East Davis Street Reconstruction

Virtual Public Involvement Meeting

City of Beaver Dam

August 13, 2020

Presentation Overview

• Project Team

• Project Overview

• Proposed Improvements

• Construction

• Costs

• Schedule

• City of Beaver Dam• Todd Janssen, PE – Director of Engineer

• Wisconsin Department of Transportation• Zachary Pearson, PE – SW Region Local Program Project Manager

• Project Design Consultant – MSA Professional Services• Jaime Kurten, PE – Project Manager

Project Team

Project Overview

Existing Typical Section

• Storm Sewer

• Sanitary Sewer & Water Main

• Lighting

• Sidewalks

• Signage and Pavement Marking

Proposed Improvements

Proposed Typical Section

• Right of Way/Temporary Easements will be minimized to the maximum extent possible. Easements could be needed for the following

• Grading behind new sidewalk

• Driveway tie in construction

• Construction Staging

• Closed During Construction

• Detour Route via Stone Street

• Local Access will be maintained during construction

Real Estate & Construction

Detour RouteProject

Location

• STP – Urban Funding• Eligible for 80% State/Federal and 20% Local

• 100% Local Funding for non-participating items

• Sanitary Sewer and Water Utility Improvements

• Special Assessments

• City of Beaver Dam typically assesses for a portion of the replacement of non-compliant sidewalks, replacement of driveway aprons, and street lighting to the adjacent landowner

• Preliminary Cost Estimate: $2.5 million

Project Costs and Funding

Preliminary Plan Submittal May 2020

Public Involvement August 2020

Environmental Document September 2020

60% Plans/Right of Way Plat Fall 2020

Final Plans August 1, 2021

Bid Letting December 14, 2021

Construction Summer 2022

Schedule

• Comments on the proposed design are encouraged

• Email or mail comments by August 28, 2020

• For more information contact:

City of Beaver Dam

Todd Janssen, PE – Director of Engineering

Phone: 920-887-4600x326

Email: tjanssen@cityofbeaverdam.com

Project Design Consultant – MSA Professional Services

Jaime Kurten, PE – Project Manager

Phone: 608-242-6619

Email: jkurten@msa-ps.com

Public Input and Comments