albemarle rpo project update north carolina department of transportation may 2011
Post on 16-Dec-2015
219 Views
Preview:
TRANSCRIPT
Albemarle RPO Project Update
North Carolina Department of Transportation
May 2011
What is the N.C. Transportation Improvement Plan?
• A guide for NCDOT and public regarding transportation projects
• Defines how NCDOT will allocate resources in next 7 years
• Assigns schedules to transportation projects
The Draft STIP can be found at:
http://www.ncdot.org/download/performance/Draft_STIP.pdf
Highlighted Area Projects in STIP
U-4438 – US 158 (Elizabeth Street) from US 17 Business( Road Street) to east side of Pasquotank River, including replacement of Bridge #19, (Pasquotank & Camden Counties)
• Right of Way/Utility coordination underway
• Letting – May 17, 2011
Highlighted Area Projects in STIP
R-2414B – US 158 from South of SR 1139 (Country Club Rd.) to east of NC 34 (Camden County)
• Letting scheduled for June 21, 2011
Highlighted Area Projects in STIP
R-2507A – US 13/US 158 from US 158 near Winton to US 158 at Tarheel (Hertford & Gates Counties)
• Design-Build letting – scheduled for Summer 2011
• Completion of design will commence upon award of contract
• Right of Way acquisition and Construction will follow completion of design
• Includes new bridge over Chowan River
R-2507 B & C – US 13 from US 158 to Virginia Line (Gates County)
• R/W & Construction – Unfunded in Draft STIP
Highlighted Area Projects in STIP
R-2579 – US 158 from NC 32 in Sunbury to US 17 at Morgan’s Corner (15 miles) (Gates & Pasquotank Counties)
• Planning currently underway
• R/W Acquisition - 2019
• Construction – Unfunded in Draft STIP
R-2578 – US 158 from US 13 to NC 32 in Sunbury (15 miles) (Gates County)
• R/W & Construction – Unfunded in Draft STIP
Highlighted Area Projects in STIP
R-2574 – US 158 east of NC 34 at Belcross to NC 168 at Barco (Camden & Currituck Counties)
• Planning to move forward
• R/W Acquisition - 2020
• Construction – Unfunded in Draft STIP
Highlighted Area Projects in STIP
R-2544/R-2545 – US 64 from 0.9 miles east of Columbia to US 264 (27.3 miles) (Tyrrell & Dare Counties)
• Planning and Design currently underway
• Right of Way – SFY 2014 (R-2545 AA & AB – Tyrrell County)
SFY 2016 (R-2544 – Dare County)
• Construction – SFY 2014 (R-2544B – Alligator River Bridge)
SFY 2016 (R-2545 – Tyrrell County)
SFY 2018 (R-2544 – Dare County)
Highlighted Area Projects in STIP
R-4467 – US 17 Business/NC 37 Perquimans River Bridge (S-Bridge) & Causeway (Perquimans County)
• Planning and Design currently underway
• Right of Way – FFY 2015
• Construction – FFY 2016
Highlighted Area Projects in STIP
R-3620 – Proposed NC 32 Connector from US 64 to the intersection of NC 32 & NC 94 (Washington County)
• Planning and Design currently underway
• Right of Way – SFY 2012
• Construction – SFY 2014
Highlighted Area Projects in STIP
R-5014 – Colington Road (Dare County)
• Planning has been initiated
• $2.5 million programmed for 2017
• Additional Funding will be needed
Highlighted Area Projects in STIP
R-2576 – Mid-Currituck Bridge, Coinjock to Corolla (7.0 miles) (Currituck County)
• Planning and Design currently underway by N. C. Turnpike Authority
• Preferred Alternative selected
• Record of Decision anticipated Fall 2011
Highlighted Area Projects in STIP
B-2500 – Replacement of Herbert C. Bonner Bridge over Oregon Inlet (Dare County)
• Record of Decision signed December 2010
• Short-list of Design-Build Teams has been developed
• Design-Build letting – scheduled for Summer 2011
Highlighted Area Projects in STIP
Various Infrastructure Health Projects
• Pavement Rehabilitation Projects
• Bridge Replacement Projects
Questions?