Lessons from a mega project:the importance of leadership, collaboration and culture
Allen Garner, CEO, Regional Rail Link Authority
![Page 2: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/2.jpg)
22
Regional Rail Link
![Page 3: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/3.jpg)
33
• Creates capacity for an extra 23 metro services and
10 regional services during each morning and evening
peak period
• More trains, less delays
• More efficient and predicable scheduling
• Less crowding on trains
• More accessibility to and from regional centres
• New communities get access to rail for the first time
Increasing reliability and capacity
![Page 4: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/4.jpg)
44
• $4 billion Photo
• 14.1 million man-hours
• 15,000 individuals worked on the project
• Peak daily workforce of 3,800• Lost-time Injury Frequency Rate: 0.6
• Total Recordable Injury Frequency Rate: 10.4
• Average $100 million per month turnover
• peaking at $180 million per month
• 119 kilometres of track installed
• 40 bridges and grade separations constructed
• 5 new or rebuilt stations
• 50 occupations
• including 9 major occupations
• 1000’s of kilometres of wires
Project stats
![Page 5: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/5.jpg)
55
![Page 6: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/6.jpg)
66
• Make up of the authority
• VPS and VicRoads staff seconded, new VPS staff
• Rail & construction specialists
• Metro Trains and V/Line project staff
• Design, commercial & probity consultants
• An overseeing RRLA board
• Informed authority experienced in project management
• Integrated and cross agency approach
• Focus on continuous improvement, collaboration and
innovation
Regional Rail Link Authority
![Page 7: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/7.jpg)
77
Matrix-style organisation structure
![Page 8: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/8.jpg)
88
• Focused on:
• Strategic management
• Relationships
• Stakeholders
• Government
• Agencies
• Councils
• Community
• Performance
• Legacy
Leadership team
![Page 9: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/9.jpg)
99
• Getting the right mix
• Co-location leading to
• cohesion
• cooperation
• collaboration
• Interaction with industry and government
• Timing
Planning and approvals
![Page 10: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/10.jpg)
1010
• Strategic Procurement Plan
o established work packages and delivery models
• Strong focus on ensuring the right balance of ARO
involvement, industry capacity and open to as many
bidders as possible
• Design and scope
Project development
![Page 11: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/11.jpg)
1111
Six work packages
Southern Cross $250m
City – Maribyrnong River $600m
Footscray – Deer Park $950m
Deer Park – West Werribee Junction $550m
West Werribee Junction $50m
Rail Systems $250m
![Page 12: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/12.jpg)
1212
![Page 13: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/13.jpg)
1313
• Collaboration with contractors, AROs, VicRoads, councils,
government agencies, stakeholders and local community
• Managing interfaces
• Mitigating risk
Success through collaboration
![Page 14: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/14.jpg)
1414
Participants
Objectives
• All interfaces coordinated and managed
• Encourage sharing between parties and lessons learnt
• Discuss innovation relevant to project delivery (eg. driver
simulator, sleeper procurement, safety initiatives)
• Ensuring sub-committees minimise impact of coordination
of activities
• Review project progress and issues
• Identify synergistic time and cost savings between work
packages
Joint Coordination Committee
![Page 15: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/15.jpg)
1515
Joint Coordination Committee
Governance Structure
![Page 16: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/16.jpg)
1616
• RRL Master Program
• Milestone Definition Process
• Delivery of staged benefits
Setting milestones
![Page 17: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/17.jpg)
1717
Setting milestones
![Page 18: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/18.jpg)
1818
![Page 19: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/19.jpg)
1919
• A project first that will change the way rail projects are
delivered in Victoria
• Successful planning, communications and delivery
• 7 major line occupations
• 72 weekend occupations
• 718 after last / before first service occupations
Major rail occupations
![Page 20: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/20.jpg)
2020
RRLA has worked closely with:
• Victorian and Federal Government and Ministers
• DTPLI, DPC, DSE, DTF and Commonwealth
• Public Transport Victoria, Growth Areas Authority,
VicRoads
• Metro Trains Melbourne, V/Line, VicTrack, ARTC
• City of Melbourne, Brimbank City Council, Wyndham City
Council, Maribyrnong City Council, Shire of Melton
• City of Ballarat, City of Greater Geelong, City of Greater
Bendigo
Delivering Regional Rail Link
![Page 21: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/21.jpg)
2121
• High focus on engagement by the project team
• Managed at multiple levels
• Executives in contractors and client teams involved
• Critical to project success
Stakeholder management
![Page 22: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/22.jpg)
2222
• Effective communication and consultation arrangements
• Individuals and groups affected by the project had
opportunities to participate in its development
• Provided a local perspective
• Assisted in plans for managing construction impacts
Community Reference Group
![Page 23: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/23.jpg)
2323
Multiple communication channels
• 1800 number (24/7)
• Website
• Newsletters
• Fact sheets
• Letter box drops
Communications
![Page 24: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/24.jpg)
2424
![Page 25: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/25.jpg)
2525
• Defining scope
• Strong change management controls
• Proactive contract management
• Robust reporting & review monthly
cycle
• Good people
• Assurance processes
• Project controls & processes
• Enormous value in our stakeholder
relationships
• Communications
In conclusion
![Page 26: Allen Garner, Regional Rail Link Authority](https://reader034.vdocuments.site/reader034/viewer/2022042715/558ba755d8b42aed278b4592/html5/thumbnails/26.jpg)
2626
Conclusion