green recycling network toward a greener tomorrow... today!

Post on 28-Dec-2015

227 Views

Category:

Documents

3 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Green Recycling Network

Toward a Greener Tomorrow... Today!

Outline

• A brief introduction

• Markets primer

• Greening office renovations

• Deconstruction case study

• Best practices

• Future

Deconstruction

The Deconstruction process is cost effective relative to traditional demolition because we avoid costly land disposal by leveraging off the expertise of our affiliated, integrated companies. Thus, no matter the job or the mix of materials, clients get great green results even when a project involves a diverse mix such as salvage, drywall (including painted), unusable furniture, carpet, ceiling tile, and even mixed debris.

Deconstruction

Deconstruction’s approach allows maximum diversion of materials from landfills disposal as the goal no matter the client or certification being sought. This standardized approach, coupled with market development capabilities focused on finding outlets for problem materials and with highly trained crews capable of consistently beating expected timelines, allows outstanding results every time (typical diversion rates routinely exceed 90%).

So where does it all go?

Market: aggregate

Market: cardboard / paper

Market: carpet / pad

Market: ceiling tile

Market: metal

Market: plastic

Market: wallboard

Market: wood

Market: salvage (residential)

Market: salvage (commercial)

Deconstruction: greening office renovations

• Selective demolition; construction in reverse

• More labor intensive than traditional demolition

• Has highest diversion capability

• Costlier than demolition? NO!

• More time consuming? NO!

• How? PLANNING!

Case study

Getting started

Following the hierarchy

Cleaning house

Creating value

Project results

• Completed 1 week AHEAD of schedule

• Approach saved owner > 50% of budget

• Consignment contract returns $$

• Clean space drastically reduces cost of

remediation and final demolition

• Avoided cost of temporary shoring

• Landfill diversion rate exceeded 75%

Recent office fit-out results

• Slightly more expensive than typical due to

building constraints and drywall logistics,

however….

• Total diversion = 90.1%

• 6.3 tons salvage (doors, lights, ceiling

tile); 28.6 tons recycled (drywall, carpet,

metal); 3.84 tons went to landfill.

Best practices

• Specify

• Design for recycling

• Innovate

• Look to the future

Get what you want: specifyDEMOLITION WASTE MANAGEMENT SPECIFICATIONS1.THIT IS A REQUIREMENT FOR THIS PROJECT THAT THE GENERAL CONTRACTOR RECYCLE, REUSE AND/OR SALVAGE AS MUCH MATERIAL AS POSSIBLE. ALL CONSTRUCTION DEMOLITION OF EXISTING BUILT CONDITIONS SHALL BE RECYCLED AS NECESSARY TO MEET MINIMUM REQUIREMENT OF AT LEAST 50% DEMOLITION DEBRIS.2.THE PATH FOR ALL DEMOLISHED MATERIALS SHOULD BE FIRST TO REUSE, SECOND TO RECYCLE, AND LASTLY TO LANDFILL. THE BID BREAKDOWN SHALL INCLUDE A WASTE HANDLING PLAN THAT IDENTIFIES HOW THE WASTE STREAMS WILL BE SEPARATED AND MANAGED, AND SHALL INCLUDE THE FOLLOWING CATEGORIES:

a. WHAT ITEMS WILL BE SALVAGED VS RECYCLED VS LANDFILLEDb. HOW THEY WILL BE SALVAGED OR RECYCLEDc. WHAT PERCENTAGE OF TOTAL DEMOLITION IS BEING SALVAGED VS RECYCLED VS LANDFILLEDd. WHERE WILL THE SALVAGED AND RECYCLED ITEMS BE DIVERTED TO

3.UNLESS OTHERWISE INDICATED, DECONSTRUCTION WASTE BECOMES THE PROPERTY OF THE CONTRACTOR.4.SCHEDULE OF DECONSTRUCTION ACTIVITIES: INDICATE THE FOLLOWING:

a. DETAILED SEQUENCE OF DECONSTRUCTION AND REMOVAL WORK, WITH STARTING AND ENDING DATES FOR EACH ACTIVITY.

b. INTERRUPTION OF UTILITY SERVICES IF REQUIRED. INDICATE HOW LONG UTILITY SERVICES WILL BE INTERRUPTED.

c. COORDINATION FOR SHUTOFF, CAPPING AND CONTINUATION OF UTILITY SERVICES.d. USE OF ELEVATOR AND/OR STAIRS.e. LOCATIONS OF PROPOSED DUST- AND NOISE-CONTROL TEMPORARY PARTITIONS AND MEANS OF

EGRESS.f. MEANS OF PROTECTION FOR ITEMS TO REMAIN AND ITEMS IN PATH OF MATERIAL REMOVAL FROM

BUILDING.5.DOCUMENT GENERAL CONDITION OF MATERIALS TO BE SALVAGED PRIOR TO REMOVAL. CONDUCT PRE-DECONSTRUCTION CONFERENCE ONSITE. REVIEW METHODS AND PROCEDURES RELATED TO DECONSTRUCTION. DESIGNATE AREA(S) ON SITE FOR SEGREGATED OR COMMINGLED COLLECTION OF RECYCLABLE MATERIALS.6.DOCUMENTATION BY THE DEMOLITION CONTRACTOR IS REQUIRED TO VERIFY ALL REUSED AND/OR RECYCLED MATERIALS. HAUL TICKETS AND RECEIPTS SHALL BE PROVIDED BY THE RECIPIENTS OF SALVAGED AND RECYCLED MATERIALS; RECEIPTS SHALL BE MAINTAINED AND MADE AVAILABLE UPON REQUEST.

Plan for end of life

• Do markets exist?

• Are outlets local?

• Forecast infrastructure changes

• Examine installation practices

Think outside of the box

Reusing just Reusing just 1010 doors doors at a 5,000 SF office fit-at a 5,000 SF office fit-out completely pays for out completely pays for the deconstruction the deconstruction expense!expense!

New 10 doors: $10,000New 10 doors: $10,000Salvage 10 doors: Salvage 10 doors: $2,000$2,000Savings: $8,000Savings: $8,000 Vs.Vs.Avg. Demo:Avg. Demo: $7,500 $7,500

Future: green-to-green facilities

Huge capacity

End product capability

THANK YOU!

Contact Information:

Scott Shepard

O. (703) 880-8428

C. (703) 819-5558 scott@GreenRecyclingNetwork.com

www.GreenRecyclingNetwork.com

top related