AGENDA FOR THE 7th MEETING TO BE HELD ON 17TH APRIL 2012 AT WRPC, MUMBAI TO REVIEW PROGRESS OF ONGOING TRANSMISSION

PROJECTS IN WESTERN REGION 1. Confirmation of the minutes:

The Minutes of 6th meeting held on 11th August 2011 at WRPC, Mumbai to

review ongoing transmission projects in Western Region were forwarded vide letter no

WRPC/Comml-II/2/TRM/Min/2011/7591 dated 19.08.2011. No comment on the minutes

has been received.

Minutes of 6th meeting to review progress of ongoing transmission projects in western region may be confirmed. 2. Status of Important lines identified for completion on priority: The progress of ongoing transmission schemes under construction executed by

GETCO, MPPTCL, CSPTCL, MSETCL, PGCIL, Western Region Transmission

(Maharashtra) Pvt. Ltd. & Western Region Transmission (Gujarat) Pvt. Ltd. are

reviewed regularly under following categories as decided during 2nd TRM held on 8th

June 2010

a) Progress of transmission schemes associated with evacuation and system

strengthening scheme for own Generating Station.

b) Progress of transmission schemes associated with evacuation and system

strengthening scheme for Generating Station set up by IPP.

c) Progress of interconnected transmission schemes associated with PGCIL Sub-

station.

d) Progress of transmission schemes and system strengthening schemes set up

through IPTC route.

e) Progress of Intra-state transmission schemes.

Page 3: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

2

2.1 The present status of lines identified for completion on priority is as below:-

S.No. Line Implementing

Agency Anticipated target

1 400 kV D/C line from Bhusawal II to Aurangabad (Loc. No. 1 to 270)

Maharashtra 23.12.11

2 400 kV Vapi(PG)-Navi Mumbai D/C

PGCIL Mar-13

3 400 kV D/C Mundra-Jetpur PGCIL May -12 4 400 kV D/C Gandhar-Navsari PGCIL March -12 5 400 kV D/C Navsari- Mumbai line(Boisar) PGCIL March-13 6 LILO of Lonikhand (MSEB)- Kalwa

(MSEB) 400 kV D/C at Pune (PG) Reliance (IPTC route)

March -12

7 400 kV D/C Rajgarh(PG) – Karamsad (GEB)

Reliance (IPTC route)

November-12

8 400kV D/C Vindhyachal-IV - Vindhyachal Pooling Station line (Q)

PGCIL November-12

9 765kV S/C Vindhyachal Pooling Station - Satna line (Ckt-I)

PGCIL February-13

10 765kV S/C Vindhyachal Pooling Station - Satna line (234km+12km D/C Portion)Ckt-II

PGCIL February-13

11 LILO of 765 kV S/C Sipat-Seoni line at WR Pooling station near Sipat

PGCIL March-12

12 LILO of 765 kV S/C 2nd Sipat-Seoni line at WR Pooling station near Sipat at Bilaspur (Pooling Stn.)

PGCIL March-12

13 400 kV D/C Raipur(PG)-Wardha(PG) line PGCIL December-12 14 400kV D/C Mauda STPS - Wardha line

(Quad) PGCIL April-12

15 765 kV 2nd S/C Seoni - Wardha line PGCIL 01.03.12 16 400 kV D/C Korba (NTPC) – Birsingpur

(MPGENCO) PGCIL 29.02.12

The updated details of ongoing transmission schemes under construction are enclosed

at Annexure-1, 2, 3, 4, 5 and 6 respectively under heads as given above.

Committee may like to discuss progress.

Page 4: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

3

2.2 Important EHV lines commissioned during the year 2011-12:

S.No. Line Charged on

1 400 kV D/C Vadinar-Hadala 25.04.11

2 400 kV D/C Korba STPS-Raipur 21.06.11

3 400 kV D/C Rourkela – Raigarh 29.06.11

4 LILO of 400 kV D/C Bina-Nagda line at Sujalpur 29.05.11

5 400 kV D/C Limbdi(Chorania)(GEB)-

Ranchodpura(Vadavi)(GEB)

16.05.11

6 LILO of one circuit of 220KV Bina-Shivpuri at 765KV S/s

PGCIL, Bina

18.04.11

7 220kV D/C Bhat-Pirana line with AL-59 Cond. 11.05.11

8 220 kV LILO at Mota S/S from 2nd Ckt.of Ukai(T)-Vav line 14.04.11

9 220KV Ukai-Vav 09.04.11

10 400 kV D/C Korba- Raipur 21-06-11

11 400 kV D/C Mundra-Bachchau 29-09-11

12 400 kV D/C Bachchau- Ranchodpura 29-09-11

400 kV D/C Vadavi)GEB) -Kansari(GEB) 16.11.2011

13 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 31.07.2011

14 400 kV D/C Parli(MSEB)-Parli(PG) line 01.07.2011

15 220kV D/C Kosamba-Zagadia line 09.07.2011

16 400 kV D/C line from Bhusawal II to Aurangabad (Loc. No.

1 to 270)

23.12.11

17 765 kV 2nd S/C Seoni - Wardha line 01.03.12

18 400 kV D/C Korba (NTPC) – Birsingpur (MPGENCO) 29.02.12

Committee may like to note.

Page 5: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

4

2.3 Important EHV lines, which are expected to be commissioned during

the current year 2012-13:

S.No. Line Implementing Agency

Anticipated target

1 400 kV D/C Mundra-Jetpur PGCIL June -12 2 400 kV D/C Gandhar-Navsari PGCIL March -12 3 400 kV D/C Navsari- Mumbai line(Boisar) PGCIL March-13 4 LILO of Lonikhand (MSEB)- Kalwa

(MSEB) 400 kV D/C at Pune (PG) Reliance (IPTC route)

March -12

5 LILO of 765 kV S/C Sipat-Seoni line at WR Pooling station near Sipat

PGCIL March'12

6 LILO of 765 kV S/C 2nd Sipat-Seoni line at WR Pooling station near Sipat at Bilaspur (Pooling Stn.)

PGCIL March'12

7 400 kV D/C Raipur(PG)-Wardha(PG) line PGCIL June-12 8 400kV D/C Mauda STPS - Wardha line

(Quad) PGCIL April 12

Committee may like to note.

3. Any other item 4. Date and venue of next meeting.

* * * * *

Page 6: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

(A) Transmission Schemes associated with State Generating Stations

1 Utran CCPP (2009-10) (374 MW) Nov 091.1 220kV Utran-Kosamba D/C line No.2 86.00 144 4 Mar-12 Work under progress. Severe ROW

problems

1.2 220kV D/C Kosamba-Mobha line 178.20 300 222 194 38.59 Jun-12 Work in progress.

1.3 220kV D/C Gavasad-Salejada line with AL-59 cond. 194.00 313 19.00 - - To be reinvited

2 Sikka Unit 3&4 (2x250 MW) C.O.D.- Dec'122.1 220kV D/C Sikka-Moti Paneli line with AL-59 cond. 156.00 248 19.00 - - To be reinvited

2.2 LILO to Sikka from 220kV Jamnagar-Jetpur ckt. 1 116 178 - - - Yet to be awarded.

2.3 LILO to Sikka from 220kV Jamnagar-Jetpur ckt. 2 120 187 - - - Yet to be awarded.

3 Ukai Extension (2010-11) (500 MW) C.O. D.- Jul'113.1 400kV D/C Ukai-Kosamba line 144 215 159 123.00 29.07 May-12 Work in progress.

3.2400 kV D/C Kosamba-Chorania line (Package I)(From Chorania S/S to AP-54)

222.4 308 225 173 50.83 Aug-12 Work in progress.

3.3400 kV D/C Kosamba-Chorania line (Package II)(From Kosamba S/S to AP-54)

234.6 328 240 172 - Aug-12 Work in progress.

3.4 LILO to Kosamba from 400kV Asoj-Ukai line 64.00 96 96 96 62.57 Dec-11 31.12.113.5 220kV D/C Kosamba-Zagadia line 48.4 86 86 86 47.67 Jun-11 09.07.114 Dhuvaran CCPP-III (360 MW) July'13

4.1 LILO of 220kV Kasor-Vartej S/C at Dhuvaran CCPP-III 82.00 148.00 - - - Oct-12 WIP

4.2 LILO of 220kV Karamsad-Vartej S/C at Dhuvaran CCPP-III 78.00 143.00 - - - Oct-12 WIP

Tower erected

Anticipated completion

Target

Annexure-1(1/3)Status of Ongoing Transmission Progress in Gujarat (February-12)

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 01.03.12

Stringing completed

Remark Stub

setting

Page 7: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

(B) Transmission Schemes associated with IPP 5 Adani Power, Mundra (Bid-II)(2011-12) (1000 MW)

Feb'125.1 400 kV D/C Mundra-Zerda line No. 1 664.00 901 78.00 27.00 - Dec-12 Package-I-Work in progress.

Package-II-Work in progress. Package-III-Order placed on 12.05.11

5.2 400 kV D/C Mundra-Zerda line No. 2 660.12 921 734 656 329.83 May-12 Work in Progress6 Essar Power, Vadinar (Bid-3) (2011-12)(1000 MW)

Feb'116.1 400 kV D/C Vadinar-Hadala line 226.00 353 353 353 225.77 - Line Charged on 25.04.116.2 400 kV D/C Vadinar-Amreli line 356.02 531 309 181 58.42 Sep-12 Work in progress

7 GSPC Pipavav Power Co. Ltd.(2010-11) (2x350 MW) Mar'11

7.1 220 kV D/C GPPCL-Dhokadva line 100.00 154 91 80 - Aug-12 Work in progress.Severe ROW problem

7.2 LILO to GPPCL from 220 kV Savarkundla-Otha Ckt. No. 1 90.52 149 149 147 81.79 Mar-12 Work in progress.Severe ROW problem

7.3 LILO to GPPCL from 220 kV Savarkundla-Otha Ckt. No. 2 82.60 131 116 114 60.85 Mar-12 Work in progress.Severe ROW problem

7.4 220 kV D/C Otha-Sagapara line 95.60 163 68.00 40.00 - Sep-12 Work in progress8 GSEG Extension Phase-I (350 MW) Jan'11

8.1 220 kV D/C GSEG-Kosamba line 124.74 211 211 211 124.74 Aug-11 Line Charged on 24.08.118.2 220 kV D/C GSEG-Mota line with AL-59 conductor 111.06 182 66 38 1.14 Sep-12 Work in progress

9 Bhavnagar Energy Co. Ltd.(BECL)(2011-12) (2x300 MW)

9.1 220 kV D/C BECL-Botad line 188.52 292 5.00 - - Sep-12 WIP9.2 220 kV D/C BECL-Sagapara line 82.40 135 7.00 4.00 - Sep-12 WIP9.3 LILO of 220kV Savarkundla-Vartej at BECL 56.20 97 40.00 24.00 - Sep-12 WIP

Remark Stub setting

complete

Tower erected

Anticipated completion

TargetStringing completed

Length in Ckt

Km

Present Status as on 01.03.12Annexure-1(2/3)

Total LocationSr. No. Name of Transmission line

Page 8: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-1(3/3)

(C) Transmission Schemes associated with PGCIL Substation

1 LILO OF 220 kV to Bhachau from Morbi -Halvad ckt.no.1 217.00 315 312 305 142.91 Apr-12 Work in progress.(Severe ROW problems)

2 LILO OF 220 kV to Bhachau from Morbi -Halvad ckt.no.2 216.40 333 332 317 141.54 May-12 Work in progress.(Severe ROW problems)

3 220kV D/C Bhat-Pirana line with AL-59 Cond. 28.94 57 57 57 29.32 May-11 Line charged on 11.05.11

(D) Transmission Schemes through IPTC route NIL

(E) Intrastate transmission schemes1 400kV Mundra-Hadala LILO to Halvad 89.40 124 35 4 - Sep-12 Work in progress.

2 400 kV D/C Amreli-Kasor line(Part-1) (Amreli Gantry to AP-28)

160.95 214 36 - - Mar-13 Work in progress.

3 400 kV D/C Amreli-Kasor line(Part-1) (AP-28 to AP-44) 164.34 218 18 - - Mar-13 Work in progress.

4 400 kV D/C Amreli-Kasor line(Part-1) (AP-44 to Kasor Gantry)

145.26 194 39 8 - Mar-13 Work in progress.

5 220kV D/C Hadala - Halved line. 168.00 272 222 194 38.59 Jun-12 Work in progress. 6 220 kV D/C Nakhatrana-Varsana line with AL-59 Cond. 213.76 352 305 273 131.7 Jun-12 Work in progress.

7 220kV D/C Bhutiya - Kheralu line 98.63 163 162 162 98.25 Dec-11 Line charged on 20.01.128 220kV LILO to Kangasiyali from Gondal - Rajkot line 28.00 56 56 56 27.74 Jun-11 27.06.119 220 kV LILO to Shapur from Jetpur - Kesod line 3.22 7 7 7 3.22 Mar-12 Line charged on 18.02.12

10 220 kV LILO at Mota S/S from 2nd Ckt.of Ukai(T)-Vav line 9.60 16 16 16 9.60 _ 220KV Ukai-Vav Line Charged on 09.04.11 and 220 KV Mota-Vav Line charge on 14.04.11

11 220 kV LILO at Kukma s/s from one ckt. Of Shivlakha-Nanikhakhar line.

34.00 54 40 40 17.74 Work in progress.(Severe ROW problems)

12 220kV D/C Tharad - Thavar line 97.09 160 160 156 56.72 Mar-12 Work in progress. 13 220kV D/C Tharad - Deodar line 77.46 130 128 118 4.952 Apr-12 Work in progress. 14 220kV D/C Sankhari - Jangral line 64.00 111 111 111 59.858 Mar-12 Work in progress. 15 220kV D/C Wagra - RVNL line 18.36 33 33 33 18.522 Line chaged on 17.12.201116 220kV D/C Charanka - Jangral line(Charanka to AP-13/0) 29.10 53 53 53 29.6 Jan-12 Line chaged on 28.02.12

17 220 kV LILO to Lalpar from Dhrandhara- Morbi S/C 13.42 24 24 24 13.42 Line chaged on 11.01.1218 220 kV D/C Halvad-Sadla line 76.00 124 11 - - Jun-12 Work in progress. 19 220 kV LILO to Sadla from Chorania-Gondal line 48.74 78 - - - Jun-12 Work in progress. 20 220 kV D/C Varsana - Jamanwada line 346.00 561 444 402 150 Apr-12 Work in progress. 21 220 kV D/C Nyara - Tebhda line 180.18 326 326 326 180.18 Apr-12 One ckt. Charged on 01.10.11

Anticipated completion

TargetStub

setting complete

Stringing completed

Present Status as on 01.03.12Total

Location Tower erected

Remark Sr. No. Name of Transmission lineLength in Ckt

Km

Page 9: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-2(1/2)

A.

Transmission Schemes associated with evacuation and system strengthening scheme for own Generating Station.( Malwa Power 2*600)

1 Malwa-TPH-Pithampur 400KV DCDS Line 300 405 319 130 - September/12 Work is in progress.

2 Malwa TPH-Chhegaon 400 KV DCDS Line 102.8 153 127 108 - June/12 Work is in progress.

3 Chhegaon-Julwania 400 KV DCDS Line 230 338 188 72 - September/12 Work is in progress.

4 Pithampur- Indore 400KV DCDS Line 128 188 158 54 2012-13 Work is in progress.

5 Malwa TPH-Chhegaon 220KV DCDS Line 95.708 160 160 160 - June/12 25.02.20126 Satpura TPH-Ashta 400KV DCDS Line 470 - - - - December/12 Forest proposal submitted.

B

Transmission Schemes associated with evacuation and system strengthening scheme for Generating Station set up by IPP.( Bina Power)

1 400KV Bina S/s to BPSCL's Bina TPS 400KV DCDS Line 40 - - - - September/12 Complete work including survey

being carried out by BPSCL

2 Maheshwar-Pithampur 220KV DCDS Line 119.64 195 190 190 114.88 December/11 25.01.12

C Transmission Schemes associated with PGCIL Substation.

1 Pithampur-Indore (PGCIL) - 400 kV DCDS Line 130 188 33 - - June/12 Work is in progress

2 LILO of one circuit of 220KV Bina-Shivpuri at 765KV S/s PGCIL, Bina 1.66 5 5 5 1.66 May/11 Line charged on 18.04.11

Status of Ongoing Transmission Progress in Madhya Pradesh (February-12)

Sr. No. Name of Transmission lineLength in Ckt Km

Total Location Tower

erectedStringing

completed

Present Status as on 01.03.2012 Anticipated

completion Target

Remark Stub

setting

Page 10: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

DTransmission Schemes and system strengthening schemes set up through IPTC Route.

NIL

1Satpura TPH-Astha 400kV DCDS line

470 - - - - December/13 Work is being carried out

through PPP mode

E Intra-State Transmission Schemes

1LILO of 220KV Pithampur-Indore & 220KV Pithampur-Badngar line at 400KV Substation Pithampur

66 93 2 - - March/12 Work is in Progress.

2 LILO of both CKT. OF Nimrani-Julwania 220KV Line at Julwania 400KV 40 - - - - March/12 Survey to be taken up

4 Ashta 400-Indore-II(Jetpura) 220 kV DCDS line 200 - - - - June/12 Survey Under progress.

5 Ratlam-Daloda 220 KV DCSS Line 60 - - - - March/12 Survey Under progress.

6 LILO of 220 KV DCDS Nagda-Neemuch line at Daloda S/S 9 18 1 - - March/12 Work is in Progress.

7 LILO of 220 KV Itarsi-Narsinghpur Line at Chichli S/s. 5 - - - - June/12 Survey Under progress.

LILO of 220 KVSatna(PGCIL)-Katni line 220kV S/s. at Maihar 4 5 5 3

Work completed. Line charged on 28.11.11

8 Second circuit stringing of 220kV Satpura(Sarni)-Pandhurna line 35 - - - 27.5 December/11

Forest proposal submitted to CCF SAG meeting due in July' 11

Remark Stub

setting

Annexure-2(2/2)

Sr. No. Name of Transmission lineLength in Ckt Km

Total Location

Present Status as on 01.03.2012 Anticipated

completion TargetTower

erectedStringing

completed

Page 11: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-3

(A) Transmission Schemes associated with State Generating Stations

1 1x500 MW Korba West TPP Power Evacuation Scheme ( June-2012)

1.1 LILO of 400 kV Korba (West)-Bhilai at Raipur DCDS 47.10 70 70 69 25 Mar.12 Work under progress.

1.2 400 kV Korba(West)- Khedamara DCDS Ckt. I &II 448.00 640+8G 606 582 165.45 Mar.12 Work under progress.

1.3 400 kV Khedamara- Raita DCDS 112.00 168 28 Nov .12 Work under progress.

2 2x500 MW Marwa TPP Power Evacuation Scheme (Nov-2012)

2.1 400kV DCDS Marwa-Raipur(Raita) 281.00 379 358 258 100.05 Jun.12 Work under progress.

2.2 LILOof 400kV K(W)-Khedamara line at Marwa (one ckt.)

115.52 179 11 - - Jan.13 Survey work completed

2.3 220kV line Marwa to Banari DCDS 28.26 49+12G 50 44 13 Mar-12 Work is in progress.

(B) Transmission Schemes associated with IPP NIL

(C) Transmission Schemes associated with PGCIL Substation NIL

(D) Transmission Schemes through IPTC route NIL

(E) Intrastate transmission schemes

6.1 400 kV Raipur (Raita)- Jagdalpur DCDS 650 May-14 Survey under progress.

6.2 220 kV Korba -Bishrampur DCSS 153.00 509 357 316 37.67 Dec-12 Final Forest approval received on 19.08.2011

6.3 220 kV DCDS Lines Chhuri to Mopka (Bilaspur) 189 346 289 246 4.6 Mar-12 Work under progress.

6.4 220 KV Line Raigarh to Saraipali(DCDS) 200.00 384 338 287 93.00 Mar-12 Work under progress.6.5 220 kV DCSS line Bemetara to Mungeli 38.34 124 110 81 - Apr-12 Work under progress.

6.6 220 kV 2nd Ckt of Khedmara-Rajnandgaon (Telkadih) DCSS

49.82 _ _ _ 15.00 Mar.-12 Work under progress.

6.7 LILO of 220KV Raigarh- Budipadar at 400 kV PGCIL S/S 400 kV PGCIL S/S Raigarh.

9.38 18.76 - - - Mar-12 Work to be awarded shortly

Remark Stub

setting Tower

erectedStringing

completed

Status of Ongoing Transmission Progress in Chhattisgarh (February-12)

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 01.03.2012 Anticipated

completion Target

Page 12: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-4(1/3)

(A) Transmission Schemes associated with State Generating StationsI. 400 KV Lines

1 400 KV D/C line from Bhusaval-II to A'bad. (Loc. No. 1 to 270) 191 283 283 283 191.00 Sep.11 Charged on 23.12.11

2 400 KV D/C line from New Bhusaval - Aurangabad (Loc. No. 271 to Waluj S/S) 179.2 251 251 251 179.200 Sep'11 Charged on 23.12.11

3 400 KV S/C line from 400 KV New Khaperkheda - 400 KV Koradi 4.05 13 12 12 3.5 March-12

Work stopped. ROW problem

4 400 KV D/C line from Koradi-TPS to Wardha S/S 239 329 278 246 67.18 Dec 11 Work in progress.

II. 220KV Lines

1 LILO on 220 KV Tarapur-Borivali line for Boisar II S/S 16 15 15 12 8.700 Dec 11 No work since last 2 years. Order is short closed

2 220 KV Koradi II to Butibori II D/C line on M/C tower at 400 KV Koradi II S/S 106 176 114 85 0.4 Mar'12 Work in progress.

3 220KV Parli TPS-Nanded M/C line( Waghala) 361.2 299 291 291 140 Dec.11 Work in progress.

( M/s. Bajaj )

4 220 kV D/C on D/C from 400 kV new Bhusaval - 220 kV Amalner S/S 190.8 331 331 331 190.8 Dec.11 Commissioned on 06.11.11

5 220 kV line D/C line on M/C tower from 400/220 kV new Bhusaval -II S/S - existing 400 kV Khadka 18.302 53 44 43 8.42 Oct'11 Work in progress.( M/s. ATSL )

6 220 kV Paras-Balapur MIDC M/C -M/C 22.44 30 21 15 0 Dec.11 Work in progress. ( M/s. Bajaj )

7 220KV M/C- M/C from 400 New K'Kheda to 220KV Existing K'Kheda 12 19 19 15 12 Mar/12 Work in progress.

( M/s.Shirke )

(B) EVACUATION (LINES & S/S) FOR IPPs

Mauda Transmission System1

400 KV D/C Jaigad - Karad line. 222 300 300 300 218.8 Sep. 11 Ckt I Charged on 02.12.11 & Ckt II Charged on 28.09.11

Status of Ongoing Transmission Progress in Maharashtra (December-11)

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 01.01.2012Anticipated completion

TargetTower erected

Stringing completed

Remark Stub setting completed

Page 13: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

I. 400KV Lines

1 400KV Chandrapur-II Wardha PGCIL Via Warora D/C 245.6 360 317 287 78.108 Mar.12 Work in progress. ( Quad conductor)( M/s. Cobra-KCL )

2 400KV D/C line from Koradi-II to Wardha S/S(PG) 239 336 289 277 35.5 Mar.12 Work in progress.( M/s. Cobra-KCL )

II. 220KV Lines

1 220KV D/c on M/C tower from 400KV PGCIL Talegaon to 220KV Urse 21.76 40 40 40 21.76 Sep'11

2 LILO on Apta-Kalwa & Kandalgaon-Kharghar for Navi Mumbai S/S 16 26 - - - Mar.12 Work awarded to M/S KPTL. ROW problem.

3 220kV D/C line from Pune(PG) to Talegaon 7.2 18 7 7 0.2 Mar/12

4 220kV D/C line from Chincholi(PG) to South Solapur 10.64 18 18 18 - Oct.11

5 220kV D/C line from Wardha(PG) to Ghatodi 322 503 52 - - MAR.12

6 LILO on 220kV Bhugaon-Pusad SC at Wardha(PG) 30 - - - - Dec.11

(D) LINES & S/S LINKING WITH PROJECTS- IPTC Routes NIL

(E) SYSTEM STRENGTHENING LINES (INTRA STATE)

I. 220KV Lines 1 220KV D/C Nagothane Wadkhal. 60 93 56 44 - Contract closed.2 LILO on 220 KV Padghe - Kalwa for Temghar S/S. 3 8 8 8 3 Jul. 11 Commissioned on 26.07.11

3 LILO on 220 KV Mulund - Borivali by U/G cable for Bhandup GIS S/S. 4 2 - - - Dep. 11 Commissioned on 30.11.11

4 220 KV D/C from Phursungi - 400 KV Jejuri S/S. 62 101 101 101 62 Mar.11 Line is charged on 16.06.11

(C.)- EVACUATION (LINES) LINKED WITH PGCIL Present Status as on 01.01.2012 Anticipated

completion Target

Remark Stub setting completed

Tower erected

Stringing completed

Annexure-4(2/3)

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Page 14: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-4 (3/3)

I. 220KV Lines 1 shifting of 220KV Telco-Bhosari interconnecting bay at 0.5 6 6 5 0.133 Sep.11 Cable laying completed

2 220KV D/C line on M/c tower LILO on 220KV Bhosari-Chinchwad D/C on M/C. for 400KV Chakan S/s. 18 31 16 2 Mar.11 Commissioned on 14.04.11

3 220 kV D/C line Jeur - Paranda 68.76 115 Sep.11 Work order is to be cancelled as it passes through WLS. Case in Supreme court.

220 kV D/C Beed- Patoda line 86.338 151 142 138 56 Mar.12 Work in progress. ( M/s. Bajaj )

4 220KV D/C-D/C Jalna - Chikli 150 267 258 251 61 Dec.11 Work in progress. ( M/s. Bajaj )

5220 KV Line from Boisar PGCIL to 220 KV Wada S/S 114 210 173 164 55.836 Dec 10 Work held up due to ROW problems. ROW

problems & 3 Nos. Court Cases. Forest proposal yet to be approved.

Sr. No. Name of Transmission lineLength in Ckt

Km

Total Location

Present Status as on 01.01.2012Anticipated completion

TargetRemark

Stub setting completed

Tower erected

Stringing completed

Page 15: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-5(1/3)

PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION BY PGCIL (As on 29.02.12)

Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)

765 kV & 400 kV Lines 1 Western Region Stregthening Scheme-II1.1 SET-A: For absorbing import in eastern&central part of WR1.1.1 765 kV 2nd S/C Seoni(PG)-Wardha(PG) line (initially to be operated at

400kV)261 704 704 704 261 Feb-12 29.02.12

1.1.2 400 kV D/C Wardha (PG)-Parli (PG)(Quad.) 674 897 897 897 674 Jun-11 Commissioned on 31.07.111.1.3 400 kV D/C Raipur(PG)-Wardha(PG) line 741 989 953 917 614 Jun-12 Work affected due to ROW problem in line. &

forest clearence awaited.1.1.4 400 kV D/C Parli(MSEB)-Parli(PG) line 10 15 15 15 10 Feb-11 01.07.20111.2 SET-B: For Regional strengthening in Southern Maharashtra

Implemented through IPTC route by Western Region Transmission (Mah) Pvt.Ltd. Progress indicated saperately

1.3 SET-C: For Regional strengthening in Gujarat Implemented through IPTC route by Western Region Transmission (Guj) Pvt.Ltd. Progress indicated saperately

1.4 SET-D: For Regional strengthening in Northern Madhaya Pradesh

1.4.1 400 kV D/C Korba(NTPC)-Birsighpur(MPGENCO) line 454 645 645 645 454 Mar-12 29.02.121.5 Trans. Sy. Associated with Gandhar-II (GBPP)2 Western Region Stregthening Scheme-V2.1 400 kV Vapi(PG)-Navi Mumbai D/C line 258 385 136 80 2 Mar-13 Severe ROW problem being faced in

Maharashtra & DNH on allmost all locations. Compltion uncertain.

2.2 LILO of Lonikhand(MSEB)-Kalwa(MSEB) 400 kV S/C line at Navi Mumbai

10 28 14 7 2 Mar-12 Severe ROW problem in Maharashtra on allmost all locations.

PRESENT STATUS

Page 16: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-5(2/3)Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

(Nos)

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)3 Western Region Stregthening Scheme-IX3.1 LILO of 400 kV D/C Bina-Nagda line at Sujalpur 44 61 61 61 44 Mar-11 29.05.114 Western Region Stregthening Scheme-X4.1 LILO of 765 kV S/C Sipat-Seoni line at WR Pooling station near Sipat 8 25 24 22 1 Mar-12

5 Western Region Stregthening Scheme-XI5.1 LILO of 765 kV S/C 2nd Sipat-Seoni line at WR Pooling station near

Sipat at Bilaspur (Pooling Stn.)8 25 23 6 Mar-12

6 Transmission System associated with Korba-III6.1 400 kV D/C Korba STPS-Raipur line 424 596 596 596 424 Jun. 11 Line completed & test charged on 21.06.11

7 Mauda Transmission System 7.1 400kV D/C Mauda STPS - Wardha line (Quad) 247 345 316 288 117 Mar. 12 Stringing commenced from Jun'118 Transmission System Associated with Mundra UMPP8.1 Part-A Transmission System of Mundra UMPP8.1.1 400 kV D/C Mundra-Limbdi line (Tripal snowbard) 628 863 848 783 480 Feb-12 29.02.128.1.2 400 kV D/C Mundra-Bachchau line (Tripal snowbard) 198 285 285 285 198 August' 11 Line completed & test charged on 29.09.118.1.3 400 kV D/C Bachchau- Ranchodpura line (Tripal snowbard) 566 755 755 755 566 Sep' 11 Line completed & test charged on 29.09.118.1.4 400 kV D/C Mundra- Jetpur line (Tripal snowbard) 668 919 714 528 165 Jun-128.2 Part-B Regional System Strengthening in WR for Mundra UMPP8.2.1 400 kV D/C Gandhar-Navsari line 212 288 287 285 197 Mar. 128.2.2 400 kV D/C Navsari- Boisor line 432 614 290 204 Oct-12 Awarded in Mar'11. Line is now proposed to be

terminated at Boiser S/stn in place of Mumbai new loc.

8.2.3 400 kV D/C Wardha- Aurangabad line 700 980 470 161 Oct-12 Tower erection commenced from June'118.2.4 LILO of both Ckt of Kawas-Navsari 220 kV D/c at Navsari 68 138 138 123 22 Mar. 12

PRESENT STATUS

Page 17: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

Annexure-5(3/3)Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

(Nos)

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)9 Transmission System Associated with Sasan UMPP9.1 Part-A Transmission System of Sasan UMPP9.1.1 765 kV S/C Sasan-Satna line-I 246 689 643 635 199 Dec. 129.1.2 765 kV S/C Sasan-Satna line-II 243 676 591 513 134 Dec. 129.1.3 765 kV S/C Satna-Bina line-I 274 738 738 738 274 Dec. 12 Charged in Jan-12 at 400 kV9.1.4 765 kV S/C Satna-Bina line-II 276 737 737 726 220 Dec. 129.1.5 400 kV D/C Bina-Bina (MPPTCL) line 10 25 Dec. 12 Engg. in progress.9.1.6 LILO of both Ckt Vindhyachal-Jablapur 400 kV D/c at Sasan 12 26 26 25 9 Mar-129.2 Part-B Regional System Strengthening in WR for Sasan UMPP9.2.1 765 kV S/C Bina-Indore line 311 828 828 818 296 Dec. 129.2.2 400 kV D/C Indore-Indore(MPPTCL) (quad) line 100 139 138 139 98 Dec. 1210 Inter-regional lines10.1 East-West Transmission corridor strengthening scheme10.1.1 400 kV D/C Rourkela - Raigarh 420 589 589 589 420 Jun-11 Line completed & test charged on 29.06.1110.2 Transmission System of Vindhyachal-IV and Rihand-III(1000MW

each) Gen. Proj10.2.1 400kV D/C Vindhyachal-IV - Vindhyachal Pooling Station line (Q) 62 86 67 58 39 Nov'1210.2.2 765kV S/C Vindhyachal Pooling Station - Satna line (Ckt-I) 253 681 161 41 Nov'12 Foundation work commenced from June'1110.2.3 765kV S/C Vindhyachal Pooling Station - Satna line (234km+12km D/C

Portion)Ckt-II234 628 134 46 Nov'12 Foundation work commenced from June'11

10.2.4 765kV S/C Satna-Gwalior line (Ckt.-I) 392 984 274 56 Nov'12 Foundation commenced from May'1110.2.5 765kV S/C Satna-Gwalior line (359Km + 60Km D/C Portion) Ckt.-II 331 897 225 3 Nov'12 Award placed in Dec10. Engg. In Progress.10.2.6 765kV S/C Sasan-Vindhyachal Pooling Station line 6 18 11 Nov'1210.2.7 400kV D/C Sasan-Vindhyachal Pooling Station line 10 15 16 3 Nov'12 Award placed in Mar'10. Engg. In Progress.

PRESENT STATUS

Page 18: AGENDA FOR THE 7 MEETING TO BE HELD ON 17 …wrpc.gov.in/meetings/7_TRM_Agenda.pdf · review ongoing transmission projects in Western Region were forwarded vide letter ... GETCO,

PROGRESS OF TRANSMISSION LINES UNDER CONSTRUCTION TROUGH IPTC ROUTE (31.01.2012)

Sr.No.

Name of transmission line Length in Ckt. Km

Total Locations

(Nos)

Anticipated Completion

REMARKS

Stub Setting completed

Tower erected

Stringing completed

Target

(Nos.) (Nos) (Ckm)WRSSS-II (Set-B)

2.2 SET-B: For Regional strengthening in southern Maharashtra implemented through IPTC route by Western Region Transmission (Mah) Pvt.Ltd.

2.2.1 400 kV D/C Parli(PG)-Pune 622 842 741 641 272 Sep-12 Forest NOC obtained. Final report with Director PTCC, Delhi.

2.2.2 400 kV D/C Pune(PG)-Aurangabad(MSEB) 472 641 519 383 - Nov-12 Pending approval by DET PTCC, Mumbai.

2.2.3 400 kV D/C Parli(PG)-Solapur 272 354 354 354 272 Aug-11 Charged on 08.10.2011

2.2.4 400 kV D/C Solapur(PG)-Kolhapur(MSEB) 438 572 529 455 186 May-12 For forest clearence all cases submitted & clearence received.For PTCC final report with Director PTCC. Power line Xing 4/5 NOC received. Pending 1 case approval under process.

2.2.5 LILO of Lonikhand(MSEB)-Kalwa(MSEB)400 kV D/C at Pune(PG) 2.5 9 9 7 1 Mar-12 Forest clearence not required. PTCC clearance received.Ckt-1 charged on 15.04.2011

WRSSS-II (Set-C)2.3 SET-C: For Regional strengthening in Gujarat implemented

through IPTC route by Western Region Transmission (Guj) Pvt.Ltd.

2.3.1 400 kV D/C Rajgarh(PG)-Karamsad(GEB) 468 652 634 612 264 Nov-12 Proposal submitted to DCFO(Social Forest) Vadodara, Anand, Panchmahal & Dahod. Inspection completed for both PF & NPF. Report compilation in progress with respective RFO & DCFO.

2.3.2 400 kV D/C Limbdi(GEB)-Vadavi(GEB) 206 270 270 270 206 Mar-11 Line cimmissioned on 29.04.20112.3.3 400 kV D/C Vadavi(GEB)-Kansari(GEB) 282 375 375 375 282 Aug-11 Line cimmissioned on 16.11.2011

PRESENT STATUS

Annexure-6