construction of segmental concrete bridge
Post on 03-Jun-2018
245 Views
Preview:
TRANSCRIPT
-
8/12/2019 Construction of Segmental Concrete Bridge
1/72
METHOD OF CONSTRUCTION OF
SEGMENTAL CONCRETE BRIDGE
By ,
P P AMBEDKAR
-
8/12/2019 Construction of Segmental Concrete Bridge
2/72
Objective Of Dissertation work
Construction of segmental bridge involves use of different machineries
and requires huge amount of skilled manpower. Hence the intention of
dissertation is to study the Methods & techniques used in Construction
of Segmental Bridge by Under Slung Methodwhich consist of
following activities.
1.Construction of Sub-structure
2. Construction of super-structure
-
8/12/2019 Construction of Segmental Concrete Bridge
3/72
Development of precast segmental bridge construction
First segmental bridge
Second segmental bridge
Segmental bridges in India
-
8/12/2019 Construction of Segmental Concrete Bridge
4/72
What is segmental construction
Pier
PC segments
Prestressing cables
-
8/12/2019 Construction of Segmental Concrete Bridge
5/72
Method of construction of segmental bridge
1.Cast-in-Place Segmental Construction (Balance Cantilever method)
Bridge across the Lahn River in Germany
-
8/12/2019 Construction of Segmental Concrete Bridge
6/72
2. Precast Segmental Construction
Flyover at Agriculture College Pune
-
8/12/2019 Construction of Segmental Concrete Bridge
7/72
General design consideration
Principal Dimension of Segment
W = Top Slab width
D = Construction depth
B = Bottom slab width
L = Segment length
-
8/12/2019 Construction of Segmental Concrete Bridge
8/72
-
8/12/2019 Construction of Segmental Concrete Bridge
9/72
Construction of substructure
Cast-in-situ Pile
Detailed breakdown of activities is mentioned below
1. Setting Out
2. Removal of Overburden3. Driving Permanent Liner
4. Boring / Chiseling
5. Reinforcement Cage Lowering
6. Concreting
-
8/12/2019 Construction of Segmental Concrete Bridge
10/72
1. Setting Out
-
8/12/2019 Construction of Segmental Concrete Bridge
11/72
2. Removal of overburden
3. Driving permanent liner
Tripod
Driving cap
Drivingmonkey
Liner
-
8/12/2019 Construction of Segmental Concrete Bridge
12/72
4. Boring/ Chiseling
BAILER
CHISEL
-
8/12/2019 Construction of Segmental Concrete Bridge
13/72
BailerExcavated mud
Removing of excavated material with help of bailer
-
8/12/2019 Construction of Segmental Concrete Bridge
14/72
5. Reinforcement cage lowering
6.Concreting
Chute
Funnel
Tremie pipe
-
8/12/2019 Construction of Segmental Concrete Bridge
15/72
Major Equipment Required
1) F 35d/d winch - 4 no2) Pile driving tools & accessories - 4 set
3) Tripod - 4 set
4) Generator 70 KVA - 2 no
5) Welding machine - 2 no
6) Concreting equipments - 2 set
7) Batching Plant - 1 no
-
8/12/2019 Construction of Segmental Concrete Bridge
16/72
TIME CYCLE
Sr.No. Activity Duration
1 Road breaking/removal of top overburden/
Identification of utility services.
2 days
2 Positioning tripod / winch 2 hours
3 Survey & setting out 2 hours
4 Permanent liner driving/ boring 20 hours
5 Chiseling(6m @ 0.1m/hour) 60 hours
6 Cage lowering 2 hours
7 Tremie Pipe lowering/flushing 2 hours
8 Concreting 3 hours9 Removal of tripod/winch 2 hours
Total time for pilling 93 hours
There fore total time for one pile @ 20hours per day
working
4.5 days
-
8/12/2019 Construction of Segmental Concrete Bridge
17/72
Construction Of Pile Cap
Detailed breakdown of activities is mentioned below
1. Clear area for excavation and marking
2. Exaction up to pile cap bottom level
i. Excavation in soft soil
ii. Chiseling in hard strata
3. Simultaneously chipping of pile
4. Preparation of bed with PCC
5. Cutting and bending and preparation of reinforcement
cage
6. Shuttering for pile cap
7. Concreting
-
8/12/2019 Construction of Segmental Concrete Bridge
18/72
1. Clear area for excavation and marking
2. Exaction up to pile cap bottom level
i. Excavation in soft soilii. Chiseling in hard strata
3. Chipping of pile
Bottom of
Pile cap Pile chipping by jack
hammer
-
8/12/2019 Construction of Segmental Concrete Bridge
19/72
4. Preparation of bed with PCC
Bed preparation
for pile cap by
laying PCC
-
8/12/2019 Construction of Segmental Concrete Bridge
20/72
5. Cutting and bending and preparation of reinforcement
cage
Pile reinforcement
bar
Tying ofreinforcement
-
8/12/2019 Construction of Segmental Concrete Bridge
21/72
6. Shuttering
7. Concreting of pile cap
Shuttering
Haizen cloth for
curing
-
8/12/2019 Construction of Segmental Concrete Bridge
22/72
MAJOR EQUIPMENTS REQUIRED
1. JCB Excavator 1 No.
2. Dumper 1 No.
3. Breaker (Jack hammer) 2 Nos.
4. Bar bending and cutting machine 1 No.5. Concrete batching plant 1 No.
6. Transit Mixer 2 Nos.
7. Needle vibrators (60 mm) 2 Nos.
-
8/12/2019 Construction of Segmental Concrete Bridge
23/72
TIME CYCLESr.No. Activity Duration
1 Waiting period for curing of pile 7 Days
2 Clearing area, survey and marking for excavation 2 Hours
3 Excavation in soft soil 12 Hours
4 Chiseling in hard rock 2 Days
5 Cutting and removing liner 4 Hours
6 Chipping piles up to pile cap bottom level PCB) 4 Days
7 Preparation of bed with PCC as leveling course 8 Hours
8 Reinforcement cutting, bending and fabricating cage 1 Day
9 Placing and fixing shuttering 3 Hours
10 Concreting 1 Hour
Total time = 8.5 days
-
8/12/2019 Construction of Segmental Concrete Bridge
24/72
Construction of Pier
Job breakdown1. Cutting, and bending of reinforcement
2. Preparation of reinforcement cage
3. Casting Pier starter
4. Erection of staging and simultaneously fixing
shutters
5. Concreting of pier
6. De-shuttering and dismantling staging
7. Curing
-
8/12/2019 Construction of Segmental Concrete Bridge
25/72
1. Cutting, and bending of reinforcement & preparation of
reinforcement cage
2.CastingPierstarter3. Erection of staging and simultaneously fixing shutters
Pier shutter
Staging for supporting pier shutter
& providing working platform at
top for concreting
-
8/12/2019 Construction of Segmental Concrete Bridge
26/72
4. Concreting of pier
5. Curing
MAJOR EQUIPMENTS REQUIRED
1. HM 101 Crane -1 No
2. Bar bending and cutting machine-1 No.
3. Concrete batching plant -1 No.
4. Transit Mixer - 2 Nos.5. Concrete Pump -1 No.
6. D.G. Set -1 No.
7. Compressor - 2 Nos.
8. Needle vibrators (60 mm) - 2 Nos.
-
8/12/2019 Construction of Segmental Concrete Bridge
27/72
TIME CYCLE
Sr. no. Activity Duration
1 Cutting and Bending Reinforcement 2 Days
2 Tying and Cage Preparation 1 Day
3 Casting Starter and Curing 2 Hrs.
4 Staging and Simultaneously Shuttering 1 Day
5 Concreting 3 Hrs.
6 Waiting till achieving strength for deshuttering 1 Day
7 Deshuttering 12 Hrs.
8 Curing 28 Days
Total time required excluding curing = 3 days
-
8/12/2019 Construction of Segmental Concrete Bridge
28/72
CONSTRUCTION OF APPROCHES
Construction of approach involve two major activity that are
as follows:
i) Construction of Abutment wall.
ii) Construction of Wing wall (Retaining wall)
-
8/12/2019 Construction of Segmental Concrete Bridge
29/72
Types of abutment:
Masonry abutments:
RCC abutments:
-
8/12/2019 Construction of Segmental Concrete Bridge
30/72
R.C.C Abutments
In this case abutment wall is directly rest over raft /pile foundation.
Whole abutment wall made of rich mix concrete. Abutment wall
construction involves following activity:
1. Cutting, and bending of reinforcement
2. Preparation of reinforcement cage
3. Casting abutment starter
4. Erection of staging and simultaneously fixing
shutters
5. Concreting of abutment.
6. De-shuttering and dismantling staging
7. Curing
-
8/12/2019 Construction of Segmental Concrete Bridge
31/72
Staging
arrangement
Shuttering
RCC Abutment
-
8/12/2019 Construction of Segmental Concrete Bridge
32/72
The wings walls are of masonry or RCC masonry, now days wings wall are constructed
with new technique that is Geosynthetic Soil Retaini ng wallin which precast RCC
panel is used. The advantage of this construction system is given below.
1. It requires very limited construction space compared to the conventional wall
systems.
2. The completed structure occupies less space compared to the conventional wallsystems.
3. By using a facing of high rigidity, the stability of the wall system is increased while the
deformation is minimized.
4. The geosynthetic layers are closely spaced so that a wide range of backfill can be
used without affecting performance.
Wing wall
-
8/12/2019 Construction of Segmental Concrete Bridge
33/72
Component of part of GSR Wall
1.Concrete leveling Pad:
2.Precast concrete facing panels
3.Joint material
4.Geogrids
5.Backfill
-
8/12/2019 Construction of Segmental Concrete Bridge
34/72
Construction of Superstructure
Construction of Superstructure of segmental bridge involves two
major activities that are as follows:
1) Segment Casting
2) Segment Erection
Different method of segment casting:
1)Long line casting
2)Short line casting
-
8/12/2019 Construction of Segmental Concrete Bridge
35/72
Long line casting
-
8/12/2019 Construction of Segmental Concrete Bridge
36/72
Short line casting
-
8/12/2019 Construction of Segmental Concrete Bridge
37/72
Segment casting involves following activities
1) Base mould preparation
2) Surveying and marking
3)Reinforcement cage leveling
4)Lowering and positioning stopend
5)Placing and fixing inner formwork
6)Concreting and finishing
7)Deshuttering of inner formwork and stopends
8)The segment used for match casting is then placed in the stacking yard and the newlycasted segment is used for next match casting.
-
8/12/2019 Construction of Segmental Concrete Bridge
38/72
1)Pre-cast Bed Survey and Setting out of moulds as per
the co-ordinates.
-
8/12/2019 Construction of Segmental Concrete Bridge
39/72
2)Changing/re-fixing of linermaterial where required and
cleaning of beds.
RUBBER LINER
3)Surveying and marking
4)Reinforcement cage lowering:
LIFTING FRAME
REINFORCEMENT CAGE
EOTCRANE
-
8/12/2019 Construction of Segmental Concrete Bridge
40/72
5)Lowering and positioning stopend:
Turn buckels
False work
Stopend
REINFORCEMENT CAGE
-
8/12/2019 Construction of Segmental Concrete Bridge
41/72
6. Placing and fixing inner-
formwork:
Inner formwork
7.Concreting and finishing:
-
8/12/2019 Construction of Segmental Concrete Bridge
42/72
8.Deshuttering INF& Stopend:
9. Lifting and stacking of segments:
MAJOR EQUIPMENTS REQUIRED FOR SEGMENT
CASTING
1) EOT 120T Capacity - 1 No.
2) Welding Machine - 2 No.
3) Gas-cutting Equipment - 2 No.
3) Concreting Equipments - 2 Sets
4) Batching Plant - 1 No.
5) Transit Mixer - 2 No.
-
8/12/2019 Construction of Segmental Concrete Bridge
43/72
TIME CYCLESr. No. Activity Description Time
Required
in Hrs.
1 Base mold cleaning, rectification of rubber liner and applying
POP
6
2 Survey and marking 1
3 Lowering reinforcement cage 1/2
4 Lowering and aligning stopend with jacks and knuckle bolts 1
5 Placing and fixing inner-formwork 8
6 Concerting and finishing 3
7 Curing till deshuttering stopend 248 Deshuttring stopend 2
9 Curing till deshuttering inner-formwork 46
10 Lifting and stacking segment 1
Total time= 92 Hrs
-
8/12/2019 Construction of Segmental Concrete Bridge
44/72
Segment Erection
Probably the most significant classification of segmental bridges is bymethod of construction. Although construction methods may be varied as
ingenuity of the designers and the contractor they fall into two basic
categories:
1) Cast-in-Place segmental construction. (Balance Cantilever method)
2) Precast segmental construction.
-
8/12/2019 Construction of Segmental Concrete Bridge
45/72
-
8/12/2019 Construction of Segmental Concrete Bridge
46/72
Precast segmental construction
1)Segment erection by Crane
2) Segment erection byWinch and Beam
-
8/12/2019 Construction of Segmental Concrete Bridge
47/72
3)Launching Gantry(Over head method)
4)Segment erection by Under-slung
method
-
8/12/2019 Construction of Segmental Concrete Bridge
48/72
Segment erection by Under Slung Method
Segment erection involves following activities
1. Survey and Barricading
2. Erection of EOT
3. Fabrication and erection of staging
4. Erect sliding trolley with jack arrangement5. Launch precast segments
6. Temporary pre stressing of segments
7.Permanent pre stressing
-
8/12/2019 Construction of Segmental Concrete Bridge
49/72
1. Survey and Barricading
2. Erection of EOT
Rail track alignment
EOT crane of 125 tone
capacity
-
8/12/2019 Construction of Segmental Concrete Bridge
50/72
3. Fabrication and Erection of Staging
Main girder
Seating girder
Concrete block
Cribs
Bracing
-
8/12/2019 Construction of Segmental Concrete Bridge
51/72
4. Erect Sliding Trolley with Jack Arrangement
Screw jacks arrangement
with pot bearing
Main girder
Tie box
-
8/12/2019 Construction of Segmental Concrete Bridge
52/72
-
8/12/2019 Construction of Segmental Concrete Bridge
53/72
Inside temporary prestressing
-
8/12/2019 Construction of Segmental Concrete Bridge
54/72
8. Bearing Installation
-
8/12/2019 Construction of Segmental Concrete Bridge
55/72
-
8/12/2019 Construction of Segmental Concrete Bridge
56/72
C S d
-
8/12/2019 Construction of Segmental Concrete Bridge
57/72
Case Study
NAME OF PROJECT:
PUNE FLYOVER ATUNIVERSITY CIRCLE
& AGRICULTURE COLLAGE.
SITE ADDRESS:
GANESHKHIND ROAD,
UNIVERSITY CIRCLE,
PUNE 411 007
NAME OF CONTRACTOR:
AFCONS INFRASTRUCTURE LIMITED
NAME EMPLOYER:
MAHARASTRA STATE ROAD
DEVELOPMENT CORPORATION
NAME CONSULTANT:
DAR CONSULTANTS (U.K) LTD.
in association with
DAR CONSULTANTS (I) PVT. LTD
-
8/12/2019 Construction of Segmental Concrete Bridge
58/72
-
8/12/2019 Construction of Segmental Concrete Bridge
59/72
UNIVERSITY CIRCLE JUNCTION:
GENERAL FEATURES OF UNIVERSITY CIRCLE FLYOVER
1) Length = 700 M between abutments
2) Carriageway = Single three lane carriageway
3) Foundation = Bored cast-in situ piles resting on rock
4) Substructure = RCC Piers
5) Superstructure = Segmental, Deck width 12 M
-
8/12/2019 Construction of Segmental Concrete Bridge
60/72
AGRICULTURE COLLEGE JUNCTION
GENERAL FEATURES OF AGRICULTURE COLLEGE FLYOVER
1) Length = 210 M between abutments
2) Carriageway = Dual two lane carriageway
3) Foundation = Bored cast-in situ piles resting on rock
4) Substructure = RCC Piers
5) Superstructure = Segmental, Deck width 16.4 M
-
8/12/2019 Construction of Segmental Concrete Bridge
61/72
The pre-casting Yard includes the following:
Casting Bay : For casting deck segments.
Curing Yard : For curing deck segments.
Stacking Yard : For stacking deck segments.
Reinforcement Yard : For fabrication of reinforcement of all structural elements
like pile, pile cap, pier, precast segment, etc.
Casting, Curing & : For casting, curing & stacking of Parapet, Retaining
Stacking Bay wall & Kerbs.
Fabrication workshop: For fabrication of structural steel for shuttering,
supportive elements & temporary works.
Mechanical workshop : For fabrication of tie rod
CLASSIFICATION OF SEGMENTS
-
8/12/2019 Construction of Segmental Concrete Bridge
62/72
No TypeSegment
widthLocation & Function
1
End Diaphragm (ED) 1.45 ED rest on Abutment. It also has a
downstand that enables it to sit onbearings. It has a wall ... It houses
coupler cones for pre-stressing
cables which are locked here.
2Adjacent to End Diaphragm
(EDA)
2.095It is located adjacent to ED segment.
3 Internal Diaphragm (ID)
2
ID segment rest on all the piers except
expansion piers.
4Standard Segment(SS) 2.725 There are 3 nos. SS in the middle of
every span.
5
Coupling segment stressing
end (CSS)
2.917 CSS segment last segment of
intermediate span which has
stressing
6Coupling segment coupling
end (CSC)
2.917 CSC Segment is starting segment of
next span
-
8/12/2019 Construction of Segmental Concrete Bridge
63/72
TYPICAL SECTION THROUGH DECK SEGMENT (CS) 16.4M WIDE
-
8/12/2019 Construction of Segmental Concrete Bridge
64/72
SEGMENT ERECTIONThere are 3 types of spans to be erected i.e.:
Type A-Beginning span of each bridge unit,
Type B-Internal spans,
Type C- End of each unit.
Type A has 13 segments to be erected with an End diaphragm at the start of
the span. And a CSS segment at the end of the span.
Type B Span start with CSC segment & end with CSS segment.
Type C Span start with CSC segment & end with ED segment.
-
8/12/2019 Construction of Segmental Concrete Bridge
65/72
-
8/12/2019 Construction of Segmental Concrete Bridge
66/72
For erection of 16.4 m wide segment involves following activities
1. Survey and Barricading
2. Erection of EOT
3. Fabrication and erection of staging
4. Erect sliding trolley with jack arrangement
5. Launch precast segments
6. Temporary pre stressing of segments
7. Permanent pre stressing
MAJOR EQUIPMENTS DEPLOYED
-
8/12/2019 Construction of Segmental Concrete Bridge
67/72
MAJOR EQUIPMENTS DEPLOYED
1) EOT 60T Capacity - 1 No.
2) EOT 120 T capacity - 1 No.
3) Service crane PH 320 - 2 No
4) JCB Excavator -
2 Nos.
5) Trailer of 40 T capacity - 3 No.
6) Trailer of 100 T capacity - 1 No.
Labour required for segment erection including staging& gluing :
Welder = 01
Grinder = 01
Gas cutter = 01
Skilled labour = 17
Unskilled labour = 10
TOTAL NO. = 30
-
8/12/2019 Construction of Segmental Concrete Bridge
68/72
-
8/12/2019 Construction of Segmental Concrete Bridge
69/72
Following were the main reasons to delay in the completion of project
Land acquisition problem
Improper matching of segment
Delay in decision making
Labour strike
Delay in approval of drawings from consultant
Delay in diversion of utilities
-
8/12/2019 Construction of Segmental Concrete Bridge
70/72
CONCLUSION
After studying detail procedure segmental construction that
segmental bridges posses following advantages
Rapid erection of superstructure.
High quality & high strength of concrete can be achieved.
Whenever we need to allow traffic underneath even during
construction.
The structural geometry may be adopted to any horizontal or vertical
curvature or any roadway super-elevation.
Concrete shrinkage & creep substantially reduced.
Segmental construction relatively insensitive to weather condition.
Enhanced durability of bridge.
Segmental bridge reveals following disadvantages
-
8/12/2019 Construction of Segmental Concrete Bridge
71/72
Segmental bridge reveals following disadvantages
Need for higher level of technology in design
Necessity for a high degree of dimensional control.
The possible solution to the problems discussed in the case
study can be enlisted as follows:
Perfect matching of segment at site can be achieved by considering vertical &
horizontal alignment of bridge profile at the time of segment casting.
Whenever the segments are not matched properly considerable time is lost in
chipping out the segment faces. Hence the segment casting should be done
accurately in accordance with drawings.
-
8/12/2019 Construction of Segmental Concrete Bridge
72/72
Thank You