Status report on MicroMegas

mechanics

CERN PH/DT

30/01/14Francisco Perez Gomez CERN PH/DT

Concept remind Vacuum table manufacturing and

measurements MM panels design Construction of the first panel

◦ Measurements and results Status and future plans

30/01/14Francisco Perez Gomez CERN PH/DT

Content

A sandwich of two soft skin is glued without mechanical constraints.

A sandwich is:o One glass fibre skin (0.5mm)o Aluminium honeycomb surrounded with an aluminium frameo Second glass fibre skin (0.5mm)

Sandwich schematic view

Francisco Perez Gomez CERN PH/DT

Concept (1/2)

30/01/14

Manufacturing concepto The skins are sucked with two vacuum tableso The vacuum table surfaces are perfectly flato The vacuum table surfaces are set in parallel position

Francisco Perez Gomez CERN PH/DT

Concept (2/2)

30/01/14

Dimensions: 1300X600 Manufactured at CERN Use granite table (flatness

<10 mm) as mould Outer surface: Epoxy gel coat

‘’EP Gel coat Weiβ’’ (1+1 reinforced layer).

Structural layer: Glass fibre “Glasgewebe 92150 FK-144 345g/m2 Leinwand’’ + AXSON Epolam 5015 (5 layers).

4 perforated sides aluminium honeycomb.

Araldite 2011

Vacuum table components

30/01/14Francisco Perez Gomez CERN

PH/DT

Francisco Perez Gomez CERN PH/DT

Vacuum table exploded view

Gel coat + Glass fibre (3.5mm)

Glass fibre (3mm)

Perforated Al Honeycomb (60mm)

Al profile (60X30mm)Al inserts

(Ø40mm)30/01/14

Francisco Perez Gomez CERN PH/DT

MM Vacuum table (1300mmX600mmX60mm)

30/01/14

Francisco Perez Gomez CERN PH/DT

Vacuum Table Cross section

Perforated Al honeycomb

30/01/14

Francisco Perez Gomez CERN PH/DT

Vacuum table inserts

30/01/14

Francisco Perez Gomez CERN PH/DT

Vacuum table QC

CERN Metrology lab CERN PH/DT

Temperature: 20°C Planarity : 0.077mm

Temperature : 21°C Planarity : 0.08mm

Temperature : 22.5°C Planarity : 0.03mm

There’s a temperature influence on flatness to be taken into account (work at constant temperature ± 0.2°C).

30/01/14

Francisco Perez Gomez CERN PH/DT

Reference holes on boards for alignment Ultem plugs to avoid drilling panels after

assembly All plugs are precisely pre-glued on the

board using a dedicated tool Aluminium frame pre-assembled on tool Aluminium honeycomb Araldite 2011 is the best candidate for

gluing Panel manufacturing in one shot

MM panel Design

30/01/14

Francisco Perez Gomez CERN PH/DT

4 reference holes.

Assembly tool

30/01/14

Francisco Perez Gomez CERN PH/DT

4 reference holes.

Board alignment on assembly tool

30/01/14

Francisco Perez Gomez CERN PH/DT

Ref.

Ref.

Board Alignment

30/01/14

2 pins Ø5g6 X Ø6,5g6

Francisco Perez Gomez CERN PH/DT

Ø5.50

Ø5.0

Reference plugs gluing

Ø5.50

30/01/14

Francisco Perez Gomez CERN PH/DT

Reference plugs gluing

Alignment pin

Reference plug glued

Cyanoacrylate 3M

EC50

30/01/14

Francisco Perez Gomez CERN PH/DT

Ref.

Spacer

Board

Alignement

All plugs glued

30/01/14

Francisco Perez Gomez CERN PH/DT

Ref.

Board installation and indexation on vacuum table

… vacuum pump ON

30/01/14

Francisco Perez Gomez CERN PH/DT

Aluminium frame assembly

30/01/14

Francisco Perez Gomez CERN PH/DT

2 reference holes per profile

Aluminium frame assembly

30/01/14

Francisco Perez Gomez CERN PH/DT

Aluminium frame installation

30/01/14

Francisco Perez Gomez CERN PH/DT

Honeycomb installation

30/01/14

Francisco Perez Gomez CERN PH/DT

Ref.

Ref.

2nd board installation on 2nd VT

30/01/14

Francisco Perez Gomez CERN PH/DT

Vacuum Table Ref.

Vacuum Tables alignment

30/01/14

Francisco Perez Gomez CERN PH/DT

Vacuum tables alignment

Precision shims (11,6mm)

30/01/14

Francisco Perez Gomez CERN PH/DT

Polymerisation

30/01/14

Francisco Perez Gomez CERN PH/DT

Real Assembly of the first panel

30/01/14

30/01/14Francisco Perez Gomez CERN

PH/DT

Real assembly of the first panel

Francisco Perez Gomez CERN PH/DT 30/01/14

Real Assembly of the first panel

Francisco Perez Gomez CERN PH/DT

Real Assembly of the first panel

30/01/14

Results….

Upper side view Some measurements

Top side flatness: 160µm (max-min)

Bottom side flatness: 90µm (max-min)

30/01/14Francisco Perez Gomez CERN

PH/DT

30/01/14Francisco Perez Gomez CERN

PH/DT

Results I Planarity: 40 µm (rms)

30/01/14Francisco Perez Gomez CERN

PH/DT

Results II Planarity: 22 µm (rms)

Idea: Produce a spacer made from several pieces.

Straight pieces have the same profile with different lengths for mass production

Two symetric models of corner piecesTwo ref holes/ element for alignment

Use granite table in order to obtain a flat, parallel and precise surface for the gluing of the mesh

Liquid glue (Axson Epolam 5015) for the mesh gluing

Use “capillary effect”

Francisco Perez Gomez CERN PH/DT

Spacer and mesh gluing

30/01/14

Francisco Perez Gomez CERN PH/DT

Assembled and glued on drift panel using alignment holes

Mesh glued on well defined surface.

May act as gas manifold.

Large gluing area. Ground connection

Mesh support frame (Spacer)

30/01/14

Francisco Perez Gomez CERN PH/DT

Spacer gluing on drift panel procedure

The gluing procedure is first tested in a smaller prototype (200X200mm) In particular the assembly of the corner pieces and leak tightness were verified.

Create a new plane, parallel to drift panel

30/01/14

Drift

Gluing zonesDrift

Francisco Perez Gomez CERN PH/DT 30/01/14

Laying on precise shims on granite table

Teflon pins

30/01/14Francisco Perez Gomez CERN

PH/DT

Mesh gluing on dedicated tool

Plexiglass mould

Mesh frame

Mesh support installed under “press”

Francisco Perez Gomez CERN PH/DT

Injection of glue

30/01/14

Injection points distance 100mm

Francisco Perez Gomez CERN PH/DT

Mesh after polymerisation

30/01/14

Planarity 40µm

Prepare all needed elements for 1 panel assembly (frame, plugs, pins, etc..)

Manufacturing of 1 full set of mesh support. Investigation of temperature and humidity influence on

VT flatness Drill reference holes on vacuum tables. Assembly and QC of 1 panel for tooling and procedure

validation Test on gas distribution Test on mesh gluing Ground connections tests Test on zebra fixation Electrical tests on Zebra connectors

Francisco Perez Gomez CERN PH/DT

STATUS“Future plans and tasks 15.01.14”

30/01/14

Understand deformations on the first panel Improve and tune the panel manufacturing

procedure Build the first real panel ….

Francisco Perez Gomez CERN PH/DT

Future Plans

30/01/14

Francisco Perez Gomez CERN PH/DT

spares

30/01/14

Francisco Perez Gomez CERN PH/DT

Zebra connector for FE connection

30/01/14

Francisco Perez Gomez CERN PH/DT

Board connection

Alignment pin

Board

Fixation pins and ground connection

Deflection = 0.01mm

30/01/14

Francisco Perez Gomez CERN PH/DT

View of Zebra connector encapsulated

30/01/14