C S 4 1 0 - B L U E G R O U P
Final Presentationcommunicate2Me
CS 410 blue Group
2
A Brief Overview
CS 410 Blue Group Spring 2009 April 2, 2009
• The Problem• Our Solution• Evaluation Plan• Funding/Budget• Risks and their mitigation
• Four Phases
o Staffingo Costs
• What is being provided and what is not• Cost to develop
• Closing Statements
May 5, 2009
CS 410 blue Group
3
Meet the Team
May 5, 2009
CS 410 blue Group
4
Overarching Problem
CS 410 Blue Group Spring 2009
Passenger needs are not addressed by mass transportation systems.
April 2, 2009May 5, 2009
CS 410 blue Group
5
Regional Transit Need Is Increasing
CS 410 Blue Group Spring 2009
Source: http://www.hrtransit.org/pdf/hrtbrochure/HRT_Brochure.pdf http://www.gohrt.com/pdf/strategicplan/Strategic%20Plan%20Final%20--%20November%202008.pdf
April 2, 2009May 5, 2009
CS 410 blue Group
6
Congestion
• Buses in the HRT System: 343
• Average bus capacity is currently only at 15%
• Severe congestion is
expected on 1,221 lane miles in Hampton Roads in 2026
Source: http://www.gohrt.com/pdf/strategicplan/Strategic%20Plan%20Final%20--%20November%202008.pdfMay 5, 2009
CS 410 blue Group
7
Preventing Congestion
May 5, 2009
CS 410 blue Group
8
May 5, 2009
CS 410 blue Group
9
Texting Efficiency
May 5, 2009
CS 410 blue Group
10
A Proposed Solution: communicate2Me
CS 410 Blue Group Spring 2009
Increase efficiency of transit authority systems by providing potential passenger information
April 2, 2009May 5, 2009
CS 410 blue Group
11
The Solution
CS 410 Blue Group Spring 2009
Needs: Information for the transit
authority to learn about:o potential customers o possible customer
frustration While remaining: Accessible, convenient,
and unobtrusive to end users
Reasonable cost for transportation companies
April 2, 2009May 5, 2009
CS 410 blue Group
12
communicate2Me
May 5, 2009
CS 410 blue Group
13
Planned Components
May 5, 2009
CS 410 blue Group
14
A Feasible Implementation
CS 410 Blue Group Spring 2009
Passengers will be provided with methods to:• Allow Bus Schedule Query via:
o Cellular Phone / Short Message Service(SMS) Texting • Have notifications of changes in schedule
o SMS notification service
Result:• Increased Passenger Awareness and Satisfaction• Increased Statistical Information for Transit Authorities
April 2, 2009May 5, 2009
CS 410 blue Group
15
Benefits
CS 410 Blue Group Spring 2009
Passengers:• Better Service• More Interaction• Greater Satisfaction
Transit Authorities• Passenger Query Statistics • Warning of Waiting Passengers• More Efficient Routes
April 2, 2009May 5, 2009
CS 410 blue Group
16
Project Goal And Objectives
• Time o Measured against baseline project plan
• Cost o Measured against budget plan per phase
• Scope o Measured against requirements document
• Quality o Measured by customer and end user satisfaction
May 5, 2009
CS 410 blue Group
17
Phase 0 - Concept Development
Milestones Problem Area DevelopmentFeasibility ResearchMilestone SchedulingWebsite DevelopmentSBIR Proposals
Acceptance Criteria
Review Board Acceptance
May 5, 2009
CS 410 blue Group
18
Phase 0 Organizational Chart
May 5, 2009
CS 410 blue Group
19
Phase I - Prototype Development
Milestones
Prototype SpecificationsTest PlanUser ManualsProposalPrototype Construction Demonstration
Acceptance Criteria
Review Board Acceptance
May 5, 2009
CS 410 blue Group
20
{phase i} - Organizational Chart
May 5, 2009
CS 410 blue Group
21
Phase I - Prototype Components
May 5, 2009
CS 410 blue Group
22
{phase i} - Financials
May 5, 2009
CS 410 blue Group
23
Phase I - Hardware Requirements
May 5, 2009
CS 410 blue Group
24
Phase II - Organizational Chart
May 5, 2009
CS 410 blue Group
25
Phase II - Critical Design
Milestones
Web InterfaceWeb Message Algorithm
SMS Gateway Development
Algorithm DevelopmentAlgorithm Testing
Transit InterfaceInterface Test
Acceptance Criteria
Interfaces with Google Transit
Receives SMS Messages
Passes Tests
Connects with Transit Authority's Systems
May 5, 2009
CS 410 blue Group
26
Phase II - Major Components
May 5, 2009
CS 410 blue Group
27
{phase ii} - Financials
May 5, 2009
CS 410 blue Group
28
Phase II - Hardware Requirements
hardware qty cost Total SMS Server 2 $1000. $2,000Web Server 1 $2000. $2,000Algorithm Server 2 $2000. $4,000SMS Service / Credits (yearly) 1 $36,000 $36,000 overall hardware costs $44,000
May 5, 2009
CS 410 blue Group
29
{phase iii} - Production & Beyond
Milestones
Support Current Installations Improvement: Modifications to Interface Improvements to Algorithm
Acceptance Criteria
Market Penetration Market Acceptance
Profitability
May 5, 2009
CS 410 blue Group
30
{phase iii} - Organizational Chart
May 5, 2009
CS 410 blue Group
31
{phase iii} - Financials
May 5, 2009
CS 410 blue Group
32
In The Box
• Service to set up and maintain: o Short Messaging Service gatewayso Web serverso Application servers
• Algorithm to communicate between end users and transit authorities
May 5, 2009
CS 410 blue Group
33
Not In The Box
• Buses• Wireless communication between buses
and Transit Center• Tracking system for buses (GPS, RFID)
May 5, 2009
CS 410 blue Group
34
Who Is The Customer?
Initial customers: Transportation • Hampton Roads Transit (HRT)• Metropolitan Transportation Authorities
May 5, 2009
CS 410 blue Group
35
Current Competition
CS 410 Blue Group Spring 2009 April 2, 2009May 5, 2009
CS 410 blue Group
36
Risks & Pitfalls
1. Interoperability problems
2. Latency Issues3. Abuse of the system4. SMS message costs 5. Down Time6. Phone incompatibility7. Transit operator
ignoring system
May 5, 2009
CS 410 blue Group
37
Risk Mitigation
Interoperability: • Direct Communication with each Transit Authority's
technicians Latency:• Optimize Incoming SMS Processing Time• Synchronize Driver Updates based on Position
Abuse of the System:• No way to mitigate without tracking passengers
Transit Operator Ignoring System:• Education• Tracking of Requests to Pickups
May 5, 2009
CS 410 blue Group
38
Funding
Grants.gov• Innovative Small Research Projects to Advance Public
Transportation Planning $ 750,000• State Operating Assistance
$840,550References: http://www07.grants.gov/search/search.do;jsessionid=MgLfJcyflkGLZ3tLyF7Rj6GTJrn0PfTyyFvzsQtD1TNF10WzQqWS!-802466050?oppId=46140&flag2006=false&mode=VIEWhttp://www.gohrt.com/pdf/budget/Budget_2009.pdf
May 5, 2009
CS 410 blue Group
39
Budget
Funding Source: Department of Transportationo SBIR – Phase 1: $100,000o SBIR – Phase 2 : $650,000o SBIR –Phase 3: Small Business Loan/Venture Capatilists
http://www07.grants.gov/search/search.do;jsessionid=MgLfJcyflkGLZ3tLyF7Rj6GTJrn0PfTyyFvzsQtD1TNF10WzQqWS!-802466050?oppId=46140&flag2006=false&mode=VIEW
http://www.gohrt.com/pdf/budget/Budget_2009.pdf
May 5, 2009
CS 410 blue Group
40
Price Point
May 5, 2009
CS 410 blue Group
41
Cost To Develop
• Phase 0:o Free
• Phase 1:o Hardware Resources - $4,300.00o Personnel Resources - $14,525.00
• Phase 2:o Hardware Resources - $44,000.00o Personnel Resources - $443,114.00
• Phase 3:o Hardware Resources - $37,200.00o Personnel Resources - $286,860.00
Total - $829,999.00
May 5, 2009
CS 410 blue Group
42
Assumptions: minimum of 5 new customers per year while maintaining current customers.
Revenue
May 5, 2009
CS 410 blue Group
43
Closing Statements
Current Systems are One-Way: • Informing the passengers, not Interacting with them.
communicate2Me promises to:• Connect Passengers with Information• Connection Transit Authorities with Potential Customers
Each phase is feasible in terms of:• Cost• Requirements• Staffing
let's do it!
communicate2MeMay 5, 2009
CS 410 blue Group
44
Any Questions?