albuquerque public schools capital master plan review
TRANSCRIPT
Albuquerque Public Schools Capital Master Plan Review Committee 2012
Meeting 1: SB9 13-19 & GO 13
November 1, 2012
2
Purpose • Capital recommendations for:
• SB9 14-19, 2 mill levy
• GO Bond 13
• Formerly GO 14
• Accelerated a year to realign the CMP to accelerate project delivery
• Consolidate two elections and save taxpayer / district resources
3
Agenda • Background
• CMP Update (Reprioritized)
• District Growth Outlook (See Growth section)
• SB-9 14–19 2 Mill levy & 2013 GO Bond
• Financial and Revenue Outlook
• CMP Obligations
• Where we are now (Project update)
• Proposed priority categories
• Next meeting – Wednesday, November 7, 11:30 a.m.
4
Background • CMP Update (Reprioritized, November 2011)
• Why?
• Realign CMP project obligations to revised lowered revenue collections
• Realign CMP to account for new Charter school legislative obligations
• Realign CMP to account for increased costs to complete projects undertaken between 2006 to 2009 (peak of construction inflation)
• Strengthen and maintain financial processes
5
Background • Total impact 2010 to 2018 = $152.5 million
Decreased Revenues
• $47.1 million less than previously projected to be collected from tax payers from 2010 to 2016
• +$40 million will flow directly from County Assessor to Charter Schools between 2010 and 2018 and not to CMP/Construction
• +$18 million from 2010 HB33 election
• +22 million from 2013 SB-9 election
Increased Expenses
• $65.4 million to complete and make up for inflation obligation of projects from 2006-10 Strategy
6
SB-9 14–19 2 Mill levy & 2013 GO Bond
7
SB-9 14–19 2 Mill levy & 2013 GO Bond
Will be asking voters to approve a total of $368.4 million (No Tax Increase) $200 million in School General Obligation Bonds $168.4 million in the reauthorization of a 2 Mill Local property tax levy over the next six years
• Revenue outlook
• GO Bond
• $200 million (four years)
• $170 million for capital projects
• $30 million for Educational Technology Notes
• Projects have been prioritized and assigned to available revenue during the 2011 reprioritization
• SB 9 14-19 = $180.4 million
• $168.4 million over 6 years projected (@ 0% revenue growth) local tax collection
• Reduced approximately 10% due to economic downturn
• Anticipate $12 million in state match ($2 million / year)
8
SB-9 14–19 2 Mill levy & 2013 GO Bond
• CMP Obligations
• Maintenance of 14+ million square feet of educational facilities
• Additional 4 million square feet since 2005
• Decreased maintenance personnel due to operational budget reductions by the state
• Completion of the 2011-16 CMP capital strategy as reprioritized and approved in 2010 and 2011
• New statutory mandate that distributes a portion of the mill levy directly to charter schools ($20.2 million over 6 years)
9
Ongoing Construction Projects
1. Sandia High School 2. Del Notre High School 3. Chaparral Elementary School 4. APS Community Stadium 5. Inez Elementary School 6. Montessori of the Rio Grande Charter School 7. South Valley Academy Charter School
Where we are Now
Upcoming 2012 Construction projects
•McKinley Middle School •Eldorado High School •Adobe Acres Elementary •Sandia Base Elementary School •Monte Vista Elementary School •Jefferson Middle School •Central Kitchen •e-Academy Alternative School •MacArthur Elementary School •SW K – 8 School •Lincoln Complex Buildings A1 and G Roof
10
On-Going Construction Projects
11
Construction Schedule
12
Sandia High School Address: 7801 Candelaria Rd NE
Square Footage: 330,699
Year Opened: 1958
Current Projects: • New Site Master Plan Study • New Science/Math classroom Building & New
Library • Landscaping/Site stabilization/ Infrastructure
Upgrades • Athletic Fields Reconstruction
Budget: $22,316,937.00
Architect: Mahlman Studio
General Contractor: TBD
Est. Date of Completion: Aug 2014
13
Address: 5323 Montgomery Blvd NE Square Footage: 280,744 Year Opened: 1964-65 Current Project: Rebuild school (3 phases) Phase 1 - COMPLETE Construct new classroom building Demolish a portion of 100 Building Construct new administration building Architect: Dekker/Perich, Greg T. Hicks O/E, and Allison
Eng. O/E General Contractor: Shumate Constructors
Phase 2- On-Going Demolish rest of 100 Building and 500 Building Remove portables
Phase 3 Demolish 300, 400 and 500 buildings Finish student commons Kitchen/Cafeteria Est. Date of Completion: Aug 2013
Total Budget: $58,911,244
Del Norte High School
Address: 6325 Milne Rd NW Square Footage: 54,299 Year Opened: 1984 Site Traffic Improvements & Site Development
Plan Kindergarten, Classroom and Cafeteria
Additions, Design Services Architect: Cherry/See/Reames General Contractor: TBD Budget: $14,529,000 Est. Date of Completion: Aug 2014
15
Chaparral Elementary School
15
Address: 1601 Arroyo Vista Blvd NW Current Projects: Football Stadium Track and Field Softball court Tennis court
Budget: $36,361,300 Architect: SMPC General Contractor: Shumate
Constructors, inc Est. Date of Completion: Apr. 2013
Albuquerque Public Schools Community Stadium
16
Inez Elementary School
Address: 1700 Pennsylvania St NE Square Footage: 51,841 Year Opened: 1952 CMP 2011-16 Strategy Projects: Kindergarten addition Renovation of existing buildings Drainage/Site Improvements Budget: $3,568,580 Architect: NCA Architects General Contractor: T.A. Cole& Sons Est. Date for Completion: Sept 2013
17
2012 Upcoming Projects
Address: 3426 Blake SW Year Opened: 1999 Grade Levels: 9 -12th CMP 2011-16 Strategy Project: Phase 1A - Library, Administration,
Special Programs and Food Services Spaces
Budget: $7,214,377 Architect: Studio SW General Contractor: TBD Est. Date of Completion: Fall 2013
South Valley Academy Charter School
Address: 16550 Gabaldon Dr NW Square Footage: 12,000 Year Opened: 2004 Grade Levels: K-5 This school is one of 6 pilot charter schools that
are currently undergoing design for new permanent public facilities in partnership with Albuquerque Public Schools.
Currently the charter school is on APS owned facility.
CMP 2011-16 Strategy Project: School Improvements Budget: $2,614,218 Architect : G. Don Dudley General Contractor: Famco Inc Est. Date of Completion: July 2013
20
Montessori of the Rio Grande Charter School
Address: 4500 Comanche NE Square Footage: 78,124 Year Opened: 1956 Current Projects: Science Lab Renovations Electrical Improvements
Budget: $710,157 Architect: Architect Studio Contractor: TBD
CMP 2011-16 Strategy Project Classroom Addition Budget: $ 6,281,190
Architect: TBD (Requesting RFP) General Contractor: TBD Est. Date of Completion: Fall 2014
McKinley Middle School
21
21
Eldorado High School
Address: 11300 Montgomery NE Square Footage: 324,085 Year Opened: 1970 CMP 2011-16 Strategy Projects: Renovate Math, Fine Arts & Humanities Buildings Asbestos removal Budget: $6,479,667 Architect: Van Gilbert General Contractor: TBD Est. Date for Completion: Fall 2013
22
Adobe Acres Elementary School
Address: 1724 Camino Del Valle SW Square Footage: 43,451 Year Opened: 1964 CMP 2011-16 Strategy Projects: Classroom and Cafeteria Addition School Wide General Renovations Health & Safety Drainage corrections Budget: $3,612,433 Architect: RMKM General Contractor: TBD Est. Date for Completion: Fall 2013
23
Address: 21001 Wyoming SE - KAFB East Square Footage: 46,632 Year Opened: 1950 CMP 2011-16 Strategy Projects:
Parent Drop Off
New Classroom Building (phase 1a)
Athletic Field Replacement (phase 1b)
Budget: $1,212,769 Architect: Claudio Vigil Architects General Contractor: TBD Est. Date for Completion: Fall 2013
Sandia Base Elementary School
Address: 3211 Monte Vista Blvd NE Square Footage: 51,805 Year Opened: 1931 CMP 2011-16 Strategy Projects:
Roofing Repairs
Restroom Upgrades
Refurbish classrooms and offices
Budget: $1,447,595 Architect: Westwork General Contractor: TBD Est. Date for Completion: Fall 2013
Monte Vista Elementary School
25
Address: 712 Girard NE Square Footage: 116,204 Year Opened: 1938 CMP 2011-16 Strategy Projects:
New Track with Drainage System
Parent Drop Off
Budget: $808,194 Architect/ Engineer: High Mesa Consulting
Group General Contractor: TBD Est. Date for Completion: Spring 2013
Jefferson Middle School
26
Address: 5200 Cutler Ave NE Square Footage: 44,369 sq. ft. Year Opened: 1915
CMP 2011-16 Strategy Project: Phase 2 Cafeteria and Site development Budget: $4,552,167 Architect: Greg T. Hicks General Contractor: TBD
Est. Date of Completion: Dec 2013
eAcademy Alternative School
27
MacArthur Elementary School Address: 1100 MacArthur Rd NW Square Footage: 42,604 Year Opened: 1948 Current Projects: • Kindergarten Classroom & Play Lot • Cafeteria Addition / Kitchen Upgrades • Improve Site Lighting for Security • Install Security Fencing • Site Improvements Budget: $3,689,297 Est. Date of Completion: Dec 2013 Architect: Wright & Hammer General Contractor: TBD
28
Address: 800 Louisiana St NE Year Opened: 2012 CMP 2011-16 Strategy Projects:
New food services facility
Budget: $14.4 Million Architect: TBD ( Programming phase) General Contractor: TBD Est. Date for Completion: Summer 2014
Central Kitchen
29
Recently Completed Projects
30
Address: 12015-B Tivoli Ave NE Square Footage: 44,601 Year Opened: 1970 Completed Projects: Classroom addition Art room Playground Improvements Restroom Renovations
Date of Completion: July 2011 Budget: $7,020,251 Architect: Greg T. Hicks O/E General Contractor: Makwa Builders
John Baker Elementary School
31
Address: 24 Public School Rd Tijeras, NM 87059
Square Footage: 64,002 Year Opened: 1991 Completed Projects: Kindergarten and Computer Lab
Addition Electrical Upgrade
Date of Completion: June 2011 Budget: $2,809,999 Architect: Design Plus Contractor: Janstar Builders, Inc.
A. Montoya Elementary School
32
Address: 620 Georgia Street SE Square Footage: 58,500 Year Opened: 1952 Completed Projects: Kindergarten Addition Site Work - LEED Art Room Refurbish Restrooms Playground Improvements
Date of Completion: Jan 2011 Budget: $2,938,667 Architect: AECOM General Contractor: Vigil & Rio Conchos
Emerson Elementary School
33
Address: 721 Tomasita NE 87123 Square Footage: 84,416 Year Opened: 1965 Completed Projects: HVAC Improvements Admin. Addition and Refurbish
Date of Completion: July 2011 Budget: $2,406,547 Architect/Eng: WH Pacific General Contractor: Michael S. Rich CMP 2011-16 Strategy Projects: Supplemental Admin addition Upgrade science area Music area renovation Budget: $2,320,147 Architect: TBD General Contractor: TBD
Kennedy Middle School
34
Address: 1505 Candelaria NW Square Footage: 341,710 Year Opened: 1954-55 Completed Projects: HVAC in Gym Shop/Fine Arts Addition & Police
Facility Remodel Pool Locker Rooms
Date of Completion: Nov 2011 Budget: $10,760,888 Architect/Eng: NCA, Allison Engineers General Contractor: Shumate
Constructors
CMP 2011-16 Strategy Projects: Renovate Building Construction of New Classroom &
Soccer Field Relocate Tennis Courts and Police
Station Budget: $ 8,151,554
Valley High School
35
Address: 1100 Solar NW Square Footage: 38,424 Year Opened: 1952 Projects: Kindergarten Addition Playground / Basketball Court
Improvements Date Completed: March 2010 Budget: $2,046,214 Architect: G. Donald Dudley General Contractor: Famco
Alvarado Elementary School LEED Silver Certified
36
Address: 6300 Claremont Ave NE Square Footage: 53,058 Year Opened: 1960 Completed Projects: Cafeteria Kitchen Additions &
Renovations Site improvements Electrical upgrades
Budget: $1,613,624 Architect: Greg T. Hicks General Contractor: Jim Sena
Construction Co., Inc. Date of Completion: Aug 2012
Zuni Elementary School
37
Address: 6700 Palomas NE Square Footage: 63,608 Year Opened: 1983 Current Projects: Administration Expansion Loop Road Improvements Electrical / Lighting Upgrade Site Health & Safety Projects
Budget: $1,237,354 Architect: Westwork General Contractor: CC Construction Date of Completion: Aug 2012
E. G. Ross Elementary School
38
Truman Middle School
Address: 9400 Benavides SW Square Footage: 88,269 Year Opened: 1975 CMP 2011-16 Strategy Projects: Construct Classroom Wing Parent Drop-off/Pick-up Drainage Upgrades Budget: $7,268,941 Architect: Fanning Bard Tatum General Contractor: T.A. Cole & Sons Date of Completion: Dec 2011
39
Address: 5200 Cutler Ave NE Square Footage: 44,369 sq. ft. Year Opened: 1915 Phase 1 completion: April 2011 Administration/Classroom Building
LEED Date of Completion: April 2011 Budget: $8,262,423 Architect: Integrated Design &
Architecture General Contractor: Longhorn
eAcademy Alternative School
Address: 12015 Tivoli NE 87111 Square Footage: 10,0122 Year Opened: 1966 Current Projects: Cafeteria Kitchen Renovation and
Addition Gym and Locker room upgrades HVAC improvements
Date of Completion: December 2012 Budget: $1,202,464 Architect/Eng: DWL General Contractor: CC Construction
CMP 2011-16 Strategy Projects:
Supplement for Cafeteria/Kitchen renovation and Gym locker upgrades
Site improvements
Budget: $2,391,855
Date of Completion: May 2012
41
Hoover Middle School
Address: Bldg. 25000- KAFB East Square Footage: 57,895 Year Opened: 1952 Grade Levels: K-5 Current Projects: New Parking and Drop-off improvements Classroom Addition
Total Budget: $3,190,511 Architect: Design Group General Contractor: Lockwood Date of Completion: Aug 2012
Wherry Elementary School
42
Atrisco Heritage Academy High School Address: 10800 Dennis Chavez Blvd SW Square Footage: 463,000 Date of Opening: Aug 2008 for 9th grade Aug 2009 for 10th grade Aug 2010 for 11th grade Aug 2012 for 12th grade Budget: $132,000,000 Architect: Fanning Bard Tatum Architects/
Perkins & Will General Contractor: Phase 1: Gerald Martin-COMPLETE Phase 2: Bradbury-Stamm-COMPLETE Phase 3: McCarthy-COMPLETE
This school was constructed to relieve primarily West Mesa High School and the future growth areas of Rio Grande High School and the SW Mesa of Albuquerque
Completed PAC 12th Grade Academy
43
Draft Recommendation
• SB9 14-19
• See handout