DULLES HIGH SCHOOLPhase 3 - BP24
FBISD 2014 Bond ProgramProgram Manager: JacobsProject Manager: Gaurav AgarwalProject Architect: Stantec Architecture, IncGeneral Contractor:Location: 550 Dulles Avenue, Sugar Land, TX 77478
SCHEDULE SUMMARY Main Construction Scope of Work Schedule (Excludes Cameras, Keying and Civil SOW if applicable)
COSTBUDGET COMMITMENTSFinancials include Security Cameras, Keying and Civil if applicable
A D E H=D+E+F+G I=C-H JB C=A+B K=J/CF G
Description Cost To DateBudget Changes
Current Budget
OriginalBudget
% ExpendedOriginalCommitments
Approved Changes
Pending Commitments
Estimate to Complete
ProjectedCommitments
ProjectedOver/Under
$917$0$456,509$257$824$456,527 ($18) $456,509Architect & Engineering/Professional Services 0%$0 $455,428
$338,456$0$4,002,989$0$413,958$4,000,122 $2,867 $4,002,989Construction 8%$0 $3,589,031
$0$0$29,194$0$0$29,194 $0 $29,194Site Development 0%$0 $29,194
$0$0$202,900$0$1,680$202,900 $0 $202,900Administrative and Other Project Costs 0%$0 $201,220
$0$0$260,712$0$0$262,633 ($1,921) $260,712Project Contingency 0%$0 $260,712
$113,553$0$288,000$0$130,736$288,000 $0 $288,000Security Cameras 39%$0 $157,264
$452,926$0$5,240,304$257$547,198$5,239,376 $928 $5,240,304 9%Totals $0 $4,692,849
SCOPE/COMMENTS PROJECT PHOTO BUDGET /COST STATUSSCOPE: BP24: Access Control including video intercom, Security Vestibules, Teller Window/Door Upgrade, Window Film, Central Cooling, Domestic Water Equipment, Carpeting, Wall Coverings, Wall Painting and Coating, Replacement of Public Address, Metal Exterior Door, Bleachers, Boiler/Air Handler HVAC Component, Water Heater Plumbing Fixtures, Drains, Gutters, Package Roof Top Unit, Exterior Condenser, Fan Coil HVAC Component, Motor Control Center, Roof Condenser, Generator, Panelboard, Power Service, Distribution Panel, Electrical Disconnect, Switchgear, and Electrical Transformer
BP01 and BP01A: Re-key Doors, Interior Door Hardware and Security Cameras BP02: Update Existing Sidewalk
COMMENTS: Architectural services were approved by the Board of Trustees and notice to proceed was issued. This work is scheduled for the last phase of the 2014 Bond program.
As approved by Board of Trustees on 05/16/2016, $928 was transferred from the Program Contingency in relation to BP02.
DULLES HIGH SCHOOLReport Date: 10/10/2016 42