alternative procurement
TRANSCRIPT
-
7/28/2019 Alternative Procurement
1/18
-
7/28/2019 Alternative Procurement
2/18
Titles Sealed Quotation
Direct Purchase
Users Committee
Force account
NGOs
Training /Designs specialties
Repairs
Rent Service Contract
Consultant Qualification Selection (CQS)
2July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
3/18
Some Complex Procurements
SOP 58 has some examples where PPA or PPR
either has no answer or is impracticable.
Schedule 3 (Types of Goods Contract), Schedule
4 (Works Contract) and Schedule 5 (Service
Contracts) have no procedures in PPA/PPR.
Trading Items cannot be purchased based on
PPA/PPR.
Reverse auction is not accompanied by PPA.
3July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
4/18
General Process- Same as Bid
4July 19, 2013 PMAN- by BN Dahal
Plan
ning
Estima
tion
Notice Openin
g
Evaluation Award
Sealed quotation
PPR97
a a a a a a
Direct Purchase a a ra r a a
Users Committee a a a (or
by)
r Fixed a
Force Account a a r r r r
-
7/28/2019 Alternative Procurement
5/18
Sealed Quotation
Ceiling- Rs. 1m (goods) , 2m works at estimated
cost (Estimation means Total estimation)
Slices, package or unit rate- allowed
Frame Work contract practiced by some entity.
Notice period-15 days,
Validity - 45 days , Bank Guarantee - 75 days
SBD of PPMO; cost Rs. 300,
If otherwise stated in PPA40/PP84 mutatis
mutandisas BID.
5July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
6/18
Sealed Quotation
If less than 3, further notice without saying RE-
Validity? Modification? Withdrawal? Opening?
No modification, withdrawal-First tier-offer(?)
(game theory)
Public Opening- same formalities as bid.
Evaluationsimilar as bid.
Awards within 7 days with PerformanceGuarantee 5%.
6July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
7/18
Direct Purchase- Minor purchase
Restrictions:
If goods in stock, no direct purchase (PPR86)
Agreement is not required (?)
Annual restriction-
Rs. 3 lakh for goods, Rs. 3 lakh for other service; Rs. 5
lakh for works
Single Party Obligor - no twice within above limit.
Written quotation to be obtained from at lease 3
suppliers if Estimate (AND/OR contract) is >50K.
No retention, no bank guarantee.
7July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
8/18
Direct Purchase- Domestic Production
If produced in Nepal by many producers
direct from producer to the extent of Rs. 1.5 m.
Dealer and retail price published.
PE is treated as a dealer.
Single purchase within a year. PPMO may test the
price (ultraviolet comparing to PPA65(2)
If produced in Nepal by only one producer
direct from producer to any requirement
Dealer and retail price published.
PE is treated as a dealer. 8July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
9/18
Direct Purchase- Single supplier
Technical skill or competency with single
supplier (foreign or domestic).
Single supplier (proprietary goods or unique
service provider) around reasonable situation.
Compatibility of existing facility (Proprietary
goods)- to 30% of original cost.
Public notice required for three above.
Attachable with main (VO)- higher approval.
Written offer to be obtain
Negotiation required. 9July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
10/18
Direct Purchase- Critical points
Practical ambiguity of minor limit- per case or
total for each year?
If budget availed? If unexpected required?
Definition of proprietary goods/unique service.
10July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
11/18
Direct Purchase- Design
Regular architectural designs, urban plan
TOR to be prepared and design competition
may be done. Only won participant is paying
party.
PPR87
11July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
12/18
Direct Purchase- Training and CQS
Training, seminar, workshop
Direct negotiation to the extent of Rs. 100,000,
required higher approval for above amount.
PPR82
Selection Based on Consultants Qualifications
(CQS)- PPR83
Regular, small value, small timing but high skillrequirement.
Only few consultant available in the market
For competitive, takes much time.12July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
13/18
Consumer Committee
Cost reimbursable method applied (PPR97)
Limit upto cost estimate of Rs. 6 million in total.
Work and associated service only. After completion
works to be transferred to UC and repair by UC
fund only.
Notice publication or offer from UC.
Agreement by both party
Advance (1/3rd) and settlement for next advance.
All bills to be publicly audited and submitted to PE.
Man work only.13July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
14/18
Force Account
Small works in scattered places, where bidder
may not be interested.
Goods from PE and direct-labor
Single force account less than Rs. 100,000
(slicing permissible).
Always higher approval required.
PPR98
14July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
15/18
NGO
PPA46/PPR99
Public awareness training, main-streaming,
strengthening activities
Based on NGO objectives (listed in standing list)
15 days notice for RFP; public opening and
evaluation (same as bid)
Lowest evaluated substantially responsive offer. No Bank guaranatee (bidding or performance)
15July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
16/18
Other
Service Contract (PPR95)
Per case service contract
Upto Rs. 100,000- direct negotiation
Above 15days notice (national- valley, regional and
notice board- other places)
No Bank guarantee
If performance is not good, correction notice then
termination.
16July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
17/18
Othercont.
Repair and Maintenance
Cost estimate required each case. If in own
workshop approval may done based on job-card.
Own workshop or outsider.
Replacement of goods worth more than Rs. 5000.
House/Land Rent (PPR94)
Based on Rent Committee
Renew possible
17July 19, 2013 PMAN- by BN Dahal
-
7/28/2019 Alternative Procurement
18/18
Common elements
Planning as usual (except minor purchases).
Estimation approval as usual (workshop repair
may be after repair based on job-card).
Notice in most case or letter or post-purchase
public notice.
Most cases, agreement required
Contract management is similar.
18July 19, 2013 PMAN- by BN Dahal