Project Name: AGRARIAN REFORM COMMUNITIES PROJECT II Executing Agency: DEPARTMENT OF AGRARIAN REFORM Country: PHILIPPINES Loan (Grant) Number: 2465-PHI Loan Amount: $208.9 MILLION Coverage of Plan 2009-2014 Date of First Procurement Plan: 2009 Date of Approval of Plan 12 September 2013 A. Process Thresholds, Review and 18-Month Procurement Plan 1. Project Procurement Thresholds 1. Except as the Asian Development Bank (ADB) may otherwise agree, the following thresholds shall apply to procurement of goods and works Method Threshold* International Competitive Bidding for Works At least $5,000,000 International Competitive Bidding for Goods At least $1,000,000 National Competitive Bidding for Works Less than $5,000,000 but more than $100,000 National Competitive Bidding for Goods Less than $1,000,000 but more than $100,000 Shopping for Works Less than $100,000 Shopping for Goods Less than $100,000 Community Participation Less than $30,000 * Project Administration Instruction (PAI) 3.04 Revised April 2008 Method Threshold* Quality and Cost Based Selection Above $200,000 Consultants' Qualifications Selection Below $200,000 Least Cost Selection Below $100,000 Single Source Selection Individual Selection * Project Administration Instruction (PAI) 3.04 Revised April 2008 2. ADB Prior or Post Rview 2. Except as ADB may otherwise agree, the following prior or post review requirements appy to the various procurement and consultant recruitment methods used for the project. Procurement Method Prior or Post Comments Procurement of Goods and Works NCB Works Post NCB Goods Post Shopping for Works Post Shopping for Goods Post BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS

Upload: others

Post on 13-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Project Name: AGRARIAN REFORM COMMUNITIES PROJECT II Executing Agency: DEPARTMENT OF AGRARIAN REFORM

Country: PHILIPPINES Loan (Grant) Number: 2465-PHI

Loan Amount: $208.9 MILLION Coverage of Plan 2009-2014

Date of First Procurement Plan: 2009 Date of Approval of Plan 12 September 2013

A. Process Thresholds, Review and 18-Month Procurement Plan

1. Project Procurement Thresholds

1. Except as the Asian Development Bank (ADB) may otherwise agree, the following thresholds shall apply to procurement of goods and works

Method Threshold*

International Competitive Bidding for Works At least $5,000,000

International Competitive Bidding for Goods At least $1,000,000

National Competitive Bidding for Works Less than $5,000,000 but more than $100,000

National Competitive Bidding for Goods Less than $1,000,000 but more than $100,000

Shopping for Works Less than $100,000

Shopping for Goods Less than $100,000

Community Participation Less than $30,000* Project Administration Instruction (PAI) 3.04 Revised April 2008

Method Threshold*

Quality and Cost Based Selection Above $200,000

Consultants' Qualifications Selection Below $200,000

Least Cost Selection Below $100,000

Single Source Selection

Individual Selection * Project Administration Instruction (PAI) 3.04 Revised April 2008

2. ADB Prior or Post Rview

2. Except as ADB may otherwise agree, the following prior or post review requirements appy to the various procurement and consultant recruitment methods used for the project.

Procurement Method Prior or Post Comments

Procurement of Goods and Works

NCB Works Post

NCB Goods Post

Shopping for Works Post

Shopping for Goods Post

BASIC DATA

PROCUREMENT OF CONSULTING SERVICES

PROCUREMENT OF GOODS AND WORKS

Page 2: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Recruitment of Consulting Firm

Quality and Cost Based Selection Prior

Consultants' Qualifications Selection Prior

Land Tenure Improvement (LIT) Surveys

- LTI contracts costing more than $75,000 Prior

- LTI contracts costing $75,000 and below Post

- New areas Prior for first two LTIs of each new project area

Individual Selection Prior

3. Goods and Works Contracts Estimated to Cost More Than $1 Million

4. Consulting Services Contracts Estimated to Cost More Than $100,000

4. The following table lists consulting services contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.

Package Amout (PhP) Amount (US$)Mode of

ProcurementPQ Advertisement Dte Remarks

A. CONSULTING SERVICES

1 30,000,000.00 667,052.07

a. 15 Individuals 30,000,000.00 667,052.07 Individual N 2nd Qrt 2012 On-going procurement

2 619,838,960.18 13,782,162.14

a. 248 contracts 196,198,344.18 4,362,483.75 LCS N 2nd Qtr 2010 On-going procurement

b. 1 package 30,000,000.00 667,052.07 QCBS N 2nd Qtr 2012 For procurement

1 package 20,000,000.00 444,701.38 QCBS N 3rd Qtr 2013 For Procurement

1 package 7,000,000.00 155,645.48 CQS N 3rd Qtr 2013 For Procurement

1 package 7,000,000.00 155,645.48 CQS N 4th Qtr 2013 For Procurement

1 package 15,000,000.00 333,526.04 QCBS N 3rd Qtr 2013 For Procurement

1 package 34,000,000.00 755,992.35 QCBS N 3rd Qtr 2013 For Procurement

1 package 100,000,000.00 2,223,506.92 QCBS N 4th Qtr 2013 For Procurement

1 package 7,396,000.00 164,450.57 CQS N 3rd Qtr 2013 Contract Awarded

1 package 19,688,000.00 437,764.04 QCBS N 4th Qtr 2011 Contract Awarded

1 package 183,556,616.00 4,081,394.05 QCBS N 2nd Qtr 2010 Contract Awarded

649,838,960.18 14,449,214.217

Engineering Quality Assurance

Special Mgt Team

Firms

CONSULTING SERVICES

Engagement for the Project Completion Report

Engineering Quality Assurance (Supplemental)

High Value Vegetable Production using the Natural

Farming System Technology

ARC Cluster Development Study

Baseline Survey / Woodfields

Conduct of Geo Tag Monitoring System for RI

TOTAL CONTRACT PACKAGES AND COST

Domestic-Individual

LTI Survey/Reso. Of Cases/Redocumentations

Engagement for the Mid-Term Review

Engagement of Experts on Geo-tagging Monitoring

System

ARCP II Consultants

Page 3: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

5

5. The following table groups smaller - value goods, works and consulting services contracts for which procurement activity is either ongoing or expected to commence within the next 18 months.

A. CIVIL WORKS

a.1

01.Magdiwang, Romblon 3,061,724.49 1 NCB N 4th Qtr 2012 On-going procurement

02.Magdiwang, Romblon 4,032,875.80 1 NCB N 3rd Qtr 2012 On-going procurement

03.Sta. Fe, Romblon 2,101,898.31 1 Shopping N 1st Qtr 2012 On-going procurement

04.Sta. Fe, Romblon 4,251,783.04 1 NCB N 3rd Qtr 2012 On-going procurement

05.San Andres, Romblon 9,918,013.12 1 NCB N 1st Qtr 2012 On-going procurement

06.Ferrol, Romblon 6,361,728.20 1 NCB N 4th Qtr 2012 For procurement

07.Ferrol, Romblon 12,799,225.49 1 NCB N 4th Qtr 2012 For procurement

08.Bulalacao, Oriental Mindoro 9,798,149.56 1 NCB N 4th Qtr 2012 On-going procurement

09.Bulalacao, Oriental Mindoro 9,993,418.46 1 NCB N 4th Qtr 2012 On-going procurement

10.Bulalacao, Oriental Mindoro 12,165,188.01 1 NCB N 3rd Qtr 2013 For procurement

11.Bansud, Oriental Mindoro 2,897,370.76 1 NCB N 3rd Qtr 2013 For procurement

12.Bansud, Oriental Mindoro 4,798,859.40 1 NCB N 3rd Qtr 2013 For procurement

13.Mansalay, Oriental Mindoro 2,880,471.89 1 NCB N 3rd Qtr 2013 For procurement

14.Mansalay, Oriental Mindoro 3,017,813.27 1 NCB N 3rd Qtr 2013 For procurement

15.Mansalay, Oriental Mindoro 2,703,668.17 1 NCB N 3rd Qtr 2013 For procurement

16.Roxas, Oriental Mindoro 4,218,122.31 1 NCB N 3rd Qtr 2013 For procurement

17.Pinamalayan, Oriental Mindoro 1,292,192.75 1 Shopping N 3rd Qtr 2013 For procurement

18.Pinamalayan, Oriental Mindoro 1,418,616.10 1 NCB N 3rd Qtr 2013 For procurement

19.Pinamalayan, Oriental Mindoro 1,290,483.29 1 Shopping N 3rd Qtr 2013 For procurement

20.Aborlan, Palawan 3,229,663.23 1 NCB N 3rd Qtr 2013 For procurement

21.Aborlan, Palawan 4,295,920.18 1 NCB N 3rd Qtr 2013 For procurement

22.Labo, Camarines Norte 2,090,172.38 1 NCB N 1st Qtr 2012 On-going procurement

23.Labo, Camarines Norte 3,185,961.76 1 NCB N 1st Qtr 2012 On-going procurement

24.Labo, Camarines Norte 1,047,440.29 1 Shopping N 1st Qtr 2012 On-going procurement

Rural Access

Rehabilitation with Spot Concreting of San Roque

Tafarma Bulalacao

Rehabilitation with Spot Concreting of Dancalan-San

Roque-Libtong Farm to Market Road

Concreting of Hinag-oman-Culasi-Guin-awayan Farm

to Market Road

Rehabilitation of Palate Farm to Market Road

Rehabilitation of Magsaysay-Pandan Farm to Market

Road

Concreting of C.M Recto-Lupog Farm to Market Road

Concreting of Sta. Maria to Villarosa Farm to Market

Road

Concreting of Cambunang-Napisian-Cogon Malapad

Farm to Market Road

Concreting of Balugo to Maliwanag Farm to Market

Road

Cons./Rehab. of Tagpit-Titibawan Farm to Market Road

Rehabilitation of Binaliwan FMR

Rehabilitation of Cataja FMR

Const. of Sanghiran-Campo-Agpudlos Proper Farm to

Market Road

Construction/Concreting of Brgy. Rosario, Sitio-

Sta.Clara FMR

Concreting of Naboongan-Igang Farm to Market Road

Rehabilitation w/ Spot Concreting of Pag-Asa-Conrazon

Farm to Market Road

Construction and Rehabilitation with Spot Concreting of

Laway I-Kantong Putol FMR

Concreting of Brgy. Papandayan, Nat'l. Highway to Sitio-

Laloma FMR

Construction of Purok 1 Farm to Market Road

Construction with Spot Concreting of Sta. Brigida to

Alegria Farm to Market Road

Construction and Concreting of San Aquilino-Lagundi 2-

Sarada-San Isidro Farm to Market Road

Concreting of Brgy. Del Razon, Sitio Antipolo FMR

Const. of Maligaya-Tarektek-Mayligan Farm to Market

Road

Concreting of Macogon Barangay Road

Number of

Contracts

Goods and Works contracts Estimated to Cost less than $ 1 Million and Consulting Services Contracts Less than $ 100,000.

CommentsValue of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

Page 4: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

25.Labo, Camarines Norte 2,736,899.89 1 NCB N 1st Qtr 2012 On-going procurement

26.Labo, Camarines Norte 2,053,405.63 1 NCB N 1st Qtr 2012 On-going procurement

27.Capalonga, Camarines Norte

4,671,016.82 1 NCB N For procurement

28.Paracale, Camarines Norte

2,509,971.09 1 NCB N 1st Qtr 2012 On-going procurement

29.Paracale, Camarines Norte

5,459,592.70 1 NCB N 1st Qtr 2012 On-going procurement

30.Paracale, Camarines Norte

10,065,808.82 1 NCB N 2nd Qtr 2012 On-going procurement

31.Paracale, Camarines Norte

6,655,383.33 1 NCB N 3rd Qtr 2012 On-going procurement

32.Paracale, Camarines Norte

2,859,457.11 1 NCB N 3rd Qtr 2012 On-going procurement

33.Paracale, Camarines Norte

5,878,071.53 1 NCB N 3rd Qtr 2012 On-going procurement

34.Paracale, Camarines Norte

9,591,074.91 1 NCB N 3rd Qtr 2012 On-going procurement

35.Basud, Camarines Norte

2,851,858.89 1 NCB N 1st Qtr 2012 On-going procurement

36.Basud, Camarines Norte

2,988,857.26 1 NCB N 1st Qtr 2012 On-going procurement

37.Basud, Camarines Norte

5,063,911.04 1 NCB N 4th Qtr 2012 On-going procurement

38.Basud, Camarines Norte

3,385,929.02 1 NCB N 4th Qtr 2012 For procurement

39.Basud, Camarines Norte

2,959,278.36 1 NCB N 3rd Qtr 2013 For procurement

40.Basud, Camarines Norte

1,632,943.91 1 Shopping N 3rd Qtr 2013 For procurement

41.Basud, Camarines Norte

737,785.48 1 Shopping N 3rd Qtr 2013 For procurement

42.Basud, Camarines Norte

863,526.62 1 Shopping N 2nd Qtr 2012 On-going procurement

43.Basud, Camarines Norte

2,303,393.87 1 NCB N 3rd Qtr 2012 On-going procurement

44.San Lorenzo Ruiz, Cam. Norte

1,230,449.78 1 Shopping N 2nd Qtr 2012 On-going procurement

45.San Lorenzo Ruiz, Cam. Norte

705,771.79 1 Shopping N 3rd Qtr 2013 For procurement

46.San Lorenzo Ruiz, Cam. Norte

4,219,578.39 1 NCB N 1st Qtr 2012 Completed Procurement

Concreting of Matnog Farm to Market Road

Construction of Laniton Farm to Market Road

Rehabilitation of Magsaysay-Benguet Farm to Marke

Road

Rehabilitation of Batobalani-Igang Farm to Market

Road

Concreting of Batobalani-Igang FMR (Phase II)

Concreting of 2.90 kms Sitio Submakin

Concreting of Malangcao-Basud (Purok 6 - Purok 7)

Farm to Market Road

Concreting of Purok 7 Farm to Market Road

Concreting of San Isidro-Sitio Too Farm to Market

Road

Concreting of San Ramon, Purok 1-Purok 2 Farm to

Market Road

Concreting of Caayunan Farm to Market Road

Concreting of Tuaca-San Pascual Farm to Market Road

Concreting of San Felipe Farm to Market Road

Concreting of ARC Access Road

Concreting of Purok 2 Matacong Farm to Market

Road

Concreting of Tuaca-San Pascual Farm to Market

Road Phase IIConcreting of San Felipe-Caayunan Farm to

Market RoadConcreting of San Felipe-Mantugawe Farm to

Market Road

Concreting of Dagang - Tabas Farm to Market Road

Rehabilitation of Matanlang-Casalugan Farm to Market

Road

Concreting of Capacuan (Purok 1-5) Farm to Market

Road

Construction of 2.10 kms Sitio Potot FMR

Page 5: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

47.San Lorenzo Ruiz, Cam. Norte

10,579,350.27 1 NCB N 1st Qtr 2012 Completed Procurement

48.San Lorenzo Ruiz, Cam. Norte

4,581,926.98 1 NCB N 3rd Qtr 2012 For procurement

49.Jose Panganiban, Camarines Norte

4,510,570.92 1 NCB N 3rd Qtr 2012 On-going procurement

50.Jose Panganiban, Camarines Norte

4,895,391.96 1 NCB N 3rd Qtr 2012 On-going procurement

51.Jose Panganiban, Camarines Norte

5,065,129.11 1 NCB N 3rd Qtr 2012 On-going procurement

52.Jose Panganiban, Camarines Norte

5,053,347.90 1 NCB N 3rd Qtr 2012 On-going procurement

53.Jose Panganiban, Camarines Norte

2,202,243.42 1 NCB N 3rd Qtr 2013 For procurement

54.Del Gallego, Camarines Sur

2,658,853.96 1 NCB N 3rd Qtr 2012 On-going procurement

55.Del Gallego, Camarines Sur

2,741,104.35 1 NCB N 3rd Qtr 2012 On-going procurement

56.Del Gallego, Camarines Sur

3,602,339.96 1 NCB N 4th Qtr 2012 For procurement

57.Del Gallego, Camarines Sur

1,508,221.64 1 Shopping N 4th Qtr 2012 For procurement

58.Del Gallego, Camarines Sur

1,696,155.99 1 Shopping N 3rd Qtr 2013 For procurement

59.Del Gallego, Camarines Sur

1,447,074.81 1 Shopping N 3rd Qtr 2013 For procurement

60.Libmanan, Camarines Sur

900,016.13 1 Shopping N Completed Procurement

61.Libmanan, Camarines Sur

1,159,674.65 1 Shopping N 4th Qtr 2012 For procurement

62.Libmanan, Camarines Sur

1,001,526.96 1 Shopping N 3rd Qtr 2012 On-going procurement

63.Libmanan, Camarines Sur

1,072,102.73 1 Shopping N 4th Qtr 2012 For procurement

64.Milaor, Camarines Sur

3,681,893.27 1 NCB N 3rd Qtr 2012 On-going procurement

65.Milaor, Camarines Sur

4,073,695.80 1 NCB N 4th Qtr 2012 On-going procurement

66.Milaor, Camarines Sur

3,711,320.66 1 NCB N 4th Qtr 2012 On-going procurement

67.Tigaon, Camarines Sur 9,462,717.98 1 NCB N 3rd Qtr 2013 For procurement

68.Tigaon, Camarines Sur 5,726,930.06 1 NCB N 3rd Qtr 2013 For procurement

69.Garchitorena, Camarines Sur

5,855,490.69 1 NCB N Completed Procurement

70.Garchitorena, Camarines Sur

5,668,411.25 1 NCB N 4th Qtr 2012 For procurement

71.Garchitorena, Camarines Sur

2,516,511.95 1 NCB N 4th Qtr 2012 For procurement

72.Garchitorena, Camarines Sur

1,385,310.59 1 Shopping N 3rd Qtr 2013 For procurement

73.Buhi, Camarines Sur 716,235.58 1 Shopping N Completed Procurement

74.Buhi, Camarines Sur 3,884,147.01 1 NCB N 3rd Qtr 2012 On-going procurement

Concreting of Bgy. San Martin Farm to Market Road

Concreting of Matacong-San Isidro Farm to Market

Road

Concreting of Matacong-San Isidro Farm to Market

Road (Extension)

Concreting of San Pedro-Bagong Silang II FMR

Concreting of Bgy. San Rafael-Sta. Rosa Farm to

Market Road

Concreting of Bgy. Tamisan Farm to Market Road

Construction of Flood Control

Rehabilitation of Aslong Farm to Market Road

Concreting of Potot Farm to Market Road

Concretingof Sitio Hamorawon Farm to Market Road

Concreting of Bgy. San Pedro Farm to Market Road

Concreting of Bahay Farm to Market Road

Construction of Cabugao Farm to Market Road

Concreting of Cabugao-Mayaopayawan-San Antonio

Farm to Market Road

Construction and Concreting of Cabugao-Maydaso

Farm to Market Road

Concreting of Antipolo-Divino Rostro FMR

Rehabilitation/Concreting of Pinagdapian Farm to

Market Road

Rehabilitation/Concreting of San Juan Farm to Maket

Road

Concreting of Penafrancia Farm to Market Road

Concreting of Tomagoktok Farm to Market Road

Construction of Tabion Farm to Market Road

Concreting of Mansalaya Farm to Market Road

Concreting of Tinawagan-Coyaoyao Farm to Market

Road

Concreting of Tinawagan-Barobaroti-Caraycayon Farm

to Market Road

Rehabilitation of Maligaw-ligaw Farm to Market Road

Rehabilitation of Poblacion-Ason Farm to Market Road

Concreting of Bahi-Ason FMR

Flood Control Structure (Revetment) Del Pilar

Page 6: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

75.Buhi, Camarines Sur 1,796,352.92 1 NCB N 4th Qtr 2012 On-going procurement

76.Buhi, Camarines Sur 1,687,108.45 1 NCB N 3rd Qtr 2013 For procurement

77.Baao, Camarines Sur

1,463,193.34 1 Shopping N 3rd Qtr 2012 For procurement

78.Baao, Camarines Sur

1,097,662.87 1 Shopping N 3rd Qtr 2012 For procurement

79.Baao, Camarines Sur

972,229.90 1 Shopping N 3rd Qtr 2012 For procurement

80.Baao, Camarines Sur

9,992,914.68 1 NCB N 4th Qtr 2012 For procurement

81.Baao, Camarines Sur

4,137,529.24 1 NCB N 3rd Qtr 2013 For procurement

82.Baao, Camarines Sur

1,115,456.47 1 Shopping N 3rd Qtr 2013 For procurement

83.Baao, Camarines Sur

1,382,048.61 1 Shopping N 3rd Qtr 2013 For procurement

84.Baao, Camarines Sur

1,399,021.04 1 Shopping N 3rd Qtr 2013 For procurement

85.Baao, Camarines Sur

636,958.54 1 Shopping N 3rd Qtr 2013 For procurement

86.Bula, Camarines Sur

8,896,798.61 1 NCB N On-going procurement

87.Bula, Camarines Sur

8,578,646.01 1 NCB N 3rd Qtr 2012 On-going procurement

88.Pili, Camarines Sur

896,461.43 1 Shopping N 3rd Qtr 2012 On-going procurement

89.Ocampo, Camarines Sur

2,618,859.00 1 NCB N 4th Qtr 2012 For procurement

90.Castilla, Sorsogon

2,079,313.40 1 NCB N Completed Procurement

91.Casiguran, Sorsogon

8,798,267.25 1 NCB N 2nd Qtr 2012 Completed Procurement

92.Casiguran, Sorsogon

5,198,307.65 1 NCB N 3rd Qtr 2012 For procurement

93.Casiguran, Sorsogon

7,141,323.45 1 NCB N 3rd Qtr 2012 For procurement

94.Bulan, Sorsogon

1,115,474.22 1 Shopping N 2nd Qtr 2012 Completed Procurement

95.Bulan, Sorsogon

2,808,495.31 1 NCB N 2nd Qtr 2012 Completed Procurement

96.Irosin, Sorsogon

5,021,434.57 1 NCB N 3rd Qtr 2012 For procurement

97.Matnog, Sorsogon

8,104,060.66 1 NCB N 3rd Qtr 2012 On-going procurement

98.Juban, Sorsogon

1,834,604.96 1 NCB N 2nd Qtr 2012 For procurement

99.Juban, Sorsogon

5,868,683.17 1 NCB N 2nd Qtr 2012 For procurement

100.Gubat, Sorsogon

3,479,800.93 1 NCB N 2nd Qtr 2013 On-going procurement

101.Pontevedra, Negros Occidental

1,022,654.77 1 Shopping N 1st Qtr 2012 On-going procurement

102.Pontevedra, Negros Occidental

890,354.04 1 Shopping N 4th Qtr 2012 For procurement

Rehabilitation of Caranday-Del Pilar Road

Concreting of Mariyokriyok Farm to Market Road

Rehabilitation of San Isidro - Nalup-an FMR

Conreting of Hanawan-Dinurog Farm to Market Road

Improvement of Binobong ARC FMR

Concreting of Iyagan-Cristo Rey FMR

Concreting of Kapatagan, Agdangan FMR

Concreting of San Rafael Farm to Market Road

Concreting og Agdangan-San Rafael Circumferential

Road

Construction of Buluang-San Isidro-Sta. Teresita-

Agdangan Service Road

Construction of Sipaya-Taboc FMR

Rehabilitation of Sipaya-Calateo Farm to Market Road

Roadway Construction and Concreting of Hidhid-

Banogao Farm to Market Road

Rehab/Const. of Gen. Malvar Farm-to-Market Road

Concreting of Gen. Malvar Proper to Purok 1 Road

Concreting of San Vicente-Antipolo-Old Road

Concreting of Tipolo-Agdangan FMR

Concreting of Napalalaba St., Sagrada FMR

Concreting of Jupi-Dita Farm to Market Road

Concreting of Bgy. Bagsangan to Monbon Farm to

Marke Road

Concreting of Lajong FMR

Concreting of Fabrica-G. Del Pilar FMR

Concreting of Sto. Domingo-San Isidro-San Agustin-

San Ramon Farm to Market Road

Concreting of Highway Lanipga Farm to Market Road

Rehabilitation of Caranday-Cristo Rey Road

Construction of Boton Flood Control Structure (Flood

Protection Works)

Construction of Trece Martires-Boton Farm to Market

Road

Construction of Boton Flood Protection Structure (Phase

II)

Page 7: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

103.Valladolid, Negros Occidental

3,714,223.63 1 NCB N 1st Qtr 2012 Completed Procurement

104.Hinoba-an, Negros Occidental

986,725.51 1 Shopping N 3rd Qtr 2012 On-going procurement

105.Candoni, Negros Occidental

3,795,136.63 1 NCB N For procurement

106.Balangiga, Eastern Samar 2,629,460.13 1 NCB N 1st Qtr 2012 On-going procurement

107.Balangiga, Eastern Samar 3,999,899.60 1 NCB N 3rd Qtr 2012 On-going procurement

108.Taft, Eastern Samar 7,267,921.30 1 NCB N Completed Procurement

109.San Julian, Eastern Samar

7,295,774.88 1 NCB N On-going procurement

110.San Julian, Eastern Samar

5,959,663.64 1 NCB N 2nd Qtr 2012 Completed Procurement

111.San Policarpo, Eastern Samar 5,067,103.72 1 NCB N For procurement

112.Salcedo, Eastern Samar 5,691,132.57 1 NCB N On-going procurement

113.Salcedo, Eastern Samar 11,811,453.27 1 NCB N 3rd Qtr 2013 For procurement

114.Lawa-an, Eastern Samar

9,999,678.89 1 NCB N On-going procurement

115.Lawa-an, Eastern Samar

3,223,681.41 1 NCB N For procurement

116.Balangkayan, Eastern Samar

7,912,717.99 1 NCB N 2nd Qtr 2012 On-going procurement

117.Balangkayan, Eastern Samar

4,367,165.99 1 NCB N 3rd Qtr 2012 On-going procurement

118.Quinapondan, Eastern Samar

10,086,130.48 1 NCB N 3rd Qtr 2013 For procurement

119.Llorente, Eastern Samar

12,517,264.52 1 NCB N 3rd Qtr 2013 For procurement

120.Alang-alang, Leyte

4,408,909.87 1 NCB N On-going procurement

121.Palo, Leyte 4,710,658.78 1 NCB N On-going procurement

122.Palo, Leyte 5,688,390.63 1 NCB N 3rd Qtr 2013 For procurement

123.Capoocan, Leyte 4,884,011.26 1 NCB N For procurement

124.Villaba, Leyte

4,741,965.71 1 NCB N 2nd Qtr 2012 On-going procurement

125.San Isidro, Leyte 8,880,741.04 1 NCB N On-going procurement

126.San Isidro, Leyte 4,777,714.73 1 NCB N 3rd Qtr 2013 For procurement

127.Javier, Leyte

2,105,294.67 1 NCB N Completed Procurement

128.Javier, Leyte

7,841,142.42 1 NCB N 3rd Qtr 2012 Completed Procurement

129.Javier, Leyte

5,580,505.12 1 NCB N 3rd Qtr 2012 Completed Procurement

130.Javier, Leyte

6,314,675.96 1 NCB N 3rd Qtr 2012 On-going procurement

Rehabilitation/Construction of Sitio Cantacson to Hag-

ik Farm to Market Road

Rehabilitation of Junction National Highway FMR

Rehabilitation of ALBAPA Farm to Market Road

Construction of Barangay 03 to Barangay 01 Farm to

Market Road

Construction of Bgy. San Miguel FMR

Concreting of Jumalag-Magsaysay Farm to Market

Road

Concreting of San Pedro-Palactad FMR w/ 6.65

l.m. RCDG BridgeConstruction with Spot Concreting of San Miguel-

Babanikon-Macaanga FMR

Concreting of San Sotero-Ulhay FMR

Concreting of Zone 1-Pinocawan-Bonifacio-Talisayan

FMR

Concreting of Odoing-Guindaponan FMR

Construction of San Agustin - Capirawan -

Cangumbang FMR

Construction/Improvement of Visares-Balugo Farm to

Market Road

Construction of Manlilisid-San Sotero FMR

Concreting of Cagaut-Cantamoja-Camanga-Carapdapan

FMR

Rehabilitation of Casilion-Tagbacan-Taclaon-Sta. Cruz

FMR

Construction of Casoroy-Layog Farm to Market Road

Construction of Panaw-nawan-Magti-aw Farm to

Market Road

Rehabilitation and Construction of Guinporlan-Bangon-

Cantubi Farm to Market Road

Rehabilitation of Sta. Cruz-Bangon FMR

Construction of Lumatod-Danao FMR w/ RCDG

Bridge

Construction of Brgy. 8-San Isidro Farm to Market

Road

Concreting of Brgy. Taguite Farm to Market Road

Const. of Capirawan-Gacao-Canhindoc-Arado Farm to

Market Road

Rehabilitation of Bawod-Paril Farm to Market Road

Construction/Improvement of Brgy. Crossing-Brgy.

Biasong FMR

Rehabilitation of Casili-on - Sambulawan FMR

Construction of Salvacion - Langit FMR

Page 8: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

131.Javier, Leyte

8,631,269.14 1 NCB N 3rd Qtr 2012 On-going procurement

132.Javier, Leyte

8,316,467.66 1 NCB N On-going procurement

133.Matalom, Leyte

3,821,396.89 1 NCB N 2nd Qtr 2012 Completed Procurement

134.Matalom, Leyte

3,635,945.90 1 NCB N 3rd Qtr 2013 For procurement

135.Kananga, Leyte

8,498,091.67 1 NCB N 3rd Qtr 2012 On-going procurement

136.Inopacan, Leyte

3,541,463.32 1 NCB N For procurement

137.Inopacan, Leyte

1,084,513.65 1 Shopping N 3rd Qtr 2013 For procurement

138.Calubian, Leyte

16,797,071.85 1 NCB N 3rd Qtr 2013 For procurement

139.Bobon, Northern Samar

2,270,482.52 1 NCB N 1st Qtr 2012 On-going procurement

140.Bobon, Northern Samar

5,138,370.84 1 NCB N 3rd Qtr 2012 On-going procurement

141.Bobon, Northern Samar

3,904,485.69 1 NCB N 3rd Qtr 2013 For procurement

142.Gamay, Northern Samar

8,802,982.59 1 NCB N 1st Qtr 2012 On-going procurement

143.Gamay, Northern Samar

11,810,260.48 1 NCB N 3rd Qtr 2013 For procurement

144.Catubig, Northern Samar 21,173,966.21 1 NCB N 1st Qtr 2012 Completed Procurement

145.San Roque, Northern Samar

10,039,119.79 1 NCB N 3rd Qtr 2012 Completed Procurement

146.San Jose, Northern Samar

1,760,955.32 1 Shopping N 3rd Qtr 2012 For procurement

147.San Jose, Northern Samar

15,655,778.88 1 NCB N 3rd Qtr 2013 For procurement

148.Laoang, Northern Samar

3,706,199.35 1 NCB N 4th Qtr 2012 For procurement

149.San Isidro, Northern Samar

14,635,329.08 1 NCB N 3rd Qtr 2013 For procurement

150.Palapag, Northern Samar 18,760,900.38 1 NCB N 3rd Qtr 2013 For Procurement

151.Tarangnan, Samar 3,767,024.84 1 NCB N On-going procurement

152.Tarangnan, Samar 10,776,419.65 1 NCB N On-going procurement

153.Pagsanghan, Samar 13,450,012.05 1 NCB N On-going procurement

154.Pagsanghan, Samar 9,016,995.59 1 NCB N 3rd Qtr 2012 On-going procurement

155.Daram, Samar 7,670,458.02 1 NCB N On-going procurement

156.Daram, Samar 5,554,546.58 1 NCB N 2nd Qtr 2012 Completed Procurement

157.Daram, Samar 20,477,225.80 1 NCB N 4th Qtr 2012 Completed Procurement

158.Sta. Rita, Samar 9,207,303.42 1 NCB N 2nd Qtr 2012 Completed Procurement

Construction of Calingnan-San Francisco-Cagugubngan-

Osmeña-Nabulo-Nabulid-San Jose Farm to Market

Road

Construction of Mabini-Astorga-San Vicente Bono-

anon Farm to Market Road

Concreting of Matambag-Osmeña-Bangon Farm to

Market Road

Concreting of Laray-Magsaysay-Malitbogay Farm to

Market Road

Construction of Sitio Km 14-Sitio Torril Barangay

Masarayao Farm to Market Road

Rehabilitation of Brgy. Esperanza-San Vicente Farm to

Market Road

Rehabilitation of Petrolio-Villanueva Farm to Market

Road

Concreting of San Sotero-Caraye Farm to Market Road

Rehabilitation of Marao-Macagoco Farm to Market

Road

Rehabilitation of Brgy. Dapdap-Lahong Farm to Market

Road

Spot Concreting of Balugo-Imelda FMR

Construction of Mabini-Mayabay-San Roque Farm to

Market Road

Construction of Pob 2-Talisay Farm to Market Road

Construction of So. Balukawe-Balat-Balud FMR

Construction of Brgy. Salvacion-Sitio Balukawe Farm

to Market Road

Concreting of Cagamutan del Norte-Bato FMR

Improvement/Concreting of Dao-Bagong Sabang-

Tubigdanao FMR

Concreting of San Juan to Entapatan Farm to Market

Road

Rehab/Improv't. of Cagamutan-Bato-Bangon FMR w/

30 l.m. One Lane RCDG Bridge

Concreting of Catigbian-Cabullaon-Sibunot Farm to

Market Road

Improvement of Bonglas (Junction-Brgy. Proper) Farm

to Market Road

Construction of Inilian-Galutan-Burac-Coroconog-

Himabug-at Farm to Market Road

Rehabilitation of Pagsanghan-Gandara (San Agustin)

Farm to Market Road

Concreting of Pagsanghan-Caloloma Farm to Market

Road

Spot Concreting of Poblacion-Tulay Farm to Market

Road

Concreting of Trojillo-Calantiao Farm to Market Road

Rehabilitation of Elevado-Pres. Garcia Farm to Market

Road

Rehabilitation of Guinsangan-Can-angay Farm to

Market Road

Page 9: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

159.Sta. Rita, Samar 9,003,308.02 1 NCB N 3rd Qtr 2013 For procurement

160.Villareal, Samar

5,130,927.23 1 NCB N On-going procurement

161.Villareal, Samar

8,217,097.78 1 NCB N 2nd Qtr 2012 On-going procurement

162.Pinabacdao, Samar 11,546,598.49 1 NCB N On-going procurement

163.Pinabacdao, Samar 10,449,237.05 1 NCB N 3rd Qtr 2013 For procurement

164.Calbiga, Samar 13,756,510.98 1 NCB N On-going procurement

165.Calbiga, Samar 5,698,707.38 1 NCB N 3rd Qtr 2012 On-going procurement

166.Calbiga, Samar 2,899,054.30 1 NCB N 3rd Qtr 2012 On-going procurement

167.Calbiga, Samar 2,791,367.82 1 NCB N 3rd Qtr 2012 On-going procurement

168.Marabut, Samar 11,267,259.09 1 NCB N 2nd Qtr 2012 On-going procurement

169.Basey, Samar 10,183,918.94 1 NCB N 2nd Qtr 2012 On-going procurement

170.Jiabong, Samar 4,249,135.78 1 NCB N 3rd Qtr 2012 On-going procurement

171.Sta. Margarita, Samar 7,835,423.32 1 NCB N 4th Qtr 2012 For procurement

172.Almagro, Samar 30,908,890.84 1 NCB N 4th Qtr 2012 On-going Procurement

173.San Jorge, Samar 12,765,666.42 1 NCB N 3rd Qtr 2013 For procurement

174.Siayan, Zamboanga del Norte

2,202,005.90 1 NCB N 3rd Qtr 2012 For procurement

175.Siayan, Zamboanga del Norte

2,852,842.94 1 NCB N 4th Qtr 2012 For procurement

176.Siayan, Zamboanga del Norte

4,878,261.71 1 NCB N 3rd Qtr 2013 For procurement

177.Siayan, Zamboanga del Norte

2,219,123.84 1 NCB N On-going procurement

178.Siayan, Zamboanga del Norte

4,272,103.23 1 NCB N 4th Qtr 2012 On-going procurement

179.Siayan, Zamboanga del Norte

2,302,666.49 1 NCB N 3rd Qtr 2013 For procurement

180.Siayan, Zamboanga del Norte

7,051,154.66 1 NCB N 3rd Qtr 2013 For procurement

181.Siocon, Zamboanga del Norte

533,293.85 1 Shopping N 2nd Qtr 2012 On-going procurement

182.Sirawai, Zamboanga del Norte

1,082,399.23 1 Shopping N 4th Qtr 2012 For procurement

183.Manukan, Zamboanga del Norte

5,754,647.63 1 NCB N 3rd Qtr 2012 On-going procurement

184.Tampilisan, Zamboanga del Norte

6,390,746.34 1 NCB N 4th Qtr 2012 For procurement

185.Tampilisan, Zamboanga del Norte

4,869,688.83 1 NCB N 3rd Qtr 2013 For procurement

186.Molave, Zamboanga del Sur

1,370,835.14 1 NCB N 3rd Qtr 2012 On-going procurement

Construction of Poblacion-Costa Rica II Farm to Market

Road

Concreting of Poblacion-Hinangutdan Farm to Market

Road

Rehab with 1.10 kms Concreting of Polayo-Denuyan

FMR

Rehabilitation with .70 km Concreting of Moyo-Sitio

Pase Farm to Market Road

Rehabilitation with 2.00 km Concreting of Sitio Bolanao-

Litolet Farm to Market Road

Rehabilitation of A. L. Micubo Farm to Market Road

Construction of Sipakit Farm to Market Road

Rehab/Concreting of Junction Muñoz-Litolet Farm to

Market Road

Rehabilitation with 0.90 km Concreting of Gonayen-

Sayaw Farm to Market Road

Concreting of Barangay 7-Tinago Farm to Market Road

Construction/Rehabilitation of Villareal ARC Road

Concreting of Villareal ARC Access Road

Concreting of Panayuran Farm to Market Road

Construction of Bacyaron-Bulao-Canbagtic-San

Mauricio FMR

Concreting of MACAPARICAN ARM Farm to Market

Road

Construction of Cogon-Cancaiyas-Villa Aurora Farm to

Market Road

Construction of Magdawat-Canlobo and Junction

Canlobo-Layo Farm to Market Road

Concreting of Lingatongan-Meses Farm to Market Road

Rehabilitation with .75-km Concreting of Paranglumba

Farm to Market Road

Concreting of Quezon-Cantaguic Farm to Market Road

Construction of Sta. Rita Farm to Market Road w/ 15 lm

RCDG Bridge

Construction of Nabong-Loctob-Catigawan-Lawaan-

Pahug FMR

Construction of Ilo-Balud Circumferential ARC Farm to

Market Road

Concreting of Barobaybay-Pasigay Farm to Market

Road

Rehab./Concreting of Poblacion-Moyo Farm to Market

Road

Upgrading/Rehabiltation of Poblacion-New Dapitan

Farm to Market Road

Concreting of Poblacion-ZNAC Farm to Market Road

Construction of Culo FMR

Page 10: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

187.Molave, Zamboanga del Sur

3,601,809.25 1 NCB N 3rd Qtr 2012 Completed Procurement

188.Molave, Zamboanga del Sur

3,111,087.89 1 NCB N 3rd Qtr 2012 On-going procurement

189.Dumingag, Zamboanga del Sur

1,230,117.50 1 Shopping N 4th Qtr 2012 For procurement

190.Mahayag, Zamboanga del Sur 4,080,038.46 1 NCB N On-going procurement

191.Mahayag, Zamboanga del Sur 17,442,694.37 1 NCB N 4th Qtr 2012 On-going procurement

192.Mahayag, Zamboanga del Sur 4,931,099.40 1 NCB N 4th Qtr 2012 On-going procurement

193.Mahayag, Zamboanga del Sur 14,255,035.41 1 NCB N 3rd Qtr 2013 For procurement

194.Mahayag, Zamboanga del Sur 3,359,321.11 1 NCB N 3rd Qtr 2013 For procurement

195.Tambulig, Zamboanga del Sur 6,936,356.52 1 NCB N On-going procurement

196.Tambulig, Zamboanga del Sur 9,712,017.60 1 NCB N 3rd Qtr 2012 On-going procurement

197.Tambulig, Zamboanga del Sur 16,770,764.83 1 NCB N 3rd Qtr 2012 On-going procurement

198.Tambulig, Zamboanga del Sur 3,795,724.35 1 NCB N 3rd Qtr 2012 On-going procurement

199.Josefina, Zamboanga del Sur 11,675,524.57 1 NCB N On-going procurement

200.Josefina, Zamboanga del Sur 3,849,405.01 1 NCB N On-going procurement

201.Josefina, Zamboanga del Sur 6,874,601.18 1 NCB N 4th Qtr 2012 On-going procurement

202.Tigbao, Zmaboanga del Sur 4,041,145.77 1 NCB N On-going procurement

203.Tigbao, Zamboanga del Sur 28,601,806.03 1 NCB N 4th Qtr 2012 Completed Procurement

204.Margosatubig, Zamboanga del Sur 10,917,658.83 1 NCB N 1st Qtr 2012 On-going procurement

205.Lapuyan, Zamboanga del Sur 25,145,499.20 1 NCB N 2nd Qtr 2012 Completed Procurement

206.Kumalarang, Zamboanga del Sur 9,797,531.28 1 NCB N 2nd Qtr 2012 On-going procurement

207.Tabina, Zamboanga del Sur 6,670,868.71 1 NCB N 4th Qtr 2012 For procurement

208.Midsalip, Zamboanga del Sur 2,576,058.41 1 NCB N 4th Qtr 2012 For procurement

209.Midsalip, Zamboanga del Sur 7,693,417.47 1 NCB N 4th Qtr 2012 For procurement

210.Tukuran, Zamboanga del Sur 4,244,383.30 1 NCB N 3rd Qtr 2012 For procurement

211.San Pablo, Zamboanga del Sur 3,462,315.74 1 NCB N 4th Qtr 2012 For procurement

212.San Pablo, Zamboanga del Sur 15,625,910.36 1 NCB N 4th Qtr 2012 For procurement

213.San Miguel, Zamboanga del Sur 7,360,810.46 1 NCB N 3rd Qtr 2013 For procurement

214.Dimataling, Zamboanga del Sur 23,144,854.48 1 NCB N 3rd Qtr 2013 For Procurement

Concreting of Grap-Salawagan-Tipangi-Sumbato-

Sugbay 1 Farm to Market Road

Construction/Improvement of Bualan-Maruing-

Pampang-Poblacion Lapuyan Farm to Market Road

Concreting of Begong-Limas Farm to Market Road

Concreting of Junction Pongapong-Upper Tubo-Pait-

Bndry. Lower Tubo-Pait Road

Rehab/Concreting of San Pablo-Sagasan-Teniapan-

Culasian Farm to Market Road

Proposed Concreting of Bgy. Lower Sto. Niño to Upper

Sto. Niño to San Jose FMR

Construction of Bgy. Lower Sto Niño FMR

Const. of Junction Poblacion Kumalarang-Bualan Farm

to Market Road

Construction of Tumapic-San Jose-Balamban FMR with

RCDG Bridge

Concreting of Bgy. Lower Salug Dako-Balamban-San

Jose DCM Farm to Market Road

Concreting of Tanducan-Tambunan FMR

Rehabilitation of Gabunon - Bag-ong - Tabugon FMR

Concreting of Lower Lodiong-Limamaan Farm to

Market Road

Concreting of Junction Limamaan-Upper Lodiong Farm

to Market Road

Rehabilitation with Spot concreting of Limamaan Farm

to Market Road

Rehabilitation/Improvement of Guinlin - Limas Farm to

Market Road

Concreting of Buloron-Lumponid FMR

Construction/Rehabilitation-Concreting of Bgy. DCM

Farm to Market Road

Const. of Tipasan-Tulapok-Poblacion FMR

Construction of Buloron-Dumalinao Farm to Market

Road

Construction of Maralag - Libertad Farm to Market

Road

Rehabilitation of Nopulan - Bogo Calabat Farm to

Market Road

Rehabilitation of Bgy. Moradje-Ebarle FMR

Rehabilitation & Concreting of Bgy. Moradje-Tagaytay-

Dawa FMR

Concreting of Purok Ferry-Purok Happy Valley Farm to

Market Road

Concreting of Purok Jupiter (Basay)-Purok Venus Farm

to Market Road

Construction with 1.248-km Concreting of Alindahaw-

Panduma Sr-Camanga Farm to Market Road

Concreting of Limonan-Kabogkabog FMR

Page 11: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

215.Dimataling, Zamboanga del Sur 3,977,133.20 1 NCB N 3rd Qtr 2012 For procurement

216.Vicenzo Sagun, Zamboanga del Sur 26,385,261.51 1 NCB N 3rd Qtr 2013 For Procurement

217.Payao, Zamboanga Sibugay

7,219,903.78 1 NCB N On-going procurement

218.Payao, Zamboanga Sibugay

2,970,573.14 1 NCB N 3rd Qtr 2012 For procurement

219.Titay, Zamboanga Sibugay

1,758,633.30 1 NCB N 4th Qtr 2012 On-going procurement

220.Titay, Zamboanga Sibugay

3,108,468.45 1 NCB N 3rd Qtr 2012 For procurement

221.Tungawan, Zamboanga Sibugay

1,361,687.42 1 NCB N 3rd Qtr 2012 On-going procurement

222.Naga, Zamboanga Sibugay

3,558,086.39 1 NCB N 3rd Qtr 2012 On-going procurement

223.Naga, Zamboanga Sibugay

6,060,641.08 1 NCB N 3rd Qtr 2013 For procurement

224.Siay, Zamboanga Sibugay

8,121,976.02 1 NCB N 4th Qtr 2012 On-going procurement

225.Mabuhay, Zamboanga Sibugay 12,541,506.08 1 NCB N 4th Qtr 2012 On-going procurement

226.Mabuhay, Zamboanga Sibugay 2,161,409.38 1 Shopping N 4th Qtr 2012 On-going procurement

227.Lamitan, Basilan

5,711,523.93 1 NCB N On-going procurement

228.Lamitan, Basilan

3,635,829.47 1 NCB N For procurement

229.Sumisip, Basilan

9,644,699.29 1 NCB N For procurement

230.Sumisip, Basilan

10,373,675.93 1 NCB N For procurement

231.Unkaya Pukan, Basilan

14,388,645.11 1 NCB N On-going procurement

232.Tipo-Tipo, Basilan

9,634,499.04 1 NCB N On-going procurement

233.Maluso, Basilan

13,277,929.70 1 NCB N For procurement

234.Tagaloan, Lanao del Sur

16,869,068.47 1 NCB N 1st Qtr 2012 On-going procurement

235.Ganassi, Lanao del Sur 17,849,849.24 1 NCB N 1st Qtr 2012 For procurement

236.Ganassi, Lanao del Sur 13,723,022.20 1 NCB N 2nd Qtr 2012 On-going Procurement

237.Poona Bayabao, Lanao del Sur 13,756,914.13 1 NCB N On-going procurement

238.Bumbaran, Lanao del Sur 12,386,771.77 1 NCB N For procurement

239.Marantao, Lanao del Sur 19,257,569.95 1 NCB N 4th Qtr 2012 On-going Procurement

240.Kabuntalan, Maguindanao 8,074,895.96 1 NCB N 3rd Qtr 2012 On-going procurement

241.Datu Paglas, Maguindanao 14,695,451.99 1 NCB N 3rd Qtr 2012 On-going procurement

242.Matanog, Maguindanao 18,123,413.57 1 NCB N For procurement

Concreting of TARBADECO ARC Network

Concreting of Phil-Asm-Buhe Pahu Tibarpeco ARCR

FMR

Concreting of CARBADECO ARC Network

Concreting of V. Sagun (Kabatan)-Danan-Biu-os Farm

to Market Road

Construction of Camalig Bandaraingud-Loway Inodaran

FMR

Concreting/Rehab of Taganonok-Taliogan-Paraaba

FMR

Rehabilitation of 9.98km Tumahubong ARC Farm to

Market Road

Concreting of Poblacion-Ligaya Farm to Market Road

Construction of Sitio Tuburan-Malinao Farm to Market

Road

Rehabilitation of Tambanan-Sulo FMR

Rehabilitation with Spot Concreting of Balungisan-

Guiwan FMR

Rehabilitation of Balungisan-Upper Sumilong Farm to

Market Road

Rehabilitation with Spot Concreting of Kitabog-Mabini

Farm to Market Road

Concreting of Brgy. Libertad FMR

Concreting of SCARBIDC FMR

Rehabilitation of Sta. Clara-Bohenange MR

Concreting of Tumahubong ARC FMR

Concreting of Tamborong-Bunawan FMR

Concreting of Kinggan-Tagoloan Pob. FMR

Improvement of Barit-Taliogan-Tabuan FMR

Concreting of Sitio Jo Rubber Farm to Market Road

Constrcution of Flood Protection Dike cum Farm to

Market Road

Rehabilitation of Culasian-Supit Farm to Market Road

Concreting of Junction Guilisan (Tipangi-Junction

Liberted FMR

Concreting of Sumogot Road

Concreting/Rehabilitation of Bubong Dimunda-Rayagan-

Gadongan FMR

Construction of Ganta-Gambar FMR

Concreting of Langkong-Bayangan Norte Road

Page 12: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

243.Maimbong, Sulu 13,642,958.02 1 NCB N 2nd Qtr 2012 Completed Procurement

244.Maimbong, Sulu 6,205,838.03 1 NCB N 2nd Qtr 2012 Completed Procurement

245.Maimbong, Sulu 3,166,939.24 1 NCB N 2nd Qtr 2012 Completed Procurement

246.Panamao, Sulu 2,525,200.71 1 NCB N For procurement

247.Pandami, Sulu 18,992,973.91 1 NCB N 2nd Qtr 2012 Completed Procurement

248.Siasi, Sulu 14,795,693.12 1 NCB N 3rd Qtr 2013 On-going Procurement

249.Bongao, Tawi-Tawi 6,680,971.84 1 NCB N For procurement

250.Bongao, Tawi-Tawi 6,771,235.13 1 NCB N For procurement

251.Sibutu, Tawi-Tawi 15,866,189.41 1 NCB N For procurement

252.Sibutu, Tawi-Tawi 3,329,607.05 1 NCB N For procurement

253.Sibutu, Tawi-Tawi 9,829,387.30 1 NCB N For procurement

254.Sibutu, Tawi-Tawi 6,864,966.04 1 NCB N For procurement

1,656,522,350.08 254

a.2

01.Magdiwang, Romblon 3,256,517.19 1 NCB N 3rd Qtr 2013 For procurement

02.Magdiwang, Romblon 2,846,615.04 1 NCB N 3rd Qtr 2013 For procurement

03.Bulalacao, Oriental Mindoro 9,332,606.51 1 NCB N 3rd Qtr 2013 For procurement

04.Bansud, Oriental Mindoro 8,833,998.47 1 NCB N 3rd Qtr 2013 For procurement

05.Aborlan, Palawan 4,314,417.04 1 NCB N 3rd Qtr 2013 For procurement

06.Aborlan, Palawan 8,444,880.64 1 NCB N 3rd Qtr 2013 For procurement

07.Tigaon, Camarines Sur 9,843,448.11 1 NCB N 3rd Qtr 2013 For procurement

08.Pili, Camarines Sur

19,503,414.43 1 NCB N 3rd Qtr 2013 For procurement

09.Sangay, Camarines Sur

19,482,753.26 1 NCB N 3rd Qtr 2013 For procurement

10.Castilla, Sorsogon

14,305,944.66 1 NCB N 3rd Qtr 2013 For procurement

11.Castilla, Sorsogon

8,371,137.52 1 NCB N 3rd Qtr 2013 For procurement

12.Casiguran, Sorsogon

8,939,179.43 1 NCB N 3rd Qtr 2013 For procurement

13.Bulan, Sorsogon

3,744,224.92 1 NCB N 3rd Qtr 2013 For procurement

14.Irosin, Sorsogon

10,482,887.70 1 NCB N 3rd Qtr 2013 For procurement

Concreting of Tubig-Basag-Lakit FMR

Concreting of 3 km Lakit Lakit-Mandulan FMR

Rehabilitation of Sangay-Hingaroy CIS (Sangay

Section)

Rehabilitation of Pili CIS

Rehabilitation of Malbog CIS

Rehabilitation of Lictin CIS

Rehabilitation/Improvement of A. Bonifacio SWIP

Concreting of Parian Dakula-Lahi-Malanta FMR

Concreting of Buan-Ratag-Siowing Sipanding & Dugo

FMR

Rehabilitation of Talakaigan Communal Irrigation

System

Rehabilitation of Apurawan Communal Irrigation

System

Irrigation

Concreting Tubig Samin Junction-Tambuan FMR

Concreting of Patao Junction-Kandang Gulangan-Ratag

Limbun FMR

Rehabilitation of Suuh-Kanduyak-Kah-Ukul FMR

Concreting of Tandubanak ARC FMR (Section 3)

Concreting of Tandubanak ARC FMR (Section 1)

Concreting of Tandubanak ARC FMR (Section 2)

Conreting of Tongehat ARC FMR (4 sections)

Sub-Total-Rural Access

Rehabilitation of Sangay-Hingaroy CIS (Tigaon

Section)

Rehabilitation of Himaao Communal Irrigation System

(CIS)

Concreting of Patao-Junction-Ipil FMR

Rehabilitation of Tabon Tabon CIS

Rehabilitation of Busay CIS

Rehabilitation of Talaba CIS

Rehabilitation of Cambunang Communal Irrigation

System

Rehabilitation of Salcedo Communal Irrigation System

Page 13: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

15.Irosin, Sorsogon 3,065,047.19 1 NCB N 3rd Qtr 2013 For procurement

Juban, Sorsogon 1,260,040.82 1 Shopping N 3rd Qtr 2013 For procurement

16.Villaba, Leyte

11,940,230.00 1 NCB N 3rd Qtr 2013 For procurement

17.San Isidro, Leyte 18,883,779.62 1 NCB N 3rd Qtr 2013 For procurement

18.Hilongos, Leyte

14,525,914.59 1 NCB N 3rd Qtr 2013 For procurement

19.Hilongos, Leyte

22,261,050.44 1 NCB N 3rd Qtr 2013 For procurement

20.Dipolog City, Zamboanga del Sur

12,458,246.07 1 NCB N 3rd Qtr 2013 For procurement

21.Midsalip, Zamboanga del Sur 6,149,693.50 1 NCB N 3rd Qtr 2013 For procurement

22.Aurora, Zamboanga del Sur 15,628,908.15 1 NCB N 3rd Qtr 2013 For procurement

23.Payao, Zamboanga Sibugay

22,200,272.26 1 NCB N 3rd Qtr 2013 For procurement

24.Titay, Zamboanga Sibugay

5,422,267.38 1 NCB N 3rd Qtr 2013 For procurement

25.Titay, Zamboanga Sibugay

7,709,197.18 1 NCB N 3rd Qtr 2013 For procurement

26.Titay, Zamboanga Sibugay

7,526,273.06 1 NCB N 3rd Qtr 2013 For procurement

27.Siay, Zamboanga Sibugay

18,874,013.76 1 NCB N 3rd Qtr 2013 For procurement

28.Parang, Maguindanao 6,887,390.04 1 NCB N 3rd Qtr 2013 For procurement

29.Barira, Maguindanao 8,477,339.72 1 NCB N 3rd Qtr 2013 For procurement

314,971,688.70 30

a.3

01.Magdiwang, Romblon 17,015,663.81 1 NCB N 3rd Qtr 2012 On-going procurement

02.Calatrava, Romblon 2,836,467.57 1 NCB N 3rd Qtr 2012 On-going procurement

03.Labo, Camarines Norte 834,727.49 1 Shopping N 2nd Qtr 2012 For procurement

04.Paracale, Camarines Norte

686,982.80 1 Shopping N 2nd Qtr 2012 On-going procurement

05.Paracale, Camarines Norte

1,157,852.00 1 Shopping N 2nd Qtr 2012 On-going procurement

06.Basud, Camarines Norte

841,367.26 1 Shopping N 2nd Qtr 2012 On-going procurement

07.Tolosa, Leyte

2,221,254.46 1 Shopping N 3rd Qtr 2013 For procurement

08.Matag-ob, Leyte

5,901,753.68 1 NCB N 3rd Qtr 2013 For procurement

09.Calbiga, Samar 4,674,381.39 1 NCB N 3rd Qtr 2013 For procurement

10. Labason, Zamboanga del Norte 266,661.05 1 Shopping N 2nd Qtr 2012 On-going procurement

11.Tambulig, Zamboanga del Sur 3,952,106.95 1 NCB N 3rd Qtr 2013 For procurement

Improvement/Expansion of Level II Water System

(Brgy. Tawig)

Construction of Upper Gabu PWS 2

Potable Water System

Construction of Calbiga Upland Barangay Potable

Water Supply

Rehabilitation of Buloron CIS

Rehabilitation of Sagrada Familia CIS

Rehabilitation of Bulawan Communal Irrigation System

Rehabilitation of Azusano Communal Irrigation System

Rehabilitation of Balogo Potable Water System

Rehabilitation of Mampili Level II Potable Water

System

Rehabilitation of Macogon Level II Potable Water

System

Construction of Balumbon Spring Level II Water

System

Rehabilitation of Burabod-San Julian CIS

Construction of Cagnocot CIP

Construction of Bunacan Communal Irrigation Project

Rehabilitation of Tabunok Communal Irrigation System

Rehabilitation of Tagbawto Communal Irrigation

System

Construction of Tampayan-Jao-asan PWS Level II

Rehabilitation of Namnama Communal Irrigation

System

Rehabilitation of Titay Communal Irrigation System

Rehabilitation of Dipolog Communal Irrigation System

Canmogsay-Capangihan PWS, Level II

Rehabilitation of Lajong CIS

Construction of Tambulig Highland B Potable Water

System

Rehabilitation of Soluan-Coloran Communal Irrigation

System

Rehabilitation of Libuan CIS

Rehabilitation of Gadung CIS

Sub-Total-PWS

Construction of Matag-ob Potable Water System

Page 14: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

12. Aurora, Zamboanga del Sur 908,147.05 1 Shopping N 4th Qtr 2012 For procurement

13.Ipil, Zamboanga Sibugay 1,256,555.80 1 Shopping N 4th Qtr 2012 On-going procurement

14.Sumisip, Basilan

3,488,034.07 1 NCB N 3rd Qtr 2013 For procurement

15.Datu Paglas, Maguindanao 509,331.86 1 Shopping N 3rd Qtr 2013 For procurement

46,551,287.24 15

a.4

01.Labo, Camarines Norte 149,452.94 1 Shopping N 2nd Qtr 2012 On-going procurement

02.Labo, Camarines Norte 149,452.94 1 Shopping N 2nd Qtr 2012 On-going procurement

03.Labo, Camarines Norte 943,742.20 1 Shopping N 2nd Qtr 2012 On-going procurement

04.Paracale, Camarines Norte

71,370.20 1 Shopping N Completed Procurement

05.Paracale, Camarines Norte

74,549.75 1 Shopping N Completed Procurement

06.Basud, Camarines Norte

199,288.22 1 Shopping N 2nd Qtr 2012 On-going procurement

07.Basud, Camarines Norte

666,412.48 1 Shopping N 2nd Qtr 2012 On-going procurement

08.San Lorenzo Ruiz, Cam. Norte

239,957.66 1 Shopping N 1st Qtr 2012 Completed Procurement

09.Garchitorena, Camarines Sur

185,333.76 1 Shopping N Completed Procurement

10.Garchitorena, Camarines Sur

185,333.76 1 Shopping N Completed Procurement

11.Bula, Camarines Sur

155,229.50 1 Shopping N 3rd Qtr 2012 On-going procurement

12.Bula, Camarines Sur

291,741.47 1 Shopping N 3rd Qtr 2012 On-going procurement

13.Pili, Camarines Sur

169,119.99 1 Shopping N 3rd Qtr 2012 On-going procurement

14.Pili, Camarines Sur

157,704.89 1 Shopping N 3rd Qtr 2012 On-going procurement

15.Sipocot, Camarines Sur

175,733.14 1 Shopping N 3rd Qtr 2013 For procurement

16.Irosin, Sorsogon

202,439.29 1 Shopping N 3rd Qtr 2012 For procurement

17.Pontevedra, Negros Occidental

200,505.97 1 Shopping N 4th Qtr 2012 For procurement

18.Pontevedra, Negros Occidental

200,505.97 1 Shopping N 4th Qtr 2012 For procurement

19.Pontevedra, Negros Occidental

402,742.68 1 Shopping N 4th Qtr 2012 For procurement

20.San Julian, Eastern Samar

1,479,850.69 1 Shopping N On-going procurement

21.Merida, Leyte

826,094.74 1 Shopping N 3rd Qtr 2013 For procurement

22.Sindangan, Zamboanga del Norte

139,438.81 1 Shopping N 2nd Qtr 2012 On-going procurement

23.Sindangan, Zamboanga del Norte

146,211.09 1 Shopping N On-going procurement

Construction of Maasin & Tiayon PWS Level II

Post Harvest Facilities

Construction of Mahayahay Potable Water System

Construction of Lanipga Solar Drier

Construction of Solar Drier San Isidro ARC

Construction of Del Pilar Solar Dryer

Construction of Agricultural Warehouse

Construction of Agricultural Warehouse

Construction of Motibot Solar Dryer

Construction of Multipurpose Pavement/Solar Drier

(Laniton)

Construction of Tumahubong Water Supply System

Spring Development Level II at Bgy. Napok

Construction of PHF/Warehouse (528 sqm) in Brgy.

Daguit

Construction of Solar Dryer (Brgy. Daguit) *

Sub-Total-PWS

Construction of Ason Solar Dryer

Construction of Solar Drier Binobong ARC

Construction of Solar Drier Bagong Sirang ARC

Construction of Multi-purpose Pavement (Purok 1)

Construction of Multi-purpose Pavement (Purok 5)

Construction of Nipaan Solar Dryer in Bgy. Nipaan

Construction of 600 sq. m. Solar Drier (So. Burabod,

Brgy. Bansangan)

Construction of Multi-purpose Pavement (Brgy.

Laniton)

Construction of Bgy. San Isidro Multi-Purpose Drying

Pavement

Construction of Cambalong Warehouse & Solar Dryer

Construction of Solar Dryer (Brgy. Malangcao Basud)

Const. Of Purok 2, Capacuan Multi-Purpose Pavement

(Solar Dryer)

Expansion of Purok 4, Dagang Multi-Purpose Pavement

(Solar Dryer)

Construction of Multi-Purpose Pavement/Solar Dryer

Page 15: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

24.Sindangan, Zamboanga del Norte

148,202.30 1 Shopping N On-going procurement

25.Labason, Zamboanga del Norte

182,494.03 1 Shopping N 2nd Qtr 2012 On-going procurement

26.Siocon, Zamboanga del Norte

508,428.87 1 Shopping N 2nd Qtr 2012 On-going procurement

27.Siocon, Zamboanga del Norte

620,993.17 1 Shopping N 2nd Qtr 2012 On-going procurement

28.Baliguian, Zamboanga del Norte

196,324.31 1 Shopping N On-going procurement

29.Dumingag, Zamboanga del Sur

827,091.74 1 Shopping N 4th Qtr 2012 For procurement

30.Dumingag, Zamboanga del Sur

814,736.60 1 Shopping N 4th Qtr 2012 For procurement

31.Dumingag, Zamboanga del Sur

827,798.60 1 Shopping N 4th Qtr 2012 For procurement

32.Dumingag, Zamboanga del Sur

818,916.02 1 Shopping N 4th Qtr 2012 For procurement

33.Dumingag, Zamboanga del Sur

817,935.95 1 Shopping N 4th Qtr 2012 For procurement

34.Dumingag, Zamboanga del Sur

823,193.72 1 Shopping N 4th Qtr 2012 For procurement

35.Ganassi, Lanao del Sur 609,346.38 1 Shopping N For procurement

36.Poona Bayabao, Lanao del Sur 60,346.38 1 Shopping N For procurement

37.Poona Bayabao, Lanao del Sur 60,346.38 1 Shopping N For procurement

38.Kabuntalan, Maguindanao 323,856.12 1 Shopping N For procurement

39.Kabuntalan, Maguindanao 323,856.12 1 Shopping N For procurement

40.Kabuntalan, Maguindanao 323,856.12 1 Shopping N For procurement

41.Kabuntalan, Maguindanao 323,856.12 1 Shopping N For procurement

42.Datu Paglas, Maguindanao 897,523.37 1 Shopping N For procurement

43.Datu Paglas, Maguindanao 897,523.37 1 Shopping N For procurement

17,818,837.83 43

a.5

01. Magdiwang, Romblon 505,801.63 1 Shopping N Completed Procurement

02.Magdiwang, Romblon 596,994.23 1 Shopping N Completed Procurement

03. Magdiwang, Romblon 402,341.74 1 Shopping N 3rd Qtr 2012 Completed Procurement

04.Magdiwang, Romblon 639,013.51 1 Shopping N 3rd Qtr 2012 Completed Procurement

05.Magdiwang, Romblon 1,056,994.85 1 Shopping N 3rd Qtr 2012 Completed Procurement

06.Magdiwang, Romblon 1,174,958.55 1 Shopping N 4th Qtr 2012 For procurement

07.

Magdiwang, Romblon 1,078,550.72 1 Shopping N 3rd Qtr 2012 Completed Procurement

Social Infrastructure

Construction of Lumay Solar Dryer

Construction of JOLAMIPAMAN Warehouse

Construction of Brgy. Tampayan Proper Health Center

Construction of Two Clasroom School Building for

(Tomas and Maria Maglaya Memorial School)

Construction of Sitio Franco Day Care Center

Construction of 2-Classroom School Building for

Ambulong Elem. School

Construction of 2-Classroom School Building for Jao-

Asan Elem. School (with Comfort Rooms)

Const of Jao-asan 2 unit Classroom School Building

with Comfort Rooms for Tomas and Maria Maglaya

Mem School ( Phase II)

Construction of Two Classroom School Building with

Comfort Room

Sub-Total - Post Harvest Facilities

Construction of Sto. Rosario Solar Dryer in Bgy. Sto

Rosario

Construction of JOLAMIPAMAN Dryer

Construction of Bgy. LiongMPP

Const. of warehouse with Solar Dryer at Brgy.

Kaluhmenga

Const. of warehouse with Solar Dryer at Brgy. Napok

Construction of Warehouse with Solar Dryer at Bgy.

Gadongan

Construction of Bgy. Pened MPP

Construction of Libertad Multi-Purpose Center with

Solar Dryer

Construction of Lower Timonan Multi-Purpose Center

with Solar Dryer

Construction of Upper Timonan Multi-Purpose Center

with Solar Dryer

Construction of Maralag Multi-Purpose Center with

Solar Dryer

Construction of Warehouse with Solar Dryer at Bgy.

Barit

Construction of Bgy. Maitong MPP

Construction of New Basak Multi-Purpose Center with

Solar Dryer

Construction of Manlabay Multi-Purpose Center with

Solar Dryer

Construction of Balas Multi-purpose Pavement

Construction of Bgy. Matilak MPP

Construction of Warehouse with Solar Dryer at Bgy.

Pantao

Page 16: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

08. Looc, Romblon 426,727.74 1 Shopping N 3rd Qtr 2012 For procurement

09.Looc, Romblon 426,727.74 1 Shopping N 3rd Qtr 2012 For procurement

10.Ferrol, Romblon 601,714.33 1 Shopping N 3rd Qtr 2013 For procurement

11.San Fernando, Romblon 973,712.35 1 Shopping N 4th Qtr 2012 On-going procurement

12.San Fernando, Romblon 973,712.35 1 Shopping N 4th Qtr 2012 On-going procurement

13.Bongabong, Oriental Mindoro 460,258.81 1 Shopping N 4th Qtr 2012 For procurement

14.Labo, Camarines Norte 544,514.15 1 Shopping N 2nd Qtr 2012 On-going procurement

15.Labo, Camarines Norte 270,939.16 1 Shopping N 2nd Qtr 2012 On-going procurement

16.Labo, Camarines Norte 427,764.89 1 Shopping N 2nd Qtr 2012 On-going procurement

17.Paracale, Camarines Norte

194,223.90 1 Shopping N 2nd Qtr 2012 On-going procurement

18.Paracale, Camarines Norte

230,071.25 1 Shopping N Completed Procurement

19.Paracale, Camarines Norte

399,817.28 1 Shopping N 2nd Qtr 2012 On-going procurement

20.Paracale, Camarines Norte

725,929.19 1 Shopping N 2nd Qtr 2012 On-going procurement

21.San Lorenzo Ruiz, Cam. Norte

380,090.40 1 Shopping N Completed Procurement

22.San Lorenzo Ruiz, Cam. Norte

380,090.40 1 Shopping N 1st Qtr 2012 Completed Procurement

23.San Lorenzo Ruiz, Cam. Norte

380,090.40 1 Shopping N Completed Procurement

24.San Lorenzo Ruiz, Cam. Norte

907,479.35 1 Shopping N 2nd Qtr 2012 On-going procurement

25. Vinzons, Camarines Norte510,374.82 1 Shopping N 3rd Qtr 2013 For procurement

26. Del Gallego, Camarines Sur 411,896.21 1 Shopping N 2nd Qtr 2012 On-going procurement

27. Libmanan, Camarines Sur 565,060.33 1 Shopping N On-going procurement

28. Libmanan, Camarines Sur 565,060.33 1 Shopping N 3rd Qtr 2012 On-going procurement

29. Libmanan, Camarines Sur 565,060.33 1 Shopping N 3rd Qtr 2012 On-going procurement

30.Milaor, Camarines Sur

654,465.23 1 Shopping N 3rd Qtr 2012 On-going procurement

31.Milaor, Camarines Sur

654,465.23 1 Shopping N 3rd Qtr 2012 On-going procurement

32.Tigaon, Camirines Sur

416,175.75 1 Shopping N 3rd Qtr 2012 On-going procurement

33.Tigaon, Camirines Sur

416,175.75 1 Shopping N 3rd Qtr 2012 On-going procurement

34.Tigaon, Camirines Sur

416,175.75 1 Shopping N 3rd Qtr 2012 On-going procurement

35.Tigaon, Camirines Sur

416,175.75 1 Shopping N 3rd Qtr 2012 On-going procurement

36.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

37.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

38.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

Construction of Sagana Health Center

Construction of Limon Norte Barangay Health Center

Construction of Limon Sur Barangay Health Center

Construction of España Multi-purpose Building

Construction of Taclobo Multi-purpose Building

Construction of Malangcao Basud Health Station

Construction of Day Care Center (Brgy. Daguit)

Construction of DARBO Multi-purpose Building

Improv't. of a Health Center P-2 (Purok 6)

Improv't. of a Day Care Center P-2 (Purok 7)

Construction of Comadaycaday Health Center

Construction of Day Care Center (Bgy. Dagang)

Construction of Multi-purpose Building (Brgy.

Batobalani)

Construction of Day Care Center (San Ramon)

Construction of Day Care Center (San Isidro)

Construction of Day Care Center (Matacong)

Construction of SIARBECO Multi-purpose Building

and Warehouse

Construction of Multi-Purpose Building (Bahay)

Construction of Multi-Purpose Building (Patot)

Construction of Multi-Purpose Building (Malinao)

Construction of 2-storey Multi-Purpose Building

(Cabugao)

Construction of Multipurpose Building

Construction of 2-storey Multi-Purpose Building (San

Antonio)

Construction of Gubat Day Care Center

Construction of San Francisco Day Care Center

Construction of Coyaoyao Day Care Center

Construction of Talojongon Day Care Center

Construction of Huyan-huyan School Building

Construction of Panagan School Building

Construction of Cabalinadan School Building (Package

I)

Construction of C.M. Recto Health Center

Page 17: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

39.Tigaon, Camirines Sur 961,885.82 1 Shopping N 3rd Qtr 2012 On-going procurement

40.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

41.Tigaon, Camirines Sur 961,885.82 1 Shopping N 3rd Qtr 2012 On-going procurement

42.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

43.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

44.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

45.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

46.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

47.Tigaon, Camirines Sur 941,321.25 1 Shopping N 3rd Qtr 2012 On-going procurement

48.Garchitorena, Camarines Sur

801,868.53 1 Shopping N On-going procurement

49.Garchitorena, Camarines Sur

801,868.53 1 Shopping N On-going procurement

50.Garchitorena, Camarines Sur

582,420.64 1 Shopping N 3rd Qtr 2012 For procurement

51.Garchitorena, Camarines Sur

513,592.15 1 Shopping N 3rd Qtr 2012 For procurement

52.Garchitorena, Camarines Sur

1,088,128.26 1 Shopping N 3rd Qtr 2012 For procurement

53.Bula, Camarines Sur

564,343.88 1 Shopping N 4th Qtr 2012 On-going procurement

54.Bula, Camarines Sur

276,281.19 1 Shopping N 3rd Qtr 2012 On-going procurement

55.Pili, Camarines Sur

653,186.37 1 Shopping N 3rd Qtr 2013 For procurement

56.Pili, Camarines Sur

653,186.37 1 Shopping N 3rd Qtr 2013 For procurement

57.Pili, Camarines Sur

474,164.73 1 Shopping N 3rd Qtr 2012 On-going procurement

58.Pili, Camarines Sur

474,164.73 1 Shopping N 4th Qtr 2012 On-going procurement

59.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

60.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

61.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

62.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

63.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

64.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

65.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

66.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

Construction of 2-Classroom School Building (Ason)

Construction of 2-Classroom School Building (Del

Pilar)

Construction of Brgy. Health Station (Del Pilar)

Construction of Day Care Center in Barangay Lanipga

Construction of 2-storey MultiPurpose Building of

Lanipga

Construction of 2-classroom School Building Binobong

ARC

Construction of 2-classroom School Building Sagrada

ARC

Construction of Brgy. Health Station (Salvacion)

Construction of 2 Classromm School Bldg. (Salvacion)

Construction of Vinagre School Building

Construction of Cabalinadan School Building (Package

II)

Construction of Tinawagan School Building (Package I)

Construction of Tinawagan School Building (Package

II)

Construction of Gubat School Building

Construction of Mabalodbalod School Building

(Package I)

Construction of Mabalodbalod School Building

(Package II)

Construction of San Francisco School Building

Construction of Salvacion School Building

Construction of One (1) Unit- Two (2) Classroom

School Building (Del Rosario)

Construction of 2-Classroom School Building (Cogon)

Construction of 2-Classroom School Building

(Macalaya/Misalay E/S)

Construction of One (1) Unit- Two (2) Classroom

School Building (Bagong Sirang)

Construction of 2-Classroom School Building (Quirapi)

Construction of 2-Classroom School Building (Pandan)

Construction of 2-Classroom School Building

(Amomonting)

Construction of 2-Classroom School Building

(Buenavista)

Construction of 2-Classroom School Building

(Cumadcad/Rosal E/S)

Construction of 2-Classroom School Building (Dinapa)

Page 18: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

67.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

68.Castilla, Sorsogon

982,446.19 1 Shopping N 3rd Qtr 2013 For procurement

69.Casiguran, Sorsogon

607,139.84 1 Shopping N Completed Procurement

70.Matnog, Sorsogon

411,896.20 1 Shopping N 3rd Qtr 2012 For procurement

71.Matnog, Sorsogon

959,884.28 1 Shopping N 3rd Qtr 2013 For procurement

72.Matnog, Sorsogon

959,884.28 1 Shopping N 3rd Qtr 2013 For procurement

73.Pontevedra, Negros Occidental

593,295.64 1 Shopping N 4th Qtr 2012 For procurement

74.Hinoba-an, Negros Occidental

274,704.69 1 Shopping N 4th Qtr 2012 For procurement

75. Hinoba-an, Negros Occidental 489,780.77 1 Shopping N 4th Qtr 2012 For procurement

76.Labason, Zamboanga del Norte

438,560.39 1 Shopping N 2nd Qtr 2012 For procurement

77.Labason, Zamboanga del Norte

438,560.39 1 Shopping N 2nd Qtr 2012 For procurement

78.Labason, Zamboanga del Norte

438,560.79 1 Shopping N 2nd Qtr 2012 For procurement

79.Labason, Zamboanga del Norte

438,560.39 1 Shopping N 2nd Qtr 2012 For procurement

80.Labason, Zamboanga del Norte

438,560.79 1 Shopping N 2nd Qtr 2012 For procurement

81.Labason, Zamboanga del Norte

438,560.39 1 Shopping N 2nd Qtr 2012 On-going procurement

82.Labason, Zamboanga del Norte

641,487.40 1 Shopping N 2nd Qtr 2012 For procurement

83.Labason, Zamboanga del Norte

641,487.40 1 Shopping N 2nd Qtr 2012 For procurement

84.Labason, Zamboanga del Norte

641,487.40 1 Shopping N 2nd Qtr 2012 For procurement

85.Labason, Zamboanga del Norte

641,487.40 1 Shopping N 2nd Qtr 2012 For procurement

86.Labason, Zamboanga del Norte

475,499.17 1 Shopping N 2nd Qtr 2012 On-going procurement

87.Labason, Zamboanga del Norte

475,499.17 1 Shopping N 2nd Qtr 2012 For procurement

88.Labason, Zamboanga del Norte

475,499.17 1 Shopping N 2nd Qtr 2012 On-going procurement

89.Siocon, Zamboanga del Norte

379,031.47 1 Shopping N 2nd Qtr 2012 On-going procurement

90.Sirawai, Zamboanga del Norte

754,373.40 1 Shopping N 2nd Qtr 2012 For procurement

91.Sirawai, Zamboanga del Norte

750,078.22 1 Shopping N 3rd Qtr 2012 For procurement

92. Leon Postigo, Zamboanga del

Norte 782,905.33 1 Shopping N 2nd Qtr 2012 On-going procurement

93. Leon Postigo, Zamboanga del

Norte 783,080.32 1 Shopping N 2nd Qtr 2012 On-going procurement

94. Leon Postigo, Zamboanga del

Norte 782,963.66 1 Shopping N 2nd Qtr 2012 On-going procurement

95. Leon Postigo, Zamboanga del

Norte 788,055.83 1 Shopping N 2nd Qtr 2012 On-going procurement

Const. Of 2-Storey Multi-Purpose Building

Construction of Health Center (Bolo)

Construction of Brgy. Asia Health Station

Construction of 2-Classroom School Building

(Dancalan)

Construction of 2-Classroom School Building (Sogoy)

Construction of 2-Classroom Building with Hallway in

Brgy. Alim

Construction of 2-Classroom School Building with

Comfort Room

Construction of Lawigan Elementary School Building

(Package I)

Construction of Lawigan Elementary School Building

(Package II)

Construction of Lawigan Barangay Health Center

Construction of Catuyan Elementary School Building

Construction of Upper Gabu Early Child Care

Development Center

Construction of Balas Early Child Care Development

Center

Construction of Lawigan Early Child Care Development

Center

Construction of Sitio Sawi Early Child Care

Development Center

Construction of Sitio Jaivy Early Child Care

Development Center

Construction of JOLAMIPAMAN ARC Multi-Purpose

Building

Construction of Sitio Sibulan Early Child Care

Development Center

Construction of Balas Elementary School Building

Construction of 2-Classroom School Building (Brgy.

Hidhid)

Construction of 2-Classroom School Building (Brgy.

Bolo)

Construction of Panabutan Elementary School Building

Construction of Delusom Elementary School Building

Construction of Bogabongan Elementary School

Building

Construction of Balas Barangay Health Center

Construction of Sitio Sibulan Barangay Health Center

Construction of Sibulan Elementary School Building

Construction of Palandok Elementary School Building

Construction of Mangop Elementary School Building

Page 19: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

96. Leon Postigo, Zamboanga del

Norte 521,793.48 1 Shopping N 2nd Qtr 2012 On-going procurement

97.Baliguian, Zamboanga del Norte

781,511.25 1 Shopping N 2nd Qtr 2012 On-going procurement

98.Baliguian, Zamboanga del Norte

773,111.79 1 Shopping N 3rd Qtr 2012 On-going procurement

99.Baliguian, Zamboanga del Norte

468,795.03 1 Shopping N On-going procurement

100.Baliguian, Zamboanga del Norte

473,274.73 1 Shopping N On-going procurement

101.Gutalac, Zamboanga del Norte

575,244.96 1 Shopping N 3rd Qtr 2013 For procurement

102.Gutalac, Zamboanga del Norte

576,077.92 1 Shopping N 3rd Qtr 2013 For procurement

103.Gutalac, Zamboanga del Norte

576,303.64 1 Shopping N 3rd Qtr 2013 For procurement

104.Gutalac, Zamboanga del Norte

574,758.31 1 Shopping N 3rd Qtr 2013 For procurement

105.Gutalac, Zamboanga del Norte

351,802.74 1 Shopping N 3rd Qtr 2013 For procurement

106.Gutalac, Zamboanga del Norte

352,287.66 1 Shopping N 3rd Qtr 2013 For procurement

107.Tambulig, Zamboanga del Sur 468,421.73 1 Shopping N 3rd Qtr 2012 On-going procurement

108.Tambulig, Zamboanga del Sur 363,148.69 1 Shopping N 3rd Qtr 2012 On-going procurement

109.Josefina, Zamboanga del Sur 465,728.85 1 Shopping N 4th Qtr 2012 On-going procurement

110.Tigbao, Zamboanga del Sur 543,708.77 1 Shopping N Completed Procurement

111.Kumalarang, Zamboanga del Sur 411,135.87 1 Shopping N 3rd Qtr 2013 For procurement

112.Midsalip, Zamboanga del Sur 372,583.08 1 Shopping N 4th Qtr 2012 For procurement

113.Tukuran, Zamboanga del Sur 380,391.56 1 Shopping N 3rd Qtr 2012 For procurement

114.Tukuran, Zamboanga del Sur 380,391.56 1 Shopping N 3rd Qtr 2012 For procurement

115.Tukuran, Zamboanga del Sur 595,122.33 1 Shopping N 4th Qtr 2012 For procurement

116.Tukuran, Zamboanga del Sur 416,609.58 1 Shopping N 4th Qtr 2012 For procurement

117.Tukuran, Zamboanga del Sur 415,069.60 1 Shopping N 4th Qtr 2012 For procurement

118.Tukuran, Zamboanga del Sur 415,069.60 1 Shopping N 4th Qtr 2012 For procurement

119.San Pablo, Zamboanga del Sur 346,098.29 1 Shopping N 3rd Qtr 2013 For procurement

120.Labangan, Zamboanga del Sur 247,235.44 1 Shopping N 4th Qtr 2012 For procurement

121.Labangan, Zamboanga del Sur 292,705.75 1 Shopping N 4th Qtr 2012 For procurement

122.Labangan, Zamboanga del Sur 292,705.75 1 Shopping N 4th Qtr 2012 For procurement

123.Dinas, Zamboanga del Sur 809,057.43 1 Shopping N 4th Qtr 2012 For procurement

Construction of Mamad Elementary School Building

Construction of Nonoyan Elementary School Building

Construction of Sta. Maria Barangay Health Center

Construction of Baclay Elementary School Building

Construction of Tabuan 1 CL Elem. School Building

Construction of Luy-a 1 CL Elem. School Building

Construction of Tinotungan 1 CL Elem. School

Building

Construction of Barangay Bagong Silang Day Care

Center

Construction of 1 unit Tribal Hall Building

Construction of 1 Classroom School Building

Construction of Tuluran Barangay Health Station

Construction of Barangay Buenavista One Unit-2 CL

School Building

Construction of Poblacion Multi-Purpose Building

Construction of Kauswagan Multi-Purpose Building

Construction of Upper Bayao Elementary School

Building

Construction of Midsalip Cluster ARC Tribal Center

Construction of Barangay Silang One Unit-2 CL School

Building

Construction of Legarda Uno Farmers Multipurpose

Center

Construction of Limamaan Multi-purpose Center

Construction of BeGCaLLi ARC Health Station

Construction of Camanga Health Station

Construction of Josefina Cluster ARC Tribal Center

Construction of Dipaya Day Center

Construction of Binayan Tribal Center

Construction of Bokong Tribal Center

Construction of Barangay Map One Unit-2 CL School

Building

Construction of Barangay Gutalac One Unit-2 CL

School Building

Construction of Barangay Upper Gutalac Day Care

Center

Page 20: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

124.San Miguel, Zamboanga del Sur 465,728.85 1 Shopping N 4th Qtr 2012 For procurement

125.Kabasalan, Z. Sibugay

151,194.98 1 Shopping N 1st Qtr 2012 On-going procurement

126.Maluso, Basilan

1,185,219.63 1 Shopping N For procurement

127.Ganassi, Lanao del Sur 782,103.37 1 Shopping N For procurement

128.Ganassi, Lanao del Sur 561,766.61 1 Shopping N For procurement

129.Ganassi, Lanao del Sur 561,766.61 1 Shopping N For procurement

130.Poona Bayabao, Lanao del Sur 1,085,533.37 1 Shopping N For procurement

131.Poona Bayabao, Lanao del Sur 1,085,533.37 1 Shopping N For procurement

132.Parang, Maguindanao 478,253.62 1 Shopping N For procurement

133.Bongao, Tawi-Tawi 495,440.06 1 Shopping N For procurement

134.Sibutu, Tawi-Tawi 779,518.13 1 Shopping N For procurement

135.Sibutu, Tawi-Tawi 550,869.16 1 Shopping N For procurement

136.Sibutu, Tawi-Tawi 779,518.13 1 Shopping N For procurement

137.Sibutu, Tawi-Tawi 1,311,982.00 1 Shopping N For procurement

138.Sibutu, Tawi-Tawi 1,311,982.00 1 Shopping N For procurement

139.Sibutu, Tawi-Tawi 1,311,982.00 1 Shopping N For procurement

140.Sibutu, Tawi-Tawi 1,311,982.00 1 Shopping N For procurement

141.Sibutu, Tawi-Tawi 1,311,982.00 1 Shopping N For procurement

142.Sibutu, Tawi-Tawi 1,311,982.00 1 Shopping N For procurement

143.Sibutu, Tawi-Tawi 701,626.15 1 Shopping N For procurement

144.Sibutu, Tawi-Tawi 701,626.15 1 Shopping N For procurement

145.Sibutu, Tawi-Tawi 701,626.15 1 Shopping N For procurement

146.Sibutu, Tawi-Tawi 1,028,037.18 1 Shopping N For procurement

147. Sibutu, Tawi-Tawi 701,626.15 1 Shopping N For procurement

97,644,165.08 147

2,133,508,328.92 489

B GOODS/EQUIPMENT Package Amount (PhP) Amount (US$) Mode of Procurement PQ Advertisement Date Remarks

b.1 4,402,595.88 97,892.02

2 Service Vehicles (2 units) 1 package 3,000,000.00 66,705.21 Shopping N 3rd Qtr 2013 For Procurement

Construction of San Miguel Cluster ARC Tribal Center

Construction of Goodyear Day Care Center

Construction of 2 clsrms school building (Mohtar

Solayman)

Construction of Brgy. Health Station (Tanduowak)

Construction of MPB at Bgy. Calang Canas

Sub-Total - Social Facilities

Construction of Day Care Center at Brgy. Lumba-

Ingued

Construction of Day Care Center at Bgy. Gadongan

Construction of 3 unit clsrms school building (Brgy.

Tandubanak)

Construction of Taungoh Health station

Construction of 3 unit clsrm school building (Brgy.

Taungoh)

Construction of 3 unit clsrm school building (Brgy.

Tongehat)

Construction of 3 unit clsrm school building (Brgy.

Tongsibalo)

Construction of 3 unit clsrm school building (Brgy.

Ungus-Ungus)

Construction of Brgy. Tongehat Health station

Service Vehicles

TOTAL CIVIL WORKS

Construction of bgy. Tandubanak Health station

Construction of 2 classrooms school building (Sheik

Makdum)

Construction of 2 clsrms school building (Tubig-Basag)

Constructiion of Brgy. Ungus-Ungus Health Station

Construction of Brgy. Tongsibalo Health Station

Construction of MPB at Bgy. Taliogan

Construction of Bgy. Health Center at Bgy.

Campongraya

Construction of 2 clsrm school building with comfort

room & wash area in Bgy. GT Biruar

Construction of MPB at Bgy. Barorao

Construction of 3 unit clsrm school building (Brgy.

Ungus-Ungus)

Page 21: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

Number of

ContractsComments

Value of Contracts

(PhP)

Procurement Method (NCB/ Shopping)

General Description Municipality/ProvincePrequalification of

Bidders

(y/n)

Advertisement Date

(quarter/year)

4 Pump boat (3 units) 1 package 586,595.88 13,043.00 Shopping N 3rd Qtr 2013 For Procurement

6 Motorcycles (12 units) 1 package 816,000.00 18,143.82 Shopping N 2nd Qtr 2013 For Procurement

b.2 683,400.00 15,195.45

2 Desktop Computer (10 units) 1 package 328,000.00 7,293.10 Shopping N 3rd Qtr 2013 For Procurement

4 Laptop Computer (10 units) 1 package 355,400.00 7,902.34 Shopping N 3rd Qtr 2013 For Procurement

b.3 4,000,000.00 88,948.19

1. Geodetic survey equipment 1 package 4,000,000.00 88,948.19 Shopping N 3rd Qtr 2013 For Procurement

b.4 690,000.00 15,342.20

2 A3 Scanner/Printer (3 units) 1 package 360,000.00 8,004.62 Shopping N 3rd Qtr 2013 For Procurement

3 DSLR Camera (3 units) 1 package 210,000.00 4,669.36 Shopping N 3rd Qtr 2013 For Procurement

4 Fax Machine (6 units) 1 package 120,000.00 2,668.21 Shopping N 3rd Qtr 2013 For Procurement

b.5 160,000.00 3,557.61

1 Air-Con Unit (2) 1 package 160,000.00 3,557.61 Shopping N 3rd Qtr 2013 For Procurement

9,935,995.88 220,935.47

C. CONSULTING SERVICES Package Amout (PhP) Amount (US$) Mode of Procurement PQ Advertisement Dte Remarks

1

2 2,000,000.00 44,470.14

a. 1 package 2,000,000.00 44,470.14 SSS N 3rd Qtr 2013 For Procurement

2,000,000.00 44,470.14

B. Indicative List of Packages Required Under the Project

6. The following table provides an indicative list of all procurement (goods, works and consulting services) over the life of the project. Contracts financed by the Borrower

and other should also be indicated with an appropriate notation on the comments section.

Estimated Value (PhP) Est. No. of Contracts Comments

2,143,444,324.80

1 Goods/Equipment 9,935,995.88 17 On-going Procurement

2 Works 2,133,508,328.92 489 On-going Procurement

Estimated Value (PhP) Est. No. of Contracts Comments

CONSULTING SERVICES 651,838,960.18

1 Individual 30,000,000.00 15 On-going

2 Firms 621,838,960.18 259 On-going

Domestic-Individual

Other Fixtures

Surveying Equipment

Other Office Equipment

TOTAL GOODS/EQUIPMENT

Procurement Method Domestic Preference Applicable

TOTAL CONSULTING SERVICES

N/A

N/A

Individual Selection

GENERAL DESCRIPTION Recruitment Method

Total Goods/Equipment and works

NCB/Shopping

QCBS/LCS/CQS/SSS

-

FTP/BTP

NCB/Shopping

Type of Proposal

GENERAL DESCRIPTION

Baseline Survey Study for Additional ARCs

Computers

Firms

Page 22: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

National Competitive Bidding Annex

1. General

7. The procedures to be followed for national competitive bidding shall be those provisions referring to open competitive bidding procedures set forth in Republic Act 9184 the Republic of the Philippines, effective 26 January 2003, and its Revised Implementing Rules and Regulations, effective 2 September 2009, with the clarifications and modifications described in the following paragraphs required for compliance with the provisions of the Procurement Guidelines, Section I and paras. 3.3 and 3.4 of Section III.

2. Eligibility

(i) Eligibility screening shall not be applied. However, bids that do not contain any of the following documents will not pass the documentary compliance check: (i) evidence of the required financial, technical or production capability; (ii) audited financial statements; (iii) credit line, or cash deposit certificate; (iv) bid security; and (v) authority of the bid signatory.

(ii) National sanction lists may be applied only with prior approval of ADB

3. Advertising

8. Bidding of NCB contracts estimated at $500,000 or more for goods and related services or $1,000,000 or more for civil works shall be advertised concurrently with the general procurement notices on ADB’s website.

4. Price of Bidding Document

9. The price of bidding documents should be nominal, covering only reproduction and mailing/courier costs.

5. Price Ceiling 10. The approved budget for the contract (ABC) may be published, but it shall not be stated or implied that bid prices may not exceed the ABC, or that bid evaluation will in any way take into account the ABC. The ABC, budgetary allocation, ceiling price, or similar estimates of contract value may not be used to reject bids without prior concurrence of ADB.

6. Preferences

(i) No preference of any kind shall be given to domestic bidders or for domestically manufactured goods.

(ii) Suppliers and contractors shall not be required to purchase local goods or

supplies or materials. (iii) Foreign suppliers and contractors from ADB member countries shall be allowed to

participate, if interested, without first being required to associate with, or enter into joint venture with, local firms.

Page 23: AGRARIAN REFORM COMMUNITIES PROJECT II...BASIC DATA PROCUREMENT OF CONSULTING SERVICES PROCUREMENT OF GOODS AND WORKS. ... Construction and Concreting of San Aquilino-Lagundi 2-Sarada-San

(iv) Foreign suppliers and contractors from ADB member countries shall be allowed to bid, without registration, licensing, and other government authorizations, leaving compliance with these requirements for after award and before signing of contract.

7. Experience Qualification

11. For works contract, the experience qualification requirement shall be: (i) at least one previous contract at 80% of the estimated cost of the contract being procured; and (ii) an annual turnover from all works averaged over the last three years equal to 100% of the estimated cost of the contract being procured.

8. Anticorruption Provisions in Bidding Documents 12. Anticorruption provisions in the Instructions to Bidders section of ADB standard bidding documents (SBDs) shall be incorporated into NCB bidding documents including those under “Corrupt Practices” and “Eligible Bidders” clauses of the SBDs.

9. Bidding Period 13. Bidders shall be given a minimum period to prepare and submit bids of 4 weeks, counted from the date of invitation to bid or the date of availability of bidding documents, whichever is later.

10. Single Bid Submission 14. When a lone bidder obtains a bidding document and submits a bid at the deadline for bid submission under a postqualification bidding, bid opening and evaluation shall not proceed but it shall be considered a failure of bidding. Before taking any alternative procurement action, a proper assessment of the cause of lack of participation shall be made and ADB prior approval shall be sought for any proposed subsequent action.

11. Shopping Method 15. If included as a procurement method in the Procurement Plan, “Shopping” shall be undertaken in accordance with the ADB Procurement Guidelines (April 2010, as amended from time to time).

12. Contract Amendment 16. In case of contracts for prior review, modifications exceeding 15% of contract amount and material changes in the conditions during implementation require prior ADB concurrence.

13. Member Country Restrictions 17. Bidders must be nationals of member countries of ADB, and offered goods must be produced in member countries of ADB.