african development bank - afdb

44
AFRICAN DEVELOPMENT BANK TUNISIA NORTH-WEST ROAD CONNECTIVITY SUPPORT PROJECT APPRAISAL REPORT RDGN/PICU November 2017 Translated document Public Disclosure authorized Public Disclosure authorized

Upload: others

Post on 07-Jan-2022

15 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AFRICAN DEVELOPMENT BANK - AfDB

AFRICAN DEVELOPMENT BANK

TUNISIA

NORTH-WEST ROAD CONNECTIVITY SUPPORT PROJECT

APPRAISAL REPORT

RDGN/PICU

November 2017

Translated document

Pu

bli

c D

iscl

osu

re a

uth

ori

zed

P

ub

lic

Dis

clo

sure

au

tho

rize

d

Page 2: AFRICAN DEVELOPMENT BANK - AfDB

TABLE OF CONTENTS

Currency equivalents .................................................................................................................. i

Fiscal year ................................................................................................................................... i

Weights and measures................................................................................................................. i

Acronyms and abbreviations...................................................................................................... ii

I - STRATEGIC THRUSTS AND RATIONALE................................................................. 1

1.1 Key Development Issues.................................................................................................. 1

1.2 Project linkages with country strategy and objectives ..................................................... 1

1.3 Rationale for Bank intervention…………………………………………………… 2

1.4 Aid Coordination ............................................................................................................. 3

II -PROJECT DESCRIPTION ............................................................................................... 4

2.1 Project objectives and components .................................................................................. 4

2.2 Technical solution adopted and alternatives explored ..................................................... 5

2.3 Project type ...................................................................................................................... 5

2.4 Project cost and financing arrangements ......................................................................... 5

2.5 Project area and beneficiaries .......................................................................................... 7

2.6 Consideration of Bank Group experience and lessons learned in project design ............ 8

2.7 Key Performance Indicators ............................................................................................ 9

III - PROJECT FEAISIBILITY........................................................................................... 10

3.1 Economic and financial performance ............................................................................ 10

3.2 Environmental impacts, climate change and social issues............................................. 11

IV - IMPLEMENTATION.................................................................................................... 13

4.1 Implementation arrangements ........................................................................................ 13

4.2 Procurement Arrangements ........................................................................................... 13

4.3 Financial Management Arrangements ........................................................................... 15

4.4 Monitoring .................................................................................................................... 16

4.5 Governance ................................................................................................................... 16

4.6 Sustainability ................................................................................................................. 17

4.7 Risk mnagement............................................................................................................. 17

4.8 Knowledge building ....................................................................................................... 18

V - IMPLEMENTATION ..................................................................................................... 18

5.1.Legal instrument ............................................................................................................ 18

5.2.Conditions associated with Bank intervention ............................................................... 18

5.3.Compliance with Bank policies ..................................................................................... 21

VI – RECOMMENDATION ................................................................................................ 21

Appendix I: Description of the planned developments

Appendix II: Country Financing Parameters

Appendix III: Project cost and financing arrangements

Appendix IV. Supporting documents and scope of the requested authorization from the Board

for the use of EIB's procurement system

Appendix V: Regional development indicator

Appendix VI: Tunisia: Comparative socio-economic indicators

Appendix VII: AfDB Portfolio Table in Tunisia

Appendix VIII: Project area map

Page 3: AFRICAN DEVELOPMENT BANK - AfDB

LIST OF TABLES

Table 1.1: Donor contribution to the financing of the sub-sector road programme

Table 2.1: - Project components

Table 2.2: Alternative solutions explored and reasons for rejection

Table 2.3: Estimated cost by component, exclusive of taxes for AfDB financed

Table 2.4: Source of project financing

Table 2.5: Summary of the estimated cost per component of the entire project

Table 2.6: Summary of Cost per Categories of expense for ADB Financing

Table 2.7: Schedule of expenditure by source of funding (Million EUR) for the entire project

Table 3.1: Outcomes of the economic analysis

Table 3.2: Country Financing Parameters

Page 4: AFRICAN DEVELOPMENT BANK - AfDB

i

Currency Equivalents (June 2017)

Unit of account 1 = 3.38997 TND

Unit of account 1 = 1.23369 EUR

Unit of account 1 = 1.38432 USD

EUR 1 = 1.1211 USD

EUR = 2.747 TND

Fiscal Year

1 January – 31 December

Weights and Measures

1 metre (m) = 3.28 feet

1 millimetre (mm) = 0.03937 inch

1 kilometre (km) = 0.62 mile

Page 5: AFRICAN DEVELOPMENT BANK - AfDB

ii

Acronyms and Abbreviations

ADEB Budget Decision Support

AfDB African Development Bank

AFESD Arab Fund for Economic and Social Development

AGTF Africa Growing Together Fund

ANPE National Agency for Environmental Protection

BTP Public Works and Civil Engineering

CBDs Competitive Bidding Documents

CSP Country Strategy Paper

DGPC Directorate-General for Highways and Civil Engineering

DREHAT Regional Directorate for Infrastructure, Housing and Regional Development

EIB European Investment Bank

ERR Economic Rate of Return

ESIA Environmental and Social Impact Assessment

ESMP Environmental and Social Management Plan

EUR Euros

GDP Gross Domestic Product

GENIS Road Maintenance Management by Service Levels

GHG Greenhouse Gases

HDV Heavy Duty Vehicle

MDICI Ministry of Development, Investment and International Cooperation

MEHAT Ministry of Infrastructure, Housing and Regional Planning

NPV Net Present Value

PACR North-East Road Connectivity Support Project

PADRCE Regional Development and Job Creation Support Programme

PAP Project-Affected Person

PDAI Integrated Agricultural Development Project

PIA Project Impact Area

PMIR Road Infrastructure Modernization Project

PMU Project Management Unit

PP Procurement Plan

RPF Resettlement Policy Framework

SDAG Sub-Directorate for General Affairs

TAF/MIC Technical Assistance Fund for Middle Income Countries

TND Tunisian Dinars

ToR Terms of Reference

UA Unit of Account

USD United States Dollar

VOC Vehicle Operating Cost

WB World Bank

Page 6: AFRICAN DEVELOPMENT BANK - AfDB

iii

Project Information Sheet

Client information

BORROWER: Tunisia

EXECUTING AGENCY: Ministry of Infrastructure, Housing and Regional

Planning, acting through the Directorate-General for

Highways and Civil Engineering (DGPC)

Financing Plan

Source Amount Instrument

AfDB

EUR 122.000 million

Loan

EIB EUR 123 million Loan

Government EUR 32.29 million Self-financing

TOTAL COST EUR 277.29 million

Key AfDB Financial Information

Loan Currency Euro (EUR) [or any other acceptable currency]

Interest Type Fully flexible loan

Maturity To be determined (up to 25 years maximum)

Grace Period To be determined (up to 8 years maximum)

Weighted Average Maturity **: To be determined (based on the amortization

profile)

Refunds Semi-annual installments after the grace period

Interest Rate Base rate + Margin on financing cost + Loan

margin + Maturity premium. This interest rate must

be greater than or equal to zero.

Base Rate Floating (EURIBOR 6 Months revised on 1st

February and 1st August or any other acceptable

rate). A free option is offered to set the base rate

Financing Cost Margin Revised Bank Financing Cost Margin on 1st

January and 1st July and applied on 1st February and

1st August with base rate.

Loan margin 80 basis points (0.8%)

Maturity Primium To be determined:

0%, if the weighted average maturity <= 12.75

years

- 0.10%, if 12.75 <weighted average maturity <=

15

- 0.20%, if the weighted average maturity> 15

years

Front End Fee 0.25% of the loan amount.

Page 7: AFRICAN DEVELOPMENT BANK - AfDB

iv

Commitment Fee 0.25% per annum of the undisbursed amount. It

begins to run 60 days after the date of signature of

the loan agreement and is payable on the interest

payment dates.

Base rate conversion option * In addition to the free option to set the base rate, the

option is offered to the borrower to return to the

floating rate or reset all or part of the loan amount

disbursed. Transaction fees are payable.

Rate ceiling or tunnel option *: The option is offered to the borrower to put a

ceiling or tunnel on the base rate for all or part of

the amount disbursed from his loan. Transaction

fees are payable

Conversion option of loan currency *:

The option is offered to the borrower to change the

currency of all or part of his loan, disbursed or not,

into another loan currency of the Bank. Transaction

fees are payable

*Conversion options and related transaction fees are governed by the Bank Conversion

Guidelines available on the website

**A weighted average maturity calculator is available on the website

Timeframe – Main Milestones (expected)

Activity Date

Concept Note Approval April 2017

Loan Agreement Negotiations November 2017

Board Presentation November 2017

Effectiveness January 2018

Closing Date 31 December 2023

Completion Report December 2022

Page 8: AFRICAN DEVELOPMENT BANK - AfDB

v

EXECUTIVE SUMMARY

1. Project Overview

1.1. The North-East Road Connectivity Support Project (PACR) is part of Tunisia's road

sub-sector strategy and supports two of the five pillars of the country's Development Strategy

Plan for the period 2016-2020. The PACR consists of the construction of a 9 km-long two-

way, two-lane (2x2) suburban highway on a new alignment bypassing the city of Bizerte to the

southwest. The new bypass will link Highway 4 and National Road 8 to Local Road 438 at the

western access to the city. The project also includes a 2.1 km-long viaduct bridge over Lake

Bizerte and access roads at both ends of the structure totalling 7.4 km. It also comprises four

interchanges, a new 1.5 km-long service road, an operations centre, a maintenance centre and

ancillary developments, in particular: (i) the construction, on the south bank, of a 2.4 km-long

asphalted road linking South Zarzouna and the Technopole in North Zarzouna and Menzel

Abderahman; (ii) the construction of a 25 000 m² landscaped park under the bridge in Zarzouna

on the left bank of the lake, which will serve as a green recreation area; and (iii) the construction

of 14 km of secondary roads, 8 km of rainwater drainage system and provision of public

lighting with the installation of 300 lighting points in the neighbourhoods crossed.

1.2. The total project cost, net of taxes and customs duties, is estimated at TND 761.72

million, equivalent to EUR 277.29 million. The project will be implemented over a period of 5

years. The project will be financed by the EIB, AfDB, and the Government of Tunisia. On 15

November 2016, the EIB approved financing for the project worth EUR 123 million. The Bank

will provide supplementary financing amounting to EUR 122.00 million under the AfDB

window. The Government will supplement the financing plan with the sum of EUR 32.29

million.

2. Needs Assessment

2.1. The PACR is a flagship project under the Development Strategy Plan (DSP). Its

implementation will: (i) improve the competitiveness of the Tunisian economy by addressing

the growing demand in terms of goods and passenger traffic, which currently crosses the

Bizerte urban area, and help to ease congestion on the access road to the three industrial areas

and the port, as well as ensure better sharing of network loads; and (ii) foster mobility and trade

between the Centre, North Eastern regions of the country.

2.2. The PACR is consistent with the 2017-2021 CSP for Tunisia and is in line with the

two pillars adopted, namely: (i) industrialization and value chains development; and (ii)

improvement of the quality of life for the people of the priority regions.

2.3. In light of the expected benefits, the PACR is also in line with the Bank's Ten-Year Strategy

for 2013-2022, especially with some of its operational pillars namely; infrastructure

development, transition to green growth by reducing carbon emissions, and interconnection

between centre and north-west regions of the country and between Tunisia and the rest of the

world, and this implies developing the Bizerte port which will support Tunisia’s new economic

orientation towards development with the rest of the continent.

2.4 Lastly, it is in line with three of the Bank's high fives, namely: (i) "Industrialize

Africa" by enabling the development of the three industrial zones where more than 60% of the

facilities are export-oriented; (ii) "Improve the quality of life for African People" by reducing

congestion costs, rehabilitating certain neighbourhoods and creating a recreational area; and

lastly (iii) "Feed Africa" by upgrading agricultural land in the project’s area of influence and

processing production surplus. It is also in line with the thematic strategy for youth employment

in Africa 2016-2025.

Page 9: AFRICAN DEVELOPMENT BANK - AfDB

vi

3. Bank’s Value Added

The PACR would enable the Bank to consolidate its position as a partner of choice in Tunisia’s

road sector. The Bank assists the Government through physical interventions in all three modes

of transport: road, air and rail, as well as through support in the area of policy and institutional

reform. However, this assistance is more pronounced in the road sector where the Bank,

through its five previous interventions in the form of loans, has helped to modernize more than

70% of the Tunisia’s network of asphalted roads. Also, through the three grants already

provided, the Bank is helping the Government to develop (i) a long-term vision for the sector

through the implementation of a transport plan; (ii) roads sector management reforms; and (iii)

new standards for road construction to improve the resilience of road infrastructure to climate

change impact.

4. Knowledge Management

4.1. The project is the first of its kind and the most complex in Tunisia both in terms of its

engineering and work site organization. Indeed, the nature of its foundations (piles 60 m deep

and 2.5 m in diameter), the great length of its spans (270 m), and also the safety standards

against possible ship collisions make it the first project of this magnitude in Tunisia and one of

the longest viaducts in Africa. Its implementation will result in knowledge building in various

fields. The measures taken within the context of the project, both in terms of the composition

of the Project Management Unit (PMU) and end-of-course engineering projects and vocational

training for young people will contribute to knowledge. The line ministry also plans to ensure

the large-scale dissemination of best practices learned during the implementation of this project

relating to major infrastructure construction projects. The dissemination will be carried out

through a website dedicated for that purpose, briefing notes and conferences with professional

and training organizations.

4.2. The effects of the impacts, which will be quantified under the monitoring/evaluation

sub-component, will ensure an assessment of the level of achievement of the project objectives,

and will be integrated into the broader framework of all previous Bank interventions. In order

to measure the impact on the development of Bank operations, particularly in its five priority

areas of action.

Page 10: AFRICAN DEVELOPMENT BANK - AfDB

vii

RESULTS-BASED LOGICAL FRAMEWORK Country and Project Name: Tunisia, North-East Road Connectivity Support Project Project Goal: Improve the movement of goods and people in the Bizerte and Beja Governorates

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION RISKS/MITIGATION

MEASURES Indicator

(including CSIs)) Baseline (2017) Target (2021)

IMP

AC

T

Improve the competitiveness of

the Tunisian Economy

1. Global Competitiveness Index (GCI)

(ranking/score 1 to 7)

2. Logistics Performance Index (LPI)

(ranking/score 1 to 5)

1. Global Competitiveness

Index (GCI): 3.9

2. Logistics Performance Index

(LPI): 2.5

1. GCI: 4.2

2. LPI: 3.0

(i). World Bank/AfDB

(ii). National statistics

OU

TC

OM

ES

1. Reduce congestion at peak

periods

2. Reduce accidents

3. Improve the living

conditions of the population

of the Bizerte and Beja

Governorates

1. Time saving

2. Number of fatal accidents on the

existing urban network per year

3.1. Number of direct jobs created per

year during the construction

3.2. Number of interns trained

3.3. Regional Development Index (RDI)

(0 to 1)

3.4. Reduction of transport-related CO2

emissions

1. 8.5 million h/yr

2. 8

3.1. 0

3.2. 0

3.3. 0

3.4. 0

1. 6.5 million h/yr.

2. 4

3.1. 700 men/month, at least

10% of performed by

women

3.2. 100 including 20 girls

3.3. 0.70 and 0.65

3.4. 33 000 t/yr.

(i). Monitoring and

evaluation

(ii). Statistics from ONSR

(iii). CO2 recording

(iv). CRP

OU

TP

UT

S

Output 1: New infrastructure

constructed

1.1. Length of roads constructed

1.2. Length of viaduct constructed

1.3. Ancillary developments

carried out

1.1. 0 km

1.2. 0 km

1.3. 0

1.1. 7.34 km

1.2. 2.11 km

1.3.1. 14 km of secondary

roads

(i) 1.3.2 8 km of rainwater

drainage system built

(ii) 300 lighting points

installed

(iii) 1.3.3 Development of a

recreational green space

of an area of 25 000 m²

(iv) (i) Works acceptance

report

(v) (ii) Reports by the

Project Management

Unit

(vi) (iii) CRP of the project

(vii) (i) Works acceptance

report

(viii)(ii) Supervision and

audit reports

(ix) (iii) ESMP

implementation reports

Risks

(i) Implementation delays: The

use of EIB procurement rules, the

project's lead financier, poses the

risk of delays in the mobilization

of companies, and lack of

proactivity in the processing of

requests from the Executing

Agency.

(ii) Cost overruns due to

physical contingencies or slow

pace of project implementation.

Mitigation measures

(i) Implementation delays:

This risk is mitigated by (i) a

Page 11: AFRICAN DEVELOPMENT BANK - AfDB

viii

Output 2: Mitigation of the

environmental and social impacts

act of the project

2.1 ESMP implementation monitoring

report;

2.2 Strengthening of the canal bank

protection

2.4 Tree planting.

2.5 Compensation and resettlement of

project-affected persons

2.1 0

2.2 0

2.3

2.4 0

2.1 48 reports ;

2.2 2 500 ml

2.3 9 750 trees

2.4 1 309 PAPs

compensated and resettled

protocol agreement between the

AfDB and the EIB identifying

the roles and responsibilities of

each donor; and (ii) regular

consultations during

supervisions or on an ad hoc

basis.

(ii) Cost Overruns: This risk is

mitigated by the detailed studies

conducted by experienced

consultants. Cost estimates also

provided for physical and

financial contingencies which

would cover possible cost

overruns.

COMPONENTS RESOURCES (EUR MILLION)

i. Works

ii. Project management and coordination

iii. Physical contingencies

Financial contingencies

I. Works and services 249.81

II. Physical contingencies 17.49

III. Financial contingencies 9.99

TOTAL RESOURCES 277.29

Page 12: AFRICAN DEVELOPMENT BANK - AfDB

ix

IMPLEMENTATION PLANNING

Years

Activities / Months J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

1 - PRELIMINARY ACTIVITIES

1.1 - Project Appraisal by Bank staff

1.2 - Board Approval

1.3 - Entry into force

2 - ROAD WORK LOT N°1

2.1 - Procurment process and notification

2.2 - Work implementation of Lot 1: South road

3 - ROAD WORK ( LOT N°2): Viaduct

2.1 -Procurment process and notification

2.2 - Work implementation of Lot 2

3 - ROAD WORK LOT N°3: North Road

3.1 - Procurment process and notification

3.2 - Work implementation of Lot 3

4 - TECHNICAL ASSISTANCE TO THE PIU

4.1 - Procurment process and notification

4.2 - Contract implementation

5 - SUPERVISION OF LOT N°1, LOT N°2

AND LOT N°3

5.1 - Procurment process and notification

5.2 - Consulting services implementation

6 - TECHNICAL CONTROL OF LOTS N°1,

LOT N°2 AND LOT N°3

6.1 - Procurment process and notification

6.2 - Consulting services implementation

7 - ANCILLARY WORKS

7.1 - Procurment process and notification

7.2 - Ancillary works implementation

8 - AUDIT

8.1 - Procurment process and notification

8.2 -Financial audit

9- PROJECT MANAGEMENT

20222017 2018 2019 2020 2021

Page 13: AFRICAN DEVELOPMENT BANK - AfDB

1

REPORT AND RECOMMENDATIONS OF THE BANK GROUP MANAGEMENT TO

THE BOARD OF DIRECTORS ON THE PROPOSED AfDB LOAN FOR THE

FINANCING OF THE NORTH-EAST ROAD CONNECTIVITY SUPPORT PROJECT IN

TUNISIA.

Management hereby submits this report and the recommendations concerning the proposed grant

of an AfDB loan of EUR 122.000 million to the Republic of Tunisia for the financing of the North-

East Road Connectivity Support Project.

I - STRATEGIC THRUST AND RATIONALE

1.1 Key Development Issues

1.1.1 The Bizerte built-up area is experiencing high population growth that has not always been

well planned and regulated. The expansion of its sub-urban areas (Zarzouna and the cities of

Menzel Jemil and Menzel Abderrahmane), over the past decades, has increased its population to

about 180,000 inhabitants from 120,000 in 1990. The analysis of Bizerte highlights the problem of

congestion at the city centre and that of commuting between the two banks of the Bizerte canal

and, by extension, between the country’s Centre and North West regions. This situation is

exacerbated when the existing mobile bridge is opened to allow ships to access the commercial

port at the city centre. This existing mobile bridge is the only connection between the two banks of

the canal. Traffic across the canal is on the steady increase and will reach around 77,000

vehicles/day by 2030. Much of this flow, about 65%, is transit traffic on highway A4 from Tunis

via the city of Bizerte to the North-west of the country.

1.1.2 Constructing a new bridge outside the city and linking it with highway A4 will help divert

traffic headed for a destination other than the Bizerte city centre, thus easing the traffic transiting

through the existing mobile bridge, which will drop to 26,000 vehicles/day by 2030. The project

will also improve the connectivity between some sub-urban areas of the city of Bizerte (Menzel

Jemil and Menzel Abderrahmen on the south side) and Greater Tunis.

1.2 Project Linkages with Country Strategy and Objectivespays

1.2.1. After achieving a successful democratic transition, Tunisia is striving to implement

economic and institutional reforms that would allow a return to strong and inclusive economic

growth in the country. Thus, in 2015, on a participatory basis, the Government prepared the

Development Strategy Plan (DSP) for the period 2016-2020. This plan, which received the support

of investors when it was presented to them in November 2016, aims to bring about structural

transformation of the Tunisian economy towards sectors with higher value added. It is based on

two pillars, namely: (i) Shifting to an economic hub, focused on increasing productivity for

competitiveness and positioning Tunisian businesses in global value chains; and (ii) Tackling

regional disparities and achieving the ambitions of internal regions, by building economic

infrastructure and supporting entrepreneurship in lagging regions.

1.2.2. By the end of the DSP implementation period, these two pillars will be concretized, in

particular:

Page 14: AFRICAN DEVELOPMENT BANK - AfDB

2

i) for the first, by developing infrastructure and logistics through (a) the reduction in

the cost of logistics from 20% of GDP in 2015 to 15% in 2020; and (b) through the

promotion of employment and employability, especially among graduates of higher

education and in regions of the hinterland; and

ii) for the second, by ensuring a 30% reduction in the existing gap between the regions,

reflected in the Regional Development Index (RDI) 1 .

1.2.3. Based on its benefits as outlined in paragraph 1.2.1 below, this North-East Road

Connectivity Support Project (PACR) is in line with these two pillars. It is a flagship project for

both the DSP and the investment plan of the Ministry of Equipment, Housing and Regional

Planning (MEHAT), which underpins the DSP implementation.

1.3 Rationale for Bank Intervention

1.3.1 The PACR is in line with the 2017-2021 CSP for Tunisia and it aligns with the two pillars

adopted, which, as already mentioned, are: (i) industrialization and the development of local

agricultural value chains; and (ii) improvement of the quality of life of populations in priority

regions. Indeed, the project's area of influence has, among others, strong agricultural potential, in

particular, for industrial crops, market gardening, arboriculture, cattle breeding and milk whose

evacuation for their processing is facing challenges due to the lack of good road infrastructure.

Similarly, the development of these crops and future industrial sites will provide sources of labor

income from Bizerte and Beja, selected as priorities with regional development indices of 0.49 and

0.39 respectively. Lastly, the underprivileged population of adjacent neighborhoods will benefit

from the related developments planned in the project.

1.3.2 In light of expected benefits, the PACR is in line with the Bank's ten-year strategy (2013-

2022), including with some of its operational pillars, namely, infrastructure development, transition

to green growth, and the integration of the centre and north-western regions of the country, and

Tunisia with the rest of the world, with the development of the port of Bizerte which will support

the new direction of the Tunisian economy oriented towards development with the rest of the

continent. Finally, it is in line with three of the Bank's five main priorities: (i) "Industrialize Africa"

by allowing the development of the three industrial zones where more than 60% of the units are

totally export-oriented, (ii) "Improve the quality of life for African people" by reducing congestion

costs, rehabilitating certain neighborhoods, and developing a recreational area, and finally "Feed

Africa") by enhancing the potential of the local agricultural land in the project area, and the

transformation of surplus production. It is also in line with the thematic strategy for youth

employment in Africa 2016-2025 by creating jobs from construction, but especially by establishing

future industrial units and services related to the Bizerte port development.

1.3.3 The PACR consolidates the Bank's position as a partner of choice in the road sector in

Tunisia. The Bank assists the Government through physical interventions in all three modes of

transport: road, air and rail, as well as through support in the area of policy and institutional

reform. However, this assistance is more pronounced in the road sector where the Bank, through

its five previous interventions in the form of loans, has helped to modernize more than 70% of

1 The Regional Development Index is a synthetic indicator of 17 variables referring to four areas, namely "wealth and employment",

"knowledge", "health and population" and "justice and equity".

Page 15: AFRICAN DEVELOPMENT BANK - AfDB

3

Tunisia’s network of asphalted roads. Also, through the three grants already provided, the Bank is

helping the Government to develop (i) a long-term vision for the sector by implementing a transport

plan; (ii) roads sector management reforms; and (iii) new standards for road construction to

improve the resilience of road infrastructure to climate change impact.

1.4 Aid Coordination

1.4.1 There is no formal framework for coordinating the operations of technical and financial

partners (TFPs) in the transport sector, in general, and in the roads sub-sector, in particular.

However, through the on-going contacts of the North Africa Regional Development and Business

Delivery Office with the authorities in charge of the sector, the Bank is kept informed of the

operations of other donors. Also, the Bank is continuing dialogue with PTFs represented or on

mission in Tunis. The dialogue covers both reform assistance and the search for supplementary

financing and reduction of transaction costs. This project, financed jointly with the European

Investment Bank (EIB), is an example of such cooperation. The Bank is also funding the national

study of the transport plan, which will serve as a framework for dialogue and the reference for

future interventions by partners in Tunisia.

1.4.2 Pending the recommendations of the plan, the TFPs were involved in the development of

the road sub-sector programme (2016-2020), of which this project is an integral part. This

programme is estimated at TND 12 billion, including an expected donor contribution of TND 9.2

billion. So far, the funding that has been mobilized or is in the process of being mobilized, pending

the project approval, amounts to TND 3.12 billion, or 34% of the projected amount.

Table 1.1

Donor contribution to the financing of the road sub-sector programme (TND million)

Status Donor Amount (%)

AFESD 1,322 14%

Acquired/ in the course of

being acquired AfDB 417 5%

EIB 1,205 13%

WB 180 2%

Sub-total 3,124 34%

To be sought 6,107 66%

Total 9,231 100%

Page 16: AFRICAN DEVELOPMENT BANK - AfDB

4

II- PROJECT DESCRIPTION

2.1 Project objectives and components

2.1.1 The project objective is two-fold: (i) improving the competitiveness of the Tunisian

economy by addressing the growing demand in terms of transporting goods and people across the

urban area of Bizerte, thus helping to ease congestion on access roads to the three industrial areas

and the port, and to equalize network loads; and (ii) fostering mobility and trade between the

Northern and Eastern regions of the country.

2.1.2 Indeed and in line with the Bizerte Urban Development Master Plan, its implementation

will help channel traffic away from the Bizerte city centre and will thus ease traffic congestion on

the existing mobile bridge. The project will therefore help to promote intra- and inter-regional trade

as well as reduce regional social disparities. Lastly, it will reduce accidents, CO2 emissions,

improve the quality of life of the populations and facilitate access to social and economic centres.

To achieve these objectives, the project operations have been grouped into three (3) components

summarized in the table below.

Table 2.1

Project components (EUR million) No. Name of component Description

1

ROAD WORKS

(263.77)

1.1. Development of a new South sub-urban two-way, two-lane (2x2)

expressway from PK 0+000 to PK 4+639, connecting road A4/RNr8 to the

Viaduct;

1.2. Construction of a 2,070 km viaduct from PK 4+639 to PK 6+749 ;

1.3. Development of a new North suburban two-way, two-lane connecting road

from PK 6+749 to PK 9+446 linking the Viaduct to RL 348;

1.4. Release of the right-of-way and displacement of networks;

1.5. Management as well as control and supervision of roadworks and the

structures.

2

ANCILLARY

DEVELOPMENTS

(5.66)

2.1. Construction on the South bank of a 2.4 km-long paved road linking the

city of South Zarzouna and the Technopole to North Zarzouna and Manzel

Abderahman;

2.2. Development of a 25,000 m² landscaped park under the viaduct;

2.3. Rehabilitation of cities crossed.

2.4. Management as well as the control and supervision of ancillary works.

3

PROJECT

MANAGEMENT

(7.86)

3.1. Technical assistance and project management;

3.2. Project technical audit;

3.3. Project accounting and financial audit;

3.4. Operation of the management entity;

3.5. Project-centred communication.

The description of project developments is provided in Appendix I.

Page 17: AFRICAN DEVELOPMENT BANK - AfDB

5

2.2 Technical Solution Adopted and Alternatives Explored

2.2.1 From the technical standpoint, the project was designed to: (i) solve the congestion problem

in Bizerte city centre, generated mainly by transit traffic, and that of mobility on the canal crossing,

stemming from the fact that the two shores are connected by a single road; and (ii) help to lift the

constraints imposed by these problems on the socio-economic development of the Bizerte and Beja

regions.

2.2.2 In this context, technical and economic feasibility studies compared seven (7) crossing

corridors, each comprising a variant that crosses the canal by means of both a viaduct and a tunnel

and meet the following criteria: (i) a two-way, two-lane (2x2) urban expressway that can

accommodate heavy duty vehicles; and (ii) compliance with the clearance allowance with a view

to maintaining navigation on the canal. These variants were the subject of a multi-criteria analysis,

integrating socioeconomic, environmental and economic returns. From this analysis, a variant was

selected consisting of a viaduct crossing of approximately 2,070 m-long, having three spans of 270

metres each. It will have a composite meshwork deck and a 25 metre-wide double composite

structure, designed to accommodate a 2x2 expressway with sidewalks.

2.2.3 The alternative solutions explored and the reasons for rejection are indicated in the

following table:

Table 2.2: Alternative solutions explored and reasons for rejection

Alternative

solutions Brief description Reasons for rejection

Increasing the

capacity of the

existing bridge

Broadening the

bridge into a two-

way, two-lane

crossing

This alternative (i) involves complex structural

interventions; (ii) entails a risk for the structure in the

event of a vessel collision; and (iii) does not resolve the

problem of urban traffic congestion.

Viaduct Cable-stayed

bridge

This type of structure was not selected because of the

proximity of the aerodrome which imposes height

restrictions.

Viaduct Arc bowstring

bridge

Cost 18% higher than the adopted solution.

2.3 Project Type `

2.3.1 The project is a standalone investment operation, co-financed with the EIB and the AfDB.

For the Bank, the proposed financing instrument is an ADB loan.

2.4 Project Cost and Financing Arrangements

2.4.1 The estimated cost of the project is TND 761.72 million, or EUR 277.29 million (at the

exchange rate of EUR 1 = TND 2.747 in June 2017). This total cost was calculated by discounting

the cost of the technical study. Physical contingencies were estimated at an average of 7% of the

base cost. The provision for price escalation was estimated at an average of 4% and according to

Page 18: AFRICAN DEVELOPMENT BANK - AfDB

6

the works implementation schedule. The summary of the total estimated project cost is given in the

table below. Table 2.3

Estimated Costs by Tax-free Component (AfDB Financing)

Composantes

Million TND Million EUR*

Currency ML Total Currency ML Total

A- Works

A1 LOT1: Development of the South Link Road 27,72 18,46 46,18 10,09 6,72 16,81

A2 LOT2: Viaduc construction 124,16 60,68 184,85 45,20 22,09 67,29

A3 LOT3: Development of the North Link Road 24,56 16,37 40,93 8,94 5,96 14,90

A4 : Related works.

A4.1: 2.4 km paved road 1,20 1,80 3,00 0,44 0,66 1,09

A4.2: Rehabilitation of a landscaped park 1,60 2,40 4,00 0,58 0,87 1,46

A4.3: Neighbourhood rehabilitation 1,10 1,90 3,00 0,40 0,69 1,09

S/Overall Works 180,34 101,61 281,96 65,65 36,99 102,64

B- Services

B2: Project management mission for the Lot 1

(including the related A4.1 works) 3,46 1,48 4,94 1,26 0,54 1,80

B4: Project Management Mission for Lot 3 3,17 1,36 4,53 1,16 0,50 1,65

B5: Technical Inspection Mission for Lot 1 (including

A4.1 related works) 0,42 0,18 0,60 0,15 0,07 0,22

B6: Technical Inspection Mission for Lot 2 (including

A4.2 related works) 6,15 2,64 8,79 2,24 0,96 3,20

B7: Technical inspection mission for Lot 3 0,40 0,17 0,58 0,15 0,06 0,21

B8: Project management and technical control mission

for A4.3 related works 0,52 0,52 0,19 0,19

S/Overall Service 13,61 6,36 19,97 4,96 2,31 7,27

Basic cost (works & services) 193,96 107,97 301,93 70,61 39,30 109,91

Physical contingencies (7 %) 13,58 7,56 21,13 4,94 2,75 7,69

Financial risks (4%) 7,76 4,32 12,08 2,82 1,57 4,40

Overall Total 215,29 119,85 335,14 78,37 43,63 122,00

Percentage 64% 36% 100% 64% 36% 100%

2.4.2 The project will be financed by the EIB, AfDB, and the Tunisian Government according to

the following table indicating the financing sources. On 15 November 2016, the EIB approved

financing for the project worth EUR 123 million. The Bank will provide supplementary financing

amounting to EUR 122.00 million, being a loan under the AfDB window. The Government will

supplement the financing plan to the tune of EUR 32.29 million.

Table 2.4: Source of financing, exclusive of taxes (EUR million)

Sources of financing L.C. F.E. Total (%)

AfDB 43,63 78,37 122 44,00%

EIB 29,81 93,19 123 44,36%

Government 32,29 32,29 11,64%

Total project cost 105,73 171,56 277,29 100%

Page 19: AFRICAN DEVELOPMENT BANK - AfDB

7

2.4.3 The EIB contribution will fully cover the out-of-tax costs of the PMU technical assistance,

and will contribute to the co-financing with the ADB for the construction of the viaduct and the

supervision mission of the viaduct. The government will finance the releasing of the right-of-way,

the relocation of the networks, the operation of the PMU, and will co-finance the rehabilitation of

the districts with the ADB. The Bank's contribution will fully fund the other works and services in

accordance with the table 2.3.

2.5 Project Area and Beneficiaries

2.5.1 The broad project impact area comprises the Bizerte and Beja Governorates. With an area

of 3 740 km², the Beja Governorate has 303,032 inhabitants, a population growth rate of 0.05%

and an urbanization rate of 44.3%. Its active population stands at 108 228 people. The Bizerte

Governorate, for its part, has a surface area of 3,750 km², a population of 568,219 inhabitants, a

population growth rate of 0.81% and an urbanization rate of 65.3%. The active population is 198

112 people.

2.5.2 The level of development of these two Governorates may be captured by the regional

development index (RDI), defined in Annex 5. On this index, the Beja and Bizerte Governorates

scored 0.39 and 0.49, respectively, on a scale of 1. These below-average scores reflect the

disparities in their disfavour. The knowledge index is more than 3 times higher in Tunis than in

Beja than and almost twice as high as in Bizerte. The scores are the same for the wealth and

employment index, and 2.42 times higher for health and population.

2.5.3 The project's direct impact area is the Bizerte built-up area. In recent decades, the city has

witnessed an unplanned and regulated urban development and expansion towards the outskirts,

notably with the development of the locality of Zarzouna, the cities of Menzel Jemil and Menzel

Abderrahmane, on the other side of the city canal, and Belvedere, Pêcherie and Kharrouba, on the

northern and north-western sides. This area has multiple and diversified potential, and is known

mainly for its strategic position in the middle of the Mediterranean, its important commercial port,

its agricultural, livestock and fishery activities, as well as its industrial traditions and its tertiary

sector. The economic activity of the region is mainly focused on agriculture, industry and fisheries.

In the region, there are 368 industrial enterprises - of which 248 are totally export-oriented –

employing over 50,000 people. These enterprises operate mainly in the textile, leather and

footwear, agri-food, mechanics and electronics sectors.

Project Beneficiaries

2.5.4 The project will improve the movement of people and goods in the Bizerte and Beja built-

up areas, as well as traffic towards Jendouba. Indeed, at the local level, the project will meet the

needs of road users crossing the urban area of Bizerte. The interchanges to be created will link the

communes and areas on the outskirts of the city of Bizerte, including Menzel Jemil and Menzel

Abderrahmane on the southern side.

2.5.5 Bizerte is the second port of Tunisia after Rades. Eventually, the project will help remove

the constraint imposed by the fact that the existing mobile bridge is opened three times a day to

allow ships to access the commercial port at the city centre. The removal of this constraint will

enable Bizerte to take the place of Rades as the leading port in Tunisia. Indeed, unlike the Rades

Port, Bizerte has 4 hectares of quayside land, making it possible to double the available area of

commercial docks. This development will not only reduce logistics costs for the region and its

export enterprises, but will also encourage the establishment of other export-oriented industries.

Page 20: AFRICAN DEVELOPMENT BANK - AfDB

8

2.5.6 As part of the ancillary developments, the rehabilitation works in the neighbourhoods will

facilitate accessibility for the 9 000 residents, since the works will entail the construction of 14 km

of secondary roads, 8 km of rainwater drainage system and the improvement of lighting with the

installation of 300 lighting points. Lastly, in terms of socio-professional integration and

employment promotion, the project will enable 700 men/months to be recruited for works

implementation. It will also enable 100 young people enrolled in work-study programmes,

including at least 20 young women, to undertake internships designed to promote their

employability.

Participatory approach to project identification, design and implementation

2.5.7 The project was adopted as part of the implementation of the Development Strategy Plan

(PDS), which was drawn up in a context of broad consultation at both the regional and national

levels. The project study was conducted using a participatory approach. During the preparation of

environmental and social impact assessment and the technical and economic studies, the various

stakeholders were also consulted. The consultations were carried out at the national level, as well

as at the level of the Bizerte Governorate, delegations and residents of the project area: (i) from 6

April 2013 to 8 October 2013 and 3 June 2014 for the preliminary project design phase; (ii) on 3

April 2016, 14 November 2016, and 26 May 2017, specifically with respect to the project-affected

persons (PAPs) in the context of the Environmental and Social Impact Assessment (ESIA) and the

Comprehensive Resettlement Plan (CRP).

2.5.8 The inventory of the affected persons and expropriated property was based on an

individual resettlement survey of all households located on the right-of-way, conducted from

February to April 2016. Consultation and awareness meetings were held with the project-affected

populations on the sidelines of the survey.

2.5.9 During the Bank's preparation and evaluation missions, the key players and institutions

were met to collect their opinions and complaints in order to address them in the project

formulation, particularly with regard to ancillary developments, the ESMP and the CRP.

2.5.10 This participatory approach, which led to the ownership of the project by the beneficiaries,

will be maintained and strengthened during project implementation through a stakeholder

engagement plan (SEP) at the national level, Bizerte Governorate, delegations and the population

of the project area. This plan, which provides for the setting up of a Monitoring, Mediation and

Accompaniment Committee, will allow: (i) regular meetings with the population of the two

Governorates (Bizerte and Beja), in an effort to increase awareness and social mobilization of these

local populations, and public and private operators; (ii) dissemination of key information on a

dedicated website of the Ministry of Equipment and Habitat and in national and local media.

2.5.11 Finally, during the appraisal mission, the Bank organized a workshop with the EIB, DGPC

and MDICI to address all co-financing risks with the EIB and the Government, as well as to validate

the operational arrangements for monitoring the project.

2.6 Consideration of Bank Group Experience and Lessons Learned in the Project Design

2.6.1 The design of the PACR incorporated the Bank's experiences in Tunisia and on the

continent. In Tunisia, the recent evaluation of the Bank Group's strategies and intervention

programmes over the period 2004-2015, carried out by IDEV, highlighted the relevance of the

Page 21: AFRICAN DEVELOPMENT BANK - AfDB

9

objectives of the transport projects insofar as they focused on concerns critical to the country.

Similarly, it noted that operations in the sector were fully in line with the Bank’s various strategic

orientations for Tunisia, especially those for the periods of 2003-2007 and 2008-2012, as well as

the 10-Year Strategy (2013-2022) and, since 2015, the High Fives.

2.6.2 However, the review highlighted two shortcomings in the sector: (i) lack of a mechanism

for infrastructure maintenance; and (ii) weak coordination among different TFPs. In addition, the

recent completion reports for road projects V and VI, dating from 2016, recommended the

establishment of a monitoring and evaluation system for measuring the impact of projects and the

development of a maintenance strategy. Lastly, the sector review of Bank operations for the 2004-

2014 ten-year period added the improvement of quality at entry to the recommendations below.

These shortcomings are compounded by the sluggish pace at which the grant-funded studies are

conducted.

2.6.3 The issue of sustainability is addressed through the Bank's dialogue with the country's

authorities and the Government has understood the importance of sustainability and has been

mobilizing significant budgetary resources since 2015. The recent Road Infrastructure

Modernization Project (PMIR), approved in 2015, envisaged a Government-financed road

maintenance component worth EUR 116 million. Also, the Bank is financing a study aimed at

proposing an action plan for the establishment of a road fund, which will thus help to secure

resources dedicated to maintenance. Regarding the lack of coordination and sector strategy, the

Bank is also financing a national transport plan that will serve as a reference for all future

interventions by all TFPs and sector dialogue. This project has been the subject of a detailed study

enabling significant improvement in its quality at entry.

2.6.4 Lastly, after 2011, projects in the sector experienced delays due to expropriation problems.

This constraint has been lifted by the recent law of July 2016, relating to expropriation for public

utility. Indeed, the Law introduces expediency in the treatment of expropriation procedures and the

ownership of land for public purposes, while preserving the rights of citizens to bring claims on

compensation benefits. For this project, the process is overseen by the Governorate of Bizerte, and

is at a stage of payments or compensation of those affected (see para. 3.1.16). Finally, with regard

to studies, the Tunis Regional Office has come up with an action plan to support implementing

agencies in order to speed up implementation.

2.7 Key Performance Indicators

2.7.1 The project’s performance will be measured using the performance indicators that are

explained in the results-based logical framework. There are eight (8) such indicators: the Global

Competitiveness Index (GCI), the Logistics Performance Index (LPI), time saving, , number of

fatal accidents, direct employment created per year during construction, number of trainees, the

regional development index (RDI), and the reduction of transport-related CO2 emissions. These

indicators are consistent with the outcomes defined by the 2017-2020 CSP which are themselves

in line with the framework of the DSP objectives.

2.7.2 In order to carry out these operations within the planned timeframes, in addition to these

outcome indicators, performance indicators have been established in relation to the Bank's

institutional performance indicators. These are mainly: (i) the loan effectiveness period; (ii) the

period of fulfilment of conditions precedent to the first disbursement of funds; (iii) contracting

Page 22: AFRICAN DEVELOPMENT BANK - AfDB

10

timeframes; (iv) the average project status indicator (PI); and (v) changes in the disbursement rate

depending on the expenditure schedule. These indicators will be monitored during joint supervision

missions by the Bank, the EIB and the Government and in the day-to-day management of the

project.

III- PROJECT FEASIBILITY

3.1 Economic and Financial Performance

3.1.1 The economic analysis of the project was carried out using the cost-benefit method based

on the “with” and “without” project situations, over a 25-year period following the commissioning

of the structures. The costs include capital expenditures, annual and periodic maintenance, as well

as expropriations and the displacement of networks. The benefits of the project were assessed by

differentiating between generalized transport costs with and without the project, that is, the vehicle

operating costs and the travel time, reduced number of accidents, and reduced CO2 emissions.

3.1.2 Vehicle operating costs (VOCs) were calculated using the HDM 4 Road Use Costs model,

based on two representative categories of traffic vehicles, namely, light vehicles, and heavy duty

vehicles. The time, accident and CO2 emission values were estimated from existing national studies

or by reference to other countries.

3.1.3 The average annual daily traffic volume on the projected highway in the year of

commissioning is estimated at 27,000 vehicles, of which 7% are heavy duty vehicles. On the basis

of socioeconomic and demographic changes in the trade emission and attraction areas, traffic

growth rates were calculated. Thus, under conservative assumptions, traffic in the light vehicle

category will increase annually by 4.4% and 4%, respectively, during the 2021-2028 and 2029-

2040 periods. For the heavy duty vehicle category, these rates will be slightly lower, standing at

4.1% and 3.7%, respectively, for the same periods.

3.1.4 Economic performance of the project: The project’s performance was measured by the

internal rate of return (IRR) and the net present value (NPV). Based on the assumptions, the IRR

is 16.7% and the NPV, at the rate of 8%, amounts to TND 817 million. The robustness of these

results was tested by varying the two key parameters: investment costs and benefits. Thus, a 10%

increase in costs, coupled with a 10% decrease in benefits, slightly reduces the IRR to 14.7% and

the NPV to TND 656 million, thus confirming the project’s positive economic rate of return. The

details of the economic analysis can be found in the technical annexes to the report.

Table 3.1: Outcomes of the economic analysis

Scenario IRR (%) NPV (TND

million)

Baseline (1) 16.6 817

+10% costs (2) 15.8 779

-10% benefits (3) 15.5 693

Sensitivity test: (2)+(3) 14.7 656

Page 23: AFRICAN DEVELOPMENT BANK - AfDB

11

3.2 Environmental Impacts, Climate Change and Social Impacts

Environment

3.2.1 Its size and the main environmental and social impacts identified, the project was

classified in Category 1, in accordance with the Bank's environmental and social assessment

procedures. An ESIA was carried out in 2015 and 2016 respectively for the permanent link and its

extension and finalized in 2017. A Comprehensive Resettlement Plan (CRP) was also prepared and

finalized in 2017. The ESIA reports were approved by the National Environmental Protection

Agency (NEPA) and the notices of compliance were issued on 31 December 2016 and 10 May

2017 respectively for the permanent link and its extension. Summarized versions of the ESIA and

CRP were posted on the Bank's website in July 2017. The project will generate significant

environmental benefits, including: (i) land recovery at the Zarzouna shoreline and the creation 25

000 m2 of urban green space under the bridge; (ii) improved air quality in the project area through

the reduction of air emissions (see Para 3.1.8); (iii) significant improvement in urban mobility while

preserving existing urban forests (Nadhour and Béchateur on the north side and Errimel forest on

the south side); (iv) the addition of another major tourist attraction to the 'Bizerte destination, and

considering its proximity to the Ichkeul park, will boost the development of ecotourism.

3.2.2 The main risks and negative impacts during the works are: (i) loss of vegetation - mainly

grass, shrubs and 250 trees at the level of the bypass, macrophytes and benthic macro-fauna in the

canal area. No status and protected area species will be affected; (ii) qualitative degradation of

water resources, temporary change in turbidity/sedimentology during the canal works; (iii) an

archaeological vestige in the Ramadia area, located 100 metres from the axis of the projected road

could be impacted.

3.2.3 The enhancement of the positive environmental impacts and the mitigation of the above-

mentioned negative impacts will be achieved by applying the following measures: (i) strict

adherence to the measures stipulated in the ESMP, including the sediment quality control plan,

waste management plan, spill emergency response plan, etc.; (ii) planting of 9,750 alignment trees

and development of green spaces; (iii) implementation of the protection plan for the Ramadia

archaeological site. The cost of implementing the ESMP measures, excluding expropriations, is

estimated at TND 3.4 million.

Climate Change

3.2.4 In terms of climate, the project was classified in Category 2, in accordance with the Bank's

Climate Safeguard System. The main risks concern: (i) the presence of flood-prone areas (around

wadi Abbes and wadi El Marj and in the Bizerte canal area), coupled with the absence of proper

drainage structures; (ii) the strength and frequency of prevailing winds (of the North-West sector).

Regarding the first risk, the project design includes appropriate measures, including: (i) flood-

proofing the road at the areas concerned; (ii) ensuring that the size of the hydraulic and drainage

structures constructed are such that they will not only protect the road infrastructure but also

improve environmental sanitation for residents of the areas concerned. The second risk will be

mitigated by the 3 metre-high transparent windbreak screens planned to be put up along his viaduct.

In terms of mitigation, the project implementation will reduce CO2 equivalent (CO2 eq) emissions

by an average of 61 000 tonnes per year, according to the average traffic growth scenario of the

assessment.

Page 24: AFRICAN DEVELOPMENT BANK - AfDB

12

Gender and Vulnerability

3.2.5 The development strategy implemented in Tunisia considers women not only as a

fundamental vector for the preservation of social cohesion, but also as key players for social and

economic success. Women account for 50.2% of the population of the Bizerte built-up area, which

is the project's direct impact area. Despite a 28.5% female unemployment rate in the area, women

are favoured for jobs because of the presence of textile, footwear and leather industries, which hire

them far more than men.

3.2.6 The inhabitants of Atomouh, Ben Nigro, El Massida, HaferMahr, and BirMasyougha – all

localities crossed by the project - live in extremely precarious conditions due to the fact that the

poor sanitation network in these neighbourhoods exposes them to flooding and the absence of

public lighting puts their safety at risk. Given the prevailing situation and the needs expressed

locally, the project has an ancillary development component. With regard to the socio-professional

integration of women and young people, the project also intends to develop the initiatives outlined

in the chapter below.

Employment

3.2.7 The unemployment rate in the direct impact area is 13.1%, of which women account for

28.5% and higher education graduates for 20.8%. In view of this situation, the project plans to

promote direct employment during the construction and operation phase, particularly through the

green spaces that will be created, but above all indirect employment by encouraging the

establishment of new industrial units in the project area and the development of the Bizerte Port.

3.2.8 700 men/months of employment, of which at least 10% for women in terms of direct

employment will be created per year during the construction phase. To this end, the local

workforce, both skilled and unskilled, will need to be identified and mobilized by the Regional

Directorate of the Ministry of Vocational Training and Employment (MFPE) through the

employment offices of the localities concerned. Preference will be given to the recruitment of

young engineers in accordance with the relevant Tunisian regulations.

3.2.9 In order to promote the employability of young people undergoing vocational training, the

MFPE Regional Directorate will help the construction company and local training institutes to

organize internships on the project site for 100 young people registered in work-study programmes,

including at least 20 girls. An agreement defining the objectives and ideal implementation

conditions will be established between the company, training institutes and possibly the Regional

Directorate of MPFE.

3.2.10 The project also plans to promote youth entrepreneurship and socio-professional

integration in sustainable development activities. In this context, cooperation will be established

with the "Green Jobs Platform in Bizerte (EPI)" project, funded by the Islamic Development Bank,

to help 850 job-seekers, of whom 100 will be helped to start their own businesses and 750 will

benefit from job placements (giving preference to girls). Thus, in the context of the development

of the landscaped park and recreational areas envisaged under ancillary developments, the

companies being established as part of the PEV project will be given special preference to carry

out the works. Moreover, the executing agency will also ensure that, in the recruitment, priority is

given to the 750 young people mobilized.

Page 25: AFRICAN DEVELOPMENT BANK - AfDB

13

Involuntary Resettlement

3.2.11 The project will involve 319 households, or 1,309 people, located in the project’s right-

of-way. Expropriations will involve residential houses (125 households), agricultural land with and

without crops (198 owners and farmers), and businesses (11 traders). In this regard, a

comprehensive resettlement plan (CRP) has been drawn up on the basis of the new Tunisian Law

No. 2016-53 of 11 July 2016 relating to expropriation in the public interest, which is much more

favourable than the previous one.

3.2.12 The relocation of project-affected persons (PAPs) and the actual start-up of works will not

take place until these persons have been compensated and the resettlement issue resolved. It is

worth noting at this juncture that the regional authorities of Bizerte have already made operational

arrangements in that regard. The PAPs will have to choose, especially regarding their houses,

whether to be compensated in kind or in cash. The total cost of implementing the CRP is TND 52

million, to be funded by the Tunisian Government.

IV- IMPLEMENTATION

4.1 Implementation Arrangement

4.1.1 Just as for previous sector-based projects, MEHAT is responsible for the implementation

of the project, through the agency of the DGPC which has already set up a project management

unit (PMU). It will be based in Bizerte, the project location. This PMU, which was already actively

involved in the project preparation, was instituted by a Decree. It is headed by a director and

comprises 11 engineers of various specialties and a financial expert. Ancillary activities in other

sectors not covered by MEHAT will be carried out through project contracting delegation

agreements.

4.1.2 The PMU will be supported by a technical assistance mission whose terms of reference

have been approved by the Bank and EIB and are attached in the technical annexes. The assistance

will consist of: (i) 4 permanent experts in procurement, monitoring and evaluation, environmental,

social, and legal supervision; and (ii) experts hired on a short-term basis when the need arises. In

addition to this assistance, the PMU will use consulting firms mandated to perform project

management and works control tasks.

4.2 Procurement Arrangements

4.2.1 The PACR is characterized by a large volume of works contracts (65.95%) and

consultancy services (10.39%) to be concluded at the national and/or international levels2. To

facilitate the implementation of the project, the following arrangements were agreed upon.

4.2.2 Applicable procurement policy and framework: All procurement of works and

consultancy services financed or co-financed3 with Bank resources (AfDB and AGTF) will be done

in accordance with the Procurement Policy for Operations Financed by the Bank Group ("AfDB

Procurement Policy"), October 2015 edition, and in accordance with the provisions set out in the

3 There is provision for EIB co-financing for the viaduct construction

Page 26: AFRICAN DEVELOPMENT BANK - AfDB

14

Financing Agreement. Pursuant to this policy and following the various assessments carried out, it

was agreed that:

(a) All procurement of road rehabilitation works of the cities crossed will be carried out

in accordance with the Borrower's procurement system ("National System") and

using the Competitive Bidding Documents (CBDs) commonly utilized in Tunisia;

(b) Works procurement for the North-bound and South-bound connecting roads

(including the asphalting of roads as part of ancillary developments) and the choice

of consultants shall be done in accordance with the Bank's procurement system

("AfDB System"), using the Bank’s competitive bidding documents (CBDs); and

(c) The procurement of the viaduct construction works (contiguous landscaping

included), to be co-financed with the EIB, will be in accordance with the EIB's

Procurement System. In this respect, insofar as the Mutual Reliance Agreement

(MRA) negotiated between the Bank and the EIB to supervise the procurement of

projects jointly financed by these two institutions is not yet approved, a formal

waiver by the Bank's Board of Directors for the application of EIB's procurement

policies for the procurement of the viaduct works has been requested. To oversee

the implementation of the project, a specific agreement will be signed between the

Bank and the EIB for the implementation of the tender for the viaduct works to: (a)

endorse the choice made by the Bank for this project, to designate the EIB as co-

financier-lead; (b) set the conditions governing the delegation of the fiduciary

responsibilities of the Bank to the co-financier-lead in connection with the tender

for the viaduct. Since the EIB does not have a standard Tender Dossier, it was agreed

between the two partners that the Bank's Standard Solicitation Files be used after

adjustment to fit the context. The implementation details of the agreed procurements

between the Borrower, the Bank and the EIB have been provided in Table B.5.d and

the Procurement Plan (Section B.5.8) of Technical Annex B. 5.

4.2.3 Efficient organization of procurement: All procurements within the context of the project

implementation will be carried out by the PMU set up within MEHAT's DGPC. This unit has been

provided with qualified staffs who have in the past been involved in projects financed by the

national budget, the Bank and the EIB.

4.2.4 Assessment of procurement risks and capacities: In order to address the specificities of

the project, the Bank assessed: (i) the risks at the national, sector and project levels; and (ii) the

capacities of executing agencies. The results of these assessments led to the conclusion that the

overall level of procurement risk was substantial and to the identification of the mitigation

measures proposed in paragraph 5.9 of Annex B.5. The resources required for the implementation

of these measures are loans secured from the AfD and the EIB.

4.2.5 Advance procurement actions: Given the time constraints related to the Borrower’s

agenda and in an effort to address the concern raised in Presidential Directive DP02/2015 on

speeding up project implementation, a reasoned request for advance procurement actions relating

to the viaduct construction works was received by the Bank, which proceeded to authorize it on 4

April 2017.

Page 27: AFRICAN DEVELOPMENT BANK - AfDB

15

4.2.6 Special arrangements: Use of the EIB procurement system: In the absence of a Mutual

Reliance Agreement formally approved by the Bank's Board of Directors, the use of EIB’s

procurement system for the implementation of the viaduct-related invitation for bids envisaged

under the project co-financed by the Bank, requires that a waiver be requested and obtained from

the Board contained in the note in Appendix IV of this report..

4.2.7 Other specific terms proposed: In an attempt to secure the resources required to fulfil its

fiduciary obligations under the National System, the Bank and the Borrower agreed on a series of

measures whose rationale, objectives and details are presented in paragraph B. 5.7.1 of Annex B5.

These measures include: (i) monitoring and management of complaints; (ii) provision by the

Borrower of the names of the owners of companies that win high-value contracts, and publication

of contract awards by the Bank using these names; (iii) maintenance of prices at a reasonable level

in relation to the estimates of the contracting authority; (iv) submission of quarterly reports on the

progress of the project, which should include the list of contracts signed and the companies that

won them, the complaints filed and how they were handled; and (v) the integrity of the electronic

bid submission platform.

4.3 Financial Management Arrangements

4.3.1 The DGPC will be responsible for the project implementation and the management of

project resources. An evaluation of the project's financial management system was carried out in

accordance with Bank guidelines and covered aspects related to budget management, accounting,

internal oversight, financial reporting and external audit. It took into account the assessment of

Tunisia’s fiduciary risk conducted by the Bank in 2016 within the context of the CSP and the

conclusions of the audit and financial supervision reports of previous road projects carried out by

the DGPC. The evaluation found that the initial fiduciary risk posed by the project for the Bank

was moderate due to the DGPC’s sound knowledge of the procedures of the Bank and other donors,

gained from having implemented various Bank projects. In addition, given the scope and technical

complexity of the project, the PMU will be supported by international consultants through technical

assistance in the areas of procurement, technical and financial monitoring and external supervision

and independent technical control of works. However, specific arrangements are required to ensure

reliable and up-to-date project accounting, timely submission of audit reports and satisfactory

follow-up to the auditor's recommendations. Thus, the Sub-Directorate of General Affairs (SDAG)

will be responsible for the financial management of the project with the support of the Project

Management Unit (PMU). The latter will prepare disbursement requests, quarterly financial reports

and annual project financial statements. In that regard, the DGPC will furnish, prior to the first loan

disbursement, evidence of the appointment of a financial officer at the SDAG with qualifications,

experience in the financial management of projects and terms of reference deemed satisfactory by

the Bank.

4.3.2 Project resources will be partly managed using the national public finance management

system. Thus, expenditure financed with loan resources and counterpart contributions will go

through the public spending circuit and will be subject to national procedures and control

concerning: (i) expenditure commitment using the ADEB system, subject to approval by the

expenditure controller; (ii) settlement of expenditure by the technical and financial services after

acknowledgement of the service performed (acceptance of works or services by the external

supervisors and technical works controllers); (iii) authorization of expenditure payment by the duly

empowered authorizing officer (the Director-General of DGPC for payments from AfDB and EIB

Page 28: AFRICAN DEVELOPMENT BANK - AfDB

16

resources, and the MEHAT Finance Director for payments from the national budget); and (iv)

payment of expenditure by the public accountant attached to the Ministry of Finance (MF) for

expenditures financed from the national budget.

4.3.3 The DGPC uses a budgetary accounting system and does not keep the accounts of the

projects it manages. Thus, project financial information will be compiled using a computer

application duly configured to monitor resources by source of financing, and expenditure by

component and by category. Quarterly financial reports will be prepared using the format provided

by the Bank. Annual project financial statements will be prepared in accordance with the Bank’s

ToR. The project’s financial management will be supervised once a year and quarterly financial

and audit reports will be reviewed.

Disbursement arrangements

4.3.4 The disbursements of the Bank’s loans will be subject to the Bank's disbursement rules in

force as set out in the Bank’s Disbursements Handbook. The project will use the direct payment

method for the settlement of eligible expenditure from the loans, given the limited number of

contracts envisaged and the relatively high amounts of individual disbursements. The financing

plan detailing the funding percentages of each donor per contract will be recorded in the tripartite

agreement (AfDB-EIB) specific to the project’s implementation.

Audit arrangements

4.3.5 The General Finance Control (CGF) will audit the project's financial statements covering

all the sources of financing (AfDB, AGTF, EIB and counterpart contributions) on a year-on-year

basis, in accordance with the terms of reference for auditing investment operations financed by the

Bank Group. The project audit reports, including internal audit reports, should be submitted to the

Bank and the EIB within six months of the end of the fiscal year concerned. The PMU will ensure

proper planning of the audit mission and the monitoring of the implementation of the auditor's

recommendations. Furthermore, the project may be subject to verification by State control

institutions. The Bank will obtain and utilize such control mission reports.

4.4 Monitoring

4.4.1 The PMU will include a multidisciplinary team which will be responsible for monitoring

the implementation of all project components. This team will produce semi-annual reports to be

forwarded, through the DGPC, to the AfDB and the EIB. These reports will provide an update on

the level of physical and financial implementation of each project component. Specific reports will

be prepared on the ESMP and CRP implementation. Lastly, separate reports will also be prepared

on the monitoring and evaluation of project impacts based on the identified indicators, depending

on the status of implementation. The Bank, through the Tunis Regional Office, will monitor, on an

on-going basis, the implementation of the project, which will be supplemented by two annual field

supervision missions, conducted jointly with the EIB.

4.5 Governance

4.5.1 In terms of governance, with a score of 66.9 out of 100, Tunisia ranks 8th out of 52

countries in the Mo Ibrahim Index of African Governance (IIAG). This score is up 2.6 spots from

2010, attesting to the country’s unquestionable progress in that area. In the 2016 Transparency

Page 29: AFRICAN DEVELOPMENT BANK - AfDB

17

International ranking, Tunisia scored 41 points versus 38 and 40 in 2015 and 2014, respectively.

This score of 41 points places Tunisia 75th out of 176 countries. The improvement, although still

fragile, is the result of the major anti-corruption measures taken in 2015, such as the passing of the

Information Access Act - one of the most progressive laws in the region - and the adoption of a

national anti-corruption strategy.

4.5.2 In the road sector, good governance practices are intended to result in projects that are: (i)

more efficient, (ii) more relevant, (iii) more sustainable, and (iv) more beneficial to vulnerable

groups. Undeniable progress has been made in this direction. Thus, the sector’s development plan

for 2016-2020 has been widely participatory and was appropriated by various civil society

categories at all territorial levels. Project distribution and allocation were made with a view to

fairness towards the most deprived regions and included accompanying measures for women and

vulnerable groups. Transparency and accountability are also progressing at both the State and

legislative levels. The same applies to the national procurement system and procedures which have

moved closer to international standards.

4.6 Sustainability

4.6.1 Over the past two decades, the Government has been working to upgrade the existing road

network with Bank support and now intends to focus its policy on the preservation of the network

rather than on its extension. Since 2015, despite the scarcity of budgetary resources and the needs

of other sectors, the government has allocated a substantial amount for the maintenance of the road

network, estimated at 629 million TND, and the planned allocation for 2018 is estimated at 219

million TND in a net increase compared to previous years. Besides increasing allocations, the

Government is seeking to improve the resource use efficiency by (i) gradually privatizing road

maintenance through transfer of the activity to SMEs which will be supported in terms of

professionalization; and (ii) initiating pilot experiments in road maintenance management by

service levels, which will be generalized if they prove to be positive.

4.6.2 These measures for ensuring the sustainability of investments will be supplemented by the

recommendations of the on-going study to upgrade the road sub-sector, financed by the Bank under

the Road Infrastructure Modernization Project (PMIR). This study will review, among other things,

the issue of road financing and maintenance, and the possibility of establishing new structures for

commercializing road management and ensuring the sustainability of road maintenance financing.

4.6.3 Regarding this project, the funding needed for the maintenance of the planned facilities

and the viaduct, in particular, was estimated at TND 2.10 million per year. This will be covered by

the resources fromthe State Budget. Lastly, revenues from the rental of the planned recreational

infrastructure will be used to ensure the sustainability of the landscaped park.

4.7 Risks Management

4.7.1 The project implementation poses minor risks in view of: (i) the detailed studies involved

in its preparation; (ii) the capacity and experience of the DGPC which will be supported with

technical assistance; and (iii) the high competition expected in the procurement process. Thus, the

risks of cost overruns and delays will be minimal. The rights-of-way release problems hindering

the successful implementation of projects in Tunisia were addressed by the law of July 2016

relating to expropriation in the public interest and the advanced stage of the process for the project

which is at the level of paying or compensating affected persons (see paragraphs 2.1.24 & 3.1.6).

Page 30: AFRICAN DEVELOPMENT BANK - AfDB

18

In this respect, the first installments will be budgeted in the 2018 financial year, and work on a

given area is subject to proof of compensation of affected persons in that area. The two potential

risks relate to the co-financing of the project:

Implementation delays: the use of EIB procurement rules, the lead financier for the

viaduct construction, poses the risk of delays in the mobilization of enterprises and

of lack of proactivity in the processing of requests from the executing agency. This

risk is mitigated by the decisions of the joint meeting which agreed to: (i) a protocol

agreement between the AfDB and the EIB defining the roles and responsibilities of

each donor; and (ii) regular consultations during supervision or on an ad hoc basis;

Cost overruns due to physical contingencies or performance delays. This risk is mitigated by the

detailed studies which were carried out by experienced consultants. In addition, cost estimates

provided for physical and financial contingencies to cover possible cost overruns.

4.8 Knowledge Building

4.8.1 The project is the first of its kind and the most complex in Tunisia both in terms of its

engineering and work site organization. Indeed, the nature of its foundations (piles 60 m deep and

2.5 m in diameter) and the great length of its spans (270 m) make it the first project of this scale in

Tunisia. Its implementation will result in knowledge building in various fields. The measures taken

within the context of the project, both in terms of the composition of the Project Management Unit

(PMU) and end-of-course engineering projects and vocational training for young people will

contribute to knowledge. The line ministry also plans to ensure the large-scale dissemination of

best practices for major infrastructure construction projects learned during the implementation of

this project. The dissemination will be carried out through a website dedicated for that purpose,

briefing notes and conferences with professional and training organizations.

4.8.2 The effects of the project, which will be quantified under the monitoring and evaluation

sub-component, will allow an assessment of the level of achievement of project objectives and will

be integrated into the broader framework of all previous Bank interventions in order to measure

the impact on the development of the Bank's operations, particularly in its five priority areas of

action.

V- LEGAL FRAMEWORK

5.1 Legal instrument

The Bank will finance the project through the following instruments:

i) An agreement for a loan from ADB resources concluded between the Tunisian State

and the Bank in the amount of EUR 122.000 million;

5.2 Conditions associated with the Bank's intervention

A) Conditions precedent to the effectiveness of the ADB loan agreement

5.2.1 The effectiveness of the Loan Agreement shall be subject to compliance by the Borrower

with the provisions of Section 12.01 of the General Conditions Applicable to Loan Agreements

and Guarantee Agreements of the African Development Bank.

Page 31: AFRICAN DEVELOPMENT BANK - AfDB

19

B) Conditions precedent to the first disbursement of ADB loan

5.2.2 The Bank's obligation to make the first disbursement of the ADB loan shall be subject to

the effectiveness of the Loan Agreement in accordance with Section 5.2.1 above , and the

fulfillment, to the satisfaction by the Borrower, of the following condition, to the Bank's

satisfaction.

5.2.3 The provision of evidence of the appointment of a financial officer within SDAG with the

qualifications, experience in project financial management and the terms of reference that are

satisfactory to the Bank.

C) Special condition prior to disbursement of loan resources for works involving

expropriation

In addition to the entry into force of this Agreement and the fulfillment of the condition precedent

to first disbursement of Loan resources, the disbursement of Loan resources for works involving

expropriation shall be subject to the performance by the Borrower, to the satisfaction of the Bank,

subject to the following condition:

5.2.4 Provide, as the works progress and prior to the start of works in any area concerned,

evidence of compensation of the project-affected persons in that area and/or of procurement of the

land required for the construction, in accordance with the Environmental and Social Management

Plan (ESMP), the Complete Resettlement Plan (CRP) and the Bank's relevant rules and procedures,

including the Policy on Involuntary Displacement and its integrated safeguard system.

5.2.5. It is specified that where such compensation or resettlement is not feasible because of the

impossibility of identifying the beneficiaries or in case of dispute, litigation or other duly justified

reasoning acceptable to the Bank (hereinafter referred to as the "Contentious Case"), the condition

may be considered fulfilled if the Borrower provides evidence that the resources allocated to the

compensation and / or relocation of the Contentious Cases, as defined in the PCR, are deposited in

an account dedicated to the Public Treasury assigned to this compensation and / or resettlement, or

to a bank account acceptable to the Bank specifically earmarked for this indemnification and / or

resettlement, or deposited with a trusted third party acceptable to the Bank.

D) Undertakings

5.2.6 The Borrower undertakes, to the satisfaction of the Bank, to:

Implement the project, the CRP and the ESMP and ensure their implementation by

its contractors, in accordance with (a) Bank rules and procedures; (b) national

legislation; and (c) recommendations, requirements and procedures contained in the

ESMP, and CRP;

Not to start work on an affected area without having fully compensated the affected

persons in that area; and

Provide the Bank with semi-annual reports on the implementation of the ESMP and

the CRP, including any shortcomings and corrective actions undertaken or to be

undertaken.

Page 32: AFRICAN DEVELOPMENT BANK - AfDB

20

5.3 Compliance with Bank policies

The project complies with all applicable Bank policies.

VI- RECOMMENDATION

Management recommends that the Board of Directors approve, subject to the conditions set out in

this report: (i) in the case of the procurement of the viaduct works and the technical inspection

mission of Lot 2, exceptionally waive the application of the Bank's procurement rules and authorize

the application of the EIB's procurement policies; and (ii) approve, subject to the conditions

stipulated in this report, grant the Tunisian government an AfDB loan of EUR 122.00 million to

help finance the implementation of the North-East Road Connectivity Support Project.

Page 33: AFRICAN DEVELOPMENT BANK - AfDB

I

APPENDIX I

DESCRIPTION OF PLANNED WORKS

I. Development of the two new South and North suburban connection roads: The

development works will cover a linear of 7,270 km, corresponding to the geometric

characteristics of a 2x2 lane expressway at a speed of 80 km / h. The route will

include four interchange points, three of which are completely leveled by

interchanges, and the connection at the end of the project through a roundabout.

II. Construction of the viaduct: The proposed viaduct will be a crossing structure of

2,070 km in length that will cross the canal with three spans of 270 m range. It will

have a 25 m deck to accommodate a 2x2 expressway pavement with sidewalks for

maintenance and safety passage. The viaduct was designed to cope with the strictest

seismic and safety standards, with occasional connections every 400 m to allow

traffic diversion from one roadway to another in case of emergency and a system of

video surveillance to control the emergency stop band. Likewise for safety reasons

and because of its fast track nature, its use by pedestrians and cyclists is not

envisaged.

III. Related Works: related works will be carried out in neighborhoods crossed by the

connecting roads and hosting interchanges, including crossing areas whose

populations live in unsettling precariousness. These include: (i) the construction on

the south banks of a 2.4 km paved road linking the Zarzouna South city and the

Zarzouna Nord Technopole and Menzel Abderrahmane; (ii) the development of a

25,000 m² landscaped park under the bridge in the Zarzouna banks area, on the left

banks of the lake, giving rise to a recreational green space; (iii) the construction of

14 km secondary roads, the construction of 8 km of rainwater drainage network and

public lighting with the installation of 300 light points in neighborhoods crossed.

IV. Project management. It will be supported by technical assistance which will also

provide monitoring and evaluation services for the socio-economic and

environmental impacts of the project; the road safety audit and the technical and

financial audits of the project and project implementation communication.

Page 34: AFRICAN DEVELOPMENT BANK - AfDB

II

APPENDIX II

COUNTRY FINANCING PARAMETERS Introduction

1. This Note presents the country financing parameters for Tunisia in accordance with the

Bank’s policy on expenditure eligible for financing46. This policy enables the Bank to finance the

necessary expenditure to be able to achieve the development objectives of the operations financed

by the institution’s resources. The Note is designed as a framework for assessing the risks

concerning the viability of public finances with a view to ensuring that the Bank’s resources are

used appropriately and in accordance with the terms of its mandate. Moreover, the new policy

offers greater flexibility in the use of loans and grants to finance expenditure.

2. Macroeconomic context and public finance situation. Tunisia has suffered from a lack

of growth since 2011. The growth rate fell from 3.6% in 2010 to 0.8% in 2015 but could reach

1.6% in 2016. The fall in growth has been mainly due to uncertainties concerning security, the

different strike actions which have affected the production rate in the mining and hydrocarbons

(phosphates and gas) sector but also weak public investment. Since 2011, the composition of public

expenditure is mostly focused on current expenditure. The civil service wage bill has more than

doubled since 2010 as a result of recruitments and consecutive salary increases. In 2015, it

accounted for 46% of the budget and 13% of GDP. This deterioration is also linked to the

continuing subsidies on some staple products and energy, which represent about 16% of the annual

budget. In all, current expenditure accounts for between 60 and 65% of the overall budget and

between 75% and 80% of the budget net of debt servicing. The five draft budget laws have all been

passed with deficits since 2011 and the cumulative financing gap stood at 42 billion dinars in 2016.

For its part, the public debt increased significantly from 40.7% to 62% in 2016, i.e. an average

annual growth rate of 7.4% much higher than the 1.76% economy growth rate. Moreover, 70% of

outstanding debt is composed of external debt and Tunisia is exposed to an exchange rate risk since

the Tunisian Dinar has lost 32% of its value since 2010.

3. Portfolio. The Bank Group’s active portfolio currently comprises 43 operations,

representing total commitments of UA 1.25 billion. There are 13 public sector operations

representing 85a % of commitments. Tunisia’s portfolio also includes twenty-five (25) technical

assistance operations for a cumulative amount of UA 20.8 million. The lending portfolio’s

performance is deemed satisfactory overall despite slippage on the implementation of the technical

assistance portfolio due to the complexity of the functioning of the public procurement system.

4. Cost sharing. Due to the specific macro-fiscal context described above, increased

vulnerability of the economy and public finances and pressure on the budget which is expected to

continue during implementation of the PSD up to 2929 concerning current expenditure, the

Tunisian government’s fiscal leeway and ability to increase its counterpart funding of Bank-

financed operations is expected to remain limited. Consequently, in a prudential and pragmatic

approach, the Bank proposes to apply two (2) rates for financing its projects and programmes: the

Bank will finance 50% of the cost of projects with an immediate return in the productive sector

Page 35: AFRICAN DEVELOPMENT BANK - AfDB

III

(water, agriculture, industry and services) and 60% of projects with a high social content

(education, health, employment, women, etc.) with a limited and /or gradual rate of return. The

balance will be covered by the Government and/or other donors. The Tunisian Government will

undertake to finance at least 10 % of all project costs.

5. Financing of recurrent costs. The Bank will not finance recurrent expenditure of projects

financed by it. Such expenditure should normally be covered by the Government. However, the

Bank may consider the possibility of financing them on a case-by-case basis.

6. Financing costs in local currency. The Bank’s practice is to finance the foreign exchange

costs of projects financed by it and consequently, most disbursements are made in foreign

exchange. In view of the deep public finance deficit and the existence of large construction

companies and the use of savings on loans, the financing of local currency costs should not be

limited and actual amounts should be fixed on a project-by-project basis.

7. Taxes and duties. Projects financed by the Bank are not generally subject to specific taxes.

The Bank consider on a case-by-case basis the possibility of financing taxes and duties for its

projects. The financing parameters for Tunisia are described below.

Table 3.2 : Country Financing Parameters

Item Parameter Explanation/Comments

Cost sharing. Maximum

proportion of project costs

that the

Bank can finance.

Productive sector with a high

economic rate of return

(structures, public services,

industries, agriculture,

mines, etc.): 50%

Social sector with a limited

and gradual rate of return

(education, health,

employment, women and

youth, etc.): 60%

The effective share of Bank

financing will be limited to

60% of all costs for projects

of a social nature and to 50%

of all costs for projects in the

productive sector (in

particular, infrastructure).

The balance will be covered

by co-financing. The

Government shall undertake

to finance a minimum of 10%

of the total project cost

excluding wages and salaries

Financing of recurrent costs.

Limits if necessary

concerning the total amount

of recurrent expenditure the

Bank may finance

Flexible The Bank can finance some

recurrent costs on a case-by-

case basis

Financing of costs in local

currency. The Bank’s

financing conditions for

expenditure in local currency

are met, in particular: (i) the

financing requirements of the

country’s development

YES The financing conditions for

local currency costs are met.

The Bank may finance local

currency costs in order to

achieve the objectives of

individual projects

Page 36: AFRICAN DEVELOPMENT BANK - AfDB

IV

programme exceed the own

resources of the public sector

(for example, tax and other

revenue) planned borrowings

on the domestic market; and

(ii) the financing of

expenditure in foreign

exchange alone would enable

the Bank to contribute to the

financing of individual

projects

Taxes and duties. Are there

taxes and duties that the Bank

would not finance?

YES There are no unreasonable

taxes and duties.

There is, however, a slight

probability that the Tunisian

Government may borrow to

pay taxes and duties. The

Bank will not finance the

payment of taxes and duties

by borrowings

Page 37: AFRICAN DEVELOPMENT BANK - AfDB

V

APPENDIX III

PROJECT COST AND FINANCING DEVICES

Table 2.5: Summary of the estimated cost per component of the overall project Components

Million TND Million EUR*

Total Currency Total Currency ML Total

A- Works

A1 LOT1: Development of the South Link Road 27,72 18,46 46,18 10,09 6,72 16,81

A2 LOT2: Viaduc Construction 350,19 87,55 437,74 127,48 31,87 159,35

A3 LOT3: Development of the North Link Road 24,56 16,37 40,93 8,94 5,96 14,90

A4 : Related works.

A4.1 : 2.4 km paved road

1,20 1,80 3,00 0,44 0,66 1,09

A4.2 : Rehabilitation of a landscaped park

1,60 2,40 4,00 0,58 0,87 1,46

A4.3 : Rehabilitation of neighborhoods 2,20 3,80 6,00 0,80 1,38 2,18

B- Services

B1: Support Mission to the PMU

11,15 4,78 15,93 4,06 1,74 5,80

B2: Project Management Mission for Lot 1 (including

A4.1related works)

3,46 1,48 4,94 1,26 0,54 1,80

B3: Project Management Mission for Lot 2 (including A4.2

layout)

29,04 12,44 41,48 10,57 4,53 15,10

B4: Project Management Mission for Lot 3 3,17 1,36 4,53 1,16 0,50 1,65

B5: Technical Inspection Mission for Lot 1 (including A4.1

related works)

0,42 0,18 0,60 0,15 0,07 0,22

B6: Technical Inspection Mission for Lot 2 (including A4.2

related works)

6,15 2,64 8,79 2,24 0,96 3,20

B7: Technical inspection mission for Lot 3 0,40 0,17 0,58 0,15 0,06 0,21

B8: Project management and technical inspection mission for

A4.3 related works

0,52 0,52 0,19

C: Release of Right-of-way 59,00 59,00 21,48 21,48

D: Network displacement 8,00 8,00 2,91 2,91

E: PMU operation 4,00 4,00 1,46 1,46

Basic costs

461,27 224,96 686,23 167,92 81,89 249,81

Physical contingencies (7 %) 32,29 15,75 48,04 11,75 5,73 17,49

Financial Risks (4%) 18,45 9,00 27,45 6,72 3,28 9,99

Overall Total

512,01 249,71 761,72 186,39 90,90 277,29

Percentage 67% 33% 100% 67% 33% 100%

Page 38: AFRICAN DEVELOPMENT BANK - AfDB

VI

The project will be financed by the EIB, the AfDB and the Tunisian Government according to the

table below giving the financing sources. As at 15 November 2016, the EIB has approved EUR

123 million for the project. The Bank will provide additional financing of EUR 122.00 million

through a loan from its ADB window. The Government will complete the financing plan with EUR

32.29 million. The tables below provide a summary of the cost by category of expenditure and the

expenditure schedule by source of funding respectively:

The tables below provide a summary of the cost by expenditure category and

expenditure schedule by financing source respectively:

Table 2.6: Cost Summary by Spending Categories for AfDB financing

Components

Million TND Million EUR

Currency ML Total Devise ML Total

Works 180,34 101,61 281,96 65,65 36,99 102,64

Services 13,61 6,36 19,97 4,96 2,31 7,27

Various 0,84 0,84 0,31 0,31

Basic cost 194,80 107,97 302,77 70,91 39,30 110,22

Physical contingencies an

financial risk 20,49 11,88 32,37 7,46 4,32 11,78

Total Général 215,29 119,85 335,14 78,37 43,63 122,00

Table 2.7: Schedule of expenditure by financing source (Million EUR) for the entire project

SOURCE 2018 2019 2020 2021 2022

ADD 14,12 32,34 40,34 27,13 8,07

EIB 5,88 35,29 40,29 35,66 5,88

Tunisian Government 8,69 8,69 8,69 4,12 2,1

Overall Total 28,69 76,32 89,32 66,91 16,05

Page 39: AFRICAN DEVELOPMENT BANK - AfDB

VII

APPENDIX IV

RATIONALE FOR AND EXTENT OF THE WAIVER SOUGHT

FROM THE BOARD FOR THE USE OF THE EIB PROCUREMENT

SYSTEM

Context and Rationale:

To facilitate the implementation of projects co-financed with other partners and in accordance with the

requirements of the Bank's New Procurement Policy, the relevant Bank services have initiated discussions

with several financial partners with whom the institution co-finances projects. A Mutual Reliance

Agreement governing the implementation of procurement aspects of projects to be co-financed with the

EIB was discussed and negotiated with the EIB. This document is awaiting approval by the Boards of the

two institutions. Pending such approvals, and in the absence of a Mutual Reliance Agreement formally

approved by the Board of Directors of the Bank, the use of the EIB's procurement system for invitation for

bids relating to the viaduct planned under the project and co-financed by the Bank requires the adoption of

the following special measure based on the rationale detailed below:

Request for a waiver allowing the use of EIB's procurement system: In accordance

with the provisions of Article 8.1 of the Bank's new Procurement Policy, Bank-

financed goods and services may be procured using the borrower's procurement

system (if certain conditions are met) or following the Bank's procurement policy.

This requirement is also applicable in a co-financing situation unless the Bank's

Board of Directors ("the Board") grants a waiver allowing the implementation of

the procurement policy, regulations, and guidelines of another co-financier (see Art.

10.3 of the Bank's Procurement Policy). Accordingly, in order to enable the EIB's

procurement policy to be applied to invitation for bids for the viaduct construction

works, a formal waiver will be sought from the Bank's Board of Directors for:

(i) the implementation of EIB procurement policies;

(ii) the application of the EIB's eligibility rules which are broader than those of

the Bank's AfDB window;

(iii) the extension of the list of sanctionable practices of the Bank to include

"money laundering" and "terrorist financing" as defined by the European

Community Directives and the anti-fraud policy of the EIB.

If this waiver is formally obtained, the EIB's procurement policy, as well as its eligibility and

integrity rules, could legally apply to the invitation for bids in question even if it is co-financed

with Bank resources. The advance procurement action authorized by the Bank refers to the need to

obtain the waiver.

Page 40: AFRICAN DEVELOPMENT BANK - AfDB

VIII

APPENDIX V

REGIONAL DEVELOPMENT INDICATOR

Regional Development Index

I Introduction

In 2012, the Tunisian Ministry of Regional Development and Planning developed a comparative

study of the country's regional development. Due to the unavailability of data required to build a

regional GDP, the Department developed one that incorporates 17 variables, grouped into four

areas: (i) knowledge, wealth and employment; (ii) health and population; (iii) wealth and

employment; and (iv) justice and equity.

In order to ensure proper monitoring/evaluation, this index, the first version of which is in progress,

will be updated periodically.

II Definition of variables

Dimension Sub-dimension Weight Variables

Education 1 i. Success at the “A” Level (Baccalaureat) (in 2010)

ii. Enrolment rate among 6 to 14-year-olds (in 2010)

Knowledge

Index iii. Literacy rate (in 2010)

Communication 1 iv. Percentage of households with internet access (in 2007)

v. Telephone density (Landlines and GSM) by Governorate (in 2004)

Population 1 vi. Total fertility rate (TFR) (in 2009)

Population and

Health Index Health 1 vii. Number of physicians per 1,000 inhabitants (in 2008)

viii. Number of hospital beds per 10,000 inhabitants (in 2008)

Employment 1 ix. Unemployment rates by Governorate (in 2008)

x. PME density (Number of PMEs per 1,000 inhab.) (in 2009)

Wealth and

Employment

Index Wealth 1 xi. Poverty rates (in 2005)

xii. Drinking water access rates (in 2010)

xiii. Rate of household connection to the water supply system (in 2010)

xiv. Number of cars per 1 000 inhabitants (in 2010)

Justice 1 xv. Crime rate 1, 000 inhabitants (in 2009)

Justice et

Equity Index

Gender

Equality 1 xvi. Disparity between male and female enrolment rates (in 2005)

xvii. Disparity between male and female employment rates (in 2010)

Page 41: AFRICAN DEVELOPMENT BANK - AfDB

IX

APPENDICE VI: TUNISIA - COMPARATIVE SOCIO-ECONOMIC

INDICATORS

Year Tunisia Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2016 164 30 067 97 418 36 907Total Population (millions) 2016 11,4 1 214,4 6 159,6 1 187,1Urban Population (% of Total) 2016 66,9 40,1 48,7 81,1Population Density (per Km²) 2016 73,2 41,3 65,1 33,8GNI per Capita (US $) 2015 3970 2 153 4 509 41 932Labor Force Participation *- Total (%) 2016 47,7 65,7 63,5 60,0Labor Force Participation **- Female (%) 2016 25,1 55,7 48,9 52,1Sex Ratio (per 100 female) 2016 97,6 100,1 106,0 105,0Human Dev elop. Index (Rank among 187 countries) 2015 97 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2010 2,0 ... 18,3 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2016 1,1 2,5 1,3 0,6Population Grow th Rate - Urban (%) 2016 1,3 3,6 2,4 0,8Population < 15 y ears (%) 2016 23,5 40,9 27,9 16,8Population 15-24 y ears (%) 2016 15,1 19,3 16,9 12,1Population >= 65 y ears (%) 2016 7,8 3,5 6,6 17,2Dependency Ratio (%) 2016 45,5 79,9 54,3 52,0Female Population 15-49 y ears (% of total population) 2016 27,0 24,0 25,7 22,8Life Ex pectancy at Birth - Total (y ears) 2016 75,2 61,5 69,9 80,8Life Ex pectancy at Birth - Female (y ears) 2016 77,6 63,0 72,0 83,5Crude Birth Rate (per 1,000) 2016 17,6 34,4 20,7 10,9Crude Death Rate (per 1,000) 2016 6,6 9,1 7,6 8,6Infant Mortality Rate (per 1,000) 2015 12,1 52,2 34,6 4,6Child Mortality Rate (per 1,000) 2015 14,0 75,5 46,4 5,5Total Fertility Rate (per w oman) 2016 2,1 4,5 2,6 1,7Maternal Mortality Rate (per 100,000) 2015 62,0 476,0 237,0 10,0Women Using Contraception (%) 2016 66,4 31,0 62,2 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2005-2015 164,8 41,6 125,7 292,2Nurses and midw iv es (per 100,000 people) 2005-2015 318,9 120,9 220,0 859,4Births attended by Trained Health Personnel (%) 2010-2015 98,6 53,2 69,1 ...Access to Safe Water (% of Population) 2015 97,7 71,6 89,4 99,5Access to Sanitation (% of Population) 2015 91,6 39,4 61,5 99,4Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2015 0,1 3,4 ... ...Incidence of Tuberculosis (per 100,000) 2015 37,0 240,6 166,0 12,0Child Immunization Against Tuberculosis (%) 2015 97,0 81,8 ... ...Child Immunization Against Measles (%) 2015 98,0 75,7 83,9 93,9Underw eight Children (% of children under 5 y ears) 2010-2015 2,3 18,1 15,3 0,9Prev alence of stunding 2010-2014 10,1 33,3 25,0 2,5Prev alence of undernourishment (% of pop.) 2015-2016 5,0 16,2 12,7 ...Public Ex penditure on Health (as % of GDP) 2014 4,0 2,6 3,0 7,7

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2010-2016 114,2 101,2 104,9 102,4 Primary School - Female 2010-2016 112,5 98,4 104,4 102,2 Secondary School - Total 2010-2016 88,2 52,6 71,1 106,3 Secondary School - Female 2010-2016 94,2 50,2 70,5 106,1Primary School Female Teaching Staff (% of Total) 2010-2016 60,0 47,1 59,8 81,0Adult literacy Rate - Total (%) 2010-2015 81,1 66,8 82,3 ...Adult literacy Rate - Male (%) 2010-2015 89,7 74,3 87,1 ...Adult literacy Rate - Female (%) 2010-2015 72,8 59,4 77,6 ...Percentage of GDP Spent on Education 2010-2015 6,3 5,0 4,0 5,0

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2014 18,7 8,7 11,2 10,3Agricultural Land (as % of land area) 2014 64,8 41,7 37,9 36,4Forest (As % of Land Area) 2014 6,6 23,2 31,4 28,8Per Capita CO2 Emissions (metric tons) 2014 1,9 1,1 3,5 11,0

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

June 2017

0

10

20

30

40

50

60

70

80

90

100

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Infant Mortality Rate( Per 1000 )

Tu nisi a Af r ica

0

500

1000

1500

2000

2500

3000

3500

4000

4500

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

GNI Per Capita US $

Tu nisi a Af r ica

0,0

0,5

1,0

1,5

2,0

2,5

3,0

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Population Growth Rate (%)

Tun isi a Af r ica

01020304050607080

20

00

20

05

20

09

20

10

20

11

20

12

20

13

20

14

20

15

Life Expectancy at Birth (years)

Tu nisi a Af r ica

Page 42: AFRICAN DEVELOPMENT BANK - AfDB

X

APPENDIX VII

TABLE OF AfDB OPERATIONS IN TUNISIA AS AT 30 SEPTEMBER 2017

Project Title Sector

Approval

Date

Effective

Date

Date 1st

disbursement Commitment

Disbursement

Rate

Completion

Date Age

NATIONAL GAS TRANSPORTATION AND

DISTRIBUTION NETWORK DEVELOPMENT Energy 04/01/2015 09/23/2015 03/02/2016 41,511,527.24 0.00 12/31/2017 2,52

SOUTH TUNISIAN GAS PIPELINE - TUNISIA Energy 06/26/2014 02/23/2015 03/18/2015 52,657,445.76 100.00 08/19/2027 3,28

Total Energy 94,168,973.00 56% STUDY - -RISK MANAGEMENT AND

ESTABLISHMENT OF AN AS SYSTEM Agriculture 08/02/2016 09/28/2016 02/08/2017 325,000.00 1.93 12/31/2018 1,18

GAFSA NORTH INTEGRATED AGRICULTURE

DEVELOPMENT PROJECT Agriculture 02/13/2013 02/14/2014 03/07/2014 18,587,313.73 41.41 06/30/2019 4,64

GABES II INTEGRATED AGRICULTURE

DEVELOPMENT PROJECT (PDAI) Agriculture 11/26/2014 06/23/2015 09/07/2015 17,357,684.97 22.98 06/30/2020 2,86

MIC GRANT FOR THE PREPARATION OF ZAGHOAUN

PDAI Agriculture 10/27/2014 11/28/2014 09/07/2015 390,000.00 45.37 12/31/2018 2,85

Total Agriculture 36,659,998.70 32%

RURAL DRINKING WATER SUPPLY PROGRAMME

(RWSSI)

Water and

Sanitation 10/12/2011 02/24/2012 02/24/2012 79,694,736.05 88.87 12/31/2018 5,99

RURAL DRINKING WATER SUPPLY PROGRAMME

Water and

Sanitation 09/06/2016 05/29/2017 05/29/2017 103,967,927.11 4.04 12/31/2021 1,08

RURAL DRINKING WATER SUPPLY PROGRAMME

Water and

Sanitation 09/06/2016 03/01/2017 03/01/2017 840,484.46 10.00 12/31/2021 1,08

DEVELOPMENT OF TUNISIA’S WATER VISION AND

STRATEGY 2050

Water and

Sanitation 06/20/2016 02/01/2017 02/14/2017 1,130,451.59 0.00 12/30/2018 1,29

TREATED WASTE WATER QUALITY IMPROVEMENT

PROJECT

Water and

Sanitation 01/11/2012 02/29/2012 05/15/2013 27,273,720.57 37.89 12/31/2018 5,74

Total Water and Sanitation 212,907,319.78 40% INCLUSIVE REGIONAL DEVELOPMENT SUPPORT

PROGRAMME (PADRI) Social 11/02/2016 12/19/2016 12/19/2016 151,287,201.94 100.00 12/31/2017 0,92

MIC - INVESTMENT PROMOTION SUPPORT PROJECT

AND Social 06/03/2015 08/11/2016 296,373.00 0.00 06/30/2018 2,34

Total Social 151,583,574.94 100% 0,00

INDUSTRIAL POLICY DESIGN SUPPORT PROJECT Ind/Mini/Quar 08/14/2015 11/19/2015 791,380.00 0.00 08/31/2017 2,15

STRUCTURAL TRANSFORMATION AND GROWTH Ind/Mini/Quar 08/14/2015 11/19/2015 04/24/2017 798,310.00 3.17 02/28/2018 2,15

Page 43: AFRICAN DEVELOPMENT BANK - AfDB

XI

SECTOR

Total Ind/Mini/Quar 1,589,690.00 2% 0,00

STUDY TO DEVELOP A NATIONAL TRANSPORT

MASTER PLAN Transport 07/14/2014 11/28/2014 01/23/2015 800,000.00 11.30 06/30/2017 3,23

GABES-RAS-JEDIR HIGHWAY CONSTRUCTION

PROJECT Transport 06/21/2011 09/19/2011 04/13/2012 115,432,135.08 43.34 10/31/2019 6,30

ROAD INFRASTRUCTURE MODERNIZATION

PROJECT (PMIR) Transport 10/28/2015 02/25/2016 03/09/2016 121,029,761.55 18.30 12/31/2020 1,94

ROAD INFRASTRUCTURE MODERNIZATION

PROJECT (PMIR) Transport 10/28/2015 02/25/2016 03/09/2016 38,763,143.08 18.76 12/31/2020 1,94

ROAD INFRASTRUCTURE MODERNIZATION

PROJECT (PMIR) Transport 10/28/2015 11/19/2015 12/23/2015 1,200,000.00 0.00 12/31/2020 1,94

ENFIDHA AIRPORT PROJECT Transport 01/14/2009 03/13/2009 03/13/2009 57,097,655.05 100.00 01/01/2023 8,73

Total Transport 334,322,694.76 41%

FAPA TUNISIE PME BFPME Finance 08/05/2013 02/27/2014 02/27/2014 666 994,31 4.08 06/30/2018 4,17

FINANCIAL SECTOR MODERNIZATION SUPPORT

PROGRAMME Finance 07/13/2016 10/10/2016 10/10/2016 225,249,834.00 100.00 12/31/2017 1,23

AFRICAN SME PROGRAMME - LOC HANNIBAL

LEASE Finance 07/14/2017 6,723,875.64 0.00 07/08/2018 0,23

II° LINE OF CREDIT FOR THE BANQUE DE L'HABITAT Finance 02/27/2002 08/27/2002 08/27/2002 23,953,806.97 100.00 12/31/2006 15,61

BANQUE HABITAT TUNISIE - LOC II Finance 07/21/2003 12/18/2003 12/18/2003 67,238,756.42 100.00 03/31/2008 14,22

SME APEX FACILITY TUNISIA Finance 07/13/2011 02/24/2012 04/10/2013 35,104,963.84 70.43 07/22/2021 6,24

TRADE FINANCE LINE OF CREDIT TO BHT Finance 10/19/2016 02/27/2017 03/28/2017 50,429,067.31 100.00 08/27/2020 0,96

Total Finance 409,367,298.49 95% PUBLIC PROCUREMENT REFORM ACTION SUPPORT

PROJECT Multi-Sector 12/27/2013 04/02/2014 10/17/2014 530,100.00 41.40 12/31/2017 3,78

OPERATIONALISING PPPS IN TUNISIA (PPP

ADVISORY) Multi-Sector 06/14/2013 10/15/2014 10/15/2014 789,000.00 23.09 06/30/2018 4,31

Total Multisector 1 319 100,00 30%

GRAND TOTAL - (EXCLUDING MENA TF and TFT) 1,241,918,649.67 67%

Page 44: AFRICAN DEVELOPMENT BANK - AfDB

XII

APPENDIX VIII

Project Area Map

This map has been provided by the staff of the African Development Bank exclusively for the use of the readers of the

report to which it is attached. The names used and the borders shown on this map do not imply on the part of the AfDB

Group and its members any judgement concerning the legal status of a territory nor any approval or acceptance of these

borders.