9/25/08 J. Lajoie - Muon Trigger Upgrade Review 1
Muon Trigger Upgrade LL1 Electronics
Iowa State University
John LajoieCesar Luiz daSilva
Todd KempelAndy GoersRoy McKayGary Sleege
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 2
Trigger Algorithm• Momentum selectivity through online
sagitta measurement– Uses MuTR 1,2,3 and RPC1,3 planes
PHENIX LL1 decision time 40xBCLK (4s)
Implement trigger using fast, parallel logic on FPGA’s
RPC3
RPC1
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 3
Trigger Board Block Diagram
VMEInterface
P1
P0
P2
P3
12 x xcvr
Virtex-5LX110T
(RPC1,3 @ 2.8Gbit)
(MuTr St2 @ 2.8Gbit)
(MuTr St1 @ 2.8Gbit)
(MuTr St3 @ 2.8Gbit)
One board processes four trigger octants (one octant per tile).
Virtex-5LX110T
(7 fibers per octant)
Virtex-5LX110T
Virtex-5LX110T
Virtex-5LX110T
12 x xcvr
12 x xcvr
12 x xcvr
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 4
LL1 Trigger Tile Development
• Rev0 Trigger Tile – Nov’07– Power supply operation and testing
• ADuC control, I2C communication– Signal integrity on serial pairs
• TDR testing to measure pair impedance• Rev1 Trigger Tile – April’08
– Full population and assembly– Power consumption
• FPGA, scaling with GTP use– Testing of FPGA interface
• JTAG, PROMS, power-up programming– Serial communication testing
• BERT testing on all serial lines– Chain test with MuTr MRG board
• Rev2 Trigger Tile – Sept’08– Minor changes to ease assembly– Revised memory interface and connector
More on BERT tests and MRG board tests to
follow.
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 6
Test Stand Setup
• All GTP Connections Verified– Verified with BERR testing
• Used Xilinx IBERT tools and GTP internal PRBS generators
– All GTP tiles working at 2.8Gbps and 3.125Gbps
• Using XpressO +/- 50ppm clock• BERR < 5.1x10-15 with 8b/10b
– Tested up to 8 tiles (16 GTP’s) in single LX110T design
• Requires heat sink and fan• Current draw as expected (~2A
on 3.3V w/all GTP’s)
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 7
MuTr MRG to LL1 Data Format
TLK3101(TI)
TLK3101(TI)
140MHz
data[15:0]
TX_ENTX_ER
FTLF8524E2KNL(finisar)
FTLF8524E2KNL(finisar)
Optical driver850nm laser
….……
Head
er
Carrier Extend(no data)
idle idleidle
to LL1
to LL1
event data
14 packets for 1 cycle
additional idle packetowing to asynchronous system(9.4x14MHz 140MHz)
next event
color
Data format agreed to between LL1 and MuTr FEE group (April ’08 workshop at ISU).
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 8
Communication Tests
Two MRG Board Prototypes
Pattern Generator for input
LL1 Trigger Tile
Laptop for power control, chip monitoring (voltages, temps, etc), Chipscope for signal monitoring
~30m fiber connecting the two boards
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 9
MRG->LL1 Testing at BNL (Aug ’08)
• Optical connection between MRG and LL1 trigger tile established:– Patterns sent from
MRG board with alternating parity
– Parity calculated and checked at LL1 end
– System ran for ~14 hrs w/o error
– Clock domain logic in tile FPGA fully tested (REF, 14xBCLK, BMCLK)
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 10
Base Board Design
• Base board design and layout nearly complete– Design in final
stages at ISU– Many lessons
learned from Tile design integrated into base board
9/25/08 J. Lajoie - Muon Trigger Upgrade Review 11
Schedule and Integration• Rev2 Tiles Available Oct 20th
– Checkout at ISU to follow
• Base Board Schedule– Out for production Oct. 6th
– Assembled, in testing Oct. 27th
• Algorithm Development/Programming– Underway through Jan. ’09
• Basic trigger functionality at this point
• Integration at BNL Dec.’08-March’09