afbc co-firing of coal and hospital waste/67531/metadc623728/m2/1/high... · afbc co-firing of coal...

32
AFBC CO-FIRING OF COAL AND HOSPITAL WASTE Quarterly Progress Report COOPERATIVE AGREEMENT: DE-FG21-91 MC27205 May 1 1995 to July 31 1995 Prepared by James M. Stuart DONLEE TECHNOLOGIES INC. 693 North Hills Road York, PA 17402 Prepared for the U.S. DEPARTMENT OF ENERGY

Upload: doanbao

Post on 15-Mar-2018

227 views

Category:

Documents


10 download

TRANSCRIPT

AFBC CO-FIRING OF COAL AND HOSPITAL WASTE

Quarterly Progress Report COOPERATIVE AGREEMENT: DE-FG21-91 MC27205

May 1 1995 to July 31 1995

Prepared by

James M. Stuart

DONLEE TECHNOLOGIES INC. 693 North Hills Road

York, PA 17402

Prepared for the

U.S. DEPARTMENT OF ENERGY

DISCLAIMER

This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manu- facturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.

This report has been reproduced directly from the best available COPY.

Available to DOE and DOE contractors from the Office of Scientific and Technical Information, 175 Oak Ridge Turnpike, Oak Ridge, TN 37831; prices available at (615) 576-8401.

Available to the public from the National Technical Information Service, U.S. Department of Commerce, 5285 Port Royal Road, Springfield, VA 22161; phone orders accepted at (703) 487-4650.

1.

I I .

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May 1,1995 - July 31,1995)

Page i

CONTRACT DE-FC21-91 MC27205

TABLE OF CONTENTS

I NTROD UCTl ON ................................................................................. A. Project Objectlve .......................................................................... B. Reporting Period .......................................................................... C. Report Layout ..............................................................................

. .

TASK ONE - Design, Specify, Procure, Install and Start- U p Facility . .... . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . A. Subtask 1-A Design ..................................................................... B. Subtask 1-B Equipment Purchase and Fabrication ....................... C. Subtask 1-C Installation .............................................................. D. Subtask 1-D Shredder System Verification ..................................

..

E. Subtask 1E Start-up .................................................................... 111. TASK TWO - Obtain Permits ............................................................

IV. TASK THREE - Procure Coal, Limestone and Ash Disposal Contracts ..........................................

V. TASK FOUR - Conduct One Year Test Program ............................

VI. TASK FIVE - Prepare Final Report ...................................................

VII. PROJECT COSTS ....................................................................................

6

VIII. SUMMARY .......................................................................................... 11

- DONLEE EYESGY S'/STEILIS -

2

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May 1,1995 - July 31,1995)

Page ii

CONTRACT DE-FC21-91 MC27205

LIST OF TABLES

Table 1. Lebanon VA Project Equipment Status Report ............................. 12

Table 2. Lebanon VA Project Cost-to-Date Summary ................................ 16

Table 3. Lebanon VA Project Equipment Costs ......................................... 17

Table 4. Lebanon VA Project Schedule ..................................................... 25

- ECNLEE EEIESGY S'/STELIS -

3

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 1

CONTRACT DE-FC21-91 MC27205

Date 6/1/95

7/3/95 7/13/95

1. INTRODUCTION

Task Description The Estimate of Costs to Complete LVAMC Project was submitted by DONLEE

Formal Application for Funding was made by DONLEE to DOE-METC. The LVAMC Proiect Review Meetine was held at Lebanon VA Medical Center.

to DOE-METC.

I

A. PROJECT OBJECTIVE The project objective is to design, construct, install, provide operator training and start-up a circulating fluidized bed combustion system at the Lebanon Pennsylvania Veteran's Affairs Medical Center. This unit will co-fire coal and hospital waste providing lower cost steam for heating and possibly cooling (absorption chiller) and operation of a steam turbine-generator for limited power genreation. This would permit full capacity operation of the FBC year round in spite of the VA laundry that was shut down as well as efficient destruction of both general and infectious hospital waste and steam generation. The steam generated is as follows:

Steam = 20,000 Ib/hr

Pressure = 125 psig Steam quality = -98.5%

Temperature = 353 F (saturated)

7/24/95 - 7/27/95 713 1/95

On February 3, 1995 DONLEE notitied Lebanon VA and DOE-METC that additional funding would be required to complete the project. This funding, in the amount of $1,140,127, is needed to complete the facility, start-up and shakedown the facility, perform the test program and write the final report. After review DOE-METC approved funding in the amount of $1,246,019 to be available Auhst 1,1995.

A LVAiilC Project Consmction Status Review was performed by Gilbert/ Commonwealth. The first weekly LVAiilC Project Meeting was held via a three-way telephone conference call among DOE-METC, LVXvlC and DONLEE personnel.

On March 7, 1995 the vendors were notified that the Lebanon VA Steam Plant Project was shut down and that all work outside DONLEE was stopped pending obtaining additional funding.

During the period in which the work at the LVA site was stopped, DONLEE, DOE-iMETC and Lebanon VA Medical Center personnel worked to obtain additional funding for the project

Funding is espected to be approved by August 1, 1995.

- DONLEE ENERGY SYSTEMS -

. . -

. _-

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 2

CONTRACT DE-FC21-91 MC27205

B. REPORTING PERIOD The reporting period is from May 1,1995 to July 31,1995.

C. REPORTLAYOUT .

The Progress Reports will show progress and direcrion for each task and subtask. The Final Technical Report will also provide a coherent chronology of tasks and subtasks throughout the project.

11. TASK ONE - Design, Specify, Procure, Install and Star€-Up Facility A. SUBTASKI-A - DESIGN

Progress : The process of filling out fact sheets for each piece of equipment for the operation and maintenance manual continues, and about 80% of the fact sheets have been completed.

The status of the fact sheets is as follows: 56 fact sheets have been written. 54 fact sheets have been typed and completed. 2 fact sheets have been typed and proofed. 10 fact sheets remain to be written.

Currently, the coal bins and structure have been fabricated and installed along with the combustor, boiler and economizer. X-bracing will be added to give added suen,gh to the supports of the combustor, boiler and other structures.

Work on the training manual continues. The vendor manuals will be incorporated as appendices of this manual. Shakedown, start-up and operation will begin after completion of the equipment and instrumentation installation. A computerized preventative maintenance pr0 ,m will be developed throughout shakedown, start-up and the one-year test period.

The feedwater and chemical treatment system was redesigned for the new system and will be identical to the system utilized on the existing VA boilers.

The stack has been redesigned because analysis showed the base did not meet acceptable standards and there was too great of a deflection over the length of the stack. This new design was reviewed by the buildinsJfoundation en,$neer. The stack anchoring design has not yet been completed and will be investigated further. Platforms and ladders have been redesigned for field installation. The installation will begin later this surnmer after the funding is approved.

- DONLEE ENERGY SYSTEMS -

5

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 3

CONTRACT DE-FC21-91 MC27205

The design of the Varco Pruden building has been completed and the structural steel has been placed. The roof and walls have been installed. Only the interior liner and the area above the control room need to be fully completed for the building walls and strucme to be completed.

Problems: None

Plans: Continue filling out fact sheets for the equipment. Continue design and drafting work. The orifices and venturis have been designed and procured. Several orifices and venturis have already been installed.

B. SUBTASK 1-8 - EQUIPMENT PURCHASE AND FABRICATION Progress: The status of the major pieces of equipment in the procurement process is shown on Table 1. The fabrication procedure developed for the combustor, boiler, economizer and bins allowed these items to be fabricated by DONLEE.

The coal bins, limestone silo and the limestone bins have been installed at site along with the structures. The ash silos and structure are almost completely installed.

Problems: None

Plans: Continue with authorized expenditures after funding is approved. Proceed with the building and equipment installation after the work restarts.

C. SUBTASK I-C - INSTALLATION

Progress: The construction work has been broken into smaller contracts. This allows us to take advantage of smaller constructors who specialize in specific pomons of the construction package.

Problems: None.

Plans: The installation contractor began Phase 1 of the equipment installation (those items that would be placed inside the building) on August 15. 1994. A second vendor has been chosen for the piping and their work is about 75% comp1e:e.

- CONLEE ENEFiG'/ SYSTEMS -

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 4

CONTRACT DE-FC21-91 MC27205

INSTALLED EQUIPMENT AND PIPING Circulating fluidized bed combustor with supports (additional supports are being added) Refractory duct work Boiler Economizer Coal silos and supporting structures Grizzly and hopper Coal conveying screen Bucket elevator Draining “Live Bottom” screws Coal weigh belts and structure Limestone feed system: 2-ton limestone bin and structure and 30-ton limestone silo and StNcture Bed cleaning system including the v i h M g screen and crusher Valves and drains for the various beds on the combustor Shredder system and the skip hoist Air Lines Downcomers and risers between the boiler and cooling bed coils Ash pneumatic piping systems have been installed at the baghouse and tle bed cleaning system Lime injection system was installed upstream of the baghouse Venturis and bags for the process baghouse Cooling bed and lift channel blowers Primary and ID fans Shredder blower Roots Blowers (3) Baghouse (in-place, repair to support structure that was damaged in shipping is required) Shredder hydraulic unit Air compressor Additional platforms, ladders and supporting columns Ash structures, platforms and the two silos Orificeslventuris and the associated piping Limestone silo and structure The motor control center (MCC) room Conduit and elecmcal panels were placed near the equipment and in the conuol room Thermocouple placement was begun The sand funnel and the supporting stand were designed and insralled

- GONLEE ENERGY SYSTEMS -

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 5

CONTRACT DE-FC21-91 MC27205

ADDITIONAL EQUIPMENT STORED ON-SITE UNTIL NEEDED IN THE INSTALLATION: Instruments: thermocouples, sensors, probes Electrical panels to various equipment Ash conditioner and ash rotary Various valves and slidegates Heatless air dryer

COMPLETED CONSTRUCTION DURlNG THE PREVIOUS REPORT PERIOD: Cement block work for control room; Building structural beams; Roof and the four walls of main building; and ID fan room.

D. SUBTASK I-D - SHREDDER SYSTEM VERIFIC, AND TESTING

Part of Phase I Contract testing to be done at DONLEE Pilot facility.

Progress: - Task completed in June 1992.

Problems: None.

,TIOF

Plans: Task completed in June 1992. Sterilization testing will be completed prior to completion of the installation.

E. SUBTASK I-E - START-UP Progress: None. This subtask is due only after the installation of the facility is completed.

Problems: None. This subtask has not been started at this time.

Plans: The facility is anticipated to be completed during the winter of 1995. Training Pro,oram and the Operation and Maintenance Manual.

Work has begun on the

- CONLEE ENERGY SYSTEMS - P

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 6

CONTRACT DE-FC21-91 MC27205

111. TASK TWO - Obtain Permits

Progress: Application for the extension of the Plan Approval to December 27, 1994 for the Lebanon VA facility was sent to the PA DER on January 31, 1994. DONLEE has received the Plan Approval and the 180 day extension. The Plan Approval was extended again to allow for the completion of installation and for start-up.

Problems: None. Preparation for the PA DER site review after construction wiU commence when the installation of the equipment starts.

Plans: No action with PA DER is required until site review following construction. The Plan Approval was extended a second time to November 30,1995 to cover the time of installation and the start- up period.

IV. TASK THREE - Procure Coal, Limestone and Ash Disposal Contracts

Progress: Early in the project the coal, limestone and ash disposal contracts could not be finalized because the initial supply date was in question due to NEPA approval related delays. Lebanon VA had received a supply proposal from Naughton Energy for coal, limestone and for ash disposal. During May 1994 the Lebanon VA set up a contract for procuring coal and limestone and for disposing of the generated ash when the facility is operational.

Problems: Naughton has a three-year contract (through September 1997) to supply the coal and limestone, and to dispose of the ash generated. The contract started in October 1994. From then until the time that the facility is operational, the right to purchase the coal and limestone and dispose of ash is lost

Plans: None.

- DONLEE ENERGY SYSTEMS -

ci

V.

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 7

CONTRACT DE-FC21-91 MC27205

TASK FOUR - Conduct One Year Test Program

Progress: None. This task is due after the installation, and start-uplshakedown is completed.

Problems: None.

Plans: A preliminary request for proposal for performing stack sampling tests has been written and is to be sent to three (3) vendors for competitive bids.

VI. TASK FIVE - Prepare Final Report

Progress: None. The report is due 3 months after the test program is completed.

Pro biems: None. The task is to be completed after the test program is finished.

Plans: Currently information has been gathered concerning the equipment and facility. Preparation is being made to perform a matrix of tests that will demonstrate the performance and operation limits of the CFB system, quantify emission levels, identify problem areas and aid in performing scale-up analyses for future commercial designs.

VII. PROJECT COSTS Changes to the contract The following items have undergone price increases during this project. parentheses refer to Table 3 item numbers.)

(The numbers in

The boiler required $8,111.00 of additions to meet the VA specifications. This number will be revised pending final boiler design. (8)

The coal feeders were ori_&aUy proposed to be screws. The VA has requested weighing capability. The cost was $45,690.00. (15)

Weigh belt feeders were se1ec:ed in place qf screw feeders.

The annunciator panel requested by the VA will be approximately 58160.00. (17)

- DONLEE ENESG'I SYSTEMS -

10

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 1995 - July 31 1995)

Page 8

CONTRACT DE-FC21-91 MC27205

Changes to the contract (Continued)

The emissions monitoring system required $56,500 above the proposal for the HC1 monitoring system and heated sample lines. (22)

An ash conditioner needed to be added to the contract. The Solid Waste Division of Pennsylvania's Department of Environmental Resources requires that the ash be conditioned with water before transport. The ash conditioner was supplied at a cost of $59,804 (revised), including ducts and screw conveyors. (2,3,4)

A refrigerated room is required for the storage of medical waste in the event that the unit is not operating. The cost of the refrigerated room was $14,877. (48)

The scope of the sand silo design has been reduced to a sand "funnel," resulting in a cost reduction of $5,000 to $10,000. The cost of the sand funnel was $2925. (6)

The Solid Waste Division of Pennsylvania's Department of Environmental Resources requires that the medical waste be weighed before disposal. The cost of a scale to be mounted in the loading dock was $4382. (49)

An air compressor will need to be purchased for the new facility. It was originally believed . that the present system would be able to provide sufficient air quantities but the new facilities requirements are larger than originally anticipated. The cost of a 300 cfm air compressor rated at 110 psi was $20,880. The air is supplied for the pneumatic transport of limestone and ash, pneumatic slidegates and instrumentation. (1)

A heatless air dryer was purchased to provide air dried to -40 F dewpoint, at a cost of $7,028 (revised). (74)

Soil boMgs were required to detennine soil bearing capacity before the foundation design could be started. It was originally believed that the VA had this infomtion. The cost of the soil borings was $5850. (54)

Slidegates were needed for the coal, limestone and ash handling systems at a cost of $52,665. (53) An oxygen analyzer to be used to measure oxygen at the boiler entrance and to be used to help conuol oxygen levels in the system was needed at a cost of $6429. (33)

Expansion joints were needed to allow for thermal growth throughout the system at a cost of S25,862. (34)

The eiecmcal conuactor cost for the facility installanon is currently S105,34S with change order additions. (31)

The rehctory engineering, materials and installation vendor's cost was $88.007. (47)

- CONLEE ENESGY SYSTEMS -

11

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 9

CONTRACT DE-FC21-91 MC27205

Changes to €he contract (Continued)

The start-up burner system, including its panel and motors, for the Circulating fluidized bed cost is $10,792. (55,56,57)

The general valves for the circulating fluidized bed system currently cost $26,065. (63)

Geotechnical En,oineering Services for the building and foundation have been added to ensure that the facility is constructed properly and safely. The cost is partly offset by the October 1993 budget cost of the building and foundation. The cost of the services was $9,512. (39)

Design Engineering Services have been added to provide independent supexvision for the construction. The cost of these services is included in the October 1993 budget cost of the building and foundation. The cost has since been reduced to $10,911 h m $17,000. (43)

The bed cleaning system which processes the ash generated from the combustion of the coal, limestone and medical waste currently costs $26,114. The vendor agreed to upgrade the equipment being supplied to meet the equipment specifications. (5) The cost to move the gas lines at the facility was orighally $5,500. This cost was deleted by the gas company, UGI, in early February. (29)

The cost of the economizer sootblower was $8,784. (12)

The baghouse and sorbent injection system currently cost $138,444 (revised). (19)

The cost of the vendor doing the ducting and piping has increased to $170,716. (20)

The cooling bed and lift channel blowers cost $13,060. (25)

The hospital waste handling and subsystems (or skip hoist) currently cost $36,815. (30)

The cost of the added msmitters for pressure and flow indication added to the specification, was $4,097. This cost increase is due to the number of transmitters that have been added. (33) The price of the shredder blower has increased due to a frei$t charge. The final price was $3,140. (51)

The cost of the controls computer package has increased from $83,442 to $97,001. This cost increase is due to a required increase in the UO capacity of the conuol system and for two computer courses. (17)

The total cost of the bins: ash, limestone (3) and coal has increased from $43,065 to an estimated $123,663. (73 thru 7d).

- GCNLEE ENERGY SYSTEMS -

a <7 -

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 1995 - July 31 1995)

Page 10

CONTRACT DE-FC21-91 MC27205

Changes to the contract (Continued)

The cost of the steelwork or equipment support (structure) has increased from $72,290 to $143,639 (estimated). (59)

The cost of the design and manufacture of the platfoms, supports and ladders was $27,000. (45) The cost of the vendor equipment installation, including the platform installation and extras, is now $447,575. (64)

The cost of additional payment/perfoxmance bonds has been maintained in the individual contracts (vendor equipment installation and ducting and piping). This item as a result is $0.

The air cannons were purchased for the coal silos at a cost of $5,527. (72)

The redesign of the stack is complete. The final total cost of the stack is now $44,428. (13)

The noise control pads and bases for the blowers, fans, compressor and shedder hydraulic unit have been purchased and installed at a cost of $4,288. (73)

The additional feedwater and steam valves will be ordered at a cost of $3,875. (70)

Spare sh'edder hydraulic filters were purchased for $421. (71)

The orifices and venturis for flow measurement have been designed and cost $12,932. (75)

A cart for medical waste handling was purchased to check out the skip hoist and shredder equipment. The cart cost was $682. However, this cart was returned when it was discovered that the cart design had changed, and the cart dimensions were too large to be used. Another cart design was chosen by DONLEE and LVA and will be purchased and used after funding is approved. (76) The site trailer for an office and storage space was rented for a minimum of 4 months at a cost of $2,237 for an expected 11 months. (77)

(66)

Contract Costs-to-Date: The Lebanon VA Project Costs-to-Date are shown on Table 2.

Equipment Costs The equipment costs are shown on Table 3 Lebanon VA Project Equipment Cost Summary. Several of these costs are preliminary and purchase orders have not been released yet.

- DONLEE ENERGY SYSTEMS -

kl3

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 1995 - July 31 1995)

Page 11

CONTRACT DE-FC21-91 MC27205

VIII. SUMMARY

The State permitting process required for construction is completed. Operating permits will be obtained after construction has been completed.

The installation of the equipment at site started August 15, 1994. Consmction and equipment fabrication, the purchase of equipment from vendors and the piping which began during October 1994, will all continue after additional funding has been obtained.

The vendors were notified on March 7, 1995 that the Lebanon VA Steam Plant project was shut down, and all work outside DONLEE was stopped pending additional funding.

Funding is expected to be approved by August 1,1995.

A current schedule for the project is included with this report.

. .

- DONLEE ENERGY SYSTEMS -

' Y

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 12

CONTRACT DE-FC21-91 MC27205

7a

Table 1. Lebanon VA Project Equipment Status

CoalBins

EQUIPMENT VENDOR

70062

wo

wo

wo

wo

wo

wo

?EO1

41916

wo

419178

41819

YlB4

Y l M

YlIS4

Y1A4

Ylrn

1w1m

6Rm

w1m

Y.Wd

2i2w

wo 910/95

w1m 711594

15 'Coal Slonce. Yana!ina & iaeainq ' S W U M C N T BIRCH ' : 3 e a 7R7B3 1 9 1 5 m '

'6 C ~ r m u s ~ o n C v c b ~ ~ C z o i ~ n a @ea Unit -No Tubes CCNLEf wo wrm3 11'1%-

17 Cornrois Csmute r P3cmce rnGNE?WE" %39oB W1693 911 9 5

I

- DONLEE ENESG'I S'/STEMS -

/6

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 13

CONTRACT DE-FC21-91 MC27205

6 z z I K

Table 1. Lebanon VA Project Equipment Status

2

I- P 3

VENDOR $ a m i2 s a a

w B !! 0 a a Q a

O

0

Lu ul

2 3

EQUIPMENT

19 Ow Infenion Fabdc Filter: Baqhouse 420190 1 6 5 9 4

6 I I I

! s6 jUrnestone Sloraqe. Hanallnq 8 ieedinq IMCAWBER SYSTE?? a168dB 7mEI3 1 12'1593

I 37 'Outside Review of Bldq-PreiimtnarylFina I ENTECH W4S3 ! 7tlm '

23 'Paintinq 1 CCNLEE 7t15n4 2'2E96

#

20 I Ouctlnq 8 Pipinq

23 I Emlssbns Monirorinq Eoubmem:Oxyqen

24 I ExDamionJolnw

21 UectdcaJ EaubmentB lrmaflatlon

Z2 Emissions Monirorlnq Eoubmem

c9 'P!arn EndJSile PrewFoundation: Gaoteclniul Em:. iSCHNAOEL 7cc27 2'1 &9A 7IlClA

McClUre 1 m l I M B R 4

ENERTEC I 141728 l a w 3 3

WAGREGOFiY 8 CO A)(Jdo 1 W m

SENIOR RMUUICS I 7mll I 8 I e J 3 3

OBWCamemer Enqr 50024 Zm4

40 Plant EncWSile PrewFoundaiion: 9'dg 8 Foundation"" 'ARTHUR FUNK iK23 1R'WJ Wa9A

28 I flyash Reinlenbn System: Bed Mal Bbwen

- DONLEE ENESGY SYSTEMS -

4%

RM. ASSC 1 41810 1 W m 4

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 14

CONTRACT DE-FC21-91 MC27205

Table 1. Lebanon VA Project Equipment Status

EQUIPMENT VENDOR

- 41 Plant EnVSLle PreclFourdatbn: Euildlnq

42 I Plant EncEiile RadFoundatlon: Wqn

I P ' m brySne PWFoundatlon: M u W o n

45 I Platforms. Suopons and Stairs and Oesiqn

DBO/StecWeck

DBGm&eck 43 I Planf EnUSlte WFounlatbn: Engbteer

BSM. Inc.

WNLEE

J.T.THORPE

46 I Aefraaory Materials 8 Inna[laion: lnstalhlbn

47 I Refractory M e r i a h 8 lrmalkrbn: Materials I

55 b r k u n Burner IECUPSUYORKAIRE 56 I Start-uo EumerfMod. Motor)

I 5~ IStanuo eumer panel I WNLEE

js I ISIeam Silencer VIBRATION 8 NOSE SNGR

I I WNLEE

, I i 59 lSleelwork or Eouiornenr Suwon

70626

7m.34

wo

m

m12

7M)48

387648

m

m 7

7W13

7W14

a e i5 UI ul

-1 w a

m

11119193

7 R W

w

9 1 a 3 I 1m I I

I I I 8 R a s 3 ? -

I ! 1 60 l~ten~ization System I WNLEE , -7 ' 61m4 8/t% '

f ' 61 'Slenlizatmn Tesiinq !CCNLEE i W 9 w3m4

1 I

' was4

7Cc85 7/31/94 12'119J

63 Valves & O a m e r j .IPS icoia b31,94 7-94

)Elan 8 Myers I 2 mTranslorrnerlorLeb VA Eauiornenc

- DONLEE ENERGY SYSTEMS -

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 15

CONTRACT DE-FC21-91 MC27205

64 Vendor Euuiimw Insakulon

65 Comvte~fzed Portable A~YZEI -S

€6 Addkbnal paymermperformancs bonds ITSD

67 Onske refranory cure Hotworks

68 Bondlnq and Gmundlnq TBO

, 89 Sumo putnos ard controls

70 SleaWFeedwafer Valves IPS

I keden

71 Shredder l-bdraullc Fiker

72 AirCanmns IL. , 73 Noke Suoprebsbn: MoforElowers lBR0 NohNibratlon

74 H E ~ ~ S S Alr Ower

75 Orifices and vemns

78 Can for medlcal w e

I l;wmw;v Inc.

~CONSCLIDATEO PLASTIC CO

ZI I Slte l d e r rernal - 11 mornns

7E I MeatTracinq IDONLEE

79 I Added Llqhtlnq IDONLEE

80 Sumo PumDlContmls L E D E N I : 91895

IGE CAPmL MooULAR SPACE

I

I ' WlA5

I I 81 I Cal Gases and Aequlators lSCOl7 SPECIALTY

Table 1. Lebanon VA Project Equipment Status

EQUIPMENT VENDOR 0

a

a

z W 0

0 W : 0 a 2

70081

70032

swsd

ium

7Ml96

70191

xQ93

70102

7w98

YllrM

1017194

91A5

1115%

211595

1Ro195

12R0190

Y 1 W

Z1595

Z l S

112395

l W l W 5

1WlA5

1011595

1ZlA5

91A5 1 l l l l A 5 I !LAB SAFEiY 1 1 E? SlnWShower Oewmamination Starms

# I I I I 83 /Sand for Beds 'U.S.SILICA SANO m o ' : I

1 &i !Coal Pit Cover ' CONLEE 31595 , 11115~5 I

+ e5 :GnulyCover CONLEE 315995 1111595

- DONLEE ENEiiGY SYSTEMS-

/g

A FBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31, 1995)

Page 16

CONTRACT DE-FC21-91 MC27205

Table 2. Lebanon VA Project Costs-to-Date Reported by Task

TASK ACTUAL

Feb-95 Mar-95

TASK 1: DESlG NIB UI LDIl NSTALL

TASK 11: PERMITTLNG TASK 111: OBTAIN COAL, LIMESTONE

& ASH CONTRACTS

TASK IV: TESTING

TASK V: FINAL REPORT

PROJECT TOTAL 175,945.71 68,591.31 23,257.05

COST SHARE 13,037.62 2,938.28 (304.77:

DOE BILLING 162,908.09 65,653.03 23,561 .82

Feb-S5

Apr-95 ACTUAL QRTLY 48 49 TOTAL May-95 Jun-95

264,352.63 18,814.75 33,652.01

-

3

15,671.13 68.37 64.29

May-95

Jut-95

JuI-95 TOTAL I

262,124.61 314,591.37 I-

262,124.61 31 4,690.37

21,757.74 21,753.66 4 240,366.87 292,936.71

TO-DATE

CONTRACT COSTS

$5,212,086.08

$38,030.59

$44.098.29

$0.00

$5,610,170.69

$394,735.61

$5,215,435.08

- DONLEE ENERGY SYSTEMS-

3 3 m

siva-oi aiv

cf

z w > B

6 w

- !

- I I

I

- , L '

- i z

C: 3 1 r-

CI .7 I

c

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31, 1995)

Page 18

CONTRACT DE-FC21-91 MC27205

w

t so

so,

so, $25,000

so.

so

so so to

$2,012

$81,585

$117.398

522,202

so

Table 3. Lebanon VA Project Equipment Costs

EQUIPMENT ti s 3 m

P % 8 6 0 --

$8,352

$7,92?

$21,921

$C

$7,W

$2ol,l52

$123,355

$8 3,4 4 2

-3%!?E-

$130.378

$85.292

$245.W

$135,300

$8.llQ

8 ii i U U 3 0

$8.205

$8,784

$l9,42@

$25,oOa

$7,163

5297.203

$123.355

$97.001

-SM:WO

$138,444

$170,718

$305,348

$135,300

$6,548

- $lEJz&

$26,570

$135,200

$87,050

s1

P t

n B

9

E

w z a $1.853

$881

($2,493

S25.W

$183

$6,051

$0

$13,559

so $8,068

$105.424

$60,348

L $429

w 3 I- o 8

$8.20:

$8,784

$l9,42t

$(

$(

t297,20:

$123,35!

$97,001

52o.wc

5136,432

$109.131

$187,95C

S113.09t

w.54a

- DONLEE ENERGY SYSTEMS-

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 19

CONTRACT DE-FC21-91 MC27205

Table 3. Lebanon VA Project Equipment Costs

EQUIPMENT VENDOR

7 /1W

11/13/91

7/13/9

12/5/9

7127m

6/28/93

612819:

6/23/03

$26,C99

$12,709

$54.608

S14,ZW

$10,075

sa

$2,500

so

$4,347

$17,220

Sso.861

$5,000

S 2 5.8 6 2

5 1 3 . M

$54.80€

f14,29C

$10,025

$C

$38,6lE

$l.osc

54.097

$5,428

$so,881

..

,!%so( ...

S17.2X

S72.W

sa

UI 0

f

- DONLEE ENERGY SYSTEMS-

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (Mayl, 1995 - July 31, 1995)

Page 20

CONTRACT DE-FC21-91 MC27205

Table 3. Lebanon VA Project Equipment Costs

EQlJlPMENT VENDOR

$0

$545,700

$25,725

$0

$4,400

$52,915

$7976

$14,877

$4,597

-E $3.01Q

$24.240

$9,512

$629.578

$29,128

$10,911

2 ? l o o O

$88.7s9

$08,007

s 1 p . 8 T I

$4.382

$0

$3.140

$0

$0

$209.560

- DONLEE ENERGY SYSTEMS-

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 I 1995 - July 31 1995)

Page 21

CONTRACT DE-FC21-91 MC27205

Table 3. Lebanon VA Project Equipment Costs

EQIJIPMENT VENDOR tii 3 m

P

5 B m 0

-Em

$52,461

$5.650

$9,242

$266

53.413

-- FPIW

Se,!!!l

$?loo0

$8,ooo

514,334

$194,930

$0

- DONLEE ENERGY SYSTEMS-

@- i i a IT 3 0

2 . 2 0 0

$52,664

$5,650

$9,242

$268

$1,284

$3,065

-2!4316!?

-8!!!2

-$L?k!!.

$49,400

S?e.oes

$447,575

$4,836

$26.0m

c.

E P E 6 lil

2 a $

-A!

$202

E

E

$C

$1,264

-/$!E!

-$?!,E!!

-%

1 w 2 :

$41.400

$11,701

$252.845

$4,636

A FBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (Mayl, 1995 - July 31,1995)

Page 22

CONTRACT DE-FC2i -91 MC27205

Table 3. Lebanon VA Project Equipment Costs

EQUIPMENT VENDOR

11I4.Q~

1 1 m r

11118/9c

1012Wlli

--

12/8/84

l W 4

12/15/94

12/15/94

7/31/95

7/31195 SO S14 .W $0 $14.600 50 $14.500

- DONLEE ENERGY SYSTEMS-

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , I995 - July 31,1995)

Page 23

CONTRACT DE-FC21-91 MC27205

Bo

g!

e2

E

1

Table 3. Lebanon VA Project Equipment Costs

:!!!!2 _PU~CE!!!Ok - - RAEDEN

Cal Gasos and Ronulalors

g@S&o~! Damnoarnlngatn Siallons IAB SAFETY

SIllulforEOds - .. - U.S.SILICA SAND

coal P?cov!! . ~- __ . - . DONLEE

G r ! 9 Csvu! . - ... DONLEE

SCOTT SPECIALTY

PROJECT EQUIPMENT TOTALS . - . . . _* _---_ ~ ----.-

EQUIPMENT

11/1€W4

12/15/94

7/3/95

6123194

71305

7/3/95

VENDOR

$1

$c

$1

$1

$1

$1

$2,822.61;

B i i U n 2

$2,500

$4,530

$1.750

$2,387

$3.20(1

$ 4 , W

$3,704,770

$0

$0

$a

$C

$C

$C

$2,50C

$4,5X

$1,75(

$2,36i

$3,20(

$4,80(

$972.151

x $C

- DONLEE ENERGY SYSTEMS-

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 ,1995 - July 31,1995)

Page 24

CONTRACT DE-FCZI -91 MC27205

Table 3. Lebanon VA Project Equipment Costs

NOTES:

1. 2.

3. 4.

Items 1-28 and 30-64 were all part of the ori,ginal October 1993 Budget. Item 29 was added in March of 1994 prior to the s tm of the foundation. Items 20,45 and 62 have been modified and approved after the equipment installation started. Item 64 was formed from two previous items: “Vendor Equipment Installation” and “Vendor Equipment Installation: Rentals, etc.”

- CGNLEE ENERGY SYSTEMS -

$1

AFBC Co-Firing of Coal and Hospital Waste

Quarterly Progress Report (May1 , 1995 - July 31,1995)

Page 25

CONTRACT DE-FC21-91 MC27205

Lebanon VA Project Schedule

Lebanon VA Medical Center Project 1994

ID t lme o ~ a ~ n M I A I M I J I J I A I S I O I N I D I 1EOUIPMENT FABRICATION 1

Ea E

15 TRAINING PROGRAM 251d

16 PA DER PERMTAPPROVAL od 17 REFRACTORY CURE M

18 SHAKEDOWN 14d

19 STARTUP 2od

20 COMPLETrCPN 15d

21 STACK MONITORING 88d

22 FINAL AEPORT 67d I

1995 I 1996 I F ~ M ~ A I M I J I J I A ~ S ~ O ~ N I D I J I F I M ~ A ~ M ~ J ~ J ~ A ~ S ~ O ~ ~ En I m

I + i 1 i !

I

E - -

- DONLEE ENESGY SYSTEMS -