PARTIDA : 03.00.00 MOVIMIENTOS DE TIERRAS DESCRIPCIÓN : 03.01.00 EXCAVACCION HASTA SUB-RASANTE-CON MAQUINA

UNIDAD : M3 RENDIMIENTO : 100 m3/dia

RECURSOS I.U. UND. CUAD. CANT. P- UNIT. TOTAL

EQUIPOTRACT0R DE ORUGA 140-160 HP 49 HM 1.00 0.080 170.00 13.600 13.600

MANO DE OBRAOFICIAL 47 HH 2.00 0.160 11.00 1.760PEON 47 HH 4.00 0.320 10.00 3.200 4.960

HERRAMIENTASHERRAMIENTAS MANUALES 37 %M.O. 0.050 4.96 0.248 0.248

COSTO DIRECTO 18.808

PARTIDA : 03.02.00 ELIMINACION DE MATERIAL EXECEDENTE D=10KM

UNIDAD : M3 RENDIMIENTO 200 m3/dia

RECURSOS I.U. UND. CUAD. CANT. P- UNIT. TOTAL

EQUIPOCARGADOR FRONTAL 49 HM 1.00 0.040 180.00 7.200VOLQUETE 6X4 15 M3 330 HP 48 HM 4.00 0.160 170.00 27.200 34.400

MANO DE OBRAOFICIAL 47 HH 1.00 0.040 11.00 0.440PEON 47 HH 3.00 0.120 10.00 1.200 1.640

HERRAMIENTASHERRAMIENTAS MANUALES 37 %M.O. 0.050 1.64 0.082 0.082

COSTO DIRECTO 36.122

PARTIDA : 03.03.00 CONFORMACION Y COMPACTACION DE SUBRASANTE

UNIDAD : M3 RENDIMIENTO 1000 m3/dia

RECURSOS I.U. UND. CUAD. CANT. P- UNIT. TOTAL

EQUIPOCAMION CISTERNA 48 HM 1.00 0.008 110.00 0.880MOTONIVELADORA 125 HP 49 HM 1.00 0.008 140.00 1.120RODILLO LISO 49 HM 1.00 0.008 110.00 0.880 2.880

MANO DE OBRACAPATAZ 47 HH 0.50 0.004 14.00 0.056OFICIAL 47 HH 1.00 0.008 11.00 0.088PEON 47 HH 5.00 0.040 10.00 0.400 0.544

HERRAMIENTASHERRAMIENTAS MANUALES 37 %M.O. 0.050 0.54 0.027 0.027

COSTO DIRECTO 3.451

UNIVERSIDAD PERUANA LOS ANDES FACULTAD DE INGENIERIA

PRACTICA DOMICILIARIA DE CAMINOS II

SUB-TOTAL

SUB-TOTAL

SUB-TOTAL

PARTIDA3.00

3.01

3.02

3.03

DESCRIPCION UND. METRADO P. UNIT.MOVIMIENTO DE TIERRAS

Excavación hasta Sub-Rasante con Maq 100.00 18.81

Eliminación de Material Excedente DP=10Km 1000.00 36.12

Conformación y Compactacion Sub-rasante 2000.00 3.45

Costo Directo(CD) S/.Gastos Generales (10%)

Utilidad (10%)SUB TOTALIGV (18%)TOTAL S/.

M3

M3

M2

P. PARC. TOTAL

1880.80

36122.00

6902.40

44905.20

Costo Directo(CD) S/. 44905.20Gastos Generales (10%) 4490.52

Utilidad (10%) 4490.52SUB TOTAL 53886.24

9699.52TOTAL S/. ###

PRESUPUESTO

PARTIDA DESCRIPCION

3.01Excavación hasta Sub-Rasante con Maq3.02Eliminación de Material Excedente DP=10Km

3.03Conformación y Compactacion Sub-rasanteTOTAL COSTO DIRECTO

COSTOS INDIRECTOS (10 % GG +10% U )

TOTAL PRESUPUESTO BASE SIN IGV

COEFICIENTES DE INCIDENCIA

PRESUPUESTO

PARTIDA DESCRIPCION

3.01Excavación hasta Sub-Rasante con Maq3.02Eliminación de Material Excedente DP=10Km

3.03Conformación y Compactacion Sub-rasanteTOTAL COSTO DIRECTO

COSTOS INDIRECTOS (10 % GG +10% U )

TOTAL PRESUPUESTO BASE SIN IGV

COEFICIENTES DE INCIDENCIA

PRESUPUESTO

PARTIDA DESCRIPCION

3.01Excavación hasta Sub-Rasante con Maq3.02Eliminación de Material Excedente DP=10Km

3.03Conformación y Compactacion Sub-rasante

TOTAL COSTO DIRECTO

COSTOS INDIRECTOS (10 % GG +10% U )

TOTAL PRESUPUESTO BASE SIN IGV

COEFICIENTES DE INCIDENCIA

PRESUPUESTO

DESCRIPCION UND METRADOPRECIO

TOTALUNIT.

M3 100.00 18.81 1880.80

M3 1000.00 36.12 36122.00

M2 2000.00 3.45 6902.40

44905.20

COSTOS INDIRECTOS (10 % GG +10% U ) 8981.04

53886.24

PRESUPUESTO

DESCRIPCION UND METRADOPRECIO

TOTALUNIT.

M3 100.00 18.81 1880.80

M3 1000.00 36.12 36122.00

M2 2000.00 3.45 6902.40

44905.20

COSTOS INDIRECTOS (10 % GG +10% U ) 8981.04

53886.24

PRESUPUESTO

DESCRIPCION UND METRADOPRECIO

TOTALUNIT.

M3 100.00 18.81 1880.80

M3 1000.00 36.12 36122.00

M2 2000.00 3.45 6902.40

44905.20

COSTOS INDIRECTOS (10 % GG +10% U ) 8981.04

53886.24

MANO DE OBRACAPATAZ OFICIAL PEON TOTAL

UNITARIO TOTAL UNITARIO TOTAL UNITARIO TOTAL UNITARIO

0.00 0.00 1.76 176.00 3.20 320.00 4.96

0.00 0.00 0.44 440.00 1.20 1200.00 1.64

0.06 112.00 0.09 176.00 0.40 800.00 0.54

112.00 792.00 2320.00

EQUIPOSTRACT0R DE ORUGA 140-160 HP CARGADOR FRONTAL VOLQUETE 6X4 15 M3 330 HP CAMION CISTERNA

UNITARIO TOTAL UNITARIO TOTAL UNITARIO TOTAL UNITARIO

13.60 1360.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 7.20 7200.00 27.20 27200.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.88

1360.00 7200.00 27200.00

0.03 0.13 0.50

HERRAMIENTAS COSTOSHERRAMIENTAS MANUALES INDIRECTOS

UNITARIO TOTAL TOTAL

0.25 24.80

0.08 82.00

0.03 54.40

161.20

8981.04

0.003 0.17

MANO DE OBRATOTAL

TOTAL

496.00

1640.00

1088.00

3224.00

644.80

3868.80

0.06

EQUIPOSCAMION CISTERNA MOTONIVELADORA 125 HP RODILLO LISO TOTAL

TOTAL UNITARIO TOTAL UNITARIO TOTAL UNITARIO TOTAL

0.00 0.00 0.00 0.00 0.00 13.60 1360.00

0.00 0.00 0.00 0.00 0.00 34.40 34400.00

1760.00 1.12 2240.00 0.88 1760.00 2.88 5760.00

1760.00 2240.00 1760.00 41520.00

8304.00

49824.00

0.03 0.04 0.03

equipo nacional

equipo nacional

herramientas

DESCRIPCION% incidencia %

INDICECOEFICIENTE COEFICIENTE

por rubro Incidencia Por rubro Agrupado

MANO DE OBRA 100.00% 5.98% 47 0.060 0.060EQUIPOS Y HERRAMIENTAS 0.774EQUIPO IMPORTADO 95.39% 73.79% 49 0.738

EQUIPO NACIONAL 4.22% 3.266% 48 0.033

HERRAMIENTAS 0.39% 0.30% 37 0.003

GASTOS GENERALES Y UTILIDADES 100.00% 0.167

COSTOS INDIRECTOS 16.67% 39 0.167

100.00% OK! 1.000

0.060Jr

+ 0.774EHr

+ 0.167GUr

= kJo EHo GUo

SIMBOLO CODIGO DESCRIPCION% INCIDENCIA COEFICIENTE INDICE UNIFICADO INDICE UNIFICADO COEFICIENTE

POR RUBRO INCIDENCIA POR RUBRO AGRUPADO DIC. 2014 SEP. 2015 REAJUSTADO

J 47 MANO DE OBRA 100.00% 5.98% 0.060 0.060 523.70 544.59 0.06

49 3.26% 2.52% 0.025 0.774 264.41 288.48 0.03

49 CARGADOR FRONTAL17.27% 13.36% 0.134 0.774 264.41 288.48 0.15

4865.26% 50.48% 0.505 0.774 346.68 358.59 0.52

48 CAMION CISTERNA 4.22% 3.27% 0.033 0.774 346.68 358.59 0.03

49 MOTONIVELADORA 125 HP5.37% 4.16% 0.042 0.774 264.41 288.48 0.05

49 RODILLO LISO 4.22% 3.27% 0.033 0.774 264.41 288.48 0.04

37HERRAMIENTAS MANUALES

0.39% 0.30% 0.003 0.774 293.38 296.62 0.00

GU 39 100.00% 16.67% 0.167 0.167 404.87 418.76 0.17

K= 1.05

TRACT0R DE ORUGA 140-160 HP

VOLQUETE 6X4 15 M3 330 HP

GASTOS GRALES + UTILIDAD