agenda fpd overview andrew 30 mins tunnel status: 1) castle status christophe 2) detector status...

30
Agenda FPD Overview Andrew 30 mins •Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier Status Victor 50 mins Discussion •Trigger Overview and PW08 Status Pierrick 30mins •Tunnel+PW08 access plans Pierrick 10 mins •Trigger Eqs Molina 10 mins •Run Plan and analysis Mike 10 mins •DAQ+SDAQ Victor 10 mins •Software Sergio Tracking Jorge B. Unpacking Naeem MC Andre 40 mins Discussion

Upload: derrick-walsh

Post on 08-Jan-2018

217 views

Category:

Documents


0 download

DESCRIPTION

Series of 18 Roman Pots forms 9 independent momentum spectrometers allowing measurement of proton momentum and angle. 1 Dipole Spectrometer ( p )  min 8 Quadrupole Spectrometers (p or p, up or down, left or right) t > t min Q4Q4 D S Q2Q2 Q2Q2 Q3Q3 Q3Q3 Q4Q4 S A 1Q A1SA1S A 2Q A 2S P 1Q P 2S P 1S P 2Q p p Z(m) A D2 A D1 Detector Bellows Roman Pot Forward Proton Detector Layout p Beam pFpF P

TRANSCRIPT

Page 1: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Agenda• FPD Overview Andrew 30 mins

•Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier Status Victor 50 minsDiscussion

•Trigger Overview and PW08 Status Pierrick 30mins•Tunnel+PW08 access plans Pierrick 10 mins•Trigger Eqs Molina 10 mins•Run Plan and analysis Mike 10 mins•DAQ+SDAQ Victor 10 mins•Software Sergio Tracking Jorge B. Unpacking Naeem MC Andre 40 mins

Discussion

Page 2: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

FPD OverviewFPD Overview

FPD DayDecember 12, 2001Fermilab

Andrew BrandtUniversity of Texas, Arlington

No, it doesn’t work yet, but it will all be

ready March 1 July 1Soon!

Page 3: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Series of 18 Roman Pots forms 9 independentmomentum spectrometers allowing measurementof proton momentum and angle.

1 Dipole Spectrometer ( p ) min

8 Quadrupole Spectrometers (p or p, up or down, left or right) t > tmin

Q4D SQ2Q2 Q3 Q3Q4S

A1QA1S

A2QA2S

P1Q

P2S

P1S

P2Q

p p

Z(m)

AD2 AD1

Detector B

ello

ws

Roman Pot

Forward Proton Detector Layout

233359 3323057

pBeam pF

P2)( FBeam PPt

PPxp

1

Page 4: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

FPD Summary July 11, 2000• Hard diffraction exists, but not well-understood: large data samples and precise measurements needed

• Large c.m. energy and luminosity of Tevatron necessary for these measurements

• FPD will be a completely integrated sub-detector of the DØ detector: Combination of quadrupole and dipole spectrometers gives ability to tag both p’s and ’s over large kinematic range, allows alignment, understanding of backgrounds

• Beams Division work for installation of FPD complete

• Preparations underway for Engineering Run: all Roman pot castles will be installed, some arms instrumented

• Control of pots (motors) using DØ online system has been tested

• Detector production underway at UTA

• Funding still not secured for phototubes and trigger electronics

p

Page 5: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Quadrupole CastleQuadrupole Castle

Photo of a quadrupole castles installed in Tevatron tunnel.All 6 FPD castles were installed in fall of 2000.

Page 6: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Engineering Run (9-10/00)

Setup a standalone DAQ system close to D0CR.

Cabling (PMT, HV, TV, 1553, etc) SCR to Tunnel.

Installation of the castles in the beam line: Dipoles (fully equipped) + proton castles partially equipped

Installation of two full detectors and some scint.

Test of remote pot motion via a Python script.

Data taking.

Some problems found:Some problems found:

Everything takes longer than you think!

Rack monitor heating (noise from switch, fixed).

Flooding in the tunnel (need umbrellas).

Loss of pot control (new procedures, safeguards).

Page 7: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Hit Reconstruction

• This event (from Engineering Run data) represents a hit in our detector at the location:

xd = 5.6 mmyd = 3.8 mm

Page 8: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

FPD Manpower• UTA

– Andrew Brandt – Mike Strang (grad student)– Pierrick Hanlet (post-doc) –5/31/02– Christophe Royon (Saclay faculty) 7/18/02– Victor Bodyagin (Moscow State faculty) 2/28/02– Jia Li (engineer/physicist)– Tom Lytle (grad student)– Petra Krivkova (grad student –8/31/01)– Lionel Peyrichoux (engineer –8/31/01)

• Brazil – Alberto Santoro (faculty group leader)– Sergio Novaes (faculty at Fermi)– Jorge Molina (grad student at Fermi)– Gilvan Alves (faculty) – Helio da Motta (faculty)– Newton Oliveira (engineer)– Eduardo Gregores (post-doc)– Mario Vaz (engineer)– Jorge Barreto (faculty)– Vitor Oguri (faculty)– Carley Martens (faculty)– Marcia Begalli (faculty)– Andre Sznajder (post-doc)– Wagner Carvalho (post-doc)

• Other – Mike Martens (FNAL)– Carlos Avila (Bogata)– S. Ahmed (Nijmegen)– Brian Cox (Manchester)– Vladimir Sirotenko (Fermilab)

Page 9: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

FPD Status 3/01/01• All 6 castles with 18 Roman pots comprising the FPD have been installed in Tevatron

• Most cables and pot motion electronics installed (~full time work for 6 FTE from Dec-Mar)

• Electronic safety review completed

• Two complete detectors and four pseudodetectors (trigger scintillator only) installed and waiting for beam.

• Testing of all systems underway

• Work continues on trigger, software

• Some additional funds ($38,000) secured by Brazil, still need $67,000 to complete 10 detectors ($25,000 promised by DOE)

Page 10: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

May Shutdown Plans• Test upgraded pot motion program and obtained pot motion approval

• Continued cabling

• Installed new cameras

• Added a couple more pseudo-detectors

• Many miscellaneous tasks

At end of shutdown :

Prepared and approved for collisions

Tunnel work should essentially completedexcept for installation of additionaldetectors

Page 11: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Pot Motion: LVDT vs. Encoder

Page 12: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Pot Motion Tests and Safeguards • The pot motion software was upgraded and

extensively tested during the May shutdown.

• The software is reliable and gives reproducible results. The pots always moves to the desired position

• The software verifies the direction of the intended pot motion to make sure that it is correct before the pot is moved. If this is not the case the command is reissued, and if it is still wrong, the pot is returned home.

• The drivers are disabled with a switch in the SCR when the pots are not being moved.

• The pots are hooked to an emergency line which bypasses the software to send the pots back to the home position.

Page 13: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

More Pot Motion

• Smoke detector alarms disable the pot motion (haven’t had any, but have tested).

• An alarm is given if contact with the IIB is interrupted. If this situation continues the emergency line could be used.

• The pot positions are in ACNET as well as variables which indicate all pots are in home position, which are checked by the MCR before beam injection.

• Halo rates are displayed, and after some experience is gained, alarms will be added if the halo rate changes significantly.

• A pot motion manual has been provided to all shifters and a copy is in the SCR

Page 14: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Pot Motion Tests

Initially pot motion tests restricted to end of stores, so progresss slowEventually gained confidence of BD, allowed to insert pots anytime

Page 15: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Summer Run Plan

• Dedicated FPD shifts with pots inserted close to beam

• Used stand-alone DAQ/trigger in small control room

• Full system tests (excluding DØ trigger)

• Debugging, data-taking, algorithm development, pot insertion procedure, documentation, etc.

Page 16: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Goals for Oct. Shutdown

• Detector Upgrades– Install and test 8 new detectors

• Readout & Triggering– Installation of AFE interface and AFE and

DFE boards – Commissioning readout chain– Commissioning trigger chain

• Pot Motion– Installation of multiplexors– Software upgrade, database update

• Veto Counters– Installation of new scintillation veto

counters (5.2<||<5.9)

Page 17: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Detector Upgrades

Done:• Test and bin MAPMT’s and L0 PMT’s• Cartridge Assembly • Cable tests• Map detectors with optical scanner• Installing detectors • Detector tests• Amplifer tests• Low voltage tests• Noise studies

To Do:• Final low voltage purchase

Page 18: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Readout and TriggeringDone:• Design and building of AFE cassette

support• Cabling in collision hall • Design of Transition boardIn Progress: • Construction of Transition Board• Final comb supportTo Do:• Tests with AFE boardsPrognosis: • Progress slow, have been hampered by

unavailability of LM/AFE boards, non FPD/AFE contact edict

• Full integration with DØ will not happen for another couple/few months

Page 19: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Transition Board

Page 20: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Pot MotionDone:• Get Newton to Fermilab• Multiplexor board constructionIn Progress: • Tests of Mux boardsTo Do• Upgrade pot motion software• Switchover to muxPrognosis: • Need a magnet failure at some future date

to install mux

Page 21: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Veto Counters

Done:• Veto counter feasibility study • Veto counter and support design (Jia Li and A.B.)• Counter construction and support

machining (Lab 6, Lab 8, DØ)• Counter assembly and installationTo Do:• Commission Counters

Page 22: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Veto Counter

Page 23: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

FPD Funding StatusCost to complete FPD Stage I (10 pots):

Item Cost63 MAPMT(@$1540)

$97,000*

AFE interfaceMultiplexor,misc.

$8,000

Total $105,000

Funds available:

Source Amount

Fermilab $42,000

LAFEX $38,000

DOE Sup. $25,000

Total $105,000

•Additional $97,000 needed for 18 pots ($30k of this just obtained from ARP)

Page 24: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

FPD Parts and CostsOutstanding Phase I costs:

TPP Boards: $3,400TPP Stuffing $800?TPP components $3000Amp LV $2200Vicor AFE LV $2000Backplane $1000?LM LV $2000

Shutdown personnel costs:$8800

Page 25: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Software Effort Proton ID leaders: G. Alves, S. Novaes

L1: Proton Tracking M. Martens, J. BarretoM.Vaz, J.Molina - hardware equations

MI and Halo Rejection W. Carvalho

Resolutions M. Martens, J. Barreto

L2: Gap Tool M. Strang

L3: Tracking G. Alves M. Martens, J. Barreto, M. Souza SI Tool S. Novaes, E. Gregores

ONLINE: Calibration C. Royon, H. da Motta

Alignment C. Avila, M. Martens

OFFLINE: Monte Carlo G. Alves, Andre Sznadjer

Calibration H. da Motta, C. Royon

MC Studies S. Novaes, E. Gregores

TrigSim W. Carvalho, G. Alves

Reco J. Barreto, M. Martens

Page 26: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Long Range Plan• Begin data taking with improved system in December (still standalone)

• Use sDAQ to start integration in DØ

• Install AFE’s when available (January?)

• Firmware and Trigger development

• Demonstrate working system, usefulness of horizontal plane, and secure funding for remaining MAPMT in 2002

• Early papers: NIM Elastic t-distribution Single diffraction distributions Diffractive jet production Double tagged double pomeron exchange

Page 27: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Responsibilities• Data Taking and Analysis Coordinator (Mike S.)

• FPD Electronics/Firmware (Pierrick)

• Pot Motion/MUX (Christophe)

• SDAQ/PDAQ (Victor)

• Software (Sergio, Gilvan, et al)

• L1 Tracks (Jorge) with Mario+Wagner

• MC (Andre)

• NIM (Helio)

• Calibration (Helio?)

• Alignment (Carlos)

• Physics

• Other

Need detailed plans from each area, manpower and resourcerequirements, schedules etc.

Page 28: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Issues• Do detectors work properly? Efficient? • Can we reconstruct tracks?• Can we reduce halo rates?• Can we reject halo?• Mu metal shields work?

• Manpower for trigger/firmware effort

• Extra funds for trigger electronics

• Funds for Phase II

Page 29: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Goals/Milestones• First Track 12/25/01• SDAQ 1/1/02 • Examine 1/15/02• TPP tested 1/15/02• Mux ready 1/31/02• TM operational 1/31/02• AFE installed 3/1/02• FPD data with full system 4/1/02

Page 30: Agenda FPD Overview Andrew 30 mins Tunnel Status: 1) Castle Status Christophe 2) Detector Status Mike S. 3) Elec. rewiring+safety Pierrick 4) Amplifier

Conclusion

• Tremendous progress in installation and commissioning

• Entering a new phase of FPD: 1) Installation almost complete 2) We have funding for Phase I!

• Emphasis shifts to software and operations

• Trigger hardware and firmware a MAJOR concern

• Starting to think about physics a little!

• Need renewed commitment, more manpower at Fermilab, higher % of time from non-local people to succeed