1 Confidential AMANDELBULT LEADERSHIP DEVELOPMENT FORUM - PROJECTS OVERVIEW 8 November 2017

Upload: ledat

Post on 30-May-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

1

Confidential

AMANDELBULT LEADERSHIP

DEVELOPMENT FORUM - PROJECTS

OVERVIEW 8 November 2017

2

Confidential

AMANDELBULT PROJECTS OVERVIEWLocality of Projects

Longer term projects:

• Middellaagte has

been identified through

the ABC study to be

the next major project

as a potential Tumela

Mine replacement

project (ahead of the

Tumela 1#),

comprising of a new

decline from surface

with the preferred

mining method being

Narrow Reef

Mechanised Fleet.

Mine within a mine:

• Dishaba ore reserve

generation and

infrastructure upgrade

project.

• Two replacement projects have been identified, maximising value largely off existing infrastructure to mitigate the

overall declining production profile, reducing the AISC of the mine and delaying major capital expenditure:

15E drop down - Narrow Reef Mechanised Fleet trial mining section, producing c.55koz pa (Pt)

62E raisebore shaft – c.10 years replacement project, producing c.81koz pa (Pt)

5

5

3

Confidential

AMANDELBULT PROJECTS OVERVIEWLocality of Projects

4CONFIDENTIAL

Preliminary BP2018 Production Profile – Tonnes Milled

DISHABA 62E AND TUMELA 15E

Tumela

Dishaba

Tum 15E

Dish 62E

Middellaagte

Tumela 1 Sub #

Current Concentrator

Capacity – 7.7 mtpa

Additional work

required to achieve

higher concentrator

capacity

5

Confidential

DISHABA 62E RAISEBORE

6

Confidential

UNDERGROUND INFRASTRUCTURE

PFS B:

• 62SI Tip ore directly into 5L Orepass vs Cross Tramming

• Extend 62SI Shaft from 9 to 12L

7

Confidential

MINING – ALTERNATIVE 1Capital Infrastructure

8

Confidential

MINING - BACKGROUNDRegional Mine Design and Layout

9

Confidential

ROCK TRANSPORT OPTIONS

• PFS B: Road Transport (Base) vs Rail Trade-Off vs Rail + Conveyor

10

Confidential

TUMELA 15E DROPDOWN

11

Confidential

15E INFRASTRUCTURE

12

Confidential

MINING - BACKGROUNDCurrent and Project Infrastructure

13

Confidential

TUMELA 15E PROJECT OVERVIEW Surface Placement of Infrastructure

15

Confidential

CHROME RECOVERY PLANT

16

Confidential

CHROME RECOVERY PLANTProject Overview

• Currently the Merensky Concentrator tailings chrome content is being deposited on the tailings dam.

Need identified to harvest this chrome.

• Feasibility study for a new chrome recovery plant is complete, currently in the approval process.

• New plant is based on the existing one, using Spiral technology.

17

Confidential

CHROME RECOVERY PLANTSurface View

18

Confidential

PROJECT TIMELINESProject Milestones

19

Confidential

CHROME RAIL SIDING

20

Confidential

CHROME RAIL SIDINGProject Overview

• The objectives of this project is to reduce the cost of transporting chromite from the Amandelbult chrome

pad to the Pendoring rail siding in Britz. By extending the existing railway line at Amandelbult, the need

for trucking of chromite is eliminated, resulting in a monthly cost saving.

• The project essentially consists of additional shunting rail at Tussenin siding, extending the existing rail

past the chrome pad, load out facilities at the chrome pad and extension of the gravel road near the

chrome pad.

• Project completion is expected by end 2018.