Highway Construction Program Monthly Delivery Progress Report Watch List
US 2/Corridor Improvements Project Information Project Milestones
PIN: 100210K As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: US 2 Current Status: Construction Legislative Districts: 39, 44
Project Description The legislature provided an additional $2M for corridor improvements on US 2 in 17-19 in BIN N00200R. This PIN will replace $2M of funding for the scope of work under 100210J.
Contractor: 009363 - GRANITE CONSTRUCTION COMPANY - $1,124,536.54 - 02/01/2019
As of November 2019: The construction duration has lengthened to align with the number of working days established within the contract. This has delayed the project completion date.
Milestone Original Date Current Date Status
Project Definition Complete Q2 2017 Q2 2017 On Schedule
Preliminary Engineering Start Q3 2017 Q3 2017 On Schedule
Environmental Complete Q3 2018 Q3 2018 On Schedule
Right of Way Complete
Contract Advertisement Q4 2018 Q4 2018 On Schedule
Operationally Complete Q4 2019 Q3 2020 Late
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$595$595
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $2,000 $2,000
$0 $1,405 $1,405
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$595
Pre-Existing
Funds
$2,000
$1,405
$0
CWA
$0
$0
$0
$0 $2,000
$1,405
$0
$595
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us2/bickford-sofie/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 1
https://www.wsdot.wa.gov/projects/us2/bickford-sofie/homehttp:1,124,536.54
-
US 2/Pilchuck River Bridge - Expansion Joint Rehabilitation Project Information Project Milestones
PIN: 100212B As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: US 2 Current Status: Completed Legislative Districts: 44
Project Description The project will rehabilitate the two bolt down panel expansion joints on bridge 2/10 at spans 2 and 6, based on recommendations from Bridge Office
Contractor: 009363 - GRANITE CONSTRUCTION COMPANY - $129,967.06 - 02/01/2019
Milestone Original Date Current Date Status
Project Definition Complete
Preliminary Engineering Start
Environmental Complete
Right of Way Complete
Contract Advertisement Q4 2018 Q4 2018 On Schedule
Operationally Complete Q4 2019 Q4 2019 On Schedule
As of November 2019: During construction, a differing site condition was identified, which required some redesign work that delayed the completion of the paving on US 2 and extended the construction into a second construction season.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$82$44
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $206 $244
$0 $162 $162
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$82
Pre-Existing
Funds
$244
$162
$0
CWA
$0
$0
$0
$0 $244
$162
$0
$82
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us2/bickford-sofie/home
US 2/Roosevelt Rd Vic to Cascade View Dr Vic - Paving Project Information Project Milestones
PIN: 100214B As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: US 2 Current Status: Completed Legislative Districts: 39
Project Description This project will mill & fill with 0.15 of HMA US 2 between MP 10.75 to MP 14.10, work will include rehabilitation of bridges 2/17, 2/18 and resurfacing bridge 2/19.25 as recommended by Bridge Condition Reports (BCRs). The project will update a roadway delineation to current WSDOT requirements. Other safety work will be performed as needed.
Contractor: 009363 - GRANITE CONSTRUCTION COMPANY - $2,066,792.64 - 02/01/2019
Milestone Original Date Current Date Status
Project Definition Complete Q2 2017 Q2 2017 On Schedule
Preliminary Engineering Start Q3 2017 Q3 2017 On Schedule
Environmental Complete Q3 2018 Q4 2017 Early
Right of Way Complete
Contract Advertisement Q4 2018 Q1 2019 Late
Operationally Complete Q4 2019 Q4 2019 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$141$31
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $2,605 $2,262
$0 $2,575 $2,121
As of November 2019: During construction, a differing site condition was identified, which required some redesign work that delayed the completion of the paving on US 2 and extended the construction into a second construction season.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$141
Pre-Existing
Funds
$2,262
$2,121
$0
CWA
$0
$0
$0
$0 $2,262
$2,121
$0
$141
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us2/bickford-sofie/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 2
https://www.wsdot.wa.gov/projects/us2/bickford-sofie/homehttp:2,066,792.64https://www.wsdot.wa.gov/projects/us2/bickford-sofie/homehttp:129,967.06
-
US 2/Eagle Falls Vic to Tye Creek - Bridge Decks Overlay Project Information Project Milestones
PIN: 100231C As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: US 2 Current Status: Construction Legislative Districts: 39
Project Description Remove the existing overlay deck, place new HMA, and modify the transverse joint seal and expansion joints/headers at some bridges within project limits. Crack sealing, HMA saw cut and seal, and extruded curb and energy dissipation pad installations will also be performed on some other bridges.
Milestone
Project Definition Complete
Preliminary Engineering Start
Environmental Complete
Right of Way Complete
Contract Advertisement
Operationally Complete
Original Date Current Date Status
Q3 2017
Q2 2018
Q3 2017
Q2 2018
On Schedule
On Schedule
Q3 2019 Q2 2019 Early
Q4 2019
Q3 2020
Q4 2019
Q3 2020
On Schedule
On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$233$353
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $4,654 $4,534
$0 $4,301 $4,301
As of April 2019: Following a recent Bridge Deck Condition Report, four additional bridge decks need to be addressed within the project limits. Additionally, the original scope of work did not require work to the bridge approaches. However, the significant change in bridge deck grades will require the approaches to be rebuilt. This has increased the cost of the project.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$233
Pre-Existing
Funds
$4,534
$4,301
$0
CWA
$0
$0
$0
$0 $4,534
$4,301
$0
$233
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us2/eagle-falls-tye-creek/home
I-5/NB S Spokane St Vic - Concrete Pavement Replacement Project Information Project Milestones
PIN: 100516G As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: I-5 Current Status: Completed Legislative Districts: 11
Project Description Replace the concrete pavement, adjusting concrete panel longitudinal joints to match with existing lane lines while maintaining the elevation of the drainage features. The ITS induction loops will be pre-formed and cast-in-place. NHS Bridges 5/536E, 5/538E, and 5/538E-N are excepted but will be striped through.
Contractor: 008952 - GUY F. ATKINSON CONSTRUCTION, LLC - $8,091,703.94 - 5/9/17
Milestone
Project Definition Complete
Preliminary Engineering Start
Environmental Complete
Right of Way Complete
Contract Advertisement
Operationally Complete
Original Date Current Date Status
Q1 2014
Q3 2014
Q1 2014
Q3 2014
On Schedule
On Schedule
Q4 2016 Q4 2016 On Schedule
Q4 2016
Q3 2019
Q4 2016
Q4 2019
On Schedule
Late
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$727$727
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $11,454 $11,454
$0 $10,728 $10,728
As of December 2019: The cost has increased due to unsuitable soil conditions that required removal and replacement and added work to mitigate exposure to lead materials during demolition and replacement of the expansion joints.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$921
$208
$0
$713
Nickel
$0
$0
$0
$0
TPA
$14
Pre-Existing
Funds
$10,533
$10,520
$0
CWA
$0
$0
$0
$0 $11,454
$10,728
$0
$727
Total
Project Web Site: https://www.wsdot.wa.gov/projects/i5/mlktoravennapaverepair/default.htm
Change Orders Web Site: http://www.wsdot.wa.gov/publications/fulltext/construction/changeorders/8952_CO_18_Redacted.pdf
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 3
http://www.wsdot.wa.gov/publications/fulltext/construction/changeorders/8952_CO_18_Redacted.pdfhttps://www.wsdot.wa.gov/projects/i5/mlktoravennapaverepair/default.htmhttp:8,091,703.94https://www.wsdot.wa.gov/projects/us2/eagle-falls-tye-creek/home
-
I-5/NB I-90 to SR 520 - Active Traffic Management Project Information Project Milestones
PIN: 100521W As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: I-5 Current Status: Construction Legislative Districts: 37, 43
Project Description NB I-5 between I-90 & SR 520 experiences severe congestion. Installing metering on the Cherry St to NB I-5 ramp and the NB I-5 collector-distributor ramp, and extending the Active Traffic Management System on NB I-5 to SR 520 will improve mobility along the corridor.
Milestone Original Date Current Date Status
Project Definition Complete Q2 2013 Q2 2013 On Schedule
Preliminary Engineering Start Q3 2013 Q3 2013 On Schedule
Environmental Complete Q4 2014 Q4 2014 On Schedule
Right of Way Complete
Contract Advertisement Q4 2018 Q4 2018 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,738$1,738
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $14,396 $14,396
$0 $12,657 $12,657
Reported February 2019: The bids on the project exceeded the funding available for construction. The project will be delayed while the department develops alternatives to deliver the scope within budget. As of December 2019: Additionally, this project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$1,738
Pre-Existing
Funds
$14,396
$12,657
$0
CWA
$0
$0
$0
$0 $14,396
$12,657
$0
$1,738
Total
Project Web Site: https://www.wsdot.wa.gov/projects/i5/senecato520improve/default.htm
I-5/NB Seneca St to Olive Way - Mobility Improvements Project Information Project Milestones
PIN: 100521X As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: I-5 Current Status: Construction Legislative Districts: 37, 43
Project Description NB I-5 between Seneca St & Olive Way experiences severe congestion. Providing an additional NB lane between Seneca St and the Olive Way off ramp will improve mobility along the corridor.
Milestone Original Date Current Date Status
Project Definition Complete Q2 2013 Q2 2013 On Schedule
Preliminary Engineering Start Q3 2013 Q3 2013 On Schedule
Environmental Complete Q4 2014 Q4 2014 On Schedule
Right of Way Complete
Contract Advertisement Q4 2018 Q4 2018 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,476$1,476
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $6,838 $6,838
$0 $5,362 $5,362
Reported February 2019: The bids on the project exceeded the funding available for construction. The project will be delayed while the department develops alternatives to deliver the scope within budget. As of December 2019: Additionally, this project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$1,476
Pre-Existing
Funds
$6,838
$5,362
$0
CWA
$0
$0
$0
$0 $6,838
$5,362
$0
$1,476
Total
Project Web Site: https://www.wsdot.wa.gov/projects/i5/senecato520improve/default.htm
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 4
https://www.wsdot.wa.gov/projects/i5/senecato520improve/default.htmhttps://www.wsdot.wa.gov/projects/i5/senecato520improve/default.htm
-
I-5/Marine View Dr to SR 528 - Peak Use Shoulder Lane & I/C Improvements Project Information Project Milestones
PIN: 100549B As of Date: December 2019 Milestone Original Date Region: Northwest Regional Admin: M. Cotten Project Definition Complete Q2 2017
State Route: I-5 Preliminary Engineering Start Q2 2017Current Status: Pre-Construction Legislative Districts: 38
Environmental Complete Q2 2020Project Description NB I-5 between Everett and Marysville experiences severe congestion during peak travel Right of Way Complete Q2 2020 periods. Widening the outside shoulder (right shoulder) by 1' and re-striping NB I-5 to create a Contract Advertisement Q3 2020peak use shoulder lane and installing an Active Traffic Management system will improve mobility and increase highway capacity by allowing motorists to use the outside shoulder for driving Operationally Complete Q4 2022during peak traffic hours. This project will also complete the half-interchange at SR 529 by constructing a new NB I-5 Off-ramp to SR 529 and a new SB on-ramp from SR 529 to I-5.
Contractor: 009435 - TRIMAXX CONSTRUCTION, INC. - $6,338,297.00 - 05/13/2019
Reported June 2019: A Cost Risk Assessment (CRA) was completed May 2019. The CRA included an increase associated with market conditions project the total cost of the project may exceed the budget amount provided by the Legislature. The Project team is looking for in-budget alternatives. As of September 2019: Following community engagement, WSDOT has selected the preferred solution alternative that will build a permanent fourth lane, designated for HOV. The
Watch List Description
new lane will extend the existing HOV lane in Everett to SR 529. The official title of the
Current Date Status
Q2 2017 On Schedule
Q2 2017 On Schedule
Q2 2020 On Schedule
Q1 2020 Early
Q2 2020 Early
Q4 2022 On Schedule
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$5,323$7,900
$500
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$500
Total $0 $84,192 $84,242
$0 $75,792 $78,419
project will be revised in 2020, after legislative approval, to I-5/NB Marine View Drive to SR 529 Corridor and I/C Improvements. The change in solution is within the CRA total cost of the project, which may exceed the budget amount provided by the Legislature. The Project team continues to look for in-budget alternatives.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Project Phase Nickel TPA
Preliminary Engineering $0 $0
Right of Way $0 $0
Construction $0 $0
Total $0 $0
Project Web Site: https://www.wsdot.wa.gov/projects/i5/marine-view-sr-528/home
I-5/Maddox Creek - Fish Passage
Pre-Existing
Funds CWA Total
$23 $5,300 $5,323
$0 $500 $500
$0 $78,419 $78,419
$23 $84,219 $84,242
Project Information Project Milestones PIN: 100565U As of Date: December 2019
Region: Northwest Regional Admin: M. Cotten State Route: I-5
Current Status: Pre-Construction Legislative Districts: 10
Project Description Remove the existing fish passage barrier and replace it with a fish passable structure.
Milestone
Project Definition Complete
Preliminary Engineering Start
Environmental Complete
Right of Way Complete
Contract Advertisement
Operationally Complete
Original Date Current Date Status
Q2 2015
Q4 2015
Q2 2015
Q4 2015
On Schedule
On Schedule
Q4 2019
Q3 2023
Q4 2019
Q3 2023
On Schedule
On Schedule
Q4 2023
Q4 2024
Q4 2023
Q4 2024
On Schedule
On Schedule
As of June 2019: WSDOT and Local stakeholders have partnered on a drainage study alternative analysis. The results from the study, which will inform the selection of the preferred alternative, are not expected until early 2020. This delay has increased the cost due to inflation.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,646$1,646
$68
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$68
Total $0 $12,611 $12,611
$0 $10,897 $10,897
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$1,646
Pre-Existing
Funds
$12,611
$10,897
$68
CWA
$0
$0
$0
$0 $12,611
$10,897
$68
$1,646
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 5
https://www.wsdot.wa.gov/projects/i5/marine-view-sr-528/homehttp:6,338,297.00
-
I-5/Northbound On-Ramp at Bakerview - Improvements Project Information Project Milestones
PIN: 100591R As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: I-5 Current Status: Construction Legislative Districts: 42
Project Description The overcrossing at I-5 and Bakerview Road experiences significant congestion. This project will construct a northbound on-ramp on the east side of I-5 to address congestion, enhance regional multimodal transportation circulation and support economic development in north- western Bellingham.
Milestone Original Date Current Date Status
Project Definition Complete Q2 2017 Q2 2017 On Schedule
Preliminary Engineering Start Q2 2017 Q2 2017 On Schedule
Environmental Complete Q3 2018 Q3 2018 On Schedule
Right of Way Complete Q4 2019 Q3 2019 Early
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,500$1,500
$2,349
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$2,349
Total $0 $10,000 $10,000
$0 $6,151 $6,151
Reported September 2019: The right-of-way acquisition is taking longer than previously planned because one parcel is going through the condemnation process. There is a potential that the advertisement date may be delayed. Reported October 2019: Delays with acquiring right-of-way have delayed the advertisement. Additionally, the budget is at risk due to the uncertainty of the right-of-way costs. As of December 2019: Additionally, this project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$1,500
$2,349
$6,151
$10,000 $10,000
$6,151
$2,349
$1,500
Total
SR 9/Acme Vic to Mt Baker Highway Vic - VWIM Enforcement Area Project Information Project Milestones
PIN: 100901E As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 9 Current Status: Not Started Legislative Districts: 42
Project Description The project will construct a Virtual Weigh-in-Motion Enforcement Area location. Washington State Patrol WSP will be able to police freight traffic on SR 9 more effectively as a result of this project.
Milestone Original Date Current Date Status
Project Definition Complete Q2 2025 Q2 2025 On Schedule
Preliminary Engineering Start Q3 2025 Q3 2025 On Schedule
Environmental Complete Q1 2026 Q1 2026 On Schedule
Right of Way Complete Q3 2026 Q3 2026 On Schedule
Contract Advertisement Q4 2026 Q4 2026 On Schedule
Operationally Complete Q4 2027 Q4 2027 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$557$557
$269
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$269
Total $0 $2,752 $2,752
$0 $1,926 $1,926
As of April 2019: The cost increased significantly due to higher costs for the pull off enforcement area than previously estimated. Additionally, due to the cost increase Washington State Patrol requested to defer this project so that higher priorities projects could be addressed.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$2,752
$1,926
$269
$557
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$0
$0
$0
$0 $2,752
$1,926
$269
$557
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 6
-
SR 9/SR 204 Intersection - Improvements Project Information Project Milestones
PIN: 100910K As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 9 Current Status: Pre-Construction Legislative Districts: 44
Project Description Construct improvements at the SR 9 and SR 204 intersection.
Contractor: 009374 - MARSHBANK CONSTRUCTION, INC - $1,201,059.80 - 03/25/2019
Milestone Original Date Current Date Status
Project Definition Complete Q3 2015 Q3 2015 On Schedule
Preliminary Engineering Start Q3 2015 Q3 2015 On Schedule
Environmental Complete Q4 2019 Q4 2019 On Schedule
Right of Way Complete Q4 2020 Q4 2020 On Schedule
Contract Advertisement Q1 2021 Q1 2021 On Schedule
Operationally Complete Q4 2022 Q4 2022 On Schedule
As of December 2019: This project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$13,100$13,100
$8,900
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$8,900
Total $0 $69,500 $69,430
$0 $47,500 $47,430
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$13,100
$8,900
$47,430
$69,430 $69,430
$47,430
$8,900
$13,100
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr9/sr204improvements/default.htm
SR 9/108th St NE - Intersection Improvements Project Information Project Milestones
PIN: 100924C As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 9 Current Status: Completed Legislative Districts: 39
Project Description This project will reduce the risk of collisions and provide relief at the SR 9/108th St NE intersection.
Contractor: 009195 – GRANITE CONSTRUCTION COMPANY $2,326,408.72 - 2/7/18
Milestone Original Date Current Date Status
Project Definition Complete
Preliminary Engineering Start Q3 2016 Q3 2016 On Schedule
Environmental Complete Q4 2017 Q4 2017 On Schedule
Right of Way Complete
Contract Advertisement Q4 2017 Q4 2017 On Schedule
Operationally Complete Q2 2019 Q2 2019 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$412$412
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $3,481 $3,481
$0 $3,069 $3,069
Reported April 2019: The contractor has submitted a delay claim that could increase the cost of the project. As of October 2019: The schedule is delayed due to design discrepancies that resulted in changes to the alignment for the SR 9 Roundabout that affected the weekend closure and weather work windows, which extended the project into an additional construction season.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$412
Pre-Existing
Funds
$3,481
$3,069
$0
CWA
$0
$0
$0
$0 $3,481
$3,069
$0
$412
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr9/108thstimprove/default.htm
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 7
https://www.wsdot.wa.gov/projects/sr9/108thstimprove/default.htmhttp:2,326,408.72https://www.wsdot.wa.gov/projects/sr9/sr204improvements/default.htmhttp:1,201,059.80
-
SR 20/Deception Pass Bridge - Painting Project Information Project Milestones
PIN: 102026K As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 20 Current Status: Construction Legislative Districts: 10
Project Description Paint existing structure.
Contractor: 009344 - EAGLE INDUSTRIAL PAINTING, LLC - $8,073,163.92 - 01/07/2019
Milestone Original Date Current Date Status
Project Definition Complete Q3 2016 Q3 2016 On Schedule
Preliminary Engineering Start Q3 2016 Q3 2016 On Schedule
Environmental Complete Q4 2018 Q4 2018 On Schedule
Right of Way Complete
Contract Advertisement Q4 2018 Q4 2018 On Schedule
Operationally Complete Q3 2020 Q3 2020 On Schedule
As of November 2019: During construction the paint thickness on the bridge was greater than anticipated, which may extend the contract into a third construction season.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$608$608
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $10,599 $10,599
$0 $9,992 $9,992
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$186
$186
$0
CWA
$608
$0
$9,805
$10,413 $10,599
$9,992
$0
$608
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr20/deceptionpassbrdgpaint/home
I-90/Raging River Bridge to Bandera Vic - Stormwater Retrofit Project Information Project Milestones
PIN: 109065K As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: I-90 Current Status: Construction Legislative Districts: 05
Project Description This section of I-90 has been identified in a statewide effort in 2012 as a high priority corridor for improving water quality.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2017 Q3 2017 Early
Preliminary Engineering Start Q4 2017 Q4 2017 On Schedule
Environmental Complete Q4 2019 Q1 2018 Early
Right of Way Complete
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
As of December 2019: This project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$270$310
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $2,065 $1,943
$0 $1,755 $1,673
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$270
Pre-Existing
Funds
$270
$0
$0
CWA
$0
$0
$1,673
$1,673 $1,943
$1,673
$0
$270
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 8
https://www.wsdot.wa.gov/projects/sr20/deceptionpassbrdgpaint/homehttp:8,073,163.92
-
SR 99/George Washington Bridge - Painting (Stage 2) Project Information Project Milestones
PIN: 109946C As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 99 Current Status: Construction Legislative Districts: 36, 43
Project Description Clean and paint bridge in order to preserve its structural integrity.
Contractor: 009168 - Liberty Maintenance, Inc. - $27,979,476.51 - 12/19/2017
Milestone Original Date Current Date Status
Project Definition Complete
Preliminary Engineering Start Q2 2016 Q2 2016 On Schedule
Environmental Complete Q2 2017 Q2 2017 On Schedule
Right of Way Complete
Contract Advertisement Q4 2017 Q4 2017 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
As of November 2019: During construction the contractor identified the pack rust in between the steel plates and joints on the bridge was greater than anticipated, which increased the bid item quantity and the project cost.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$676$676
$135
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$135
Total $0 $32,032 $32,032
$0 $31,221 $31,221
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$676
Pre-Existing
Funds
$32,032
$31,221
$135
CWA
$0
$0
$0
$0 $32,032
$31,221
$135
$676
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr99/aurorabridgepainting/default.htm
SR 104/Lyon Creek - Fish Passage Project Information Project Milestones
PIN: 110414A As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 104 Current Status: Pre-Construction Legislative Districts: 46
Project Description Remove the existing fish passage barrier and replace it with a fish passable structure.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2014 Q4 2014 On Schedule
Preliminary Engineering Start Q4 2014 Q4 2014 On Schedule
Environmental Complete Q1 2020 Q1 2020 On Schedule
Right of Way Complete Q1 2021 Q1 2021 On Schedule
Contract Advertisement Q1 2021 Q1 2021 On Schedule
Operationally Complete Q4 2021 Q4 2021 On Schedule
As of July 2019: During design, hazardous materials associated with a collapsed culvert section at a gas/service station was discovered, which has increased the project. Additionally, the project cost and schedule remain at risk due to multiple buried utilities that will require relocation.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,318$1,318
$273
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$273
Total $0 $4,877 $4,877
$0 $3,286 $3,286
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$172
Pre-Existing
Funds
$172
$0
$0
CWA
$1,146
$273
$3,286
$4,705 $4,877
$3,286
$273
$1,318
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 9
https://www.wsdot.wa.gov/projects/sr99/aurorabridgepainting/default.htmhttp:27,979,476.51
-
SR 202/Little Bear Creek - Fish Barrier Removal Project Information Project Milestones
PIN: 120200D As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 202 Current Status: Completed Legislative Districts: 45
Project Description Remove and replace the existing culvert with a structure sufficient to accommodate Little Bear Creek and allow fish passage.
Contractor: 008865 - Olson Brothers Excavating, Inc. - $4,995,037 - 4/8/16
Milestone Original Date Current Date Status
Project Definition Complete
Preliminary Engineering Start Q4 2011 Q4 2011 On Schedule
Environmental Complete
Right of Way Complete Q1 2016 Q1 2016 On Schedule
Contract Advertisement Q1 2016 Q1 2016 On Schedule
Operationally Complete Q3 2018 Q3 2018 On Schedule
As of April 2019: The contractor has submitted a claim that could increase the cost of the project.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$822$822
$232
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$232
Total $0 $8,881 $8,881
$0 $7,827 $7,827
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$822
Pre-Existing
Funds
$8,881
$7,827
$232
CWA
$0
$0
$0
$0 $8,881
$7,827
$232
$822
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr202/littlebearcreek/default.htm
SR 202/Evans Creek & Patterson Creek - Fish Passage Project Information Project Milestones
PIN: 120215A As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 202 Current Status: Construction Legislative Districts: 45
Project Description Remove the existing fish passage barriers and replace them with fish passable structures.
Contractor: 009269 - HAMILTON CONSTRUCTION CO. - $7,686,813.47 - 04/03/2019
Milestone Original Date Current Date Status
Project Definition Complete Q1 2017 Q1 2017 On Schedule
Preliminary Engineering Start Q2 2016 Q2 2016 On Schedule
Environmental Complete Q4 2018 Q4 2018 On Schedule
Right of Way Complete Q2 2018 Q2 2018 On Schedule
Contract Advertisement Q4 2018 Q4 2018 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
As of December 2019: Design and construction of a structure that allows for natural regrade of the stream over time will increase the cost of the project.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,826$1,826
$129
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$115
Total $0 $11,247 $11,232
$0 $9,291 $9,291
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$8,821
$8,821
$0
CWA
$1,826
$115
$470
$2,412 $11,232
$9,291
$115
$1,826
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr202/evans-patterson-creek-fish-passage/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 10
https://www.wsdot.wa.gov/projects/sr202/evans-patterson-creek-fish-passage/homehttp:7,686,813.47https://www.wsdot.wa.gov/projects/sr202/littlebearcreek/default.htm
-
SR 509/I-5 & SR 516 I/C to 28th/24th Ave S - SR 509 Completion Stage 1 Project Information Project Milestones
PIN: 150907E As of Date: December 2019 Region: Gateway Projects Regional Admin: C. Stone
State Route: SR 509 Current Status: Pre-Construction Legislative Districts: 33
Project Description This project will construct a new four lane SR 509 from 28th/24th Ave S to its connection with I-5. The project will also construct a two lane southbound collector-distributor along I-5 and reconstruct the SR 516 interchange into a diamond interchange and construct a new under- crossing of I-5 connecting Veterans Drive to the southbound I-5 off-ramp.
As of December 2019: This project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Milestone
Project Definition Complete
Preliminary Engineering Start
Environmental Complete
Right of Way Complete
Contract Advertisement
Operationally Complete
Original Date
Q3 2017
Q3 2016
Q1 2018
Q1 2020
Q2 2025
Current Date
Q3 2017
Q3 2016
Q1 2018
Q1 2020
Q2 2025
Status
On Schedule
On Schedule
On Schedule
On Schedule
On Schedule
SR 527/Penny Creek - Fish Passage
PIN: 152714B As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 527 Current Status: Construction Legislative Districts: 44
Project Description Remove the existing fish passage barrier and replace it with a fish passable structure.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$28,380$28,380
$58,335
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$58,335
Total $0 $462,901 $462,901
$0 $376,186 $376,186
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$36,750
$36,750
$0
CWA
$28,380
$58,335
$339,436
$426,151 $462,901
$376,186
$58,335
$28,380
Total
Project Information Project Milestones
Milestone Original Date Current Date Status
Project Definition Complete Q1 2017 Q1 2017 On Schedule
Preliminary Engineering Start Q2 2016 Q2 2016 On Schedule
Environmental Complete Q3 2019 Q2 2019 Early
Right of Way Complete Q4 2019 Q4 2019 On Schedule
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,434$1,853
$329
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$315
Total $0 $7,949 $7,518
$0 $5,768 $5,768
Reported April 2019: The increase is due to a change in the site condition as the sanitary sewer identified for relocation is planned to be relocated within a parking lot known to have hazard materials contamination. The level of risk regarding hazardous materials could further impact the budget and schedule. As of December 2019: The cost increase is approved as a part of the 2019 Plan Update. The schedule remains at risk due to continuing delays associated with utility relocation and right-of-way.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$1,434
$315
$5,768
$7,518 $7,518
$5,768
$315
$1,434
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 11
-
SR 530/Trafton Creek - Fish Passage Project Information Project Milestones
PIN: 153026A As of Date: December 2019 Region: Northwest Regional Admin: M. Cotten
State Route: SR 530 Current Status: Construction Legislative Districts: 10
Project Description Remove the existing fish passage barrier and replace it with a fish passable structure.
Contractor: 009143 - KIEWIT INFRASTRUCTURE WEST CO. - $10,449,700.74 - 05/30/2018
Milestone Original Date Current Date Status
Project Definition Complete Q3 2013 Q3 2013 On Schedule
Preliminary Engineering Start Q4 2013 Q4 2013 On Schedule
Environmental Complete Q1 2019 Q1 2019 On Schedule
Right of Way Complete Q4 2017 Q4 2017 On Schedule
Contract Advertisement Q1 2018 Q1 2018 On Schedule
Operationally Complete Q3 2020 Q3 2020 On Schedule
As of June 2019: The project is delayed while the culvert is re-designed by the Design-Builder. The final design must be approved by the project's stakeholders. There is a potential that the re-design culvert may increase the total project cost.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$672$672
$47
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$47
Total $0 $14,144 $14,144
$0 $13,425 $13,425
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$672
Pre-Existing
Funds
$4,667
$3,994
$0
CWA
$0
$47
$9,431
$9,477 $14,144
$13,425
$47
$672
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr530/trafton-creek-and-schoolyard-creek/home
SR 28/35th Street - Roundabout and Access Control Project Information Project Milestones
PIN: 202801J As of Date: December 2019 Region: North Central Regional Admin: D. Bierschbach
State Route: SR 28 Current Status: Construction Legislative Districts: 12
Milestone Original Date Current Date Status
Project Definition Complete Q1 2018 Q4 2017 Early
Preliminary Engineering Start Q1 2018 Q1 2018 On Schedule
Environmental Complete Q3 2018 Q3 2018 On Schedule
Right of Way Complete Q4 2019 Q4 2019 On Schedule
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
Project Description Access to SR 28 from the local roadway network between the Columbia River and SR 28, immediately south of US 2/97, is provided by stop-controlled intersections that have mobility and safety performance opportunities. Recent safety improvements at the intersection of US 2/97 and SR 28 altered to Cascade Avenue, leaving westbound travelers in this area to access the highway network at these stop controlled intersections along SR 28. Constructing a roundabout at SR 28 and 35th St. and revising access to Cascade Avenue at US 2/97 to right-in only will improve safety, access to local roadway network, and aide access for future economic development in the area.
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$541$343
$700
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$500
Total $0 $3,133 $3,041
$0 $2,090 $2,000
Watch List Description As of December 2019: This project has a possible delay and cost increase due to increased intersection capacity needs.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$3,041
$2,000
$500
$541
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$0
$0
$0
$0 $3,041
$2,000
$500
$541
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr28/35th-street/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 12
https://www.wsdot.wa.gov/projects/sr28/35th-street/homehttps://www.wsdot.wa.gov/projects/sr530/trafton-creek-and-schoolyard-creek/homehttp:10,449,700.74
-
US 97A/Dan Gordon Bridge - Approach Slab Replacement Project Information Project Milestones
PIN: 209704F As of Date: December 2019 Region: North Central Regional Admin: D. Bierschbach
State Route: US 97 Current Status: Construction Legislative Districts: 12
Project Description This project will replace the south bridge approach slab on the Dan Gordon Bridge. The approach slab has slid off it's support and bent the anchors. Maintenance crews paved over the approach slab but it continues to settle leaving a lip between the pavement and bridge deck.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2017 Q1 2018 Late
Preliminary Engineering Start Q1 2018 Q1 2018 On Schedule
Environmental Complete Q3 2025 Q4 2018 Early
Right of Way Complete
Contract Advertisement Q4 2025 Q4 2019 Early
Operationally Complete Q4 2026 Q4 2020 Early
As of October 2019: This project has a increase mainly due to incorporating the northern approach slab, and the design solutions change for the expansion joint modification strip seal, sidewalk and barrier design.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$51$108
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $1,011 $371
$0 $903 $320
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$51
Pre-Existing
Funds
$371
$320
$0
CWA
$0
$0
$0
$0 $371
$320
$0
$51
Total
US 12/Anderson Rd to Moon Rd - Safety Improvement Project Information Project Milestones
PIN: 301201G As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: US 12 Current Status: Completed Legislative Districts: 20, 24
Project Description This section of highway has been identified as a Collision Analysis Corridor. By constructing a roundabout at Anderson Road, implementing access management improvements at Moon Road, and other operational improvements along the corridor, this project has the potential to reduce the frequency of collisions and enhance motorist safety.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2015 Q1 2015 On Schedule
Preliminary Engineering Start Q1 2016 Q1 2016 On Schedule
Environmental Complete Q2 2018 Q4 2017 Early
Right of Way Complete Q4 2019 Q1 2018 Early
Contract Advertisement Q4 2019 Q1 2018 Early
Operationally Complete Q4 2020 Q2 2019 Early
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$405$697
$105
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$99
Total $0 $3,352 $3,018
$0 $2,550 $2,515
As of May 2019: The current scope initially planned to build two roundabouts on US 12 at the intersections of Anderson Road and Moon Road SW. However, Thurston County committed to closing 188th St at Moon Rd, which eliminated the need to construct a roundabout at this location. Additionally, the schedule has being delayed due to a lengthy environmental process and right-of-way negotiations.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$405
Pre-Existing
Funds
$3,018
$2,515
$99
CWA
$0
$0
$0
$0 $3,018
$2,515
$99
$405
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us12/andersontomoonrdsafety/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 13
https://www.wsdot.wa.gov/projects/us12/andersontomoonrdsafety/home
-
US 101/Siebert Creek - Remove Fish Barrier Project Information Project Milestones
PIN: 310104F As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: US 101 Current Status: Construction Legislative Districts: 24
Project Description The existing drainage structure at this location has been identified as a fish passage barrier. By replacing the existing structure with a fish passable structure, the restriction to fish passage will be eliminated.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2014 Q4 2014 On Schedule
Preliminary Engineering Start Q3 2014 Q3 2014 On Schedule
Environmental Complete Q2 2019 Q2 2019 On Schedule
Right of Way Complete Q4 2019 Q1 2020 Late
Contract Advertisement Q4 2019 Q1 2020 Late
Operationally Complete Q4 2021 Q1 2022 Late
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$2,851$2,200
$118
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$121
Total $0 $22,923 $23,705
$0 $20,606 $20,734
Reported October 2019: The design of the secant pile walls adjacent to Siebert Creek is taking longer than previously estimated due to the challenging geotechnical site conditions. This has lengthened the design effort and delayed the environmental process, right-of-way acquisition, and construction phase and has resulted in an increase to the project cost. As of December 2019: This location is known historically for landslides and the recently completed seismic geotechnical analysis required the installation of drilled shaft walls and soil reinforcement to excavate the new creek bed and maintain stability around the existing US 101 eastbound and new westbound bridge piers. This will increase the cost of the project.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$2,694
Pre-Existing
Funds
$23,549
$20,734
$121
CWA
$157
$0
$0
$157 $23,705
$20,734
$121
$2,851
Total
US 101/N of SR 107 - Stabilize Slope Project Information Project Milestones
PIN: 310121G As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: US 101 Current Status: Completed Legislative Districts: 19
Project Description The side slope along this section of US 101 is experiencing slope failure. This project will stabilize the slope and reduce the risk of roadway closures.
Contractor: 009430 - ROGNLIN'S, INC. - $6,650,000.00 - 05/10/2019
Milestone Original Date Current Date Status
Project Definition Complete Q2 2017 Q2 2017 On Schedule
Preliminary Engineering Start Q4 2017 Q4 2017 On Schedule
Environmental Complete Q3 2018 Q3 2018 On Schedule
Right of Way Complete
Contract Advertisement Q2 2019 Q2 2019 On Schedule
Operationally Complete Q4 2019 Q4 2019 On Schedule
As of September 2019: During construction the contractor identified a greater amount of riprap (large rocks) where the stone columns are being installed to stabilized the slope. This change in conditions and may increase the project cost.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$614$614
$7
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$7
Total $0 $8,880 $8,880
$0 $8,259 $8,259
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$614
Pre-Existing
Funds
$8,880
$8,259
$7
CWA
$0
$0
$0
$0 $8,880
$8,259
$7
$614
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us101/sr-107/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 14
https://www.wsdot.wa.gov/projects/us101/sr-107/homehttp:6,650,000.00
-
US 101/Elwha River Bridge - Bridge Replacement Project Information Project Milestones
PIN: 310135F As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: US 101 Current Status: Pre-Construction Legislative Districts: 24
Project Description The existing bridge built in 1926 is structurally deficient. This project replaces the existing bridge with a new structure designed to current standards reducing the potential for catastrophic failure and preserving the functional integrity of the roadway.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2017 Q1 2017 On Schedule
Preliminary Engineering Start Q4 2016 Q4 2016 On Schedule
Environmental Complete Q3 2019 Q2 2020 Late
Right of Way Complete Q4 2020
Contract Advertisement Q1 2020 Q4 2020 Late
Operationally Complete Q3 2021 Q2 2022 Late
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$3,584$3,085
$525
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$533
Total $0 $33,077 $33,529
$0 $29,467 $29,412
Reported December 2018: The cost increase is due to required additional work to complete the environmental permitting, hydraulic design, and geotech designs. As of September 2019: The preliminary engineering phase has lengthened due to continuing difficulties with completing the environmental permitting, which has delayed the right-of-way acquisition and construction and further increased the cost of the project.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$3,332
Pre-Existing
Funds
$33,278
$29,412
$533
CWA
$252
$0
$0
$252 $33,529
$29,412
$533
$3,584
Total
Project Web Site: https://www.wsdot.wa.gov/projects/us101/elwhariverbridgereplace/default.htm
US 101/Bagley Creek - Remove Fish Barrier Project Information Project Milestones
PIN: 310198G As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: US 101 Current Status: Construction Legislative Districts: 24
Project Description The existing drainage structure at this location has been identified as a fish passage barrier. By replacing the existing structure with a fish passable structure, the restriction to fish passage will be eliminated.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2017 Q4 2017 On Schedule
Preliminary Engineering Start Q3 2016 Q3 2016 On Schedule
Environmental Complete Q3 2019 Q4 2018 Early
Right of Way Complete Q4 2019 Q4 2019 On Schedule
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2021 Q4 2020 Early
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,668$1,668
$117
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$116
Total $0 $16,983 $16,982
$0 $15,198 $15,198
As of October 2019: The cost increase is due to incorporating an additional fish passage barrier within the project limits. In addition, the design solution for the structure crossing James Page Road was changed from a bridge to a buried structure, which also contributed to the cost increase.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$1,668
Pre-Existing
Funds
$16,982
$15,198
$116
CWA
$0
$0
$0
$0 $16,982
$15,198
$116
$1,668
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 15
https://www.wsdot.wa.gov/projects/us101/elwhariverbridgereplace/default.htm
-
SR 161/31st Ave SW Overpass - Improvements Project Information Project Milestones
PIN: 316132A As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: SR 161 Current Status: Pre-Construction Legislative Districts: 25
Project Description Perform a feasibility study, traffic analysis, and community engagement on the 31st Ave SW overpass in Puyallup's South Hill. This project will also implement low cost improvements as a near term strategy to reduce congestion on 31st Avenue SW between 94th Avenue E and SR 512 eastbound ramps.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2015 Q1 2015 On Schedule
Preliminary Engineering Start Q2 2019 Q1 2015 Early
Environmental Complete Q4 2019 Q2 2015 Early
Right of Way Complete
Contract Advertisement Q1 2020 Q1 2020 On Schedule
Operationally Complete Q2 2020 Q2 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$521$603
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $1,100 $1,100
$0 $497 $579
As of December 2019: This project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$521
Pre-Existing
Funds
$1,100
$579
$0
CWA
$0
$0
$0
$0 $1,100
$579
$0
$521
Total
SR 510/Yelm Loop - New Alignment Phase 2 Project Information Project Milestones
PIN: 351029A As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: SR 510 Current Status: Construction Legislative Districts: 02
Project Description Traffic through the City of Yelm is extremely congested at the present time. This project will construct the second stage of a new alignment for SR 510 through the City of Yelm. When complete, this project will relieve congestion and improve motorist safety.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2004 Q4 2004 On Schedule
Preliminary Engineering Start Q3 2017 Q3 2017 On Schedule
Environmental Complete Q3 2020 Q1 2019 Early
Right of Way Complete Q2 2020 Q4 2019 Early
Contract Advertisement Q3 2021 Q4 2019 Early
Operationally Complete Q4 2023 Q2 2022 Early
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$7,200$7,200
$1,100
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$1,100
Total $0 $58,500 $58,500
$0 $50,200 $50,200
Reported July 2019: This project is delayed while the department satisfies new environmental mitigation requirements necessary to protect endangered pocket gopher. As of October 2019: The schedule delay is approved as part of the 2019 Plan update but remains at risk pending final determination of the environmental mitigation requirements necessary to protect endangered pocket gopher.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$7,200
$1,100
$50,200
$58,500 $58,500
$50,200
$1,100
$7,200
Total
Project Web Site: https://www.wsdot.wa.gov/projects/sr510/yelmloopnewalignph2/home
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 16
https://www.wsdot.wa.gov/projects/sr510/yelmloopnewalignph2/home
-
I-705/I-5 to Pacific Ave - Expansion Joint Replacement Stage 3 Project Information Project Milestones
PIN: 370510A As of Date: December 2019 Region: Olympic Regional Admin: J. Wynands
State Route: I-705 Current Status: Construction Legislative Districts: 27
Project Description The strip seal expansion joints on these structures have reached the end of their usable service life and need replacement. This project will replace the expansion joints to extend the service life of the structures.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2018 Q1 2018 On Schedule
Preliminary Engineering Start Q3 2019 Q3 2019 On Schedule
Environmental Complete Q4 2019 Q4 2019 On Schedule
Right of Way Complete
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q3 2020 Q3 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$16$16
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $271 $271
$0 $255 $255
As of November 2019: : After a field inspection, it was discovered that the gaps at the expansion joints are greater than anticipated and will require an in-kind replacement. This will likely increase the project cost. In addition, SR 705 is being used as a detour route for another project and will delay this project.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$16
Pre-Existing
Funds
$271
$255
$0
CWA
$0
$0
$0
$0 $271
$255
$0
$16
Total
I-5/E Fork Lewis River Bridge NB - Replace Bridge Project Information Project Milestones
PIN: 400512R As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: I-5 Current Status: Pre-Construction Legislative Districts: 18
Project Description The existing bridge built in 1936 is functionally obsolete. This project replaces the existing bridge with a new structure reducing the potential for catastrophic failure and preserving the functional integrity of the roadway.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2013 Q1 2013 On Schedule
Preliminary Engineering Start Q4 2017 Q4 2017 On Schedule
Environmental Complete Q1 2020 Q1 2020 On Schedule
Right of Way Complete Q1 2021 Q1 2021 On Schedule
Contract Advertisement Q1 2021 Q1 2021 On Schedule
Operationally Complete Q2 2023 Q2 2023 On Schedule
As of August 2019: This project has a potential cost increase and delay due to the need for additional environmental work. The project office is reviewing bridge alignment alternatives for constructability which has a potential project cost increase.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,954$1,954
$84
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$83
Total $0 $65,246 $65,245
$0 $63,208 $63,208
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$1,954
Pre-Existing
Funds
$2,037
$0
$83
CWA
$0
$0
$63,208
$63,208 $65,245
$63,208
$83
$1,954
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 17
-
I-5/SR 506 to Rush Road Interchange - Illumination Rebuild Project Information Project Milestones
PIN: 400516I As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: I-5 Current Status: Construction Legislative Districts: 20
Project Description This project will upgrade the outdated illumination systems at the interchanges to improve reliability.
Milestone Original Date Current Date Status
Project Definition Complete Q3 2014 Q3 2014 On Schedule
Preliminary Engineering Start Q3 2017 Q3 2017 On Schedule
Environmental Complete Q3 2019 Q3 2019 On Schedule
Right of Way Complete
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
As of September 2019: This project has a potential delay due to the Geotechnical office identifying the need for additional field investigation to determine foundation needs.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$145$195
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $1,662 $1,536
$0 $1,467 $1,391
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$145
Pre-Existing
Funds
$1,536
$1,391
$0
CWA
$0
$0
$0
$0 $1,536
$1,391
$0
$145
Total
I-5/Woodland Vicinity at Horseshoe Lake - Upgrade Pump System Project Information Project Milestones
PIN: 400517W As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: I-5 Current Status: Construction Legislative Districts: 20
Project Description WSDOT currently maintains and operates a pump from the Lewis River near Woodland under I-5 to Horseshoe Lake. This prevents Horseshoe Lake from becoming stagnant. The pump intake screens do not meet current standards. WSDOT has been asked by WDFW to bring the screens up to current standards before issuing a new HPA permit. WSDOT will work with a consultant to design and install the system upgrade. This project will enable consistent flow from the Lewis River into Horseshoe Lake at this location to continue.
Milestone Original Date Current Date Status
Project Definition Complete Q2 2017 Q2 2017 On Schedule
Preliminary Engineering Start Q1 2016 Q1 2016 On Schedule
Environmental Complete Q3 2019 Q3 2019 On Schedule
Right of Way Complete
Contract Advertisement Q4 2019 Q4 2019 On Schedule
Operationally Complete Q4 2020 Q4 2020 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$955$955
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $3,154 $3,154
$0 $2,199 $2,199
As of May 2019: Completing the environmental documentation and permit process has delayed the project.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$955
Pre-Existing
Funds
$3,154
$2,199
$0
CWA
$0
$0
$0
$0 $3,154
$2,199
$0
$955
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 18
-
I-5/179th Street Interchange - Interchange Improvements Project Information Project Milestones
PIN: 400523I As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: I-5 Current Status: Not Started Legislative Districts: 18
Project Description Constructing interchange improvements to allow for commercial development in the area.
Milestone Original Date Current Date Status
Project Definition Complete Q3 2023 Q3 2023 On Schedule
Preliminary Engineering Start Q3 2023 Q3 2023 On Schedule
Environmental Complete Q2 2025 Q2 2025 On Schedule
Right of Way Complete Q2 2026 Q2 2026 On Schedule
Contract Advertisement Q2 2026 Q2 2026 On Schedule
Operationally Complete Q4 2028 Q4 2028 On Schedule
Reported July 2019: This project is likely to increase in total cost so that the existing fish passage barriers at the 179th Street Interchange area can be addressed. As of September 2019: This project has a potential further cost increase due a revised intersection design to accommodate future traffic flow.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$5,500$5,500
$3,000
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$3,000
Total $0 $50,500 $50,500
$0 $42,000 $42,000
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$500
Pre-Existing
Funds
$500
$0
$0
CWA
$5,000
$3,000
$42,000
$50,000 $50,500
$42,000
$3,000
$5,500
Total
Project Web Site: https://www.wsdot.wa.gov/projects/i5/179th-interchange/home
SR 6/Two Tributaries to Chehalis River - Fish Passage Project Information Project Milestones
PIN: 400621J As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: SR 6 Current Status: Pre-Construction Legislative Districts: 20
Project Description This project will remove a fish barrier.
Milestone Original Date Current Date Status
Project Definition Complete Q4 2018 Q4 2018 On Schedule
Preliminary Engineering Start Q2 2016 Q2 2016 On Schedule
Environmental Complete Q4 2018 Q4 2018 On Schedule
Right of Way Complete Q1 2020 Q1 2020 On Schedule
Contract Advertisement Q1 2020 Q1 2020 On Schedule
Operationally Complete Q3 2021 Q3 2021 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$1,310$1,310
$112
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$112
Total $0 $10,236 $10,556
$0 $8,814 $9,134
Reported October 2018: The need for additional scour protection work has increased the project's cost. Additional, the project is delayed while the department negotiates local funding for relocating a waterline. As of July 2019: The schedule will be further delayed while the department coordinates with local stakeholders to refine the project scope.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$1,310
Pre-Existing
Funds
$10,236
$8,814
$112
CWA
$0
$0
$320
$320 $10,556
$9,134
$112
$1,310
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 19
https://www.wsdot.wa.gov/projects/i5/179th-interchange/home
-
SR 14/E of Bingen - Port of Klickitat Access Improvements Project Information Project Milestones
PIN: Region:
State Route: Current Status:
401419B Southwest SR 14 Pre-Construction Legislative Districts:
As of Date: December 2019 Regional Admin: C. Francis
14
Project Description Improves access to the Port of Klickitat.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2016 Q1 2016 On Schedule
Preliminary Engineering Start Q4 2015 Q4 2015 On Schedule
Environmental Complete Q4 2019 Q2 2019 Early
Right of Way Complete Q1 2020 Q1 2020 On Schedule
Contract Advertisement Q1 2020 Q1 2020 On Schedule
Operationally Complete Q4 2021 Q4 2021 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$3,600$3,900
$4,200
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$4,500
Total $0 $26,000 $26,000
$0 $17,900 $17,900
Reported April 2019: Negotiations with Burlington Northern Santa Fe (BNSF) Railway identified that a railroad detour bridge is required. This increased the right-of-way and design costs for the project. As of December 2019: This project is delayed in response to the passage of I-976 and the Governor's direction to WSDOT to postpone certain projects not yet underway. Additionally, more time is required for negotiations with Burlington Northern Santa Fe (BNSF) Railway and to mitigate the Stormwater flow control system.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$3,600
$4,500
$17,900
$26,000 $26,000
$17,900
$4,500
$3,600
Total
SR 103/US 101 to Stackpole Rd with Exceptions - Chip Seal Project Information Project Milestones
PIN: 410315B As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: SR 103 Current Status: Pre-Construction Legislative Districts: 19
Project Description Resurface the deteriorating pavement (due to normal wear) with a chip seal overlay to extend the life of the pavement. This project will also address required safety items.
Milestone Original Date Current Date Status
Project Definition Complete Q1 2014 Q1 2014 On Schedule
Preliminary Engineering Start Q1 2016 Q1 2016 On Schedule
Environmental Complete Q1 2021 Q1 2021 On Schedule
Right of Way Complete
Contract Advertisement Q1 2021 Q1 2021 On Schedule
Operationally Complete Q4 2021 Q4 2021 On Schedule
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$319$135
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost
$0
Total $0 $3,072 $3,256
$0 $2,938 $2,938
Reported April 2019: This project is combined with an ADA Upgrade project for construction efficiencies. Additional time is needed to complete the ADA design and coordinate the utility relocation work, which will delay the project. Additionally, further pavement deterioration has increased the cost of project. October 2019 Update: The project cost have further increased due to stakeholder coordination and an increase paving limits at intersections.
Project Funding Summary - Current Approved Cost ($ in Thousands)
Total
Construction
Preliminary Engineering
Project Phase
Right of Way
$0
$0
$0
$0
Nickel
$0
$0
$0
$0
TPA
$0
Pre-Existing
Funds
$0
$0
$0
CWA
$319
$0
$2,938
$3,256 $3,256
$2,938
$0
$319
Total
Disclaimer: Project Web Sites may be associated with one or more PINs, and PINs may be Report As Of December 2019associated with one or more Project Web Sites.
Page 20
-
SR 103/US 101 to Stackpole Rd - ADA Upgrades Project Information Project Milestones
PIN: 410320A As of Date: December 2019 Region: Southwest Regional Admin: C. Francis
State Route: SR 103 Current Status: Pre-Construction Legislative Districts: 19
Project Description The ADA facilities within these limits need updating. This project will install or upgrade ADA curb ramps to meet current guidelines.
Milestone Original Date Current Date Status
Project Definition Complete Q3 2017 Q3 2017 On Schedule
Preliminary Engineering Start Q3 2018 Q3 2018 On Schedule
Environmental Complete Q1 2021 Q1 2019 Early
Right of Way Complete Q1 2020
Contract Advertisement Q1 2021 Q1 2020 Early
Operationally Complete Q4 2021 Q4 2020 Early
As of April 2019: The project will be delayed because additional time is needed to complete the ADA design and coordinate the utility relocation work.
Watch List Description
$0
Construction
Right of Way
Preliminary Engineering $0
Leg. Initial BudgetProject Status
$571$621
$0
Project Cost Summary ($ in Thousands)
Current Leg. Budget
Current Approved Cost