1
FIRST / TBS
Gas Turbine Rotor
Consulting Capabilities
End of Life Inspections
2
FIRST Consulting Company
History
FIRST = First Independent Rotor Service of Texas
Company Moto = Think “FIRST” Before You Commit
Incorporated in 2003
Company Description = Consulting Firm
Industry = Industrial Gas & Steam Turbine
Equipment Type = Rotating / Stationary
Services Offered = Multiple Consulting Related Tasks
Number of Consultants = 9
Years of Experience = 300 Man Years
FIRST
Core Offerings
3
Consulting Services
Work Scope
Development
TIL Rotor
Compliance
O&M / Site Training
On-Site Bkt Bld R/R
Zero-Hour Packages
RPM Speed Reduction Tb Wheel
Mfg
In-Situ Blade Mod
End of Life
Testing
F.E.A. Rotor Models
End User
Rep
Tech Repair Packages
4
TBS
Technical Bolting Solutions
Manufacturing Company
History
T.B.S. = Technical Bolting Solutions
Company Moto = Think “We Talk the Torque”
Incorporated in 2003
Company Description = Manufacturing Firm
Mfg. Locations: Texas, California, South Carolina, Illinois
Industry = Industrial Gas & Steam Turbine
Product Type = Consumable Parts for Rotating / Stationary
We currently provide over 16,000 consumable parts
We are a Certified GE Manufacturing Supplier
TBS
Manufacturing
5
Mfg
Services
Outage Bolt
Kits
Filling Outage RFQ’s
Reverse
Eng, Mfg
Steam Turbine
Bkt / Blades
Gaskets Washers
Brg Seals
Oil Deflectors
Fuel Nozzle Capitol Parts
F/7 T/P Bracket Bolts
Hyd Seals
F3 – F/9F Rotor Bolt Kits
W-191- 501F Rotor Bolting
TRI Seal Pins
Bucket Blade Hardware
6
FIRST / TBS
2013 Customer Sampling
3
7
FIRST / TBS
Patented Products & Modifications
TRI Seal Pin (Special Bucket Non-Liberating Seal Pin) (*)
RPM Modification (Slowing Down Turning Gear) (*)
In-Situ Compressor Rotor Blade R/R (*)
12 Point Locking Nut (Non-Crimp Style) (*)
Repair Shop Training
In-Place On-Site End of Life Testing
On-Site Rotor Repair (Select Rotors) (Coming in 2015)
( * ) = FIRST Holds USA / International Patents
8
9
FIRST / TBS
Offerings & Products
Without Keys With Keys
“The In Situ Modification”
United States Patent Pending #13 / 091864
10
United States Patent Pending #13 / 091864
FIRST / TBS Offerings & Products
“The In Situ Modification”
11
FIRST / TBS
Offerings & Products
“The In Situ Modification”
Old Blade is Removed & New Blade & Spacers Installed in +/- 8 Hours
United States Patent Pending #13 / 091864
12
FIRST / TBS
Offerings & Products
“The In Situ Modification”
ESTIMATED COSTS FOR FORCED / UNPLANNED ROTOR REPAIR OUTAGE
Rotor Open / Close Rotor Repair Shop Rotor Adders (30%)
Type Turbine Transportation Rotor Repair Bolting Discovery Total *
F/3 $200,000 $6,000 $85,000 $20,000 $24,000 $335,000
F/5 $275,000 $8,000 $175,000 $35,000 $53,000 $546,000
F/6 $315,000 $8,000 $190,000 $35,000 $57,000 $605,000
F/7 $325,000 $10,000 $250,000 $50,000 $75,000 $710,000
F/7F $480,000 $32,000 $450,000 $75,000 $135,000 $1,172,000
* Costs Do Not Include On-Site Crane or Cost to Buy Power
United States Patent Pending #13 / 091864
13
FIRST / TBS
End of Life Testing
Technical Information Letter #1576
TIL #1576 was issued in 2007 and it discusses
the maximum allowable starts for rotors in cyclic
operation and has a maximum fired hour limit
for rotors in base load operation.
It limits rotors to +/- 200,000 factored fired hours
with some consideration of extensions and/or
5,000 factored starts for a cycle based turbine
with no extensions.
FIRST / TBS
End of Life Testing
FIRST has developed a protocol whereas, after
the rotors have been disassembled, we
inspect specific rotor components using 3D
volumetric phased array bore-sonics and eddy
current.
We perform hardness testing & replications as
well as mechanical testing to inspect the rotors
components for changes and internal or
detrimental flaws. 14
15
FIRST / TBS
EOL Testing & Computer Modeling TIL 1576 places retirement for rotors with +/- 200,000 hours
or 5,000 starts. After the 2007 TIL issuance, we immediately
developed our team of experts to start testing rotor
components. There is a need to review found critical flaw(s)
to make decisions/recommendations to turbine owners. We
mfg rotor component fracture models to perform F.E.A.
analysis for found critical flaw(s).
By using the flaw size & flaw location, we have the ability to
place those flaws into our computer model to see if the
characteristic of the flaw is detrimental to the continued
running of the turbine. We can accurately determine how
many hours or starts remain in the life of the component
containing that critical flaw.
16
FIRST / TBS
End of Life
TIL 1576 End of Life Rotor Life Extension
Inspections Performed
F/7B,C,E,EA = 26
F/6A,B = 2
F/5P,LA,L = 21
F3H,J,F = 2
W-501B6 = 2
To Date Total = 53
FIRST / TBS Has Completed the Largest Number of Non-OEM
End of Life Rotor Inspections
17
FIRST / TBS Approach
End of Life Testing
Type of Inspections
3-D Bore Sonic Inspection for Internal Flaws
Eddy Current Inspection for Creep
Hardness and Replication for Grain Structure
Critical Diameters Measured for Bore Shrinkage
Finite Element Analysis When Flaws are Found
18
FIRST / TBS
End of Life Testing
Rotor Type = GE 5001N
TIL 1576 Specific Rotor Components Tested
Stages 13 - 16 Compressor Wheels
Distance Piece
Stage 1 Turbine Disc
Stage 2 Turbine Disc
19
3.80”
4.30”
Approximate Location of Flaw - Indication
FIRST / TBS
End of Life Testing
20 Radial Deformation Results for the Turbine Section Model
FIRST / TBS
End of Life Testing
21 Flaw Cluster as Determined by Phased-Array Inspection
Flaw No.1
Flaw No.2
Flaw No.3
Flaw No.4
Flaw No.5 FIRST
End of Life Testing
FIRST / TBS
End of Life Testing
22 Close-up of Flaw Cluster as Determined Shown in Previous Slide
Sharp projection off Flaw 1 volume
Sharp projection off Flaw 2 volume
FIRST
End of Life Testing
F.I.R.S.T.
End of Life Testing
23
FIRST / TBS
End of Life Testing
EOL On-Site Inspections
In 2013, we started performing rotor end of life
inspections on-site.
There are many on-site critical inspection points
that we can perform to assist in determining
where the rotor is along the end of life scale.
24
FIRST / TBS
End of Life Testing
EOL On-Site Inspections
As the rotor continues in age, it is critical to
establish early, comparative, base-line data.
There are critical inspections that we can
perform on site to assist us in determining
where the rotor is on the end of life scale.
25
FIRST / TBS
End of Life Testing
EOL On-Site Inspections
We can assist end users in setting up an End of
Life inspection protocol with on-site testing so
to provide a clear path on your rotors’ remaining
hours and starts.
This will allow for possible extensions beyond
the current OEM life limitations.