1

Former NAS Moffett Field

Hangar 1 Removal Action Update

Bryce Bartelma, PG

Salient Federal Solutions

supporting

Navy BRAC PMO West

November 29, 2012

RAB Meeting

2

• Control release of PCBs from Hangar 1 in accordancewith EE/CA (July 2008) and Action Memorandum(December 2008)

Demolition of interior structures

Removal of contaminated siding

Application of weather-resistant coating to steel frame

Project Objective

3

Final Material RemovedJuly 19, 2012

4

Final Scaffolding RemovedOctober 18, 2012

5

Remaining Removal Action Tasks

• Mezzanine prep and coat

• Final coating touch ups

• Soil excavations andconfirmation sampling

• Concrete slab washing andconfirmation sampling

• Perimeter Storm Drainclean-out

• Demobilize

6

Hangar 1 Interactive CD

http://historicproperties.arc.nasa.gov

7

Hangar 1 CERCLA Process

EE/CAand

ActionMemo

RemovalAction

FocusedFeasibility

Study

ProposedPlan

Record ofDecision

Land UseControls

8

Schedule

• NTCRA Demobilization

December 2012

• Draft After ActionCompletion Report

January 2013

• Focused Feasibility Study

April 2013

• Proposed Plan

June 2013

• Public Meeting (tentative)

July 2013

9

Questions?

Point of Contact:

Scott Anderson

BRAC EnvironmentalCoordinator