© Columbus JACK Corp. 2010
Axle Jack
Model 5007-55(56)
ColumbusJACK/Regent“The Strength of Experience”
© Columbus JACK Corp. 2010
5007-55(56)
• Capacity 50 tons
• Hydraulic Stroke 12 inches
• Screw Extension 3.5 inches
• Closed Height 7 inches
• Extended Height 22.5 inches
• Operating Pressure– First Stage 4020 psi
– Second Stage 5950 psi
– Third Stage 9690 psi
© Columbus JACK Corp. 2010
5007-55(56)
• Maximum Towing Speed 3 mph
© Columbus JACK Corp. 2010
5007-55
Air Pump
Hand Pump
Cylinder Assy
© Columbus JACK Corp. 2010
5007-55
© Columbus JACK Corp. 2010
5007-55
Cylinder Bushing
1st Stage Ram
2nd Stage Ram
3rd Stage Ram
Snap Ring
O-Ring & Backup Ring
© Columbus JACK Corp. 2010
Inspection
• Check hydraulic fluid in reservoir.
– If low, fill with mineral based fluid compatible with Buna-N seal material.
– For operation at temperatures below 32oF (0oC), replace 25% of the hydraulic fluid with kerosene.
• Check for missing parts, damage or leakage on hand pump assembly.
– Check pump piston OD for scoring and rust pits. Replace as necessary.
– If piston is leaking, fluid replace o-ring and backup ring.
© Columbus JACK Corp. 2010
Inspection
– Replace missing parts as required.
• Check cup adapter condition.
– Replace if damaged or missing.
– Insure adapter is securely attached to screw extension.
• Check screw extension.
– Replace if damaged.
– Insure screw extension stop is in place to prevent its removal.
– Insure the screw extension will thread up and down freely.
© Columbus JACK Corp. 2010
Inspection
• Check top of cylinder assembly for leakage.
– If fluid exists, cycle ram full stroke and clean all excess fluid from ram, then lower ram completely. Fully extend ram. If fluid continues to be present, disassembly cylinder and replace all seals.
• Check casters and floating wheel for damage or excessive tread wear.
– Replace if damaged.
– Insure all hardware is tightened securely.
© Columbus JACK Corp. 2010
Inspection
• Check attaching hardware for cylinder assembly to frame.
– Insure all hardware is tightened securely.
– If applicable, adjust leveling screw to insure cylinder base is level to ground.
• Check base of cylinder for proper thickness.
• Verify cylinder snap rings are fully engaged in grooves.
– Tap snap ring into groove with a hammer. Replace if snap ring will not stay in groove.
© Columbus JACK Corp. 2010
Inspection
• Verify rain hat is operational.
• Check hydraulic lines and fittings for damage and leakage.
– Replace if damaged.
• Check reservoir fill plug and verify vent is open.
• Drain air filter.
• Insure air relief valve/regulator is undamaged.
– Check pressure setting of regulator.
© Columbus JACK Corp. 2010
Operation – To Raise
• Locate jack under aircraft lifting point.
• Unscrew the screw extension as required.
• Operate pump until rams have raised aircraft to desired height.
© Columbus JACK Corp. 2010
Operation – To Lower
• Slowly open release valve to lower rams.
• Lower screw extension completely.
• Place rain hat over cylinder.
© Columbus JACK Corp. 2010
Evac-U-Tract (-56)
• Evac-U-Tract provides air assist in the retraction of the rams by creation a suction across the reservoir that “pulls” the oil from the cylinder.
Vacuum PumpControl Valve
© Columbus JACK Corp. 2010
Evac-U-Tract (-56)
© Columbus JACK Corp. 2010
Evac-U-Tract (-56)
© Columbus JACK Corp. 2010
Operation – To Raise
• Operate jack same as without Evac-U-Trac.
© Columbus JACK Corp. 2010
Operation – To Lower
• Slowly open jack release valve and allow rams to retract until aircraft tires are completely on the ground.
• Operate Evac-U-Trac to lower rams completely.
• Lower screw extension completely.
• Place rain hat over cylinder.
© Columbus JACK Corp. 2010
Testing Procedure
• Relief valve should be checked at least annually to insure it is operating properly.
• Cylinder assembly should be pressure checked at rated pressure after seal changes.
• Cylinder must be tested with first and second stage fully extended and the third stage partially extended.
© Columbus JACK Corp. 2010
Relief Valve Adjustment
• Relief valve should be set between rated capacity and 110% rated capacity.
• Close release valve and pressurize jack against tester using hand pump.
• Pump handle will go “soft” when relief valve setting is reached.
• If adjustment is required:
– Open release valve to release pressure in jack
– Remove spring pin.
© Columbus JACK Corp. 2010
Relief Valve Adjustment
Intake Check Valve
Relief Valve Poppet
Relief Valve Spring
Relief Valve Adjustment Screw
Release Valve
Inlet Oil Screen
Pressure Check Valve
© Columbus JACK Corp. 2010
Relief Valve Adjustment
– Close release valve and pressurize jack against tester using hand pump.
– To increase relief pressure, release pressure and rotate adjusting screw clockwise.
– To decrease relief pressure, release pressure and rotate adjusting screw counterclockwise.
– Verify relief valve is set in the correct range and re-adjust as required.
© Columbus JACK Corp. 2010
Relief Valve Adjustment
– Open release valve and lower ram(s) completely.
– Re-install spring pin.
© Columbus JACK Corp. 2010