January 22, 2016

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Arbor Heights Elementary School

Site: Maintaining temporary erosion sedimentation control (TESC) measures.

South Building: Exterior - Fluid applied air-barrier ongoing. Completed welding of southeast and southwest steel stair towers. Interior - Spray-foam insulation ongoing floor 1. Hanging Gypsum wall board (GWB) floor 1. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing floors 1, 2, and 3.

Arbor: Structural frame erection is complete.

North Building: Exterior and interior light-gauge metal stud wall framing is ongoing floors 2 and 3. Hollow-metal (HM) frame installation ongoing at floors 2 and 3. Membrane roofing ongoing at the cafeteria, kitchen, and gymnasium roof.

Arbor Heights Elementary School Site Plan

July 1, 2015 July 10, 2015

Arbor Heights Elementary School Aerial View from the South

December 30, 2015

Arbor Heights Elementary School South Wing – Southeast Stair Tower

January 15, 2016

Arbor Heights Elementary School South Wing – Exterior Air Barrier Application

January 19, 2016

Arbor Heights Elementary School South Wing – First Floor Wall Spray Foam Insulation

January 15, 2016

Arbor Heights Elementary School South Wing – Kindergarten Room 123 Gypsum Wall Board (GWB)

January 19, 2016

Arbor Heights Elementary School South Wing – Second Floor Corridor

January 19, 2016

Arbor Heights Elementary School North Wing – Commons Exterior Wall Framing

January 19, 2016

Arbor Heights Elementary School North Wing – Gymnasium

January 19, 2016

Arbor Heights Elementary School North Wing – Library

January 19, 2016

Building Excellence IV Capital Levy Cascadia Elementary School and Robert Eagle Staff Middle School

Site: Maintaining TESC measures. Preparing SW parking lots for asphalt paving late January/early February, depending on weather.

ES: Ongoing steel erection. Poured concrete slab on second floor metal deck. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing.

MS: On-going steel erection. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing rough-in. Poured stem walls for murals.

Cascadia Elementary School & Robert Eagle Staff Middle School Site Plan

Cascadia Elementary School & Robert Eagle Staff Middle School Aerial Photo

December 30, 2015

Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School - Steel Erection, Looking North

January 12, 2016

Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School - Steel Erection, Looking Northwest

January 12, 2016

Cascadia Elementary School & Robert Eagle Staff Middle School Elementary School - Slab-On-Metal-Deck Poured at 2nd Floor, Looking South

January 12, 2016

Cascadia Elementary School & Robert Eagle Staff Middle School Middle School - Slab-On-Grade Poured, Looking Southwest

January 12, 2016

Cascadia Elementary School & Robert Eagle Staff Middle School Middle School - Steel Erection, Looking South

January 12, 2016

Building Excellence IV Capital Levy Genesee Hill Elementary School

Site: Formed/poured curb at access road and stem wall at stair; installing fire department connection (FDC).

Area 1: Interior - Ceramic tile in bathrooms complete, vinyl wall covering is ongoing; casework install is complete; metal siding install is ongoing; T-bar ceiling grid install is ongoing; began installing electrical trim and ceiling lights.

Area 2: Interior - Installation of gypsum wall board (GWB) is ongoing; window frames/glazing is ongoing; electrical rough-in and sprinkler system is complete.

Area 3: GWB finishing process ongoing; interior painting ongoing; plumbing and electrical rough-in ongoing; installation of salvaged masonry is complete; window frames and glazing ongoing; casework at childcare complete.

Area 4: GWB installation and finishing process ongoing; mechanical, plumbing and electrical rough-in ongoing; prepping decking, structure and ductwork for painting.

Genesee Hill Elementary School Site Plan

Genesee Hill Elementary School Aerial Photo

Genesee Hill Elementary School Areas 1 North Elevation – Resuming Installation of Metal Siding

Genesee Hill Elementary School Area 1 Mechanical Basement – Ongoing Plumbing Rough-in to Equipment

Genesee Hill Elementary School Area 1 Level 2 Intermediate Data Room – Ongoing Terminate Data Cable

Genesee Hill Elementary School Area 1 Level 2 – Octagonal Shaped Paneling Installation Ongoing

Genesee Hill Elementary School Area 1 Level 2 – Bathroom Fixture Installation Ongoing

Genesee Hill Elementary School Area 1 Level 3 – Vinyl Wall Covering Installation Ongoing

Genesee Hill Elementary School Area 2 – Main Entrance to Building

Genesee Hill Elementary School Area 2 Level 2 – Library Window/Glazing Ongoing

Genesee Hill Elementary School Area 3 – Installing Doors at North/South Connecting Corridor

Building Excellence IV Capital Levy Hazel Wolf K-8 at Pinehurst

Site: Natural Gas, Water and Power installation complete. Electrical transformer set and to be energized next week. General site clean up.

Building A: Area (A1) Exterior and interior wall metal stud framing ongoing. HVAC, plumbing, fire-sprinkler and electrical rough-in ongoing. Green roof concrete pour. Area (A2) Exterior wall metal stud installation complete. Exterior wall sheathing and air barrier application ongoing. Window installation started. Interior wall metal stud framing complete. Wall cover inspections complete. Gypsum wall board activities started. HVAC, plumbing, fire-sprinkler and electrical rough-in nearing completion. Area (A3) Green roof dried-in. Placement of concrete floor slab complete and protected.

Building B: Placement of concrete floor slab on grade pending weather. Structural welding and bolting completed. Roofing ongoing.

Building C: Concrete slab on grade continues to be covered and protected. Metal roof deck welding complete. Roof insulation complete, roofing ongoing. Exterior wall metal stud framing started.

Hazel Wolf K-8 at Pinehurst Site Plan

Hazel Wolf K-8 at Pinehurst Aerial Photo

Hazel Wolf K-8 at Pinehurst Area A1 – Admin HVAC Ducting

January 12, 2016

Hazel Wolf K-8 at Pinehurst Area A2 – Air Barrier “Blueskin” Installation

January 12, 2016

Hazel Wolf K-8 at Pinehurst Area A2 – Air Barrier and Window Installation

January 13, 2016

Hazel Wolf K-8 at Pinehurst Area A2 – Air Barrier Window Detail

January 13, 2016

Hazel Wolf K-8 at Pinehurst Area A2 – Third Floor Classroom

January 12, 2016

Hazel Wolf K-8 at Pinehurst Area C – Metal Steel Stud Framing and Blocking

January 13, 2016

Hazel Wolf K-8 at Pinehurst Area A2, A3, and B – looking Northwest

January 12, 2016

Building Excellence IV Capital Levy Olympic Hills Elementary School

Site: Geothermal well drilling ongoing. 40 wells complete, out of 80 total. Forecasting well drilling to be complete March 2016. Maintaining TESC measures throughout site.

Building: Started formwork for footings.

Olympic Hills Elementary School Site Plan

Olympic Hills Elementary School Aerial Photo

January 1, 2016

Olympic Hills Elementary School Geothermal Well Drilling, Looking West

January 13, 2016

Olympic Hills Elementary School Footing Excavation and Formwork Prep, Looking West

January 13, 2016

Olympic Hills Elementary School Forming Footings, Looking Northwest

January 13, 2016

Olympic Hills Elementary School Bio-Detention Looking South at Southwest Corner of Site

January 13, 2016

Olympic Hills Elementary School Overall Site Looking Southeast

January 13, 2016

Building Excellence IV Capital Levy Seattle World School at T.T. Minor

Area A – Administration Office, Student Services, Health Clinic and Library: Installation of seismic glu-lam beam installation ongoing. Interior steel door frames delivered to the jobsite. Admin wood framing started. Area A overhead mechanical, plumbing, fire-sprinkler and electrical rough-in work ongoing. Exterior masonry work started.

Area B – Multipurpose, Kitchen, Boiler Room: Steel erection ongoing, structural wood and framing of the Kitchen ongoing SIP roof panel installation ongoing.

Area C – Classrooms: MEP installation ongoing, underground utility complete, CMU block wall installation complete interior steel stud framing ongoing, Fire Sprinkler installation ongoing bathroom plumbing rough in ongoing. Interior door frames on site.

Seattle World School at T.T. Minor Site Plan

Area C

Area B

Area A

Area C

Area B

Area A

Seattle World School at T.T. Minor Site – Exterior Masonry Tuck Pointing, Repair, Clean and Seal

January 19, 2016

Seattle World School at T.T. Minor Site – North Mobilization Area SIP Roof Panel Prep Area

January 19, 2016

Seattle World School at T.T. Minor Area A – Glu-lam Installation Ongoing

January 19, 2016

Seattle World School at T.T. Minor Area A – Admin Interior Wood Framing Started

January 19, 2016

Seattle World School at T.T. Minor Area B – New Commons/Kitchen Structural Glu-Lam Installation

January 19, 2016

Seattle World School at T.T. Minor Area B – New Commons/Kitchen SIP Roofing Ongoing

January 19, 2016

Seattle World School at T.T. Minor Area C – Restroom Plumbing Rough-in Ongoing

January 19, 2016

Seattle World School at T.T. Minor Area C – Interior Steel Door Frames Delivered

January 19, 2016

Building Excellence IV Capital Levy New Thornton Creek Building

Building A: Staging steel for steel erection.

Building B: Ongoing roofing for library. Ongoing exterior sheathing and interior framing on first and second floor. Ongoing ductwork on second floor. Began electrical rough-in on second. Ongoing plumbing rough-in on first floor. Ongoing rough-in for electrical and fire.

Building C: Began installing gypsum wall board (GWB) at classrooms. Completed insulation and brick veneer. Completed installation of windows and flashing. Ongoing roofing to complete final roof. Began install electrical panels in electrical closet. Began installing storefront doors.

Building D: Completed erecting structural steel and placing steel decking for roof for Covered Play Area.

New Thornton Creek Building Key Plan

Building C

Building B

Building A

D

New Thornton Creek Building Aerial Photo

January 15, 2016

New Thornton Creek Building Building A – Concrete Slab-on-grade for Administration Area

New Thornton Creek Building Building B – Exterior Sheathing on First & Second Floor

New Thornton Creek Building Building B – Stairs from Library Office to Mechanical Mezzanine

New Thornton Creek Building Building B – Second Floor Interior Framing

New Thornton Creek Building Building B – Second Floor Mechanical Penetration for Ductwork to First Floor

New Thornton Creek Building Building B – Second Floor HVAC Ductwork Installation

New Thornton Creek Building Building C – Installation of Cap Sheet on Roof

New Thornton Creek Building Building C – Insulation in Interior Walls

New Thornton Creek Building Building C – Installing Gypsum Wall Board (GWB)

New Thornton Creek Building Building C – Installing Moisture Resistant GWB in Bathroom

New Thornton Creek Building Building C – Installing Electrical Panels in Electrical Closet