facilities construction - northside independent school ... · construction period – october 2014...

Post on 10-Aug-2020

3 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Glenoaks Elementary School

Facilities Construction

NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT

Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS

Henry Acosta EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING

Jim Berg DIRECTOR OF FACILITIES CONSTRUCTION

May 2017

2014 BOND PROJECTS

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL)

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – Joeris General Contractor GMP - $110,800,000.00 Construction Period – October 2014 – May 2017 Construction Status: 96% Complete Project Scope – New 2800 Student High School

Site grading, utilities and landscaping. Interior CMU walls, drywall framing, electrical, plumbing, and HVAC

installation, Window installation, interior painting, exterior brick veneer. Fire pump, concrete drives and parking areas in progress. Punch ongoing.

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Aerial (March 20, 2017)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) Front Entrance

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (May 12, 2017)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (May 12, 2017)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (May 12, 2017)

HARLAN HIGH SCHOOL (Formerly KALLISON RANCH HIGH SCHOOL) (April 11, 2017)

KALLISON ELEMENTARY SCHOOL (KALLISON RANCH #2 ELEMENTARY)

Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – Guido Construction Contract Amount - $24,640,000.00 Construction Period – March 2016 – May 2017 Construction Status: 75% Complete Project Scope – New 800 Student Elementary School

Masonry, brick, metal steel framing and sheetrock, MEP ductwork and roofing, ceramic tile in kitchen/restrooms, millwork install, paint/texture in progress.

KALLISON ELEMENTARY SCHOOL Aerial (May 16, 2017)

KALLISON ELEMENTARY SCHOOL Front Entrance

KALLISON ELEMENTARY SCHOOL (May 12, 2017)

KALLISON ELEMENTARY SCHOOL (May 12, 2017)

KALLISON ELEMENTARY SCHOOL (May 12, 2017)

KALLISON ELEMENTARY SCHOOL (May 12, 2017)

KALLISON ELEMENTARY SCHOOL (May 16, 2017)

KALLISON ELEMENTARY SCHOOL (May 16, 2017)

MORA ELEMENTARY SCHOOL (GROSENBACHER AREA ES)

Architect – Noonan Rittiman Project Architect – John Rittiman NISD Project Manager – Chris Parker Contractor – DL Bandy Contract Amount - $24,465,000 Construction Period – March 2017 – May 2018 Construction Status – (5% Complete) Project Scope – New 800 Student Elementary School

(Prototype of Boldt ES and Cole ES) Site work and building pad in progress.

MORA ELEMENTARY SCHOOL (Prototype of Boldt ES and Cole ES)

MORA ELEMENTARY SCHOOL (April 2017)

MORA ELEMENTARY SCHOOL (April 2017)

MORA ELEMENTARY SCHOOL (April 2017)

MORA ELEMENTARY SCHOOL (April 2017)

ADDITIONS AND RENOVATIONS

PROJECTS IN PROGRESS

GLENOAKS ELEMENTARY - Administration Upgrades/Security Lobby

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – McGoldrick Construction Co. Contract Amount - $3,750,000.00 Construction Period – June 2016 – June 2017 Construction Status: 80% Complete Project Scope – New Administration Building

Roof, interior walls and masonry, HVAC, plumbing, electrical, brick, glazing, ceiling grid & tech cabling, painting & finishes in progress.

GLENOAKS ELEMENTARY (Rendering of Front Elevation)

GLENOAKS ELEMENTARY Administration Upgrades (May 12, 2017)

GLENOAKS ELEMENTARY Administration Upgrades (May 12, 2017)

GLENOAKS ELEMENTARY Administration Upgrades (May 12, 2017)

NORTHSIDE ACTIVITY CENTER RENOVATIONS

Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – O’Haver Contractors Co. Contract Amount - $5,319,485.00 Tentative Construction Period – February 2017 – January 2018 Construction Status – 7% Complete Project Scope – Addition/Renovation

Foundation and Site utilities work in progress.

NORTHSIDE ACTIVITY CENTER RENOVATIONS (May 15, 2017)

NORTHSIDE ACTIVITY CENTER RENOVATIONS (May 15, 2017)

NORTHSIDE ACTIVITY CENTER RENOVATIONS (May 15, 2017)

PAUL TAYLOR FIELD HOUSE RENOVATIONS

Architect – Garza Bomberger Architects Project Architect – Roy Lewis NISD Project Manager – Thomas Curiel Contractor – Stoddard Construction Management, Inc. Contract Amount - $3,400,000.00 Construction Period – February 2017 – August 2017 Construction Status – 16% Complete Project Scope – ADA Interior/Exterior Renovations

Demolition and Foundation framing work underway, elevator shaft work underway, plumbing work in Progress.

PAUL TAYLOR FIELD HOUSE RENOVATIONS (May 10, 2017)

PAUL TAYLOR FIELD HOUSE RENOVATIONS (May 10, 2017)

PAUL TAYLOR FIELD HOUSE RENOVATIONS (May 10, 2017)

CHILD NUTRITION CENTER Center Renovation

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – James Evans Contractor – Workman Commercial Contract Amount - $5,726,500.00 Construction Period – July 2016 – May 2017 Construction Status: 97% Complete Project Scope – Warehouse Renovation

Contract in progress. Renovation funded from Child Nutrition 2016 Growth & Improvement funds and 2010 Bond Savings.

New switch gear being installed and new CPS transformer on its way.

Walk-in cooler/freezers, walls, racks and ceilings being installed. Condensers set. Secondary power is installed. Testing of walk-in freezer will start May 5th. Substantial completion scheduled for May 22, 2017.

CHILD NUTRITION CENTER Center Renovation (April 2017)

CHILD NUTRITION CENTER Center Renovation (April 2017)

2017 SECURITY LOBBIES at (9) ELEMENTARY SCHOOLS

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – CGC General Contractors Contract Amount - $1,293,000.00 Construction Period – June 2017 – August 2017 Project Scope – New Security Lobby for (9) Elementary Schools:

Adams Hill ES, Allen ES, Beard ES, Braun Station ES, Forester ES, Hoffmann ES, Knowlton ES, Timberwilde ES, and Villarreal ES

Notice to Proceed issued March 20, 2017

Construction scheduled to start June 5, 2017. Submittal process has commenced.

2017 SUMMER FLOORING REPLACEMENTS Carson ES, Neff MS, & Warren HS

Architect – Huckabee Architects Project Architect – Jeff Rodriguez NISD Project Manager – Chris Parker Contractor – SAFFI Contract Amount – $339,120.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Flooring

Notice of Award Issued March 29, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

COLONIES NORTH ELEMENTARY Window Upgrades / ADA Work

Architect – Huckabee Architects Project Architect – Jeff Rodriquez NISD Project Manager – Chris Parker Contractor – Central Builders Contract Amount - $2,022,000.00 Tentative Construction Period – June 2017 – October 2017 Construction Status – (0% Complete) Project Scope – Window Upgrades and ADA Work

Notice of Award Issued March 29, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

KNOWLTON ELEMENTARY Cafeteria / Kitchen Renovations / Library Addition

Architect – Pfluger Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – O’Haver Contract Amount – $2,335,100.00 Tentative Construction Period – June 2017 – November 2017 Construction Status – (0% Complete) Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library

Notice of Award Issued March 29, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

NEFF MS COMPETITION GYM FLOORING AND BLEACHERS

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – Henock Construction, LLC Contract Amount – $243,600.00 Tentative Construction Period – June 2017 – August 2017 Construction Status – (0% Complete) Project Scope – Replacement of Flooring and Bleachers

Notice of Award Issued March 29, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

GLENOAKS ELEMENTARY - Window Upgrades / ADA Work

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – Central Builders, Inc. Construction Budget - $1,100,000.00 Tentative Construction Period – June 2017 – August 2017 Construction Status – (0% Complete) Project Scope – Window Upgrades and ADA Work

Schematic Design approved by Board in January. Notice of Award issued April 26, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

GLENN ELEMENTARY School Building Replacements / Security Lobby

Architect – LPA Project Architect – Mark Oppelt / Lowell Tacker NISD Project Manager – Marilyn Sevedge Contractor – Suburban Construction Construction Budget - $6,850,000.00 Tentative Construction Period – June 2017 – August 2018 Construction Status – (0% Complete) Project Scope – Replacement of Administration/Classroom Building

Notice of Award issued April 26, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

TIMBERWILDE ELEMENTARY Cafeteria/Kitchen Renovations/Library Addition

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – Chris Parker Contractor – Workman Commercial Construction Construction Budget – $2,231,800.00 Tentative Construction Period – June 2017 – November 2017 Project Scope – Renovations and Additions to Cafeteria, Kitchen & Library

Notice of Award issued April 26, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

2017 FLOORING REPLACEMENTS Elrod, Glenn, Glenoaks, & Michael Elementary

Architect – CWS Architect Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – San Antonio Floor Finishers, Inc. Contract Budget – $133,900.00 Tentative Construction Period – June 2017 – August 2017 Construction Status – (0% Complete) Project Scope – Replacement of Flooring

Notice of Award issued April 26, 2017. Construction scheduled to start June 5, 2017. Submittal process has commenced.

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2017

HOLMES HS FINE ARTS - AUDITORIUM

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke Construction Budget - $27,000,000.00 Construction Period – June 2017 – December 2018 Project Scope – Fine Arts Building Replacement

Amendment No. 2 Signed. Building Demolition scheduled to start June 5, 2017. Abatement completed.

HOLMES HS FINE ARTS - AUDITORIUM (Rendering Perspective)

HOLMES HS FINE ARTS - AUDITORIUM (April 11, 2017)

HOLMES HS FINE ARTS - AUDITORIUM (April 11, 2017)

BOONE ELEMENTARY - Administration Upgrades, Bus/Student Canopy & Security Lobby

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – James Evans Contractor – TBD Construction Budget - $4,900,000.00 Tentative Construction Period – June 2017 – August 2018 Project Scope – Administration Upgrades, Bus/Student Walkway Canopy

Modifications Contractor submitted for May Board Approval.

GLASS ELEMENTARY Window Upgrades / ADA Work

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Chris Parker Contractor – TBD Construction Budget - $1,500,000.00 Tentative Construction Period – June 2018 – August 2018 Project Scope – Window Upgrades and ADA Work

Schematic Design and Master Plan in progress.

GLENOAKS ELEMENTARY Library and Classroom Building

Architect – NextGen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $10,000,000.00 Tentative Construction Period – June 2018 – December 2018 Project Scope – Library and Classroom Building

Schematic Design in progress.

2017 DOOR HARDWARE Glass ES, Westwood Terrace ES and Holmes HS

Architect – Chesney Morales Project Architect – Richard Morales NISD Project Manager – James Evans Contractor – TBD Construction Budget – $117,000.00 Tentative Construction Period – June 2017 – August 2017 Project Scope – Replacement of Door Hardware for Accessibility

Contractor submitted for May Board Approval.

2017 GROWTH & IMPROVEMENT

2017 ATHLETIC AREAS UPGRADES Hobby MS, Pease MS, and Taft HS

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Chris Parker Contractor – CGC General Contractors Contract Amount – $1,222,000.00 Construction Period – June 2017 – August 2017 Construction Status: 0% Complete Project Scope – Installation of Athletic Storage Mobile Shelving and

Interior Renovations. Notice of Award Issued March 29, 2017. Construction scheduled to start June 5, 2017.

JORDAN MIDDLE SCHOOL Interior Painting Project

Architect – Noonan Rittimann Project Architect – Noonan Rittimann NISD Project Manager – James Evans Contractor – Cleanology Service & Supply Construction Budget – $265,000.00 Construction Period – June 2017 – August 2017 Construction Status: 0% Complete Project Scope – Paint Interior of the School.

Notice of Award issued May 2, 2017. Painting scheduled to start June 5, 2017.

ATHLETIC STORAGE BUILDING AT TAFT HS AND JOHN JAY HS

Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – Hector Barrera Construction, LLC Contract Budget – $142,868.00 Construction Period – June 2017 – July 2017 Construction Status: 0% Complete Project Scope – Installation of Athletic Storage Buildings.

Notice of Award issued April 27, 2017. Construction Scheduled to start June 5, 2017.

2016 HAIL DAMAGE

ROOFING PROJECTS

PHASE I

LIST OF SCHOOLS – Phase I

Hail Damage Roofing Projects - In Design

Roofing Consultant – Hollon & Cannon

Beard Elementary School Contract Amount - $566,480.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement and Restoration

Carnahan Elementary School Contract Amount - $2,125,200.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement

Clark High School Contractor – Port Enterprises, LTD Contract Amount - $2,490,800.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement

LIST OF SCHOOLS – Phase I

Hail Damage Roofing Projects - In Design

Roofing Consultant – Raba Kistner

South Transportation Contractor – Cram Roofing Contract Amount - $261,920.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement

Stevenson Middle School Contractor – Cram Roofing Contract Amount - $1,904,450.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement & Restoration

LIST OF SCHOOLS – Phase I

Hail Damage Roofing Projects - In Design

Roofing Consultant – Austech

Carlos Coon Elementary School Contractor – Beldon Roofing Contract Amount - $1,409,870.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement & Restoration

Elrod Elementary School Contractor – Port Enterprises Contract Amount - $784,880.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Restoration

Fernandez Elementary School Contractor – Empire Roofing Contract Amount - $1,102,400.00 Construction Period – June 2017 – December 2017 Project Scope – Roof Replacement & Restoration

2016 HAIL DAMAGE

ROOFING PROJECTS

PHASE II

LIST OF SCHOOLS – Phase II

Hail Damage Roofing Projects - In Design

Roofing Consultant – Austech

Brauchle ES, Raba ES, and Leon Springs Elementary School Contractor – TBD Budget Amount - $896,720.00 Construction Period – December 2017 – March 2018 Project Scope – Roof Replacement & Restoration

Burke Elementary School Contractor – TBD Budget Amount - $964,120.00 Construction Period – December 2017 – March 2018

Project Scope – Roof Replacement & Restoration

LIST OF SCHOOLS – Phase II

Hail Damage Roofing Projects - In Design

Roofing Consultant – Hollon & Cannon

Connally Middle School Contractor – TBD Budget Amount - $1,637,893.00 Construction Period – December 2017 – April 2018 Project Scope – Roof Replacement & Restoration

Esparza Elementary School Contractor – TBD Budget Amount - $1,493,010.00 Construction Period – December 2017 – April 2018

Project Scope – Roof Replacement & Restoration

top related