NotL AMP June 8, 2015 08/06/2015
1
David Anderson, CET
1
Draft Asset Management PlanCommittee of the Whole
June 8, 2015
Presentation Overview
• Introductions
• Background
– Provincial Requirements
• Project Approach
• State of the Infrastructure
• Financial Plan
• Asset Management Plan
• Recommendations going forward
2
NotL AMP June 8, 2015 08/06/2015
3
• Ministry of
Infrastructure
Asset Management
Defined
5
MIII Requirements for State of the Infrastructure
• State of the Infrastructure (SotI)
– Asset types
• Materials, subtypes
– Financial Accounting Valuation
• Historic
• Replacement costs
– Asset Age Distribution
• May be some difficulties with some assets
– Age of the composite asset vs the apparent age
• May estimate by material or current condition
• Asset condition using standard engineering practices
6
NotL AMP June 8, 2015 08/06/2015
4
MIII Requirements for State of the
Infrastructure
• Record of assumptions
• QA / Verification
• Supported by a database
– WorkTech Asset Manager Foundation
• Regularly Updated
– Condition Assessment Policy
– Will vary by asset group
7
Worktech Asset Manager Foundation
8
• NotL uses Worktech Asset Manager Foundation
• Can be used for any an all assets
• Budget Development, Performance Modeling, Analysis
NotL AMP June 8, 2015 08/06/2015
5
MIII Requirements -Level of Service
• Desired / Target
• Existing
• How measured?
– Operational?
– Overall Condition
– May have to have multiple measures for some assets
9
MIII Requirements- Asset Management Strategy
• Overall Asset Management Strategy should cross integrate assets
• Has to be in lock step with the financial plan
• Planned actions to include
– Non-infrastructure solutions
– Maintenance Activities
– Renewal and rehab
– Replacement
– Disposal
– Expansion
10
NotL AMP June 8, 2015 08/06/2015
6
MIII Requirements- Asset Management Strategy
• From MIII handbook
• “ The asset management strategy is the set of actions that,
taken together, has the lowest total cost - not the set of
actions that each has the lowest cost individually”
– Cross Asset Integration
• Also consider the best overall affect to asset group or groups
• Plan has to include Operating and Capital costs and activities
11
PROJECT APPROACH
12
NotL AMP June 8, 2015 08/06/2015
7
Project Approach
• 1-Documentation Review
• 2-Asset Management Policy Template
• 3- State of the Infrastructure (SotI) for assets
• 4- Development of Asset Management and Financing Strategies
• 5- Draft Asset Management Plan (staff level)
• 6- AMP Review meeting
• 7- Development of a 10 year plan and Consolidation with the Town's 10 year Capital Forecast
• 8- Final Report preparation
13
Project Approach - Asset Management Policy
14
• Council approved December
2014
• Provides direction to staff for
all assets
• As specifics are developed for
asset groups, they will be
added as appendices
NotL AMP June 8, 2015 08/06/2015
8
Project Approach
• Documentation Review
– development of the Asset Management Plan (AMP) are as follows;
– 2014 State of the Infrastructure – Roads, 4 Roads Management
Services Inc.
– 2014 Water Rate Study, DFA Infrastructure International Inc.
– 2014 Waste Water Rate Study, DFA Infrastructure International Inc.
– 2013 Structures Report, AECOM Canada Ltd.
– WorkTech Asset Manager Foundation Database, as provided by the
Town of Niagara-on-the-Lake
– 2014 Capital Budget, as provided by the Town of Niagara-on-the-Lake
15
State of the Infrastructure (SotI)
• A state of the infrastructure report was developed for all
assets in the study
• Water and Waste Water assets did not have conditions
ratings
– Condition developed based on age
• Road and Structure Assets had current condition information
16
NotL AMP June 8, 2015 08/06/2015
9
Draft AMP
• A draft AMP was developed and reviewed at the staff level
and revised March to May 2015
17
10 Year Capital Plan
• Work Plans were developed through performance models in
WorkTech Asset Manager Foundation
– Water
– Waste Water
– Roads
• Structures plan was based on 2013 AECOM
recommendations and proposed funding level
18
NotL AMP June 8, 2015 08/06/2015
10
DRAFT Asset Management Plan to Council
• Draft Report to Committee of the Whole June 8, 2015
19
STATE OF THE INFRASTRUCTURE
20
NotL AMP June 8, 2015 08/06/2015
11
SotI Overall
Asset Group Replacement Cost
Infrastructure Backlog /
Replacement Needs 1 to 10
Years
Quantity Overall Grade
Trend
Roads 188,975,800 $53,321,821 249.61 km B
Structures 25,437,832 $4,320,00038 Bridges, 19 Culverts B-
Water 211,458,210 $10,715,434 257,103m A
Waste Water 134,679,805 $610,957 125,021m A
Totals 560,537,487 $68,968,212 N/A A-
21
Table ES.1: State of the Infrastructure Summary by Asset Group
• The overall condition of the road, and W&WW assets are strongly
influenced by development that has occurred in the last 20 years,
improving the overall average. This may lead to an incorrect conclusion
regarding funding levels that are required to sustain the assets
SotI
Asset Group Poor % Fair % Good % Excellent %
Roads 12.58 6.77 29.96 50.69
Structures 7.63 7.27 2.08 83.02
Water 4.47 0.59 10.94 83.99
Waste Water 0.39 0.2 3.3 96.11
22
Table ES.2: State of the Infrastructure Condition Summary by Asset
Group and ConditionNote: Roads, Water and Waste Water condition is based on actual or estimated condition,
Structures is based on the ratio of the needs by time of need to the replacement cost.
NotL AMP June 8, 2015 08/06/2015
12
SotI –Remaining Service Life - Roads
23
SotI –Remaining
Service Life -
Structures
Figure 6.3: Remaining Design Life by Footprint – Culvert Structures
24
Figure 6.2: Remaining Design Life by Deck Area – Bridge Structures
The average age of the
bridge structures is 65 years.
The design life for the
majority of the structures is
50 years
The average age of the
culvert structures is 51
years. The design life for the
majority of the structures is
50 years.
NotL AMP June 8, 2015 08/06/2015
13
SotI –Remaining Service Life - Water
25
Water Linear Remaining Service Life –Length (m) by Time of Need
SotI –Remaining Service Life - Waste Water
26
Waste Water linear Condition and Remaining Service Life
NotL AMP June 8, 2015 08/06/2015
14
FINANCIAL PLAN
27
Sustainable Funding Requirements
Asset Type Current Funding Level
Recommended Minimum Funding
Level
Shortfall
Roads 1,748,400(average) $1,980,000 $231,600
Structures 211,200 $508,800 $297,600
Water Linear 1,368,500 2,413,000 $1,044,500
Waste Water Linear 288,250 1,571,000 $1,282,750
Totals 3,616,350 $6,472,800 $2,856,450
28
Table ES. 3: Annualized Minimum Capital / Preservation Funding RequirementsNotes: *Roads funding includes current average levy costs 2011 to 2025 equivalent to Preservation Funding
components, Gas Tax Grant and Ontario Community Infrastructure Fund (OCIF)
*OCIF Funding amount is guaranteed only for the next 3 years; if not continued there will be an additional shortfall to
deal with
*Structures funding includes current average costs 2011 to 2025
*Water and Waste Water Linear funding levels have been provided by NotL.
NotL AMP June 8, 2015 08/06/2015
15
Sustainable
Funding
Requirements
• The sustainable funding
level for assets is required
to ensure continuity in
service delivery.
• Assets replaced when
required
29
Sustainable
Funding
Requirements
30
NotL AMP June 8, 2015 08/06/2015
16
Funding Gaps –Roads and Structures
31
Table ES.4: Increased Capital /Preservation Funding Options for Roads and Structures Levy Supported
Assets ($529,200)
Option
Roads
Annual
Increase
Bridges
Annual
Increase
Total
Annual
Increase
Percentage
Increase on the
Tax Levy
Do Nothing 0 0 0 0.0%
Increase Over 5 years 46,320 59,520 105,840 1.2%
Increase over 10 years 23,160 29,760 52,920 0.6%
Increase over 15 years 15,440 19,853 35,293 0.4%
Funding Gaps - Water
32
Table ES.5: Increased Capital / Preservation Funding Options for Water Rate Supported Assets
($1,044,500)
Option Annual Increase Percentage Increase on the
Water Rates
Do Nothing 0 0
Increase over 5 years $208,900 4.51%
Increase over 10 years $104,450 2.26%
Increase over 15 years $69,633 1.50%
NotL AMP June 8, 2015 08/06/2015
17
Funding Gaps – Waste Water
33
Table ES.6: Increased Capital / Preservation Funding Options for Waste Water Rate Supported Assets
($1,282,750)
Option Annual Increase
Percentage Increase on
Rates
Do Nothing 0
Increase over 5 Years $256,550 8.99%
Increase over 10 Years $128,275 4.49%
Increase over 15 Years $85,517 3.00%
Funding Increase Recommendations
• All asset funding should be increased to sustainable levels
over 5 years
• Recommended funding for water and waste water is at the
2014 Rate Study level
34
NotL AMP June 8, 2015 08/06/2015
18
ASSET MANAGEMENT PLAN
35
Asset Management
• Asset Management by its very nature is holistic
• Asset improvement decisions in isolation is short sighted and may be more expensive in the longer term.
• Making a decision about an improvement to an asset that may be affected by, or cause an effect to other assets can add additional expense
• The ‘Building Together’ document indicates that:
‘The asset management strategy is the set of actions that, taken together, has the lowest total cost — not the set of actions that each has the lowest cost individually.’
• Recommendation going forward
36
NotL AMP June 8, 2015 08/06/2015
19
Asset Management
• Asset Management is a state of mind and a perpetual
process
• Has to be integrated into our work processes
– Daily,
– Weekly
– Monthly
– Annually
37
Typical Asset Management Plan Cycle
Page 38
Data Collection
System or Asset Group
Condition
Needs Analysis
Economic /Budget Analysis
Define Network or Assets
Implement Program
System Maintenance
$$$
NotL AMP June 8, 2015 08/06/2015
20
Annual Work Plans
• As the municipality advances the development of their Asset
Management Plan (AMP), a paradigm shift will be required
in the way that we approach management of assets.
• Traditionally, municipalities have spent a fixed amount
capital and maintenance each year.
• If assets are managed by condition, selecting the right
treatment at the right condition will cause program
fluctuation within the budget amount
• More effective use of available funding
– Improved asset group performance
39
Annual Work Plans by Asset Condition
Improve
ment
Type
Year
2015 2016 2017 2018 2019 2020 2021 2022 2023 2024
Grand
Total
CRK 81,825 44,300 500 75,600 5,600 9,525 122,850 22,225 4,300 11,350 378,075
GRR2 81,820 111,033 90,595 37,440 21,177 98,982 441,047
MICRO 5,950 7,371 6,580 26,427 7,140 7,438 15,769 12,026 88,701
PR2 108,362 449,139 311,452 388,972 353,544 475,330 2,086,799
R1 172,798 37,861 373,064 262,501 372,298 18,504 369,485 712,193 584,077 2,902,781
R2 48,296 78,363 260,093 42,857 53,571 483,180
SST 172,957 181,533 86,828 190,883 144,828 209,270 711,562 123,662 211,473 144,828 2,177,824
SST+ 259,103 259,103
SST++ 243,177 243,177
Grand
Total 1,086,518 797,146 1,039,308 743,855 903,933 1,199,875 897,496 576,381 964,912 851,263 9,060,687
40
NotL AMP June 8, 2015 08/06/2015
21
Pavement Management Strategy
Quality
41
Pavement Management
- Best Return on Investment
42
*From WorkTech Asset Manager Foundation Performance Model
NotL AMP June 8, 2015 08/06/2015
22
RECOMMENDATIONS
43
Recommendations
1. The information and budget recommendations included in
this report to further develop the corporate Asset
Management Plan.
2. Funding levels for Capital / Preservation for the respective
asset groups should be increased to the following levels
over a 5 year period.
Roads $1,980,000
Structures $508,800
Water Linear $2,413,000
Waste Water Linear $1,571,000
44
NotL AMP June 8, 2015 08/06/2015
23
Recommendations
3. Consideration should be given to creating a funding source or reserve for the roads and for structures if they do not already exist.
4. Funding should be adjusted annually to account for inflation, increase in plant and exceptional increases due to commodity pricing.
5. The cycle for review of the road system should be continued reviewing the entire system on a four year cycle.
6. The cycle for review of the structures inventory should be continued, reviewing the entire system on a two year cycle
7. A condition review and analysis cycle should be developed for the Water and Waste Water Linear Assets.
45
Recommendations
8. Rating methodologies for Water and Waste Water Assets should
be adopted.
9. NotL should consider requiring that the structure inspections
include a Bridge Condition Index (BCI) for all structures.
10. Assets within the road allowance should be linked to the road
asset ID to facilitate cross asset integration and modeling
11. Programming should be reviewed to
– Cross asset integration opportunities have been maximized
– Ensure that maintenance and preservation programs are
optimized.
46
NotL AMP June 8, 2015 08/06/2015
24
Recommendations
12. Traffic counts should be updated and repeated on a regular basis. The counting should include the percentage of truck traffic.
13. Further analysis should be undertaken on the Gravel Road system, with respect to the potential for conversion to a hardtop surface.
14. The Level of Service for the road system should be system Adequacy 60%, Physical Condition 60 and MPMP measure of Good to Very Good of 60.
15. The Level of Service for the Structures should be zero load posted structures.
16. Budgets should be adjusted annually to account for inflation, exceptional increases to specific products and plant expansion.
47
Recommendations
17. The asset management plan should be updated on an
annual basis to reflect the changes to the respective asset
groups in terms of expansion, improvements and inflation.
The funding and models should also be updated based on
current year cost experience.
48