BART SILICON VALLEY C742 Berryessa Station

Campus

April 23, 2015

2

3

C742 Site Plan

Contract Interfaces

5

Key Dates and Times

Bid Opening May 6, 2015

Contract Award Date August 6, 2015

Expected Construction NTP Date

September 11, 2015

Time for Performance 459 Calendar Days

6

Scope of Work

• Site Work: demolition, clearing and grubbing, and grading

• Roadway Improvements and Construction • 350-space parking lot • Stormwater Treatment • Utility Construction

– Storm sewer, sanitary sewer, water lines

7

Scope of Work

• BART Police Zone Building Construction • Ancillary Building Construction • Transit Center Construction

– Bus shelters, signage

• Lighting and Traffic Signals Installation • Security and Communications Systems Installation

– CCTV, Emergency Call Boxes

• Station Plaza Construction

8

Scope of Work

• Shared Pedestrian/Bike Trail Construction • Native American Contemplation Garden

Construction • Preparation for Art Installation and

Coordination