Airport considerations and airport solutions

Session 5Presentation 3

Page 2: Airport considerations and airport solutions Session 5 Presentation 3

Construction plan

• Vehicle • access requirements determine standard routes• supervision requirement need for additional airport

safety officers

• Personnel • supervision requirement need for additional airport

safety officers• safety and security familiarization implement a training

program

Page 3: Airport considerations and airport solutions Session 5 Presentation 3

Construction plan

• Facilities • Taxiways, runways, lighting, signage determine

availability

• Communication requirements with ATC • Marking and Signage requirements• FOD develop a FOD control plan• Runway recall determine the recall time• Works develop and distribute NOTAMs

Page 4: Airport considerations and airport solutions Session 5 Presentation 3

Runway use

• Multiple runways • shortened runway considerations:

• Determine new effective operational dimensions

• Single runway• Airport congestion review movement numbers

and update SOPs as required

• Runway and taxiway availability coordinate and determine

• RFF runway access review and update as required

Page 5: Airport considerations and airport solutions Session 5 Presentation 3

Traffic Management

• Aircraft parking determine if additional parking is needed

• Change in aircraft type identify additional ground handling requirements

• extended airport operating hours identify the need for additional human resources

Page 6: Airport considerations and airport solutions Session 5 Presentation 3

Weather

• Determine the effect on:• the duration of the works update NOTAM if required• site access develop alternative access• condition of materials provide protection• safety of personnel develop a contingency plan• fuel stock availability with additional aircraft traffic

requirements coordinate with fuel providers

Page 7: Airport considerations and airport solutions Session 5 Presentation 3

Not common considerations

• Emergency response plan review and revise as required

• All changes to normal operations coordinate and communicate to all airport users

• extended airport operating hours coordinate and promulgate revised hours