and

Systems ManualSubmittal & O&M

Review

Commissioning Plan

ScopingMeetings

Design DocumentReviews &

Commissioning In Specification Verify

Training

Warranty Review

10th month

Operation

Verify Installation & Checklist

Start-up

Revised Plan

Review Mechanical Systems Sequence of

Control for Clarity

Enhanced – The Design Review

Review Mechanical Equipment Submittal

Documents for Completeness

Enhanced -Submittal Review

Enhanced – Verify Training

Organizes the O&M Manual by

Commissioned System

Enhanced –Systems Manual

All of Chilled Water Storage in one Section of Manual

Enhanced -Verify Training

Training meets requirements: Review Spec & Verify meet Spec. Include General

Purpose of systems Must include use of O&M

Manuals Must include operation

all modes Must be Qualified

Trainers

Enhanced-Warranty ReviewSeasonal Testing

Functional Tests for Summer vs. WinterCheck Warranty Status and advise

Issues & Lessons Learned

General Commissioning is Part of the Design Team Contractors understand the commissioning TEAM’s

Role Energy Efficient Systems

Controls Become Complex and increase Risks Technology is beyond Contractor Experience Coordination of interposing systems is critical

Control Systems Integration is coordinated Schematic diagrams, Sequence of control and point

lists are necessary Details of BMS get input from owner

Owner Training Video tape or not? Meeting with Staff to discuss needs Detailed Description in Spec of O&M needs. Systems Manual training

Case Study

Community College Bldg. Classroom Laboratories

MEP Commissioning Started Late in Construction

Phase Issues

Integrate Phoenix Fume with ALC controls

System Balance Unoccupied Mode

Operation Success

teamwork

LEED Commissioning

Questions?

top related