air_b_eci
TRANSCRIPT
-
7/29/2019 air_b_eci
1/14
CLASS B AIR CONDITIONING CONTRACTORS
GENERAL TRADE KNOWLEDGEEXAMINATION CONTENT INFORMATION
Revised March 2009
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 1 of 14
The General Trade Knowledge examination will be
administered in one session on the morning of thefirst day of the examination administration. It willconsist of 80 equally weighted questions.
The examination will have questions relating to thefollowing content areas and necessary knowledgefor each area includes: reading and interpreting plans and
specifications reading and interpreting codes basic mathematics
(addition, subtraction, multiplication, division,
calculations of area and volume, fractions,decimals, percentages, calculating the sides oftriangles, square roots, powers of numbers,and solving simple algebraic equations forunknown variables)
You should be prepared to respond to examinationquestions on any of the content areas listed.Questions asked and content areas tested onprevious examinations should not be assumed tobe the only possible questions to be asked orcontent areas to be tested on this examination.
The percentage of questions shown for eachcontent area may vary by as much as plus orminus three (3) percent. Please refer to theCandidate Information Brochure and the ReferenceList for additional information.
Content Area A 15%Pre-Installation
1. Reading and interpreting plans andspecifications
knowledge of symbolsknowledge of scales
2. Recommending changes to plans and
specificationsknowledge of equipment costingknowledge of equipment efficiencyknowledge of design requirements
3. Recommending different types ofequipmentknowledge of equipment costingknowledge of effects on equipment efficiencyknowledge of heating and cooling loadsknowledge of seasonally adjusted and energyefficiency ratio
knowledge of air flow and duct designknowledge of psychrometrics diagramsknowledge of pump curvesknowledge of fan curves
4. Applying energy conservation principlesknowledge of effects on equipment efficiencyknowledge of Florida energy codesknowledge of R and U factorsknowledge of seasonally adjusted energyefficiency ratioknowledge of pump curves
knowledge of fan curves
5. Calculating thermal resistanceknowledge of R and U factorsknowledge of Florida energy codes
6. Discussing EER and SEER with owners andarchitectsknowledge of EER and SEER calculationsknowledge of Florida Energy Codesknowledge of Florida Building Energy RatingSystem
knowledge of ARI listingsknowledge of cost analysis and costeffectiveness
-
7/29/2019 air_b_eci
2/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 2 of 14
7. Determin ing HVAC load(Heating, Ventilation, Air Conditioning)knowledge of Florida energy codesknowledge of heating and cooling loadcalculationsknowledge of R and U factors
8. Determin ing material and equipment liveload requirementsknowledge of weights of materialsknowledge of structural capabilitiesknowledge of rigging
9. Designing HVAC systems(Heating, Ventilation, Air Conditioning)knowledge of equipment efficiencyknowledge of psychrometricsknowledge of heating and cooling loadsknowledge of seasonally adjusted and energy
efficiency ratioknowledge of pressure and enthalpyrelationship (diagrams)knowledge of air flow and duct designknowledge of pipe sizingknowledge of wiring requirements, proceduresand techniquesknowledge of types of controls andrequirementsknowledge of refrigeration requirements
10. Designing duct systems
knowledge of air flow and duct designknowledge of insulation requirements
11. Determining proper HVAC equipment(Heating, Ventilation, Air Conditioning)knowledge of manufacturer's equipmentknowledge of proper sizingknowledge of loadsknowledge of psychrometricsknowledge of proper locations of equipmentknowledge of codes
12. Determining proper pipe sizesknowledge of pipe sizing tablesknowledge of valves and fittingsknowledge of liquid flowknowledge of resistance to flow andfriction losses
13. Determining proper control requirementsknowledge of wiring requirements andprocedures and techniquesknowledge of types of control and requirementsknowledge of air conditioning equipmentknowledge of refrigeration equipment
14. Determining proper fan motor requirementsknowledge of wiring requirements, proceduresand techniquesknowledge of fansknowledge of fan motorsknowledge of fan performance and CFM
15. Determining proper pipe insulationknowledge of heating and cooling loadsknowledge of R and U factorsknowledge of insulating techniques andrequirements
16. Determining proper compressor capacityknowledge of heating and cooling loadsknowledge of refrigeration requirements
17. Designing grease handling duct systemsknowledge of air flow and duct designknowledge of sizingknowledge of fan and motor capabilitiesknowledge of filter requirementsknowledge of fire and building codes
18. Unloading, lifting and lowering materialsknowledge of safety requirementsknowledge of loading and lifting equipmentknowledge of rigging techniques andrequirements
Content Area B 10%Sheet Metal Ducts
1. Fabricating rectangular ducts under 2 ftknowledge of sheet metal ducts
knowledge of fiberglass ductsknowledge of flex ductsknowledge of duct fittingsknowledge of duct outlets and grilles
2. Fabricating rectangular ducts over 2 ft.knowledge of sheet metal ductsknowledge of fiberglass ductsknowledge of duct fittingsknowledge of duct outlets and grilles
-
7/29/2019 air_b_eci
3/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 3 of 14
3. Fabricating round sheet metal ductsknowledge of sheet metal ductsknowledge of duct fittingsknowledge of duct outlets and grillesknowledge of flex ducts
4. Taping duct seams
knowledge of sheet metal ductsknowledge of fiberglass ductsknowledge of flex ductsknowledge of duct fittingsknowledge of duct outlets and grillesknowledge of mastics and tapes
5. Fabricating standing seams for sheet metalductsknowledge of duct fittingsknowledge of sheet metal ducts
6. Fabricating snap lock seams for sheet metalductsknowledge of duct fittingsknowledge of sheet metal duct designrequirements
7. Fabricating other locks and seamsknowledge of sheet metal ductsknowledge of fiberglass duct liners
8. Fabricating interior lined sheet metal ductsknowledge of duct fittings
knowledge of sheet metal duct designrequirements
9. Fabricating fittings for rectangular ductsknowledge of duct fittingsknowledge of sheet metal ducts
10. Fabricating fittings for round ductsknowledge of duct fittingsknowledge of sheet metal lay out
11. Fabricating kitchen hoods
knowledge of codesknowledge of sheet metal lay out
12. Fabricating kitchen hood exhaustsknowledge of codesknowledge of sheet metal lay out
13. Fabricating drain pansknowledge of codesknowledge of sheet metal lay out
Content Area C 25 %Installation of Refrigeration and HVAC Systems
1. Installing split system air conditionersknowledge of duct fittingsknowledge of sheet metal ductsknowledge of air handlers
knowledge of refrigerant pipingknowledge of insulation requirementsknowledge of thermostatsknowledge of heat stripsknowledge of condensate pipingknowledge of condensate overflow protection
2. Installing package system air conditionersknowledge of refrigeration cyclesknowledge of thermostatsknowledge of heat stripsknowledge of condensate piping
knowledge of condensate overflow protection
3. Installing split system heat pumpsknowledge of refrigeration cyclesknowledge of condensersknowledge of air handlersknowledge of refrigerant pipingknowledge of insulationsknowledge of thermostatsknowledge of heat stripsknowledge of condensate pipingknowledge of condensate overflow protection
knowledge of fire stats
4. Installing package heat pumpsknowledge of refrigeration cyclesknowledge of heat pump installationrequirementsknowledge of thermostatsknowledge of heat stripsknowledge of condensate pipingknowledge of condensate overflow protectionknowledge of fire stats
5. Installing air cooled systemsknowledge of air cooled condensersknowledge of air cooled system installationrequirements
6. Installing water cooled systemsknowledge of water cooled condensersknowledge of water cooled system installationrequirements
-
7/29/2019 air_b_eci
4/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 4 of 14
7. Installing secondary coolant systemsknowledge of secondary coolant condensers
8. Installing chil led water(or other temperature) systemsknowledge of chilled water loopsknowledge of water chillers and evaporators
9. Installing water towersknowledge of evaporative coolingknowledge of water tower principles, forceddrag and induced draftsknowledge of secondary coolant condensers
10. Installing systems under 25 tonsknowledge of installation techniques for systemand associated componentsknowledge of dead loadsknowledge of controls
knowledge of wiring procedures andtechniquesknowledge of compressor capacities
11. Installing centrifugal compressor systemsknowledge of centrifugal compressorsknowledge of chilled water systemsknowledge of chilled water loopsknowledge of water chillers and evaporatorsknowledge of pipe fittingsknowledge of motor startersknowledge of gauges
knowledge of valves and fittings
12. Installing absorption cycle systemsknowledge of absorption cyclesknowledge of absorption cycle refrigerantsknowledge of refrigerant piping
13. Installing ultra low temperature systemsknowledge of multistage refrigerationknowledge of cryogenicsknowledge of low temperature refrigerantsknowledge of refrigeration equipment
knowledge of refrigerant piping techniques
14. Installing low and medium temperaturesystemsknowledge of refrigeration equipmentknowledge of refrigerant piping techniquesknowledge of CFC's, HFC's, and blendsknowledge of refrigerant recovery and retrofitknowledge of EPA regulations
15. Installing walk-in coo lersknowledge of refrigeration equipmentknowledge of evaporatorsknowledge of expansion valvesknowledge of defrost equipmentknowledge of refrigerant pipingknowledge of controls
16. Installing reach-in coolersknowledge of refrigeration equipmentknowledge of evaporatorsknowledge of expansion valvesknowledge of defrost equipmentknowledge of refrigerant pipingknowledge of controls
17. Installing ventilation systems (duct work)knowledge of air flow and duct designsknowledge of fire codes
knowledge of scale dimensionsknowledge of sheet metal ductsknowledge of fiberglass ductsknowledge of flex ductsknowledge of duct fittingsknowledge of duct outlets and grillesknowledge of hanging requirements
18. Installing pneumatic control systemsknowledge of control requirementsknowledge of pneumatic pipingknowledge of pneumatic controls
19. Installing g round water (geothermal) heatpumpsknowledge of water cooled condensersknowledge of refrigeration cycles
20. Installing smoke detectorsknowledge of codesknowledge of equipment
21. Installing exhaust (or make-up air) systemsknowledge of fire codes
knowledge of air flow and duct designsknowledge of sheet metal ductsknowledge of fan and motor capacities
22. Installing grease handling duct systemsknowledge of fire codesknowledge of air flow and duct designsknowledge of sheet metal ductsknowledge of filter requirements
-
7/29/2019 air_b_eci
5/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 5 of 14
23. Installing ammonia refrigerant systemsknowledge of absorption cyclesknowledge of ammonia as a refrigerant
24. Installing kitchen exhaust systemsknowledge of air flow and duct designsknowledge of fan and motor capacities
knowledge of sheet metal fabricationsknowledge of national and local fire andbuilding codesknowledge of welding
25. Testing and balancing sys temsknowledge of properties of airknowledge of fansknowledge of testing instrumentsknowledge of duct systemsknowledge of register and grillsknowledge of equations
26. Performing fire department required smoketestsknowledge of properties of airknowledge of fansknowledge of duct systemsknowledge of codes
27. Installing DDC cont rol systemsknowledge of control requirementsknowledge of DDC controls
Content Area D 15%Installation of Refrigeration and HVACEquipment Components
1. Installing air-cooled condensersknowledge of wiring requirements, proceduresand techniquesknowledge of air cooled condensercharacteristicsknowledge of metal pipesknowledge of refrigerant piping
2. Installing water-cooled condensersknowledge of wiring requirements andprocedures and techniquesknowledge of water tower characteristicsknowledge of water cooled condenserscharacteristicsknowledge of secondary coolant condensers
knowledge of metal pipesknowledge of plastic pipesknowledge of pipe fittingsknowledge of refrigerant pipingknowledge of all refrigerants
3. Installing hermetic and semi-hermeticcompressorsknowledge of wiring requirements, proceduresand techniquesknowledge of compressor characteristicsknowledge of metal pipes
knowledge of refrigerant pipingknowledge of all refrigerants
4. Installing centrifugal compressorsknowledge of wiring requirements, proceduresand techniquesknowledge of centrifugal compressorcharacteristicsknowledge of types of refrigerantsknowledge of power requirementsknowledge of design operating pressuresknowledge of motor efficiency ratings
knowledge of metal pipe fittingsknowledge of refrigerant piping
5. Installing air handlers and evaporatorsknowledge of wiring requirements, proceduresand techniquesknowledge of metal pipesknowledge of refrigerant pipingknowledge of all refrigerantsknowledge of control needs and requirementsknowledge of air handlers and characteristics
6. Installing fans and blowersknowledge of wiring requirements, proceduresand techniquesknowledge of air flow and duct designsknowledge of fansknowledge of fan motorsknowledge of air handlersknowledge of condensers
-
7/29/2019 air_b_eci
6/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 6 of 14
7. Installing motors for fans and blowersknowledge of wiring requirements, proceduresand techniquesknowledge of air flow and duct designsknowledge of fansknowledge of fan motorsknowledge of air handlers
8. Installing sheet metal duct workknowledge of sheet metal ductsknowledge of duct fittingsknowledge of duct outlets and grilles
9. Installing fiberglass duct workknowledge of fiberglass ductsknowledge of duct fittingsknowledge of duct outlets and grillesknowledge of duct hanging techniques andrequirements
10. Installing other duct work (flexible)knowledge of air flex duct installation andfastening techniquesknowledge of duct fittingsknowledge of duct outlets and grilles
11. Installing grilles, registers and volumedampersknowledge of air flow and duct designsknowledge of duct outlets and grilles
12. Installing fire dampers and metal chimneysknowledge of fire codesknowledge of fire dampers and metal chimneyinstallations and fastenings
13. Installing refrigerant pipingknowledge of brazingknowledge of refrigerant pipingknowledge of pipe fittingsknowledge of pipe hangingknowledge of pipe sizing
14. Installing horizontally supported pipingknowledge of weights of materialsknowledge of structural capabilitiesknowledge of hangersknowledge of supports
15. Installing f luesknowledge of sheet metal duct installationtechniquesknowledge of duct fittingsknowledge of gas codes
16. Installing air fi lters
knowledge of air filter installation techniques
17. Installing warm air appliances (heaters)knowledge of heater installation techniquesknowledge of wiring procedures andtechniquesknowledge of fire codes
18. Installing gas appliancesknowledge of fuel gasesknowledge of gas appliancesknowledge of installing controls
knowledge of wiring procedures andtechniquesknowledge of gas codes
19. Installing fuel oil appl iancesknowledge of fuel oilsknowledge of fuel appliance installationtechniquesknowledge of types of controls andrequirementsknowledge of wiring requirements, proceduresand techniques
20. Installing heat exchangersknowledge of heat transferknowledge of installing controlsknowledge of wiring requirements, proceduresand techniques
21. Installing receiversknowledge of receiversknowledge of refrigerant pipingknowledge of local codes
22. Installing heat st ripsknowledge of wiring requirements, proceduresand techniquesknowledge of heat stripsknowledge of fire statsknowledge of fire codes
-
7/29/2019 air_b_eci
7/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 7 of 14
23. Installing copper tubing and fittingsknowledge of copper tubingknowledge of refrigerant pipingknowledge of brazingknowledge of pressure testing
24. Installing other tubing or f ittings
knowledge of metal pipesknowledge of weldingknowledge of brazingknowledge of pressure testing
25. Welding and brazing copper tubingknowledge of weldingknowledge of copper tubing
26. Silver brazing copper to steel jointsknowledge of weldingknowledge of copper tubing
knowledge of metal pipes
27. Flaring copper tubingknowledge of copper tubingknowledge of flaring tools
28. Mechanically connecting tubingknowledge of manufacturers recommendations
29. Soft soldering copper tubingknowledge of brazingknowledge of copper tubing
30. Soldering swaged jointsknowledge of brazingknowledge of copper tubingknowledge of metal pipeknowledge of swaging tools
31. Welding metal with f iller rodsknowledge of metal pipesknowledge of welding
32. Installing s teel pipes
knowledge of piping and steel pipesknowledge of pipe fittingsknowledge of hangersknowledge of welding
33. Threading pipesknowledge of pipe fittingsknowledge of metal pipes
34. Cutting mi ld s teel w ith oxy-acetylenetorchesknowledge of oxy-acetylene torchesknowledge of metal pipe characteristics
35. Installing refrigerant tubing under 2 inchesknowledge of brazing
knowledge of copper tubingknowledge of flaring toolsknowledge of swaging toolsknowledge of copper fittingsknowledge of oxy-acetylene torches
36. Installing refrigerant tubing 2 inches or overknowledge of brazingknowledge of copper tubingknowledge of flaring toolsknowledge of swaging toolsknowledge of copper fittings
knowledge of oxy-acetylene torches
37. Installing refrigerant metering devicesknowledge of expansion valvesknowledge of capillary tubesknowledge of brazingknowledge of copper tubing
38. Installing heat pump reversing valvesknowledge of reversing valvesknowledge of copper tubingknowledge of low voltage wiring
39. Installing thermostatic expansion valvesknowledge of expansion valvesknowledge of copper tubing
40. Installing capillary tube metering deviceknowledge of capillary tubesknowledge of copper tubing
41. Installing l iquid line dryers and fi ltersknowledge of dryer and filtersknowledge of copper tubing
knowledge of vacuum systemsknowledge of refrigerant recovery
42. Installing suction line dryers and f iltersknowledge of dryers and filtersknowledge of copper tubingknowledge of vacuum systemsknowledge of refrigerant recovery
-
7/29/2019 air_b_eci
8/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 8 of 14
43. Installing heat pump line dryers and filtersknowledge of dryers and filtersknowledge of copper tubingknowledge of vacuum systemsknowledge of refrigerant recovery
44. Installing oil t raps
knowledge of oil trapsknowledge of copper tubing
45. Installing bellows-type temperature controlsknowledge of control requirementsknowledge of temperature requirementsknowledge of copper tubingknowledge of bellows type temperaturecontrols
46. Installing chilled water low temperaturecontrols
knowledge of low temperature controlsknowledge of control requirementsknowledge of temperature requirementsknowledge of low voltage wiring
47. Installing dual, high or low-pressure controlswitchesknowledge of high and low pressure controlcharacteristicsknowledge of brazingknowledge of copper tubingknowledge of pressure requirements
knowledge of low voltage wiringknowledge of control installation techniques
48. Installing mercury-bulb temperaturecontrolsknowledge of temperature requirementsknowledge of pressure requirementsknowledge of control requirementsknowledge of low voltage wiring
49. Installing oil-pressure safety controlswitches
knowledge of pressure requirementsknowledge of safety requirementsknowledge of pipe fittingsknowledge of control characteristicsknowledge of low voltage wiring
50. Installing summer-winter sw itch-overcontrolsknowledge of low voltage wiringknowledge of temperature requirementsknowledge of control requirements
51. Installing thermostats
knowledge of low voltage wiringknowledge of temperature requirementsknowledge of control characteristics
52. Installing water regulating valvesknowledge of low voltage wiringknowledge of temperature requirementsknowledge of control requirementsknowledge of pressure requirementsknowledge of bellows type temperaturecontrolsknowledge of water valves
53. Installing pressure regulators and strainersknowledge of design pressure requirementsknowledge of control characteristicsknowledge of hot gas bypasses
54. Installing humidity and thermostaticcontrolsknowledge of control characteristicsknowledge of calibrating controlsknowledge of low voltage wiringknowledge of manufacturer's recommendations
55. Installing pneumatic controlsknowledge of pneumatic pipingknowledge of pneumatic controlsknowledge of air compressorsknowledge of control requirements
56. Soldering electrical connectionsknowledge of brazingknowledge of electrical wiring procedures andtechniques
57. Installing transformersknowledge of electrical wiring procedures andtechniquesability to read wiring diagrams
58. Installing capacitorsknowledge of electrical wiring procedures andtechniques
-
7/29/2019 air_b_eci
9/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 9 of 14
59. Installing contactorsknowledge of electrical wiring procedures andtechniques
60. Installing current relaysknowledge of electrical wiring procedures andtechniques
61. Installing safety disconnectsknowledge of electrical wiring procedures andtechniques
62. Installing defrost timersknowledge of electrical wiring procedures andtechniquesknowledge of control requirementsknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship between
current voltage and resistance
63. Install ing defrost heatersknowledge of electrical wiring proceduresknowledge of control requirementsknowledge of defrost operation
64. Installing defrost thermostatsknowledge of electrical wiring procedures andtechniquesknowledge of control requirementsknowledge of wiring diagrams
knowledge of placement of electrical wiresknowledge of electrical-relationship betweencurrent voltage and resistance
65. Installing air-pressure swi tchesknowledge of pneumatic pipingknowledge of pneumatic controlsknowledge of air compressorsknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical-relationship betweencurrent voltage and resistance
66. Installing electric humidistatsknowledge of electrical wiring procedures andtechniquesknowledge of humidity control requirementsknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship betweencurrent voltage and resistance
67. Installing electronic air c leanersknowledge of electrical wiring procedures andtechniquesknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship betweencurrent voltage and resistance
knowledge of manufacturer's recommendations
68. Wiring three-phase equipmentknowledge of electrical wiring procedures andtechniquesknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship betweencurrent voltage and resistance
69. Wiring single-phase equipmentknowledge of electrical wiring procedures and
techniquesknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship betweencurrent voltage and resistance
70. Installing three-phase equipmentknowledge of electrical wiring procedures andtechniquesknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship between
current voltage and resistance
71. Installing s ingle-phase equipmentknowledge of electrical wiring procedures andtechniques
72. Installing capacitor start motorsknowledge of electrical wiring procedures andtechniquesknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship between
current voltage and resistanceknowledge of fan motorsknowledge of compressor requirements
-
7/29/2019 air_b_eci
10/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 10 of 14
73. Installing shaded pole-motorsknowledge of electrical wiring procedures andtechniquesknowledge of fan motorsknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship between
current voltage and resistance
74. Installing split-phase motorsknowledge of electrical wiring procedures andtechniquesknowledge of fan motorsknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship betweencurrent voltage and resistance
75. Installing fan blades
knowledge of fansknowledge of wiring diagramsknowledge of placement of electrical wiresknowledge of electrical relationship betweencurrent voltage and resistance
76. Installing fan control switchesknowledge of electrical wiring procedures andtechniquesknowledge of fan motorsknowledge of control requirementsknowledge of low voltage wiring
77. Installing hermetic compressor overloadprotectorsknowledge of electrical wiring procedures andtechniquesknowledge of safety requirements
78. Installing fan beltsknowledge of fansknowledge of motor amperage requirements
79. Installing drive pulleys
knowledge of fansknowledge of pulley ratiosknowledge of motor amperage requirements
80. Installing lim it con trol switchesknowledge of control characteristicsknowledge of safety requirements
81. Installing solenoid coilsknowledge of electrical wiring procedures andtechniquesknowledge of low voltage wiring
82. Installing magnetic s tartersknowledge of electrical wiring procedures and
techniques
83. Installing starting relaysknowledge of electrical wiring procedures andtechniques
84. Installing duty-motor protection devicesknowledge of electrical wiring procedures andtechniques
85. Installing motor controllersknowledge of motor controllers
knowledge of proper motor and overcurrentprotectionknowledge of circuit breakers and fusesknowledge of electrical wiring proceduresknowledge of controls
86. Installing p lastic pipes and fittingsknowledge of plastic pipes and fittingsknowledge of different grades of pipeknowledge of pressure testingknowledge of safety codesknowledge of joining materials
knowledge of cleaning and gluing materials
Content Area E 10%Maintenance Analysis of Refrigeration andHVAC Systems
1. Reading pressure and enthalpy diagramsfor various refrigerantsknowledge of pressure and enthalpyrelationshipsknowledge of reading pressures
knowledge of gaugesknowledge of refrigeration testing equipment
2. Reading and analyzing electrical circuitsknowledge of electrical wiring procedures andtechniquesknowledge of low voltage wiringknowledge of electrical testing equipment
-
7/29/2019 air_b_eci
11/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 11 of 14
3. Testing current relaysknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
4. Testing capacitorsknowledge of electrical wiring procedures and
techniquesknowledge of electrical testing equipment
5. Testing defrost thermostatsknowledge of controlsknowledge of manufacturer's recommendations
6. Testing high-voltage transformersknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
7. Testing high voltage relaysknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
8. Testing low voltage relaysknowledge of low voltage electrical wiringprocedures and techniquesknowledge of electrical testing equipmentability to utilize a amprobeability to utilize a ohmmeter
9. Testing magnetic startersknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
10. Testing potent ial relaysknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
11. Testing appropriate motor terminalsknowledge of electrical wiring procedures and
techniquesknowledge of electrical testing equipment
12. Determin ing operating pressures ofrefrigeration or air condition ing systemsknowledge of design pressure requirementsknowledge of refrigerant pressure gaugesknowledge of pressure and temperaturerelationships
13. Determining air vo lumesknowledge of air flow and duct designsability to utilize a velometerability to utilize a pitot tubeability to utilize a manometerability to utilize a volume flow meter (flow hood)
14. Determining changes in enthalpyknowledge of refrigeration testing equipmentknowledge of psychrometricsability to utilize a thermometerability to utilize a psychrometer
15. Determin ing wet bulb and dry bu lbtemperaturesknowledge of refrigeration testing equipmentknowledge of psychrometricsability to utilize a thermometerability to utilize a psychrometer
16. Determining current draw (amperage)knowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipmentability to utilize an amprobeability to utilize a volt-ohm meter
17. Determining vol tageknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
ability to utilize an amprobeability to utilize a volt-ohm meter
18. Determining power consumptionknowledge of electrical wiring procedures andtechniquesknowledge of electrical testingequipment
19. Determining working pressure in pipesknowledge of pressure testing gaugesknowledge of access valves
20. Testing non-pressure type storage tanksknowledge of tanks and pollution controls
-
7/29/2019 air_b_eci
12/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 12 of 14
21. Testing closed-liquid solar systems (eitherwater or air)knowledge of solar collector types andcharacteristicsknowledge of solar collector controlsknowledge of solar collector pipingknowledge of solar heating
knowledge of solar hot water heatingknowledge of refrigeration testing equipment
22. Using testing equipment(velometer, amprobe, volt-ohm meter,vacuum gauges,etc.)knowledge of electrical testing equipmentknowledge of refrigeration testing equipmentknowledge of how and when to use equipment
23. Using chlor ine and halogen leak detectingdevices
knowledge of refrigeration testing equipmentknowledge of how and when to use devices
Content Area F 15%Maintenance Service of Refrigeration andHVAC Systems
1. Using nitrogen regulatorsknowledge of pressure regulators
2. Using other gas regulators
knowledge of pressure regulators
3. Repairing semi-hermetic compressorsknowledge of electrical wiring procedures andtechniquesknowledge of mechanical methods andprocedures
4. Repairing hermetic compressorsknowledge of electrical wiring procedure andtechniquesknowledge of mechanical methods and
procedures
5. Repairing centrifugal compressorsknowledge of electrical wiring procedure andtechniquesknowledge of mechanical methods andprocedures
6. Repairing blowersknowledge of electrical wiring procedures andtechniquesknowledge of fansknowledge of fan motors
7. Calibrating air sensit ive thermostats
knowledge of electrical wiring procedures andtechniquesknowledge of fansknowledge of fan motors
8. Calibrating chil led-water low temperaturecontrolsknowledge of low temperature controlsknowledge of control requirementsknowledge of low voltage wiringknowledge of temperature requirementsknowledge of refrigeration testing equipment
9. Calibrating dual or low pressure controlswitchesknowledge of high and low pressure controlsknowledge of brazingknowledge of copper tubingknowledge of refrigeration testing equipment
10. Calibrating pneumatic controlsknowledge of pneumatic pipingknowledge of pneumatic controlsknowledge of air compressors
11. Calibrating proportional thermostatsknowledge of low voltage wiringknowledge of temperature requirementsknowledge of control requirementsknowledge of refrigeration testing equipment
12. Calibrating summer-winter switch-overcontrolsknowledge of low voltage wiringknowledge of temperature requirementsknowledge of control requirements
knowledge of refrigeration testing equipment
13. Adjusting thermostatic temperaturecontrolsknowledge of low voltage wiringknowledge of temperature requirementsknowledge of control requirementsknowledge of refrigeration testing equipment
-
7/29/2019 air_b_eci
13/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 13 of 14
14. Adjusting thermostatic motor controlsknowledge of low voltage wiringknowledge of temperature requirementsknowledge of control requirementsknowledge of refrigeration testing equipmentknowledge of electrical wiring procedures andtechniques
15. Adjusting super heat setting on expansionvalvesknowledge of expansion valvesknowledge of control requirementsknowledge of refrigeration testing equipmentknowledge of superheat
16. Adjusting oi l pressure safety controlsknowledge of pressureknowledge of gaugesknowledge of pipe fittings
knowledge of control requirementsknowledge of low voltage wiringknowledge of refrigeration testing equipment
17. Adjusting mercury bulb temperaturecontrolsknowledge of temperature requirementsknowledge of pressure requirementsknowledge of control requirementsknowledge of low voltage wiringknowledge of refrigeration testing equipment
18. Adjusting high pressure safety cutoutsknowledge of high and low temperaturecontrolsknowledge of electrical wiring procedures andtechniquesknowledge of low voltage wiringknowledge of control operating requirementsknowledge of refrigeration testing equipmentknowledge of pressure gauges
19. Adjusting freezer controlsknowledge of control operating requirements
knowledge of low voltage wiringknowledge of temperature measurements
20. Adjusting defrost t ime clocksknowledge of control requirementsknowledge of low voltage wiringknowledge of electrical wiring procedures andtechniquesknowledge of temperature measurement
21. Adjusting bellows-type temperaturecontrolsknowledge of control requirementsknowledge of temperature requirementsknowledge of bellows-type temperaturecontrols operating requirements
22. Operating oil safety control solid statepressure censoring deviceknowledge of pressure requirementsknowledge of safety requirementsknowledge of control operating requirementsknowledge of low voltage wiringknowledge of refrigeration testing equipment
23. Aligning drive pulleysknowledge of mechanical alignments
24. Adjusting tension of v-belts
knowledge of how and when to adjust
25. Calibrating electric actuating valvesknowledge of mechanical operationrequirementsknowledge of refrigeration testing equipment
26. Calibrating electric humidistatsknowledge of humidity control requirementsknowledge of control requirementsknowledge of low voltage wiringknowledge of refrigeration testing equipment
27. Reversing the rotation of three-phase orsingle-phase motorsknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
28. Starting seized hermetic compressormotorsknowledge of electrical wiring procedures andtechniquesknowledge of electrical testing equipment
29. Adjusting crankcase pressure regulatingvalvesknowledge of pressure regulatorsknowledge of pressure measurementknowledge of evaporatorsknowledge of compressors
-
7/29/2019 air_b_eci
14/14
Class B Air Conditioning Contractors General Trade Knowledge Examination Content InformationPage 14 of 14
30. Adjusting evaporator pressure regulatingvalvesknowledge of pressure regulatorsknowledge of pressure measurementknowledge of evaporatorsknowledge of superheat
31. Adjusting unloadersknowledge of pressure measurement (gauges)knowledge of effect of pressure on compressorcapacities
32. Cleaning cool ing towersknowledge of cleaning chemicalsknowledge of scale propertiesknowledge of water deposit controlsknowledge of bleed-off
33. Cleaning foreign matter from systems
knowledge of cleaning chemicalsknowledge of solvents
34. Cleaning water-cooled condensersknowledge of cleaning chemicalsknowledge of water-cooled condensersknowledge of organic water problems
Content Area G 10%Safety and Equipment
1. Wearing hearing and head protectionknowledge of safety requirements
2. Installing warning signs and barricadesknowledge of safety requirements
3. Wearing eye and face protectionknowledge of safety requirements
4. Using respiratory protectionknowledge of safety requirements
5. Digging with backhoes, trenchers ortractorsknowledge of safety requirements
6. Using overhead hois ts and cranesknowledge of safety requirementsknowledge of weightsknowledge of riggings
7. Using ventilation devicesknowledge of safety requirementsknowledge of toxic materials
8. Using mobi le equipment(e.g., forklifts, hi-lifts and cranes)knowledge of safety requirements
9. Using ladders, scaffolds and rollingplatformsknowledge of safety requirementsknowledge of assembly
10. Using various hand and power tools(e.g., power shears, wrenches and snips)knowledge of safety requirementsknowledge of proper operation procedures
11. Using air compressors
knowledge of safe operating pressuresknowledge of safety requirements