aes sonel kribi resettlement action plan...aes sonel kribi resettlement action plan report december...
TRANSCRIPT
AES Sonel
Kribi Resettlement Action Plan
Report December 2007
Prepared for:
the power ofbeing global
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Kribi Power Project . ISOMW Gas Plant and 225kV Transmission Line . Cameroon Resettlement Action Plan Final R e ~ o r t
Table of Contents
1 Introduction ..................................................................................... 6 I 1 Background to the Project . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.2 1-errns of Kzferwce for the FIftP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
I I' Objectives of Assiqr-rnent . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 . . . . . . . . 1 4 Scope of Work . . . . . . . . . . . . . . . . . . . . . . . 18
1.5 Str~lcture of Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I 2
2 Legal Framework .......................................................................... 13 2 1 Introduction & Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 2 Cameroon Legislative Frarnetvork 13
2.3 Cameroon Legislation . Standards and Guidelines relating to Kesett!~ment . !4
2 4 Land Titling and Registration Laws afid Policies in Cameroorl . . . . . . . . . . . . . . . . . . ^ 4
2 5 Legai and Adrniriistratlve Procedures Appiicable to :i?e Process o!
Resettlement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6 Administrative Author~ties 19
. . . . . . . . . . . . . . . 2.7 !n:ernat~ona Norms . . . . . . . . . . . . . . . . . . . . . . . 19 .
2.8 Comparisori of Cameroonian Go\~ernmerlt arid liVorid 8ank Policy c ! ~ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Resettlement . . . . . . . . . . . . . . . . 22
r r . . . . . . . . . . . 2.9 Entitlement Framework . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ir
3 Socio-Economic Assessment Methodology .............................. 33 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.1 Introduct~on .......... 33
3.2 Survey Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ? 6.
3.3 Survey Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4 Socio-Economic Baseline ............................................................ 39 . . . . . . . . . . . . . . . . . . . . . . . . 4.1 General Socio-Econcrnic Profile of The Project Area 39
4 2 Specific Socio-Economic Profile of the PAPS ~r : Edea and Kribi Subdl\~ision 04
5 Socio-Economic lmpacts & Respective Mitigation Measures .. 69 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2 Project Impacts 69
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.3 Impact Overview & Mitigation Measures 7<! . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5 .4 Entitlemefit Matrix 76
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.5 Project Att~tudes 8 Concerns . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.6 Perceived Project Benefits 87
......................................................................... 6 Budget and Costs 88 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 .1 Compensat~on Framework . . . . . . . 88
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.2 Financial Responsibility and Authority 89 6 3 Corrlpensation Rudy et . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 89
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6.A Physical Displacement 90 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6 5 Eco~omic Displacerrient 92
. . . . . . . . . . . . . . . . . . . . . 6 5 Inflatton arid Currzr~cy Variations . . . . . . . . . . . . . . . . . . . . . . 9.1
5 7 External Monitoring ar;a Eval~~aticn 34 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Scott Mlson December 200 7
Page 1
Kribi Power Project - 150hiW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5 E Total Comperlsation Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ...... . . . . . . . . 95
7 Institutions and Implementation Arrangements ........................ 96 -7 r intrx?uctior; . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ... . . . . . . . . . .. . . . . . . . . . . 06 .? ,.; i (.7rganizatior1al Urlits. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96
' . 3 Ovel-view ot lrnpiementing Orgarlisations . .. . , . . . .. . . . . . . . . . . . . . . . . . 97 -7 ,I
i. :, Pdanage!r:er;t Inforrnat~on System . . . . . . . . . . . . . . . . . , . . . . . . . . .. . . .. . . . . . . . . . , ' I 38 ; i, i ,., Cc;rr.irnuniiy Part!cipat~on . . . . . . . . . . . . . . . . . . . . . .. . . . . . .. . . . . . . . . . . . . . . . . .... 108 7 0 o C a ~ a c ~ t y St~ildrng.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109 .- -. ; :. 'Vijlnerable Feople . . . . . . . . . . . . . . . . . , .. . . ....... . . . ......... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110 , ?> ir, In7plernentatior1 Scheaule . . . . . ... . . . . . . . ... . .... ... . . . . . . . . . . . . . . . . . . 1 1 1
i> ?';!?:lo:i.torin;] at13 Evaiuat:cn . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 112 : <:
8 References .... .............................................................................. 1 16
9 Appendix ..................................................................................... 1 18 ('1 <.. :A.~:.>endix A: Pk!ot3~ av;l iL43pe. . . . . , . . . , . , . . . , . . ... , . . . . . . . . . . . . :1 113 ,. ,-'' :? .L A;?r?end!x B: The Scic-crion Prc?cess . . . , . . . . . . . . . . . . . . . . . ... . . . . . . .... . . . . . ...., . . 1 ? 9
" 3 -. 7 Apzi:nd~;f C: Addiiional Sccio-Economic characteristics of Project Area .... 121
!J A Apr;cr;dix D. h)c?finition of categories in cpen-ended questions . . . . . . . . . . . . . . 127 .~ ,- 2 2 Ap5c;ndix E: hle!hodolo~y used for Compensation i2alculalions . . . . . . . , . . . . . 1 SO
9 E Appendix F. Databse of affected people . . . . . . . . . . . . . . . . . . . . . . . , . . . . .... . . . . ? 31
i; 7 iii:.:pc+r;cljx C;: FocLis grc;ip transcr~yjt.;. . . . . . . . .. . . . . . . . . . . . . . . : 32 is Q ,\ppe~;dix 1-1. Q;iss:i,2cr;aire . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133
c; f > ,d -, :?r:;'cdix I . l'eims cf Referent.? tor the RAP. . . . . . . . . . . . . . . . . . . . . . . . . 134
Scott Wilson December 200 7
Page 2
Kribi Power Project . 150MW Gas Plant and 22SkV Transmission Line . Cameroon Resettlement Action Plan Final Report
List of Tables
Table 2.3.1 : Relevant Cameroonian Legislation ...................................................... 14 Table 2.7.1. World Bank and IFC Social Safeguard Policies ................................... 21 Table 2.7-2: International Social Development Agreements relevant to Cameroon 22
Table 2.8-1 Comparison between Cameroonian and OP 4.12 Resettlement Plan
Outlines ..................................................................................................................... 24
Table 4.2.1 - Gender Distribution in Project area ..................................................... 44 Table 4.2.2 - Sex of head of household in the Project Area ..................................... 45 Table 4.2.3. Location of household residence since the year 2000 .......................... 48
Table 5.3.1 -Category of affected assets ................................................................. 70 Table 5.3.2 -Types of Losses from Land Acquisition ................................................ 75
Table 5.4.1 - Entitlement Matrix for Direct Project Impacts ...................................... 76
Table 6.4.1 : Relocation Assistance Costs .............................................................. 92
Table 6.8-1 . Total estimated costs for compensation and associated relocation . . .
ac t~v~t~es .................................................................................................................. 95
Table 9.2.1 ESD - Number of Affected Households per Village ............................. 119
............................. Table 9.2.2 KSD . Number of Affected Households per Village 119
Table 9.2-3 ESD - Number of Affected Households per Village selected for the
Socio-Economic Survey .......................................................................................... 120
Scon W k o n December 2007
Page 3
Kribi Power Project . 150MW Gas Plant and 225kV Transm;ssion Line . Cameroon Resettlement Action Plan Final Report
List of Graphs
............................................................... Graph 4.2.1 - Ethnicity in the Project Area 46
...................................................................... Graph 4.2.2. Existing mother tongues 47
Graph 4.2-3 - Education Level per Subdivision .......................................... . . . . . . . . . 48 ......................................... Graph 4.24 - Diseases occurring in the last three years 51
.................................................................... Graph 4.2.5 - Main Place of Treatment 52 .......................... Graph 4.2.6 - Main Occupation in the Edea and Kribi Subdivision 53
................. Graph 4.2.7 - Secondary Occupation in the Edea and Kribi Subdivision 54 ............................. Graph 4.2.8 - Rearing of Animals in Edea and Kribi Subdivision 58
Graph 4.2-9 - Average Monthly Income Level of Head of Household per Edea and
Kribi Subdivision ........... .............................................................. . . . . . . . . . . . . . . . . . . . 58
Graph 4.2-10 - Percentage of Respondents in the Project Area with wealth assets 60
Graph 4.2-1 1 - Wealth Assets per Subdivision .................................................... 60 .......................... . Graph 4.2.12 - Sources of Household Water per Subdivisions .. 63
Graph 4.2-13 - Source of Fuel to Cook per Subdivision 64 ..................................... Graph 4.2.14 - Source of Fuel for Lighting per Subdivision 64
Graph 4.2.1 5 - Expenditure on Household Resource in the ESD ............................ 67 ............................ Graph 4.2.16 -Expenditure on Household Resources in the KSD 68
Graph 5.5.1 - New Location After Resettlement ...................................... . . . . . . . . . . . 82 ................................... Graph 5.5.2 - Reasons given for the location chosen above 83
Graph 5.5-3 - Main concerns regarding the project 83 Graph 5.6-1 - Project Benefits ........................................................................... 87
Scott Wilson December 200 7
Page 4
Kribi Power Project - 150MW Gas Plant and 225kV Transmission L~ne - Cameroon Resettlement Action Plan Final Report
Abbreviations
CEC DlPA DIRPECH DFl's DSCN ECAM l ECAM II ESD ESlA FA0 I FC INS KSD MlNEFl MINPAT NGO PAP
RAP UNDP ROW TOR SEB SW
Compensation Evaluation Commission Direction of animal production Direction of Fisheries in Cameroon Development Finance Institutions National Direction of Statistics and Accounting in Cameroon
First National Household Survey - Cameroon
Second National Household Survey - Cameroon Ed6a Subdivision
Environmental and Social Impact Assessment
United Nations Food and Agriculture Organization
International Finance Corporation
National Institute of Statistics
Kribi Subdivision
Ministry of Economy and Finance in Cameroon Ministry of Planning and Development in Cameroon Non Governmental Organizations
Project Affected People
Resettlement Action Plan United Nations Development Program
Right of Way
Terms of Reference Socio-Economic Baseline
Scott Wilson
Scon Wilson December ZOO 7
Page 5
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
1 Introduction
2,'l Background to the Project
1.1 .I The majority of electricity generated in Cameroon comes from hydroelectric
power stations. In 2006 Cameroon had installed electricity-generating capacity of 935 MW, of which about 80% was hydroelectric and 20% was
conventional thermal'. According to the Cameroon's Ministry of Finance's
Report of 2002, 46% of households have access to electricity of which 26%
are AES SONEL subscribers and 20% are fed illegally2. Due to existing frequent droughts, this access to electricity is often jeopardised by regular
power cuts.
1 . I .2 In order to increase energy supply and reduce the current shortages, AES
SONEL, the national power utility, has planned to invest more than $500
million between 2005 and 2009 to improve Cameroon's electrical
infrastructure.
1.1.3 It is under this investment umbrella that the development of the Kribi Power
Project is proposed as Cameroon's natural gas fired plant.
1.1.4 The Kribi Power Project comprises the construction of a 150 MW power plant fuelled with natural gas that will be located approximately 9 km north-east of
Kribi in the South Province and the erection of a I 0 0 km 225 kV transmission
line between this proposed plant and the existing Mangombe 225190 kV
substation at Edea in the Littoral province. In addition, there will be a new
step up substation at the new plant site (1 1 kV to 225 kV) and a new 225 kV
bay for connection at the Mangombe substation3.
1.1.5 'The project will be fuelled with gas from the Sanaga Sud gas field located approximately 14km offshore north west of Kribi.
' "Country Analysis Briefs -Chad and Cameroon" 2007. www.eia.doe.gov "'Conditions de vie des populations et profil de pauvrete au Cameroun en 2001 - Rapport Principal de I'ECAM 2 - AoGt 2002 ))
Scott Wilson "Environmental Impact Assessment Report for the Kribi Power Project, Cameroon" 2007
Scott Wilson December 2007
Page 6
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
1.1.6 The transmission line will be approximately 100 km in length with a 30 metre wide corridor with 15 metres from either side of the main axis of the
transmission line. This 30 metre wide corridor is called the right of way
(ROW).
1.1.7 The transmission line will go through the Littoral Province (35 km) and the
South Province (65 km). In the Littoral Province, the transmission line will
pass through 11 villages namely Apouh (APO), Koukoue (KOU), Beon (BEO),
Nlonamioh (NLO), Mbanda (MBA) Malimba Farm (MALF), Ekitel, 2, & 3, (EKI 1, 2 & 3) Ekite Pilote (EKIP) and Malimba Urbain (MALU). In the South
Province it will go through 15 villages namely Mpolongwe2 (MP02),
Bebambwe 1, 2 (BEB1 &2), Ebea (EBE), Fifindal & 2 (FIF1 & 2), Londji2
(LON2), Bipaga 1 & 2 (BIP1 & 2) Pama (PAM), Bivouba (BIV), Mbebe (MBE),
Elogbatindi (ELO), Dehane (DEH), and Bonguen (BON).
1.1.8 The 150 MW Power Plant will be located in Mpolongwe 2 within an area of
approximately 16ha.
1 . I .9 This project will be financed by the DFls and will therefore follow World Bank
and International Financial Corporation (IFC) guidelines and standards. In this context, the Kribi Power project was classed in the ESIA as a Category A
project under the World Bank OP4.01. This classification states that the
project will entail some economic or physical displacement as well as land
acquisition.
1.1.10 Due to the sensitive nature of economic and/or physical displacement and in
order to mitigate the impacts on the affected community's livelihood, the
project studied alternative plant and transmission line sites well as alternative
sources of fuel and gas. The conclusion of the study was that a gas-fired power plant located at Kribi with natural gas supplied from Sanaga Sud was
the least costly option with the least impact on the community's livelihoods.
1.1 . I 1 More in depth information regarding the degree of economic and physical
displacement of the project was identified during the Environmental and
Social Impact Assessment (ESIA). This was further complemented by the information obtained during the full land and property census undertaken in
May to June 2006 by the Compensation Commission. This Commission was established by the Kribi and Ed6a Senior Divisional Officers as specified by the Public Utility Decree signed by the Minister of State Property and Land Tenure for the Project.
Scoti Wlson December 200 7
Page 7
Kribr Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
1.1.12 The Compensation commission of each Province was headed by a President
and supported by a Secretary as illustrated below:
The Senior Divisional Officer of the Department (or its representative) - acting as the President of the Commission
The Departmental head of Service in charge of State Property - acting
as the Secretary of the Commission
With the following members:
The Departmental Head of Service of Cadastre
The Departmental Head of Service in charge of Urbanism and
Housing The Departmental Head of Service in charge of Mines and Energy
The Departmental Head of Service in charge of Agriculture
The Departmental Head of Service in charge of Routes
A Representative of AES SONEL
Concerned Deputies Parliamentarian Concerned municipal magistrates (mayors) Relevant traditional authorities (village chiefs)
1 . I . 13 The Compensation Commission concluded that approximately 680
households would be affected, albeit to different degrees. In other words the
same household could have had their crops, land or house affected or a
combination of these.
1.1.14 As a result of the households affected by the construction and operation of
the project a resettlement action plan is required. According to World Bank Operational Policy (OP 4.12), any project, which displaces andlor adversely affects more than 200 people, is obliged to produce a full Resettlement Action
Plan (RAP). AES SONEL requested Scott Wilson to undertake a
Resettlement Action Plan in full accordance with World Bank (OP 4.12) and
International Finance Cooperation (IFC) guidelines (PS 5).
"1.2 Terms of Reference for the RAP
1.2.1 The terms of reference (TOR) for the Resettlement Action Plan (RAP) were based on the World Bank's Operational Policy on Involuntary Resettlement OP4.12 and a copy is provided in Appendix 9.9. The OP4.12 requires impacts to be assessed and addressed that are caused by:
a) The involuntary taking of land resulting in:
Scott Wilson December ZOO7
Page 8
Kribi Power Project - 150MW Gas PIant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Reallocation or loss of shelter;
Loss of assets or access to assets; or
Loss of income sources or means of livelihood, whether or not
the affected persons must move to another location;
b) The involuntary restriction of access to legally designated parks and protected areas resulting in adverse impacts on the livelihoods of the
displaced persons.
1.2.2 The RAP is thus the required tool proposed to address and implement mitigation of the impacts of resettlement. In summary, the RAP includes
measures to ensure that the displaced persons are:
(i) Informed about their options and rights pertaining to resettlement; (ii) Consulted on, offered choices among, and provided with
technically and economically feasible resettlement alternatives;
and
(iii) Provided with prompt and effective compensation at full
replacement cost for losses of assets attributable directly to the
project.
(iv) Assisted in restoring or improving their livelihoods and standards
of living in real terms relative to pre-displacement levels.
(v) The RAP also provides an opportunity to identify development
options for the affected community such as employment and health etc.
1.2.3 As such, the scope of the study as dictated by the TOR includes but is not
limited to:
(vi) Detailed socio-economic sample survey of 250 affected
households;
(vii) Detailed RAP for all affected properties; and (viii) Independent valuation of the project affected household
belongings and properties for assessment of compensation;
1.2.4 In addition, the Environmental and Social Impact Assessment ("ESIA", dated
October 2006) for the power plant and transmission line stated that the World Bank's OP 4.10 on lndigenous Peoples applied to the project but did not provide further information about the lndigenous People affected or the nature
of the impact. The Cameroon Government's Minister of Environment and
Scott Wilson December ZOO7
Page 9
Kribi Power Project - 150MWGas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Protection of Nature noted this during the ESIA's assessment and the
concern was passed onto the World Bank.
1.2.5 As a result, the World Bank and IFC have asked AES SONEL to prepare a
community and lndigenous Peoples Plan ("CIPP") as part of the overall Kribi
power generation project to meet the requirements of Operational Policy ("OP") 4.10 and Performance Standard ("PS") 7, respectively, by addressing
the avoidance and mitigation of project impacts on lndigenous Peoples.
1.2.6 Furthermore, and as acknowledged in the request made by the World Bank to
AES SONEL, the Resettlement Action Plan ("RAP") is being developed to
address the direct impacts of land acquisition with respect to physical
displacement and loss of crop lands from the Right of Way of the
transmission line and Plant Site as required by the World Bank's OP 4.12 and
the IFC's PS 5. As such, neither of these circumstances directly impact on
the indigenous groups and therefore the impacts that the RAP will address
are separate from those to be considered by the CDP and vice versa. AES SONEL thus requested Scott Wilson to present a separate Socio-Economic
Baseline study of these indigenous groups, which is presented in Appendix A
of this RAP.
-I .3 Objectives of Assignment
1.3.1 The overall objective of the RAP is to identify detailed management and
mitigation measures to which AES SONEL will commit for addressing
involuntary displacement impacts caused by the construction and operational phases of the project. It also provides a framework and work plan for the
implementation of resettlement and compensation for affected people.
a .4 Scope of Work
1.4.1 In order to achieve the objectives set out above in Section 1.3, Scott Wilson
has undertaken the following activities:
1.4.2 Held consultative meetings with AES SONEL and relevant staff, with various
relevant government institutions such as the provincial government,
departments of agriculture, public works and forestry, as well as relevant NGO's working in the affected area and other relevant institutions such as the "The Voice of the Farmer" and the National Institute of Cartography.
Scott Wilson December 200 7
Page 10
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
1.4.3 Reviewed Cameroonian legislation on resettlement and compensation, and
relevant existing and pending resettlement/compensation policies or
practices. In addition, the relevant social safeguard policies of the World Bank
have been reviewed.
1.4.4 With AES SONEL's assistance, Scott Wilson has gathered and reviewed all
existing relevant documentation such as in house maps of the affected area, in house databases of the affected households, including the ESlA for the
Kribi Power Project undertaken by Scott Wilson in 2006 and the work completed by the Compensation Commission. In addition, external
documents relevant to Cameroon such as the Compensation Plan for Limbe,
the compensation plan for the Chad Export Project and the Chad-Cameroon
Pipeline EIA, were also taken into account.
1.4.5 A detailed socio-economic survey was undertaken of samples of the affected
population, ensuring that the different categories and groups of people were
represented (including the Kola indigenous ethnic group). More detailed information on the sampling methodology used and the results are presented in Chapters Two and Three of this report.
1.4.6 The purpose of this Socio-Economic Baseline (SEB) survey was to provide
information against which the impact of project and the implementation of the
RAP can be evaluated. As such, very detailed information on people's assets,
incomes, distances to key places and cultural or religious sites was gathered.
The main tasks of this SEB survey were to:
(i) Cross check the available information gathered during the census
of the divisional commissions in order to confirm the accuracy of
the data collected (namely the list of Project Affected People (PAPs) and their properties);
(ii) Establish Baseline Information (quantitativelqualitative) on affected
households including spouses, childrenldependantslrelatives,
health, land, religions, and economic and social data (sources of
income and livelihood);
(iii) Determine impact (quantitativelqualitative) of the project on the
family unit, health, land, and economic situation;
(iv) Assess impacts of losses incurred on both the affected households
and individuals, and identify accompanying or bonification measures for compensating affected communities orland socially vulnerable households
(v) Question the PAPs individually and record their preferred means of
compensation (money or in-kind).
Scott Wilson December 2007
Page I 1
Kribi Power Project - ljOMW Gas Plan! and 22jkV Transmission Line - Cameroon Resettlement Action Plan Final Report
1.4.7 Prepared a full Resettlement Action Plan (RAP) based on the validated
census information on the affected crops, land and properties including an
entitlement matrix and a proposed implementation plan for the management
of resettlement actions. In addition, include a monitoring and evaluation plan including monitoring indicators and baseline information to assess the
successful implementation of the RAP
1.4.8 Validated the methodology and rates used by the Compensation Commission for calculating the compensation for the affected buildings and
crops. The Independent Evaluator will analyse the rates used and propose a
fair market value for each crop (depending on its maturity) and each property (land, house) for compensation purposes.
I .5 Structure of Report
1.5.1 This Resettlement Action Plan for the Kribi Power Project comprises the following Chapters:
2. Legal Framework
3. Socio-Economic Assessment Methodology
4. Results: Socio-Economic Baseline
5. Discussion of the Socio-Economic Impacts and Respective
Mitigation Measures
6. Budget and Costs
7. Institutions and Implementing Arrangements
8. References
9. Appendices
Scon Wilson December 200 7
Page 12
Kribi Power Projecl- 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2 Legal Framework
2.1 Introduction & Background
2.1.1 In line with World Bank Operational Directive OP. 4.12 on Involuntary
Resettlement, the International Finance Corporation (IFC) Handbook for
Preparing a Resettlement Action Plan (RAP) and the PS5: Land Acquisition
and Involuntary Resettlement this section of the Kribi Power Project RAP
presents a policy, legal and administrative framework with:
A summary of the relevant Cameroonian Laws and customs that relate to resettlement;
An outline of the land titling and registration laws and policies in
Cameroon;
A description of the legal and administrative procedures applicable to the
process of resettlement including, administrative agencies responsible for
resettlement, land valuation, compensation and grievance redress
mechanisms;
A summary of the relevant international social agreements to which the
country is a party; and The identification of gaps between Cameroonian laws and World Bank
Group Policies, and describes project specific mechanisms to address these gaps.
2.2 Cameroon Legislative Framework
2.2.1 The Cameroonian hierarchy of norms comprises the Constitution,
International Treaties and Agreements, Primary Legislation, Secondary
Legislation, Decisions and Contracts. The legal framework in Cameroon is made up of legislative and regulatory instruments:
Legislative instruments are made up of Laws; and
Regulatory Instruments are composed of Decrees and Rules.
2.2.2 Laws are prepared by Sectoral Ministries and forwarded to the national assembly. During working sessions, these are adopted by members of parliament and later on enacted by the head of state.
2.2.3 The application of all legislative and regulatory instruments is compulsory for
all citizens and project promoters. These instruments are therefore provided
Scoll WiLFon December 200 7
Page 13
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
with sanctions for defaulters, which vary from prison sentences to fines,
dependent on the gravity of the fault.
2.3 Cameroon Legislation, Standards and Guidelines relating to
Resettlement
2.3.1 The relevant Cameroonian legislation relating to resettlement and land
requisition is outlined in Table 2.3-1 below.
Table 2.3-1: Relevant Cameroonian Legislation
Land Ordinance No. 74-1 of 6 July 1974 to establish rules governing land tenure - relating to Private and Public Property, National Lands.
Ordinance No. 74-2 dated 6 July 1974 - relating to the status of the public domain in Cameroon (the "Land Code").
Decree No. 76-166 dated 27 April 1976-relating to the management of the national domain (the "National Domain Decree");
Decree No. 76-167 dated 27 April 1976- relating to the management of the private domain (the "Private Domain Decree").
Compulsory Acquisition
Law no 85/009 of 4 July 1985 - Compulsory Acquisition of a Public Utility Decree (PUD) and payment of compensation for the Environment.
Ministerial Order No 01 3 W . 14.4/MINDAF/D220 and 01371Y.14.4/MINDAF/D220 of 26'h August 2005 - Declaring Public Utility for the Construction of the Kribi Gas fired power plant and the 225KV Transmission line from Kribi to Edea respectively.
Decree No. 8711872 of lW12/1987 implementing Law No. 8519 of 4/07/85 on expropriation for public utility purposes, Ministry of Town Planning and Housing - Relating to set up of the evaluation committee, public notification and public inquiry.
Valuation
Cultural Heritage
- - - - - - -
Decree No 200W3023 of 29/12/2006- Fixing the modes of Administrative Evaluation of The buildings in Fiscal Matters
Arrete No 009/MlNDIC/DPMPC Du 01/03/2004 - relating to the fixation of prices and tariffs for material, furntiture works and other services relating to Public Administration.
Decree No 2003/418 of 25/02/2003 - relating to the compensation payments I for crops destroyed by the construction of public utilities.
Law No 91/008 of 30 July 1991 - The protection of cultural and national heritage. This law identifies the procedures for protection of sites and materials of cultural and national heritage. It applies to cultural sites that may be found along the projected line corridor.
2.4 Land Titling and Registration Laws and Policies in Cameroon
2.4.1 Ordinance No. 74-1 of 6 July 1974 to establish rules governing land tenure - This law relates to rules governing land tenure. It categorises land into the following:
Scotl Wilson December 2007
Page 14
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
• Private Property - land that is held by private persons or entities in possession of a certificate of occupancy (the terms and
conditions of issuance to be determined by decree);
• Private Property of the State and other Public Bodies - includes personal and real property acquired by the State or public
body either without consideration or for a value consideration
according to the rules of expropriation for public utility and common law;
• National Lands - land that is not classed as public or private
property su b-divided into two categories • Lands occupied with houses
• Lands free of any effective occupation;
2.4.2 National Lands are administered by the state and allocated to customary
communities provided they are of Cameroonian nationality, peacefully
occupying or using the land. As such customary communities can apply for
land certificates in line with the provisions of the law.
• Public Property - comprises all personal or real property set apart
for either direct use by the public or for public services. Public
property is subdivided into two categories • Natural public property - Coastland waterways, subsoil
and air space • Artificial public property - roads, railways,
telecommunications, ports, national monuments, and
traditional concessions (chiefdoms)
2.4.3 Public property of the state is inalienable, imprescriptibly and non-attachable.
Land occupation or land use rights may be granted by the administrators of such lands as temporary or revocable rights.
2.5 Legal and Administrative Procedures Applicable to t h e Process of Resettlement
2.5.1 Compulsory Acquisition: Law No. 851009 of 410711985 on expropriation for purposes of public utility, Ministry of Town Planning and Housing (MINUH)
Scon Wilson December 2007
Page 15
Kribi Power Project - 150hfW Gas Plan1 and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.5.2 The above law relates to the expropriation of land for public use and the
modalities of compensation. As such the law defines that in order to achieve
the objectives of general interest, the Government may resort to expropriation
for public utility purposes (Article 1 Law No. 851009). The Kribi Gas fired
power plant and the 225KV Transmission line from Kribi to Edea has been declared as a public utility by public utility decrees (Ministerial
order no. 0001 36N14.4/MINDAF/D220 of
26/08/2005 and Decision No. 0001 37N14.4/MINDAF/D220 of 26/08/2005)
and is as such subject to Law No 851009.
2.5.3 In relation to compensation the law defines that expropriation (Article 3)
involving the transfer of property and land titles to the state, shall be subject to prior compensation in cash or kind in most cases. However, in certain
cases the beneficiary of expropriation may, prior to effective compensation, occupy the premises upon publication of an expropriation decree (after a six
month notice14.
2.5.4 The mechanisms for compensation defined within this law relating to serviced
and non-serviced land (Article 9) specify that;
Compensation for non-serviced land acquired under customary law that enabled the holder to obtain a title, will be no more than the
minimum official rate for non-serviced state-owned land situated in
the area the land title was issued.
Compensation for land (Private Land) acquired by normal legal transaction, shall be equal to the purchase price including costs
incurred in the transaction.
According to the Law No. 851009 of 4/07/1985 on expropriation for purposes of public utility, in case of emergencies the beneficiary of expropriation may, prior to effective compensation, occupy the premises upon publication of an expropriation decree after a three-month notice.
Scott Wilson December 2007
Page 16
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.5.5 In terms of compensation for crops (Article 10) the value of crops will be determined in line with Decree No. 20031418 and its additional clauses as determined by the established observation and evaluation committee set up
in line with the public utility decrees. In terms of compensation for housing
and materials, values are determined by Arrete No 009/MINDIC/DPMPC of 01/03/2004 relating to the fixation of prices for materials, furniture and other
works and services for Public Administration. This arrete sets compensation
values for materials that will be removed by the public utility, but does not
take into consideration market value of the building based on its location and
access to amenities.
Ministerial Order No 0136N. 14.4/MINDAF/D220 and 0137/Y.14.4/MINDAF/D220 of 26th August 2005
2.5.6 The two Public Utility Decrees declare the Kribi Gas fired power plant and the
225KV Transmission line from Kribi to Edka as public utilities. As such the
decrees identify the exact location of the gas plant and transmission line,
establish the ascertaining and assessment commission, define the scope of
works for the commission and the contents of the survey report to be
produced and submitted to Ministry of State Property and Land Tenure.
2.5.7 The mandate of the commission is to;
Delimit the concerned lands
Erect signboards defining the perimeter of the project
Ascertain rights, affected goods, owners and titled land
Commit, if necessary, a three-member technical sub commission to
evaluate crops and other valuable goods on the affected lands
2.5.8 The survey undertaken by the commission should include;
A survey report signed by all the members.
A bordering report and concerned lands plan showing the available
land titles, the lands in the process of obtaining titles, plots of public
property and the lands of state private property;
The various state of constructions, crops and other valuable goods
found in the different plots signed by the technical sub-commission
members and countersigned by the commission members; The rectification plans and reports of lands bordering or partly
affected lands with a land title or that are in the process of obtaining titles;
Scon Wlson December 2007
Page 17
Kribr Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
The copies and lands titles to be partially or entirely expropriated
and the files of those that are in the process of obtaining titles.
2.5.9 Decree No. 87/1872 of 16/12/1987 implementing Law No. 85/009 of 4/07/85 on expropriation for public utility purposes, Ministry of Town Planning and Housing
2.5.10 This law defines the makeup of various committees that are set up to ensure
that the affected populations participate in all inquiries. The law outlines that
(Articles 6,10 and 11) populations involved are informed within 30 days before
the date and time of any consultation via the notification of Chiefs and Elders.
The law defines that any inquiry must be undertaken in its entirety in the
presence of the owners of the property or assets in question.
2.5.1 1 Valuation
2.5.12 Decree No 20031418 of the 25th February 2003 defines the entitlement values
for crops and trees to be removed or destroyed by a public utility. The decree
defines values for leguminous plants, cereals, fruit trees, commercial crops
(cocoa, sugar cane, etc), citrus trees and medicinal plants. The decree
defines in some cases the value of an adult tree and a young tree (the
definitions of which are not specified). The methodology utilised to define
these values is omitted from Decree No 2003141 8.
2.5.13 Arete No 009lMINDIClDPMPC of the 1" March 2004 defines entitlement
values for materials to be removed or destroyed by a public utility but does
not take into consideration market value of the building based on its location
and access to amenities. .
2.5.14 Decree No 200613023 of 2911212006 relating to Fixing the modes of
Administrative Evaluation of buildings in Fiscal Matters includes methods for
the evaluation of housing and buildings for tax purposes taking into account
market values (December 2006) based on geographical location, buildings
and materials, access to services, construction materials used and location in relation to amenities. This decree is not yet in force but has been utilised in
the RAP as a more accurate tool for evaluating possible building values for the RAP budget.
Scott Wilson December 200 7
Page 18
Kribi Power Project - l5OMWGas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.5.15 Grievance and Dispute Resolution: In terms of redress in case of dispute
over the amount of compensation (Section Ill, Article 12 of Law No 851009)
the law defines that;
The expropriated party should lodge its complaint with the Ministry
in charge of Lands.
If the request is not satisfied the expropriated party shall refer the matter to the appropriate court within the area within one month of
the date of notification of the disputed decision. The court will then confirm, reduce or increase the amount of
compensation in accordance with the evaluation terms laid down in
this law and its implementing instruments.
Under Section IV, Article 14 of Law No 851009, any case pending
ruling, or subject to dispute, and any other real actions shall neither
halt the expropriation process nor prevent its effects.
2.6 Adrninistrative Authorities
2.6.1 The main administrative authorities that are responsible for resettlement are the:
Ministry of State Property and Land Tenure - Responsible for
reviewing the survey report undertaken by the Ascertaining and
Evaluation Commission and initial pre-judicial grievance redress
Local Courts - responsible for judicial grievance redress; and Ascertaining and Evaluation Commission - Responsible for
undertaking survey report in line with the Public Utility Decrees.
2.6.2 Common Practice in Cameroon
2.6.2.1 Past similar projects undertaken by AES SONEL in Cameroon such as the Limbe Power Project that have required involuntary resettlement and compensation indicate that PAPS prefer to obtain monetary compensation rather than replacement land and housing.
2.7 International Norms
2.7.1 Where appropriate for the RAP study, due reference is made to international standards in order to establish a regulatory framework for the RAP, which is
in line with local and international requirements.
Scott Wlfson December 2007
Page 19
Kribl Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.7.2 In addition to satisfying the requirements of Cameroonian legislation, it is
acknowledged that AES SONEL envisage financial support from the DFls.
Consequently this report has been prepared with reference to the World Bank
and International Finance Corporation (IFC) guidance.
2.7.3 The IFC, which is the private sector arm of The World Bank, is the largest
multilateral source of loan and equity financing for private sector projects in
developing countries. The IFC has various policy and procedural
requirements designed to ensure that the projects in which it invests are implemented in an environmentally and socially responsible manner.
2.7.4 The following IFC documents and policies which have been referred to in the
preparation of this RAP include:
lFCs Handbook for Preparing a Resettlement Action Plan lFCs 1998 Procedure for Environmental and Social Review
Projects;
lFCs Policy on Social and Environmental Sustainability (30 April
2006); lFCs Performance Standards on Social and Environmental
Sustainability (30 April 2006); and
lFCs Policy on Disclosure of Information (30 April 2006).
Scoti Wilson December 200 7
Page 20
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.7.5 Table 2.7-1 below outlines the IFCs's Performance Standards and World
Bank Safeguard Policies applicable to this RAP.
I Table 2.7-1 : World Bank and IFC Social Safeguard Policies 1 Title
PSI : Social and environmental involved in elaborating an effective assessment and social and environmental management
Relevance
Applicable, especially with regards to the grievance mechanisms to receive and address specific concerns.
PS2 Labour and Working Conditions
PS5: Land Acquisition and Involuntary Resettlement
Describes policy that restates principles of the current Forced Labor 8 Harmful Child Labor Policy through the prevention of unacceptable forms of labor, the promotion of fair treatment of workers and the assurance of a safe and health working environment and promotion of worker health
Describes policy and procedures involved for resettlement. Provides guidance on definitions, required approach, benefit eligibility, resettlement planning and instruments
Applicable, especially with regards to working conditions of the PAPS in the project.
Applicable, as the project will require resettlement both at the plant site and along the way leave of the transmission line
Applicable, as the project will require resettlement both at the plant site and along the way leave of the transmission line.
OP 4.12 Involuntary Resettlement
Describes policy and procedures involved for resettlement. Provides guidance on definitions, required approach, benefit eligibility, resettlement ~lannina and instruments.
Scott Wilson December 2007
Page 21
OP 4.10
OP 4.11
PS7 Indigenous People
Describes policy that ensures that the development process fully respects the dignity, human rights, economies, and cultures of Indigenous Peoples.
Describes policy that addresses physical cultural resources, which are defined as movable or immovable objects, sites, structures, groups of structures, and natural features and landscapes that have archaeological, paleontological, historical, architectural, religious, aesthetic, or other cultural significance.
Provides guidance to ensure indigenous peoples benefit from
Not Applicable for the RAP as the direct impact on the indigenous people is very low. Applicable for the Community and lndigenous Peoples Plan
Applicable as the project will require resettlement of places of worship such as churches and will affect tombs and graves through the reallocation of houses.
Not Applicable for the RAP as the direct impact on the
development projects and avoid or indigenous people is very low. Applicable for the Community and lndigenous Peoples Plan.
P
PS Cultural Heritage
through the reallocation of
Source: www.ifc.org, May 2006
Policy guidance on sites having archaeological, paleontological, historical, religious and unique natural values.
- Applicable as the project will require resettlement of places of worship such as churches and will affect tombs and graves
Kribi Power Project - I5OhfW Gas Plant and 225kV Transmrssion Line - Canzeroon Resettlement Action Plan Final Report
2.7.6 lnternational Protocols, Agreements and Treaties: In line with OP4.12, Table
2.7-2 identifies the lnternational Social Protocols, Agreements and Treaties to
which Cameroon is a party.
Natural and Cultural Heritage
Nature and Natural Resources
Table 2.7: lnternational Environmental Agreements relevant t o RAP in Cameroon
Convention on Protection of Natural and Cultural Heritage Ratified 1982
Cameroon Status
Party to.
Party to
Issue
Endangered Species
African Convention on the Conservation of Nature and Natural Resources Objective is to ensure the conservation, utilisation and development of soil, water, flora and faunal resources in accordance with scientific principles and with due regard to the best interests of the people (Algiers, 1968)
Convention and Objective
Convention on the lnternational Trade in Endangered Species of Wild Flora and Fauna (CITES) Objective: to protect certain endangered species from overexploitation by means of an imporVexport permits (Opened for signature: 3 March 1973, in force: 1 July 1975)
Convention on the Conservation of Migratory Species of Wild Animals
Ratified 29 September 1978
I Table 2.7-2: International Social Development Agreements relevant t o Cameroon 1 I I Issue 1 Convention and Obiective 1 status I
Women's Rights
Rights of Children
United Nations Convention on the elimination of all Forms of Discrimination against Women 1979 'For the purposes of the present Convention, the term "discrimination against women" shall mean any distinction, exclusion or restriction made on the basis of sex which has the effect or purpose of impairing or nullifying the recognition, enjoyment or exercise by women, irrespective of their marital status, on a basis of equality of men and women, of human rights and fundamental freedoms in the political, economic, social, cultural, civil or any other field.'
United Nations Convention on the Rights of the Child 1989. This outlines children's civil, political and basic human rights and includes their right to education and to end child labour and other forms of economic and or sexual exploitation.
Ratified, 23 August 1994
Ratified, C I January Igg3
Torture
2 3 Comparison of Cameroonian Government and World Bank
Policy on Resettlement
The Convention Against Torture and Other Cruel, Inhuman or Degrading Treatment or Punishment (1984) Objective to achieve the abolition of torture and ill treatment worldwide
2.8.1 The legislative requirements for compensation for involuntary resettlement in Cameroon are in general far less comprehensive than the objectives, measures and instruments contained within the World Bank
Acceded, 19 December 1986
Scott Wilson December 2007
Page 22
Kribi Power Project - l5OMW Gas Plant and 225kY Transmission Line - Cameroon Resettlement Action Plan Final Report
Involuntary Resettlement Policy, OPlBO 4.12 and IFC Performance Standard
5 (IFC PS5) -Land Acquisition and Involuntary Resettlement. The key tenets of the WB's OP 4.12 covered in part or full by current Cameroonian law
include:
Requirements to pay compensation in advance where land is
expropriated for public use (Law No. 851009);
Requirements to compensate for losses to productive assets and crops (Rule no 13-MINAGRIIDAG);
Requirements to inform and involve local communities and affected
persons;
Requirements to undertake a mapping and census survey exercise
to establish the rights, assets, land owners and tenure of displaced
people; and
Provision for prejudicial avenues for resolution of disputes and
rights of appeal.
2.8.2 The OP 4.12 and IFC PS5 obligations of the borrower or sponsor that extend
beyond those required under Cameroonian law are:
Extent of compensation and types of assistance offered
Categories of people eligible for compensation
Income restoration and assistance to displaced persons with their
efforts to improve their livelihoods and standards of living
The extent of resettlement planning and procedural requirements
Implementation of sustainable development programs to enable
project affected persons to share the benefit of the project.
Compensation based on the full replacement cost of lost assets
based on full market values and assistance to help improve
affected peoples standard of living
Ensuring that affected people are given security of tenure to their
new property.
Scon Wilson December 2007
Page 23
Kribr Power Project - 150MW Gas Plant and 225kV Transmrssion Line - Cameroon Resettlement Action Plan Final Report
2.8.3 Table 2.8-1 below is illustrating the gaps between Cameroonian Legislation and OP 4.12 in terms of the criteria to be included within a RAP.
E b l e y 8 - 1 Cbmparison between Cameroonian and OP 4.12 Resettlement Plan Outlines
~escription of the Project INA i OP 4.12 Resettlement Plan (Annex A, OP 4.12)
l~valuation of potential Impacts INA 1
Survey report (as defined by Cameroonian Legislation,
(occupants l ~ i ~ h t s affected goods, owners and titled land
-
Objectives of the Resettlement Program
Socio-economic Studies
Census Survey
\characteristics of displaced households valuate crops and valuable goods on affected land
N A
N A
Census survey
l ~ a ~ n i t u d e of expected loss lcopies of land titles
/lnforrnation on Vulnerable groups 1 and tenure Social interaction Public infrastructure Social and cultural characteristics of affected communities
~ e g a l Framework INA 1 institutional framework NA 1
(~nvironmental Protection and Management
Resettlement measures
Site Selection, preparation and relocation
Plans to Provide housing, infrastructure and social services
community Participation I
N A
N A
NA
Communities and all affected persons to be informed through public inquiry. 1
organizational responsibilities 1
Integration with host Communities
Grievance Procedures
/implementation Schedule I
N A
Formal Grievance and dis~ute mechanisms are in dace1
(costs and Budget 1 Monitoring and Evaluation N A
2.8.4 Measures required to ensure compliance with OP 4.12 will include:
Undertaking a full RAP in line with OP4.12
Where the tenets of OP 4.12 are partially covered by Cameroonian Legislation, such as public consultation, grievance redress and census surveying, AES SONEL will use both Cameroonian legislation and OP 4.12 as a framework for the full development of the RAP.
Scott Wilson December 200 7
Page 24
Kribi Power Proj'ecr - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.8.5 Public Consultation and Participation: OP 4.12 specifies that project affected
people should be informed about their options and rights pertaining to
resettlement and '...consulted on, offered choices among, and provided with technically and economically feasible resettlement alternatives' (Clause 6(i),
(11)). Additionally, the IFC has published guidelines for private sector developers on public consultation and disclosure.
2.8.6 A formal mechanism for public consultation is defined in Cameroonian
legislation (Law No 85/9), which defines that committees should be set up and every affected person informed of the project and the requirements for
resettlement. There are however no requirements for informing affected
people of their options and rights pertaining to resettlement. In order to ensure compliance with OP 4.12 this should be undertaken in addition to the
consultations outlined in the Cameroonian legislation.
2.9 Entitlement Framework
2.9.1 Introduction
2.9.2 The objective of the resettlement action plan is to avoid or minimize, to the extent possible, the hardships and impoverishment that the project may
cause, and to mitigate any adverse impacts at the household and community
levels. These objectives are detailed and made more specific in terms of the
principles and guidelines to be followed for adoption of an entitlement
framework and the planning and implementation of rehabilitation activities.
2.9.3 The RAP makes reference to the effort made to reduce project impacts
mainly through the analysis of alternative ROW considered in the Kribi ESIA
(Scott Wilson 2007). Where displacement is unavoidable the objective is to
ensure that sufficient resources are allocated to enable PAPs to regain and ideally improve their pre-project living standards through:
Adequate and appropriate compensation for private and community
assets; Resettlement and entitlement measures to enable PAPs to relocate homes or businesses; and Compensation against loss of income.
Scott Wilson December 200 7
Page 25
Krrb~ Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.9.4 Principles
2.9.5 The following represents a list of principles that form the basis for development of this RAP and will be used in the implementation of the
compensation process:
2.9.6 We will explore all possible means to ensure that impact on people by project activities is minimised. Specifically we will ensure that:
PAPs are consulted for compensation planning and throughout the
implementation phase;
PAPs are informed about their rights and options pertaining to
compensation, relocation and about grievance mechanisms available to
them;
Identification of PAPs takes place as per agreed eligibility criteria set out
in the RAP;
Lack of legal rights to land and assets occupied or used does not
preclude a PAP from entitlement to compensation and relocation
measures;
Compensation, relocation and rehabilitation measures are as fair as possible to all parties concerned and also minimise the long-term liability
of AES SONEL;
Project work does not commence on affected sites until PAPs have been
fully compensated andlor relocated.
2.9.7 Definition of PAP and Eligibility for Compensation and Rehabilitation
2.9.8 Under Section 14 of IFC PS 5, displaced persons who are entitled to compensation include persons:
(i) who have formal rights to the land they occupy;
(ii) who do not have formal legal rights to land, but have a claim to land that is recognizable under national laws (See section 2.9.5)or
Scon Wilson December 200 7
Page 26
Kribi Power Projecl- I5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
(iii) who have no recognizable legal right or claim to the land they occupy (including any new arrivals who occupy the land prior to the cut-off
date)
2.9.9 For Physically Displaced persons (i.e. persons who are required to move away from their land as a result of the project) AES SONEL will offer choices
among feasible options including adequate replacement housing (if in
categories (i) or (ii) this property will be of equal or higher value) or
compensation at full replacement cost and will provide physically displaced
people with relocation assistance.
2.9.10 For Economically Displaced People (i.e. land acquired for the project resulting
in loss of income regardless of whether or not physical displacement is
required) AES SONEL will promptly compensate for loss of assets at full
replacement cost as well as costs of re-establishing commercial activities
affected by the project. In addition AES SONEL will provide replacement
property of equal or greater value to displaced people with legal rights to their
land.
2.9.1 1 Economically displaced people without legally recognizable claims to the land
will be provided with compensation for lost assets other than land at full
replacement cost.
2.9.12 Cut-off Date
2.9.1 3 Cut-off dates determine eligibility of persons and their assets. Therefore, they
represent the actual da4e that the affected assets and infrastructure at a particular site were recorded during the census survey. Assets like land,
structures and others, which are created, encroached or acquired by individuals or groups, after the cut off dates, will not be eligible for
compensation.
2.9.14 The cut off date for the purpose of this RAP was agreed by AES SONEL as
being the 21'' and 22" February 2006 which are the dates the public
information and consultation process was publicly launched respectively by
the Kribi and Edea SDOs, followed by information meetings organised through each affected village following a schedule handed to each village
chief for publication.
Scott Wilson December 2007
Page 2 7
Kribr Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.9.1 5 Entitlements
2.9.16 Loss of Land
2.9.17 In line with the National Law No. 851009 of 4/07/1985, (Article 9)
Compensation for non-serviced land acquired under customary law5 that
enabled the holder to obtain a title, will be no more than the minimum official
rate for non-serviced state-owned land6 situated in the area the land title was
issued and compensation for land (Private Land) acquired by normal legal transaction, shall be equal to the purchase price including costs incurred in
the transaction. This means that if a person within a community purchases a land from another member of the community instead of from the state and
that, the land is currently not being serviced by the state (with no water
treatment or sewage for example), and it gets a land title for that land
afterwards (through the normal land titling procedures), compensation will be
given (as the person has a land title) but at the official rate for non serviced
state owned land (not at the cost of purchase).
2.9.18 This means that Compensation for bare non-serviced lands shall be carried
out under the following terms:
When it involved land acquired under customary law that enabled the holder to obtain a land title, the compensation shall not be more than the minimum official rate for non-serviced state-owned land situated in the area for which the land title was issued.
When it involves land acquired via a normal legal transaction or the acquisition of state-owned land, the compensation shall be equal to the purchase price, including the costs incurred in the transaction.
2.9.19 As such, only when the PAP does not have a land title or proof of a legal transaction in obtaining the land that he does not receive any compensation
for the land itself. Only what is on the land (e.g. crops, trees and buildings).
2.9.20 For this RAP, any displaced person that has either full, formal rights to the
land they occupy, or have a claim to the land that is recognizable under the
national laws, will be provided with replacement property of equal or greater
value with security of tenure or cash compensation at full replacement cost of the land and resettlement allowances.
2.9.21 Any displaced person that have no recognizable legal right or claim to the land they occupy will be offered a choice of options for adequate housing with
Customary law is generally derived from custom, meaning long-established practices that have acquired the force of law by common adoption or acquiescence
The state is not providing any services for this land such as water treatment and sewage
Scott Wilson December 2007
Page 28
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
security of tenure and, if they own structures and buildings, compensation at
full replacement cost as well as resettlement assistance where appropriate.
Any persons who encroach on the land after the cut off date will not be
entitled to any compensation.
2.9.22 In line with OP 4.12 preference will be given to land based resettlement
strategies based upon land for which a combination of productive potential, location advantages and other factors is at least equivalent to the advantages
of the land taken. Where land based options are not feasible, non-land based options built around opportunities for employment should be provided in
addition to cash compensation.
2.9.23 Loss of Income
2.9.24 Small Business Activities
2.9.25 Cameroonian legislation is silent on compensation for small business activities or trading along the ROW of the project. Any businesses situated along the ROW are likely to suffer disruption and loss of income during
resettlement.
2.9.26 In line with the principles of OP 4.12 (to ensure PAPS are not made any
worse off as a result of the project) any person owning a small business that
will lose of income or sources of income as a result of the project will be provided with options of full replacement cost for businesses and loss of
income, and with alternative locations situated in areas where infrastructure,
and public services are provided as necessary, to improve, restore and
maintain adequate levels of service for both displaced persons and their host communities.
2.9.27 Crops
2.9.28 Decree No 20031418 of the 25Ih February 2003 defines the entitlement values for crops and trees to be removed or destroyed by a public utility (See Section 2 - Legal Framework). During the survey of crops affected by the proposed
project undertaken by the Compensation Evaluation Committee (CEC), Decree No 20031418 was used to evaluate total compensation values for PAP'S.
2.9.29 Decree No20031418 defines prices for crops based on values established by the Prime Minister in 2003. The Decree does not indicate the methodology used for arriving at these values and as such it is assumed that these prices
Scon Wilson December ZOO7
Page 29
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
were obtained based upon market conditions during the 2002 farming
season.
2.9.30 In order for compensation values for crops to be in line with OP4.12 due consideration will be given to ensuring PAPs are compensated for lost
potential revenue from any agricultural activities. The values will reflect up to
date market prices. PAP will be provided with the full replacement cost of a
particular crop using the assumption that for (i) temporary crops it will take 1
year for PAPs to be fully resettled and producing them to the same level prior
to resettlement and (ii) for permanent crops such as trees, that the full time
duration of growth until it reaches the production years will be compensated.
This will vary according to each type of tree.
2.9.31 All crop owners will be given time to harvest crops prior to resettlement and
will be provided with compensation based on the full replacement cost of
crops.
2.9.32 Buildings
2.9.33 The Compensation Evaluation Committee (CEC) have valued residential
houses, small shops and associated structures during the Compensation
census. The valuation of various structures thus obtained form the basis for
determining the amount of compensation offered to PAPs, who will have the
opportunity of reconstruction on alternative land either in the vicinity or away
from the site according to their preferences. Many PAPs may also use this as
an opportunity for upgrading or expanding in comparison to their old
structures.
2.9.34 As PAPs will be relocated at short distances from the project sites, they may
continue to have access to social and public services and facilities that they
currently use, which exist outside the ROW. This applies to water supplies,
schools, health services, shops, transport services and other community services, such as religious groups.
2.9.35 As the distances involved will be very small in most cases, impacts normally
associated with relocation (such as breaking of community ties and impact on access to infrastructure and amenities) can be prevented. The close proximity of alternative land and sites should significantly reduce the impact of moving and is likely to have minimal permanent effect on the economic' and social status of the people affected.
Scon Wilson December 200 7
Page 30
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
2.9.36 Community Structures
2.9.37 Cash compensation will be provided for reconstruction of affected structures.
CEC have valued all structures, which forms the basis for alternative structures.
2.9.38 Community structures will be relocated in the vicinity of current locations, to
ensure that the existing users can continue to access the services. In
reconstruction works, preference should to be given to local labour in order to
give PAPS and other local people the opportunity to benefit from wages for their labour. The construction teams will work in close co-operation to ensure
that the replacement structures are in accordance with the preferences of the
local communities.
2.9.39 Graves
2.9.40 AES SONEL will ensure that due sensitivity is given to the location of any
graves along the ROW. Consultation with affected people will be undertaken
prior to construction and a program for graves developed which will ensure
that local customs are respected and at the very least access to these graves
are respected. No direct construction works are undertaken on any of the
graves along the ROW.
2.9.41 Construction Works
2.9.42 Construction activities may also cause some additional temporary or
permanent damage to land and assets that cannot be identified or quantified during RAP preparation. An example might be construction of access roads
resulting in the destruction of crops. Thus, wherever possible, the
construction teamlcontractor will repair the damage to the satisfaction of the
affected person. Affected persons with a claim should be required to
complete a compensation claim form and submit it to the Grievance Officer.
AES SONEL in conjunction with the construction teamfcontractor will then negotiate the required compensation measures with the sufferer, which may
include repairing the damage or payment of compensation in cash or kind.
Payment of compensation should be made promptly.
2.9.43 In order to minimise any additional damage from the construction activities, the contractorslconstruction team will be contractually obliged to incur any
Scott Wilson December ZOO7
Page 31
Kribi Power Project - 15OMW Gas Plant and 225kV Transmission Line - Canieroon Resettlement Action Plan Final Report
costs related to payments (with AES SONEL's assistance in the negotiations)
of additional compensation.
2.9.44 Other Measures
2.9.45 In order to address the impacts of resettlement in line with OP 4.12 (Article 6,
OP 4.12) displaced people will be
Informed of their options and rights pertaining to resettlement;
Offered support after displacement; and
Provided with development assistance.
2.9.46 The framework of OP 4.12 (Article 8, OP 4.12) includes arrangements for
vulnerable groups such as the landless, elderly, women and children as well
as indigenous peoples, the provisions of which are not covered under Cameroonian legislation. For this RAP
A review of the census carried out by the CEC was undertaken to
further identify vulnerable or indigenous peoples, and a framework developed for the resettlement of those groups.
2.9.47 The timing of compensation and resettlement is clearly defined in OP 4.12
(Articlel6, OP 4.12) that compensation and prior assistance will be awarded
prior to relocation, and the resettlement sites should have adequate facilities
where required.
2.9.48 An Entitlement Matrix has been developed for the RAP and is summarised in
Table 5.4-1 in Section 5.4.
Scon Wilson December 2007
Page 32
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
3 Socio-Economic Assessment Methodology
3.1 Introduction
3.1.1 To better understand the socio-economic baseline and potential impacts of the project, a detailed review was undertaken of two surveys that had already been conducted for the project.
3.1.2 The first survey was undertaken as part of the ESlA process and included
basic demographic and social information for 50 households. The ESlA
survey was carried out to assess the main impacts of the project and was a
key factor in identifying the need for a RAP. The results of this survey allowed Scott Wilson to construct the questionnaire used for the RAP in order to better
reflect the reality of the location.
3.1.3 Once the need for resettlement was established, AES supervised a full
census to enumerate the affected people, namely the compensation census.
This second census was undertaken by the Compensation Commission and
included a full survey of all the assets that were affected for each household
that was going to be affected or displaced. All the affected households were
given codes according to their affected assets (1.e. crops (CO), Buildings (BO)
and Land (LO)) and were mapped by AES SONEL. This survey thus provided
the exact number of households affected and displaced as well as a complete
detailed listing of buildings and crops. This information was provided to Scott Wilson for the development of the RAP.
3.1.4 In accordance with the World Bank and IFC requirements for a RAP a detailed sample socio- economic survey was conducted to obtain qualitative
and quantitative data on the livelihoods, health and education, daily routines
as well as preferenceslperceptions and attitudes of the affected communities, in order to determine the current standard of living of the affected people. This
specific survey will thus serve as a baseline from which to measure the true socio-economic impact of the project in the future. For ease of reference we
have named this last survey the socio-economic baseline (SEB) survey.
3.1.5 In addition to the PAP, the SEB survey was also extended to include the existing neighbouring indigenous communities such as groups formerly
known as 'Pygmies'. The objective of expanding this survey to these vulnerable communities was to understand their current relationship with the
Scott Wilson December 2007
Page 33
Kribi Power Pro~ect - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
affected communities so any potential impacts could be predicted and
mitigated, as necessary.
3.1.6 Still under the ambit of vulnerable groups, focus groups were held specifically for the households that were going to have their houses andlor graves affected. The main objective of these focus groups was to gather the groups'
main concerns regarding the relocation process, their needs and preferences.
3 2 Survey Approach
3.2.1 This draft RAP is being prepared in accordance with the standards and
procedures of the Government of Cameroon, environmental policy relevant to
involuntary resettlement and the WB, OP 4.12.
3.2.2 In order to be consistent with the WB's Disclosure Policy, the RAP will need
to be disclosed prior to appraisal. Disclosure will take place in Cameroon, as
well as the WB lnfo shop. In short AES SONEL will disclose the document in
country and forward a letter to the Bank authorising the latter to disclose the
document to the WB lnfo shop.
3.3 Survey Methods
A. Selection of Sample Households for the Socio-Economic Baseline (SEB)
Survev
3.3.1 The criteria for the eligibility of PAPS or households and displaced people is
dependent upon the location of assets in relation to the areas of direct land
take for the project. These areas have been confirmed according to the
distance from the main axis of the proposed power line. For the power line
any asset that falls within the 15 metre wide corridor either side of the main axis of the power line is considered to be affected and will be displaced. This
corridor, of a total of 30 metres in width and 100 km in length, is called the
Right of Way (ROW). For the Plant site, an area of 16 hectares has been
allowed. These areas are shown in the Photos and Maps section in Appendix
9.1.
3.3.2 The compensation census conducted by the Compensation Commission illustrated that 680 affected households fell under the area of land take for the ROW and plant site. In order to conduct a statistically significant socio- economic survey (i.e. within a 95% confidence level), Scott Wilson chose a
Scott Wilson December ZOO7
Page 34
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
sample size of 250 households, which represents approximately 36% of
affected people.
3.3.3 During the first field visit (May, 2007), the team of Scott Wilson consultants
reviewed the database of affected assets prepared from the Compensation Survey and provided by AES SONEL. Scott Wilson further developed this by
linking it with the ESlA survey in order to avoid duplication of households as
well as to enable the identification of the exact number of affected
households, independently of affected assets. This latter database was thus the basis for the random selection of the 250 households used for the SEB
survey.
3.3.4 The 680 households were grouped into their respective villages and
according to their category of affected assets. As such, the households were
divided into:
Households with land title Households with Land title and Crops
Households with Land title and House
Households with Land title, Crops and House Households with no Land title but have Crops
Households with no Land title but have House Households with no Land title, but have Crops and House
3.3.5 Consequently, the 250 households were distributed into their respective
village and by the above categories. A random selection of the 250
households per village and by category was then conducted. More detail of
the selection process is given in Appendix B.
3.3.6 Prior to the SEB survey, the chiefs of each village were informed in person by
the Consultants of the time and date that the team planned to visit the village
as well as of the names of the households that the team intended to survey.
3.3.7 For the indigenous groups, such as the Kola, that were outside the ROW but
were neighbours of the affected communities and would be indirectly affected
by the project, the SEB survey team first identified which villages they were located in. Information was then gathered from the respective village chief, which established the number of existing households in each village as it was planned to conduct interviews for 50% of the existing households.
3.3.8 In total the Kola are located among 4 villages in the South Province (Bipaga 1, Bonguen, Elogbatindi and Bivouba) and according to the traditional leaders
Scott Wilson December ZOO7
Page 35
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
of each village, there is an estimated total of 30 households. The survey team
conducted the SEB survey for 18 households (60%) of the estimated 30.
3.3.9 The SEB survey team comprised an experienced team leader, two senior surveyors and three junior surveyors. The SEB survey was undertaken
between the loth May and the 1'' June 2007. It was undertaken using an
extensive socio-economic questionnaire (see Appendix 9.8) that covered
several areas of the household's daily life, leisure time, education and health of the household, livelihood assets, income, main activities, religion, cultural
aspects, and others (see Figure 2 in Appendix 9.1)
B. SEB Survey instruments
3.3.10 The RAP study employed both quantitative and qualitative methods through
questionnaires, focus groups and semi-structured interviews.
3.3.1 1 Both the questionnaire and the focus groups with semi-structured interviews were developed in collaboration with the local consultancy team. The
questionnaire was adapted to fit the local context of the South and Littoral
Province and pre-tested on the 9th May for any errors and
misunderstandings. AES SONEL also assisted in the development of the
semi-structured interviews.
3.3.12 During the compensation census, 77 households in the project area were
identified as having one of their buildings destroyed orland tombs affected. Of
these 77 households, 71 households require their main house to be resettled
orland their tomb affected. As the main house provides protection to the
family unit7 and is considered to be the main physical asset, these
households were assume to be more vulnerable to the project and were therefore given additional assessment through the creation of focus groups.
3.3.13 Consequently, 14 focus groups ranging from 3 to 10 people were conducted
as well as semi-structured interviews with groups of two or more individuals.
Both the semi-structured interviews and focus groups had the aim of
capturing the main concerns, frustrations and needs of these people. Teams
of two people, of which one was the mediator and the other a note taker, conducted the focus groups.
' The main house is where basic key activities such as eating and sleeping are conducted by the family unit.
Scoll Wilson December ZOO7
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
3.3.14 The SEB survey's team was divided into three groups, namely groups A, B
and C. Each group was composed of one senior and one junior surveyor.
C. Data Analvsis
3.3.15 The data was inputted into an Excel database and transferred onto a
statistical analysis package - SNAP - where it was crosschecked for errors.
3.3.16 The data was analysed mainly using frequencies as well as cross tabulation.
The analysis was done by province not only due to the existing different
socio-economic characteristics of each Province but also their different
political and financial autonomy.
Scon WiLFon December 2007
Page 3 7
Kribi Power Project - l5OMW Gas Planr and 225kV Transmissron Line - Cameroon Resettlement Action Plan Final Reoort
Methodology & Quality Control of SEE Survev
3.3.17 During the socio-economic baseline survey, there were several quality control stages as described below and illustrated in Figure 3.3-1
below.
Figure 3.3-1-Stages of Socio-Economic Baseline Survey and respective quality control undertaken
Scon Wilson December 2007
Page 38
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4 Socio-Economic Baseline
4.1 General Socio-Economic Profile of The Project Area
Introduction
4.1.1 The project extends over two Provinces, the South Province and the Littoral Province. Both of these Provinces have certain climate, topography, soil types
and land use similarities, however they also differ greatly mainly in their resource endowment and socio-economic activities. This section will look at
the general socio-economic profile of both of these provinces separately.
4.1.2 This will be followed by the next section that will look at the socio-economic
characteristics of the project affected people in more detail. This will again be
dealt separately by Province.
Littoral Province - General Socio-Economic Profile of Littoral Province and Project Area
4.1.3 The Littoral province has a total surface area of 20,220km2, accounting for
4.35% of the total surface area of Cameroon. It is comprised of four divisions: Nkam (31.1% of the province area), Sanaga-Maritime (46.0%), Moungo
(18.4%), and Wouri (4.5%) and 24 Subdivisions (including the Edea
subdivision where the project is located) and 5 Districts (MINPAT, 2000). The Edea subdivision is further comprised of 11 villages affected by the project,
namely Apouh, Koukoue, Beon, Nlonamioh, Mbanda, Malimba Farm, Ekite 1, 2, & 3, Ekite Pilote, and Malimba Urbain. (Scott Wilson, 2006)
4.1.4 In 1987, the province had a population of 1,352,833 inhabitants according to
the National Census by the National lnstitute of Statistics, with an annual growth rate of 3.41% per annum. In 2005, the population of the Littoral
province was estimated at 2,704,131 inhabitants (National Institute of
Statistics, 1987). Also according to the National Census, in 1987 the Edea subdivision (ESD) had a total population of approximately 68,794 people and
it was estimated that this number would rise to 194,634 inhabitants in 2000.
4.1.5 Also according to the 1987 census; 82% of the population of the littoral province lived in the urban area with 84% living in Douala, Edea and along Douala-Melong road in the Moungo Division. The population density ranged
from highly populated subdivisions with more than 2,000 inhabitants per ~m~
Scon Wilson December 2007
Page 39
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
in Douala (Wouri Division) to less than 7 inhabitants per ~ m ' in Yabassi and
Yingui (Nkam Division), Mouanko and Ngambe (Sanaga Maritime).
4.1.6 The population is very young with an average age of 21.9 years and with 50%
of the population under 15 years of age. The birth rate is slightly lower in rural
areas (35 births per 1000 people) than in urban areas (36 births per 1000
people), but the gross mortality rate is much higher in rural areas (12 deaths
per 1000 people) than urban areas (9 deaths per 1000 people) (MINPAT,
2000).
4.1.7 According to MINPAT (2000) the unemployment rate in 2000 among young people (20-25 years) was 13% in urban areas of the province (with the
exception of Douala which is 23%), and 3,5% in rural areas. The national
unemployment level is 14,4%.
Economic Activity and Social Infrastructure of the Littoral Province and Project Area
4.1.8 As the economic capital of the country, Douala attracts most of the economic
activity of the province having most of the small to medium sized companies and industries. The second biggest industrial town in the Province is Edea
Town with two aluminium factories (ALUCAM & SOCATRAL) and two main
hydroelectric plants (EdBa and Songloulou), which are located on the Sanaga
River (MINPAT, 2000).
4.1.9 With regards to the agriculture and livestock sector, the Littoral Province
encompasses both large scale plantations that produce rubber, palm oil, fruits
and vegetables and which use modern techniques and provide employment
to the local population, as well as subsistence agriculture that relies on
traditional agricultural tools and animals with very little use of mechanised
equipment (MINPAT, 2000). The Littoral Province is considered the fourth
largest producer in Cameroon of Cocoa, the largest producer of Robusta
Coffee and the largest exporter of Bananas (MINPAT, 2000). The province
has a very high potential for livestock development but unfortunately the
sector is still very undeveloped (MINPAT, 2000).
Scott Wilson December 2007
Page 40
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.1.10 With regards to the existing social infrastructure, the majority of health and
education infrastructures are concentrated in Douala. However, all of the
villages in the Ed6a Subdivision have a primary school even though there
aren't any secondary schools with the exception of Ed6a. In addition, most of
the government and private clinics are concentrated in Ed6a (DSCN, 2001). In Ed6a there is one medical Doctor per 12,525 inhabitants compared to
11,690 inhabitants per Doctor for the Littoral Province as a whole (DSCN,
1998).
4.1.1 1 Douala and Ed6a are connected to the Cameroon Water supplier
(CAMWATER) for water however for the rest of the villages in Ed6a
subdivision, water is obtained from other sources such as the river or surface
water (MINPAT, 2000). Even though availability of electricity is more
widespread than piped water throughout the whole Province as well as in the
project area, the majority of the populations are still without connections
(DSCN, 1997).
South Province - General Socio-Economic Profile of South Province and Project Area
4.1.12 The South Province has a total surface of 47,191 ~ m ' , accounting for 9.93%
of the total surface of Cameroon. It comprises four Divisions: Dja et Lobo,
Mvila, Ntem and Ocean as well as 21 Subdivisions and one District (MINPAT,
2000). The Kribi subdivision - KSD (where the project is located) comprises
15 affected villages namely Mpolongwe 2, Bebambwel, Bebambwe2,
Londji2, Bipagal, Bipaga2, Ebea, Fifinda2, Fifindal, Pama, Bivouba, Mbebe,
Bonguen, Elogbatindi and Dehane (Scott Wilson, 2006)
4.1.13 The South province is the least populated province of the country with
373,798 inhabitants in 1987 (as per the National census by the National
Institute of Statistics), an annual growth of 1.9% (below the national average
of 2.9%) and an estimated population of 500,000 in 2000. According to the
National Census of 1987, Kribi Subdivision had a total population of
approximately 19,778 people and it was estimated that this number would rise
to 95,000 people in 2006.
4.1.14 Also according to the 1987 census, 67% of the population is rural with the
remaining urban population being concentrated mainly in the towns of Ebolowa, Kribi and Sangmelima. The population density ranges from low,
with 17 inhabitants per ~ m ' in Mvila Division to very low density with less than 12 inhabitants per ~ m ' in the other Divisions.
Scott Wilson December 200 7
Page 4 I
Krrbi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.1.15 The population is also very young with an average age of 14 years. 43% of
the population is under 14, 51% between 15 and 64 years old and only 6%
above 65 (MINPAT, 2000). Mortality rates in Kribi Subdivision are 0,14% and
0,15% in the South. Children's mortality rate (less than lyear) in Kribi is
0,0365% and 0,02816% in the South Province. The child mortality rate (1-5 year) in Kribi is 0,0184% and 0,01507% in the South Province (DSCN, 2001)
4.1.16 In 1999, the unemployment rate in Kribi was 50% and 49% in the South
Province. The employment rate for young people (more than 14 years) was
25% in Kribi and 17% in the South (MINPAT, 2000). The average annual
income per person in Kribi was 90,000F CFA and 100,000F CFA in the South
(MINPAT, 2000)
Economic Activity and Social Infrastructure of the South Province and Project Area
4.1.17 Presently, the South Province has very low economic activity when compared to its neighbouring Littoral Province. The South Province has three main
companies established, namely SOCAPALM, EMC-HEVECAM and the Chad-
Cameroon Gas Pipeline Project (MINPAT, 2000). In addition, Tourism is also
a growing sector in the Province mainly due to its 150km of Coast Line, the
biodiversity of Campo Ma'an' National Park and the existing camps (Perenco
Cameroun S.A, 2006)
4.1.18 'The South Province, albeit at a much lower level than its neighbouring Littoral
Province, has large-scale plantations that produce palm oil. These use
modern techniques and provide employment to the local population. There is also subsistence agriculture that relies on traditional agricultural tools with
very little use of mechanised equipments (MINPAT, 2000). The livestock
sector is almost non-existent, however the semi-artisanal Fisheries play a
very important role in the economy of the Province (Perenco Cameroun S.A,
2006). According to "Enquete Cadre, 1995" (1 995), 942 persons with different
nationalities were involved in a fishing activity and the people of Yassa,
Batanga and Bakoko consider it part of their cultural heritage.
Scott Wilson December 2007
Page 42
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.1.1 9 The South Province is considered as one of the least equipped Provinces of
the country with 1 doctor per 8754 inhabitants and 1 health centre per 2180
inhabitants. In addition, the teacherlstudent ratio is also the lowest in the
country (MINPAT, 2000). In the project area, most schools are found in Kribi
itself (including the only secondary schools in the subdivision). There is a primary school in Londji2 and a professional training centre (Don Bosco) at
Bebambwe. In some villages (Bipagal, Bipaga2, Ebea) children have to
travel long distances (5 to 8km) to reach the school8.
4.1.20 There are three health centres in Kribi subdivision, one in Londji2, one in
Fifindal and one in Elogbatindi. There is also a government and military
hospital in Kribi. In Londji2's health centre the consultation is free and drugs
are heavily subsidizedg.
4.1.21 Kribi is connected to the Cameroon Water supplier (CAMWATER) for water,
however, for the rest of the villages in Kribi subdivision, water is obtained from
other sources such as the river, boreholes or surface water. The percentage
of people connected to the water network is 15,96% in Kribi and 9,69% in the
South Province even though availability of electricity is higher than piped
water throughout the whole Province, as well as in the project area, the
majority of the population are still without connections (MINPAT, 2000). The
percentage of people connected to the electricity network is 13,8% in Kribi
and 15,6% in the South (DSCN, 1997).
According to data collected in the field According to data collected in the field
Scott Wilson December 2007 Page 43
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.2 Specific Socio-Economic Profile of the PAPS in Edea and Kribi
Subdivision.
4.2.1 Introduction
4.2.2 Unless cited, this section of the report is based on the information gathered
through the SEB survey using questionnaires as well as information gathered
from the focus groups (see discussion in Method 3.3, and 9.1 Appendix ).
Specific Socio-economic Profile of the Project Area
Edea & Kribi Subdivision
4.2.3 The average family size of the project area in the Edka Subdivision (ESD) was 5.9 family members, which is slightly above the national average
household size of 5.5 and the Kribi Subdivision (KSD) average size of 5.3.
The SEB survey showed that the family unit for both provinces consisted of
the head of household (of which around 84% stated they were married or
under a traditional marriage) with spouse (31% in ESD & 32% for KSD) and sons and daughters (38% in ESD & 50% KSD). Only 6.1 % of the
respondents stated they were widowed in the ESD as opposed to 4.5% of
respondents in the KSD
4.2.4 For both provinces, the SEB survey found that the affected population is quite
young with 39% of the population being under 15 years of age in the ESD as
opposed to 37% in the KSD.
4.2.5 When looking at the gender distribution in the project area both provinces
have an equal sex distribution. In other words most households consist of
50% males and 50% females (see Table 4.2-1 below).
Table 4.2-1 - Gender Distribution in Project area
4.2.6 However, when looking at the sex of the head of the household, this distribution changes significantly with the majority (81%) of the households
being headed by a male. The ESD has a slightly higher percentage of
Scott Wilson December 2007
Page 44
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
female-headed households than the KSD. One possible reason for this is that
the male heads of households are working in Douala and do not reside with
the family.
Table 4.2-2 -Sex of head of household in the Project Area
4.2.7 When looking at the main religion of the project area, there isn't a significant difference between the Edka and Kribi Subdivisions. The two main religions
mentioned were Catholic (68% of the population) and Protestant (16%).
Other religions mentioned included God's Assembly, Jehovah's Witness,
Neo-Apostolic, Pentecostal and Evangelist.
Female Total
4.2.8 It is also important to note that approximately 25% of the respondents in both
provinces stated the church as their main place of leisure, which gives an
indication of the importance of religion, as well as a religious place of worship to the community.
4.2.9 In the project area, five religiouslsacred locations will be affected by the
project albeit in different degrees.
19.8% 100%
4.2.10 In the ESD, two churches will be affected. These are:
17.5%
100%
The Diocece Catholique Mission of Edka located in Mbanda village; its
mains assets affected will be some of its crops. The Mission is also a land title owner for the land affected. The Galican Church located in Malimba Urbain village. Its affected assets
are the church itself with a 12m x 7m area, built with wattle and zinc
plaques. The Church is not a land title owner. (See picture 3 in Appendix
9.1)
4.2.1 1 In the KSD, three churches will be affected are:
Catholique Mission of Elogbatindi located in Elogbatindi village. Its main affected assets will be some of its crops. The mission is a land title owner for the land affected.
Scon Wilson December 2007
Kribi Power Project - I5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Adventist Church of the Seventh Day located in Ebea village. Its main
assets affected will be crops and the church itself, which is built from
planks and thatch roof. The Church is not a land title owner (See picture 4
in Appendix 9.1)
Presbyterian Church located in Bonguen village. Its main asset affected
will be its crops.
4.2.12 To minimise the project impact on the communities, the project must provide
full compensation at current market prices for the loss of crops, land (if land
title exists) andlor build an improved structure in a location previously
discussed and agreed with the church/mission leaders. This latter activity
must be completed before the existing structure is destroyed. In addition,
AES SONEL must assist the communities in obtaining new land as well as
incur any costs this may bring about (e.g. traditional gifts).
Ethnic Background and Mother Tongue
4.2.1 3 Cameroon has approximately 200 ethnic groups and hundreds of languages.
The Edea Subdivision consists of 9 main ethnic groups (namely, Bassa,
Mpo'o, Bassobalikol, Bavec, Ndjabane, Nyabi, Okak, Malimba and Sawa) and 13 languages whilst the Kribi Subdivision consists of 6 ethnic groups (Mbeti,
Maka, Batanga, Mabi, Baka and Kola) and 16 different languages.
Graph 4.2-1 - Ethnicity in the Project Area
Ethnic Grouos oresent in the Proiect Area
Ethnic groups I II Edea Subdivision II Kribi ~ u b d i v i s .
4.2.14 In addition, the main languages present in the project area were Bakoko, Bassa, Ewondo and Mabi. However, consistent with the Table above, the percentages of respondents that consider these languages as their mother
Scott Wilson December 2007
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
tongue differs clearly between the two subdivisions. The Table below illustrates that the ESD has a higher concentration of people that use Bakoko
and Bassa languages (from the Bassa Ethnic Group) whilst the KSD use
Ewondo (from the Mbeti ethnic group) and Mabi Languages (from the Mabi
Ethnic groups)lO.
Graph 4.2-2- Existing mother tongues
Languages Present in the Project Area
Languages 1 H Edea subdivision W Kribi subdivision 1
History o f CommunitylSettlement & Land Titles
4.2.15 Land is normally assignedlinformally sold to a new household by the
traditional/community leader or informally bought from another land occupier. However these occupiers are not recognised by law as being formal
landowners unless they obtain a formal land title (or provide proof of legal
purchase), which is not only a lengthy process but also an expensive one.
Furthermore, with regards to compensation, only landowners with land title or
proof of legal purchase are considered for compensation. Of the 681
households in the project area, only 54 have land title and are therefore
entitled to compensation for land loss.
4.2.16 In addition, as Table 4.2-3 below shows, approximately 78.8% of the family
members interviewed responded that they have been living in the same location since the year 2000, in other words a minimum of 7 years1'. This
means that the majority of the respondents are not only well established in
10 For more detailed information regarding the Ethnic and Language Groups, please see Appendix XX. " However, it is important to note that children under 7 years o f age were considered as not living in the location since the year 2000. As such, only 7% of the actual respondents (34% of the 21.2% of respondents that said no) actually lived outside the community after the year 2000.
Scoff WiLFon December 2007
Page 4 7
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
their community and particularly in the current location but have also
developed intricate social networks of support with their neighbours and other
family members.
Table 4.2-3- Location of household residence since the year 2000
4.2.17 Consequently, the resettlement may have a very big impact on people's
livelihoods as they may not only loose their established neighbourhood
support and community network but also need to obtain another land (which
is usually bought) before being able to build their new house orland cultivate
their crops.
4.2.18 The availability of idle land around the project area exists, even though as
mentioned above it usually has an owner. As such, AES SONEL must assist
the PAP in finding and negotiating the land. It must incur any costs that may
arise in obtaining this land, including for example traditional gifts. These costs should be part of the contingency costs under the overall RAP budget.
Economic Activity and Social Infrastructure of the Edea and Kribi Subdivisions
Household Education
4.2.19 According to the SEB survey undertaken in both subdivisions, the majority of
respondents have had some sort of formal education with approximately 45%
having undertaken primary schooling, 18% Middle School and less than 20%
High school and Middle technical School. 17% of the respondents stated they did not have any formal education (see Graph 4.2-3 below) or that they
didn't know their degree of education.
Graph 4.2-3 - Education Level per Subdivision
Scott Wilson December 2007
Page 48
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
None Primary Post Middle High Middle Technical Bachelor Above Don't Primary School School Technical High Honours Know School
V6U"C"AtionSL",h%l Ed Edea Subdivision
, 1 H Kribi Subdivision
4.2.20 As seen above, the education level of both provinces is fairly similar even
though there is a significant larger proportion of the population with primary
schooling in the ESD when compared with the KSD. This is probably due to
the larger number of primary schools that exist close to the project area within
this Province as well as due to the higher economic purchasing power in the ESD.
4.2.21 Given the proximity of the ESD to the economic capital of the country - Douala - one would expect a higher level of education among its residents,
however, the SEB survey showed that the KSD has in fact a higher
percentage of population with Middle School, High School, Middle Technical
and Technical School.
4.2.22 It is important to take into consideration this low level of literacy in the project
area as it can affect not only the compensation process but also the public consultation process. For example, people with low literacy levels will have
more difficulties in managing a bank account and the compensation package
received and will need additional guidance. In addition, the way information is
presented for informative and/or discussion purposes should be geared
towards more visual/oral means rather than written communications.
Household Health
4.2.23 The main diseases affecting all the members of the households in the last three years were Malaria, followed by different types of diarrhoea. Nevertheless quite a significant percentage (23% in the ESD and 30% in the KSD) stated they had not had any diseases in the last three years. When only focusing on the head of the household these figures change slightly as
Malaria becomes more predominant and there is a decrease in numbers in
Scotl M k o n December 2007
Page 49
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
the different types of diarrhoea, which suggests that this latter disease affects
children more. There was no mention of HIVIAIDS in either Province, which
might suggest lack of information regarding HIVIAIDS or an unwillingness to discuss it because of the associated stigma.
Scoti Wilson December ZOO 7
Page 50
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Graph 4.24 - Diseases occurring in the last three years
Subdivision mKribi Subdlv~s~on UHead of Household ESD HHead of Household KSD -
4.2.24 Furthermore, when asked about child mortality in the household over the last
three years, the SEE survey showed that a significant percentage of the respondents in the KSD (18% - compared to the ESD 10%) stated they had suffered from such a misfortune. Some of the main known diseases that were stated as being responsible were Malaria, Diarrhoea and Yellow Fever.
4.2.25 In addition, to the health status of the household, the SEE survey also
enquired about the main place of treatment. According to the respondents,
the main place of treatment was the local hospital followed by the bigger city
hospital. Only a very small percentage, in both provinces mentioned being
treated with traditional medication for the main diseases.
Scott Wilson December 2007
Page 51
Kribi Power Project - lSOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Graph 4.2-5 - Main Place of Treatment
4.2.26 With regards to the existing disabilities the SEB survey showed that only
around 4% of the population in the project area suffered from a disability. This
was similar for both the Edea and Kribi Subdivisions. Furthermore, the main disabilities mentioned were physical (46% for both provinces) followed by
visual (27% and 13%) and PsychologicallMental disabilities (15% and 17% in
the Edka and Kribi Subdivisions respectively).
4.2.27 Households that suffer from any kind of disability must receive special
attention by the project and should be dealt with on an individual basis in
order to minimise any disturbances brought about by the project and thus ensure a safe reallocation.
Economic Activities and Livelihood Options
4.2.28 This subsection looks at the different economic activities mentioned by the respondents in both the Edea and Kribi Subdivisions.
Scoff Wilson December 200 7
Page 52
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
/
4.2.29 As per the Table below, the main occupation mentioned by the respondents
during the household SEB survey was farming followed by student. In
addition, the Table below illustrates that agriculture, as a main occupation, is
more predominant in the ESD than the KSD. This might be explained by the
fact that the KSD has a higher percentage of students, unemployed and self-
employed people.
Graph 4.2-6 - Main Occupation in the Ed6a and Kribi Subdivision
Main Occupation in the Edea and Kribi Subdivision
4.2.30 The self-employed category includes activities such as tree cutter, hunter,
driver, fisherman, taxi driver, traditional healer, tailor, welder, hairdresser and
others. The main self-employed activities mentioned by the respondents in the Ed6a and Kribi Subdivisions respectively were commerce (39% and
36%), fishing (26% and 10%) and roadside selling of products (17% and
24%).
E 2 d
Scoti Wilson December 2007
Page 53
2 i Main Occupation .% Edea Subdivision .% Kribi Subdivision
Kribi Power Project - l5OMW Gas Plan1 and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.2.31 According to the SEB survey, 60% of the respondents had no other economic
activity besides the main activity mentioned above. However, the remaining
respondents mentioned a wide range of secondary activities that
complemented the main activity and brought additional income to the
household. The Table below illustrates the main secondary activities
mentioned (for additional Tables/charts/Graphs on this subject please see
Appendix A.2).
Graph 4.2-7 -Secondary Occupation in the Edba and Kribi Subdivision
Secondary Occupation in the Edea and Kribi Subdivision
( HEdea Subdivision (%) WKribi Subdivision ( O h ) I Secondary Occupation
4.2.32 According to the Graph 4.2-7 above and in line with the previous Graph 4.2-6,
the main secondary activities recorded are agriculture with the KSD having a
higher percentage of respondents (45%) than the ESD (37%) and hunting,
construction and fishing. The latter activity is only performed by the
respondents in the Kribi subdivision.
4.2.33 In summary, both Graphs above illustrate that agriculture and hunting are the
two main activities in both the Edea and Kribi Subdivision with more emphasis
on agriculture. These are supplemented by activities such as selling of the
products they produce.
4.2.34 The project will have an impact on both agriculture and hunting, which in turn will have a direct and indirect impact on peoples' livelihoods and subsistence.
Scott Wilson December 200 7
Page 54
Kribi Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.2.35 The direct impact on the livelihoods and subsistence of the household will be
caused by the loss of crops and trees as well as loss of forest. The indirect
impact will be caused by the loss of income brought about by the loss of
commerce due to lack of crops.
4.2.36 In order to minimize this impact, the project should provide full compensation
for the temporary crops over a period of twelve months instead of six months. The reason being that (i) different crops will start at different times of the year
some of which may overlap with project commencement and (ii) the time for
the compensation process, the finding of land, preparation of land and waiting
until collection of crops period should also be compensated. In addition, the
loss of income from loss of commerce will already be included in the
compensation as the compensation package was calculated assuming that
the household sold all of its production during that one year.
4.2.37 For the trees, compensation should be provided over the waiting period. In
other words, from the time the plant is planted to the time it starts producing.
Loss of Secondary Forest Area
4.2.38 Cameroon's forests have undergone extensive conversion, with half the
historic forest cover (cover that existed prior to extensive human disturbance)
cleared for farms and settlements. At least 20 per cent of the remaining
forests are degraded or secondary forests. Agricultural clearing and logging
are the primary causes of deforestation and degradation and logging has
significant environmental and economic consequences at both the local and
national level1*.
4.2.39 The accelerating pressure upon Cameroon's forests reserves not only has
widespread ecological impacts but it also severely disrupts the nature of local
communities and their day-to-day existence. This is particularly true for the
indigenous local communities such as the Baka and Kola groups (also known
as pygmy groups) that are mainly nomads, gatherers and hunters.
4.2.40 Deforestation and degradation reduce the availability and quality of the forest
products, which play a vital role in sustaining local livelihoods. These products are used not only as medicines, food, tools and building materials within local villages and households but are also used as an exchange coin in the existing
barter system between the indigenous groups and the non-indigenous
groups.
12 Hand On/ TVEIITDG. 2004. "Money Grows on Trees - Cameroon"
Scott Wilson December ZOO7
Kribi Power Project - 150MW Gas Plant and 225kV Transmissron Line - Cameroon Resettlement Action Plan Final Report
4.2.41 The project area, more specifically the KSD, is home to 30 households of
indigenous groups (namely the Kola), which have a high intrinsic dependency
on the forest resources (when compared to their Bantu neighbours).
4.2.42 In addition, and again depending on the degree of the project impact on the
existing forest resources, this might lead to a direct impact on the relationship
between the indigenous groups and their neighbours, the Bantu.
4.2.43 This latter impact is a consequence of their lifestyle as nomads travel
throughout the forest hunting and gathering. As mentioned above, the
cultivated foods, such as plantains and yams, are obtained from Bantu
villages in exchange for meat or plantation work. The barter system also
extends to tools, clothes and pots. With the deforestation caused by the
project, the gap between the Bantu and the Kola could widen, as the Bantu
own land and the Kola do not. This is could be further aggravated as
compensation payments for people directly affected by the project will occur
whilst the Kola whose livelihood depends on the forest, receive nothing.
4.2.44 The project will closely follow the main Edka - Kribi road and will destroy a
total area (in both ESD and KSD) of 300ha composed of secondary tropical
forest (30-40% of the route), fallow lands (40-50%) and subsistence farms
(20%). The KSD will account for 65% of the route (i.e. equivalent to 195ha
area) of which we assume that 40% is forestland (i.e. equivalent to 78ha over 65km).
4.2.45 In addition, given that the intensity of human intervention diminishes as the
distance from the road and their settlements increases, then it is safe to
assume that the existing secondary forest near the road has already suffered
extensively from human intervention. As, the Kola communities are living next
to the road, it is assumed that for their main timber and non-timber forest
products, that they travel deeper into the forest.
4.2.46 As a result, given that (i) that the project will follow the road and thus affect the secondary forest next to the road (ii) there are only 30 households of the
Kola group in the project area and (iii) that only 78ha over a 65km distance
will be affected it is believed that this impact is not only very significant but
also localised.
4.2.47 Nevertheless in order to minimise any possible potential impact, Scott Wilson, upon request from AES SONEL, has gathered additional socio-economic information on the existing indigenous households in the project area. This
Scon Wilson December 200 7
Page 56
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
information should be further investigated to determine the need for a community and indigenous peoples plan for these existing indigenous groups in the project area. This detailed information is presented in Appendix A.
4.2.48 Recognising the extreme vulnerable status of the indigenous groups, it is
recommended that the project take a few measures to help ameliorate the
indigenous group's status. As such, it is recommended that:
The indigenous group members are given priority with regards to
employment opportunities during the construction and operation phases of
the project, as well as during the RAP implementation phase.
The project helps the indigenous group members to obtain their Identity
Card
lndigenous group members are given priority with regards to any skills
enhancement training provided by the project
lndigenous groups are well informed and given priority of any income
restoration schemes undertaken by the project
lndigenous groups are well informed and part of any community
development scheme undertaken by the project (e.g. improvement of
health facilities, etc.)
lndigenous groups are part of the relevant stakeholders group consulted
during community consultations.
Animal Rearing
4.2.49 Another source of income is the raising and selling of animals such as chickens, ducks, goats, cows, and others. 46% of the households interviewed said they reared animals (40% ESD and 60% KSD). However, only 19%
reared the animals for selling with the remaining 81% rearing them for own consumption. The main animals are chickens (72%), goats (11%) and pigs
Scott Wilson December 2007
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
(10%). For additional TableslChartslGraphs on livestock rearing and selling please see Appendix 8.2.
Graph 4.2-8 -Rearing of Animals in Ed6a and Kribi Subdivision
Rearing of Animals in the Project Area
5 Animals I Littoral Province Southern Province I
4.2.50 AES SONEL should assist the reallocation of the animals and if any animal is
injured due to the reallocation, AES SONEL should provide the adequate compensation at current market prices.
Income Levels
4.2.51 Taking into account all of the activities mentioned above, the average monthly
income per head of household is shown below. Please note that this is an
underestimation of the real average monthly income, as it does not take into account income generated by the other family members such as the children or the wife.
4.2.52 The average monthly income level of the head of the household is higher for
the ESD compared to the KSD. As Graph 4.2-9 below illustrates, the KSD has a higher number of households with an average monthly income of less
than 25,000CFA (equivalent to approximately 52USD) than the ESD, which has a significantly higher number of households with a monthly average
income of more than 100,001CFA (approximately 208USD).
Graph 4.2-9 -Average Monthly Income Level of Head of Household per Ed6a and Kribi Subdivision
Scott Wilson December 2007
Page 58
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Average Monthly Income Level, of Head of Household per Province
Less than Between Between Between More than No income 25,000 CFC 25,001 to 50,001 to 75,001 to 100,001 CFC
($52) 50,000 CFC 75,000 CFC 100,000 CFC ($208) ($52-$104) ($104-$156) ($1 56-$208)
Average Monthly Income Range Edea Subdivision Kribi Subdivision
4.2.53 As the Graphs above illustrate, the existing notion of the income levels of the
present affected households is very low which could indicate that the
household is not used to managing large sums of money.
4.2.54 In order to mitigate this impact, it is recommended that AES SONEL:
Provide compensation in kind, whenever possible, especially with
regards to land acquisition, building of structures, provision of seeds,
clearing and preparation of land for crop production.
Provide the option to the PAPS of setting up a long-term compensation
process where the compensation package is made up of assets and
cash. This long-term compensation could be given seasonal or
annually depending on the nature of the asset (e.g. loss of crop
production or loss of fruit trees production). This will not only reduce
the amount in cash being given to the household at any one time but it will allow the household to make its adjustments every month in
relation to money management.
Indicators
4.2.55 Household wealth is a very good indicator of project impacts, especially positive impacts as people that are better off tend to acquire more material
Scotr Wilson December 2007
Page 59
Kribi Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
assets. However in order to measure this potential impact, an image of the current wealth of the household in the project area must be obtained. In order to achieve this the questionnaire asked the household if they had certain assets that ranged from luxury assets such as mobile phone, N, Stereo to more basic assets such as a mattress and agricultural tools. As seen in the Table below, the main assets mentioned by the respondents in the project area were BedIMattress (94.7%), Radio (73.9%), Watch (72.3%), Mobile (62.10%) and Electricity (46.6%) (See Graph 4.2-1 0).
Graph 4.2-10 - Percentage of Respondents in the Project Area with wealth assets
Does the household have any of the following assets?
" 4,be0+9cP ,j8 ,eQ
+* % of respondents that answered yes Assets
4.2.56 It is clear that both Subdivisions have similar patterns of wealth. Nevertheless, the ESD seems to be slightly wealthier than the KSD as it has a higher percentage of respondents with luxury assets such as Electricity, N, Video, Mobile, Watch, Motorcycle, Kerosene Stove, Gas Stove and Generator. More basic assets such as Radio, Mosquito Net, and Bicycles are found more in the KSD (See Graph 4.2-1 1 below).
Graph 4.2-1 1 -Wealth Assets per Subdivision
Scon Wilson December 200 7
Page 60
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Wealth Assets
Location of new landlstructurelcrop
4.2.57 The location of the new landlstructurelcrops is a very important factor in
household stability and well-being. There are several key elements that must be taken into consideration when looking at new locations. These are
proximity of education and health centreslfacilities, proximity of essential household resources such as water, fuel, forest, markets, existence of
electricity, proximity of already existing social networks and proximity to
access roads. These are illustrated below with respective time and means of travel indicators for measurement of project impact in the future.
Education and Health Structures
4.2.58 The location of the school and the health facilities is an important factor to consider when reallocating households from one area to another, as it could
influence household income and safety. E.g. if they must pay for transport due to the increased distance from schoollhealth centre. Similarly safety may be impaired, as longer distances will increase the likelihood of accidents.
Indicator
4.2.59 Currently the majority of people from the KSD travel 5 to 30 minutes to get to school whilst the majority of people living in ESD will travel 30 minutes to 1
hour. In addition, if you live in ESD then the results show that you are 7.5% more likely to travel over 1 hour to get to school. Furthermore, the main
Scott Wilson December 2007
Page 61
Kribi Power Project - l5OMW Gas Plant and 225kV Transmissron Line - Cameroon Resettlement Action Plan Final Report
means of travel is walking. This time and mean of transport indicator is useful
to measure project impacts.
Household Resources
4.2.60 The buying or fetching of water, fuel for lighting and fuel for cooking is a very
important part of the daily household routine and is considered here in greater
detail.
Water
4.2.61 The SEB survey found that when looking at the main source of water, there
were significant differences between the Edba and Kribi Subdivisions. As
seen in the Graph 4.2-12 below, the ESD has a wider distribution of water
sources with the main sources being the RiverlLakes (34%), followed by
ground sources of water (lgOh), tap water in the yard (17%) and boreholes
(15%). Only a small percentage mentioned wells and water from their
neighbours.
4.2.62 The KSD has a much wider percentage of respondents using water from the
riverllake for their household consumption (71% in comparison to 34% in
ESD). However, the respondents in the ESD use a wider range of water sources with 19% obtaining water from their neighbours, 17% from taps in
their yards and 15% from boreholes. None of the respondents in the project
area mentioned tap water inside their house.
Scon Wilson December 200 7
Page 62
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Can~eroon Resettlement Action Plan Final Report
Graph 4.2-12 - Sources of Household Water per Subdivisions
Source of Household Water
4." 8 8 $8 ,8 ue eb" TO ;r e'5 ;re4 3e+ s6e pa 8 o&Ge
;re ;.C +ae $3 b5
$8 GO && '$3 -8 & <aQ Sources of Water .+
<aQ 1 . Edea Subdivision . Kribi Subdivision 1
4.2.63 When choosing the new location for resettlement, the project must thus take into consideration the existing water sources nearby in order to minimise the impact of time spent fetching water.
Indicators
4.2.64 When asked about the time it took to collect the water as well as the means of transport, the majority of respondents in the ESD stated they took between 5 to 30 minutes to fetch water (53%) whilst 25% stated they took less than five minutes. The main means of transport recorded is walking (94%). Similarly to the ESD, 61% of the respondents from the KSD stated that they take between 5 and 30 minutes whilst 21% mentioned that they took between 30 and 60 minutes. In the same way as above, 99% of the respondents mentioned walking as their main mean of transport.
Fuel used for cooking and lighting
4.2.65 The majority of respondents use wood as the main source of fuel for cooking. Only a very small percentage use gas. Gas and kerosene are the main sources of fuel for lighting for both Subdivisions (See Graph 4.2-13 and Graph 4.2-14 below).
Scon Wilson December ZOO 7
Page 63
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Graph 4.2-1 3 - Source of Fuel to Cook per Subdivision
Sources of Fuel to Cook
Woodfuel Charcoal Gas Diesellpetrol Electricity Kerosene Other
Graph 4.2-14 -Source of Fuel for Lighting per Subdivision
Sources of Fuel for Lighting
Sources of Fuel
woodfuel Charcoal Gas Diesellpetrol Eledritity Kerosene Other
Sources of Fuel for Lighting
IS4 Edea Subdivision Knb~ Subdlv~s~on
1 Edea Subdivision Kribi Subdivision 1
4.2.66 Again, when choosing the new location the project must take into
consideration the existing fuel sources nearby in order to minimise the impact on time and income lost fetching or buying fuel. In addition, with the forest
loss as a result of the project, an increased pressure on the remaining resources (e.g. fuel wood) will occur.
Indicator
4.2.67 When asked about the time to collect fuel to cook as well as the means of transport used, the majority of respondents in the ESD stated they took between 30 to 60 minutes to collect the fuel (43%) whilst 30% stated they
Scott Wilson December ZOO7
Page 64
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
take between 5 to 30 minutes. 29% mentioned it takes more than one hour to
get the fuel. The main means of transport mentioned is walking (75%)
followed by Taxi (12%). Similarly to the ESD, 61% of the respondents from
the KSD stated they take between 30 to 60 minutes whilst, 28% stated they
take more than one hour. Similarly to water collection, 94% of the
respondents recorded walking as their main means of transport.
4.2.68 Similarly to the cooking fuel, when asked about the fuel for lighting the
majority of respondents in the ESD stated they take between 5 to 30 minutes
to collectlbuy the fuel (51%) whilst 35% stated they take between 30 to 60
minutes, however with regards to the means of transport, 64% of the
respondents mentioned a taxi as opposed to only 30% mentioning walking.
4.2.69 For the KSD, the figures change slightly with 38% of the respondents taking
between 30 to 60 minutes to collectlbuy the fuel and 32% taking between 5 to
30 minutes and 26% taking more than one hour. With regards to the main
means of transport, 63% and 31 % use taxi and walking respectively.
4.2.70 This change in means of transport towards the taxi in both Subdivisions might
be due to the fact that the main source of fuel used for lighting is gas and
kerosene and this needs to be bought in commercial establishments which
are located further away than the forest or river,
Leisure Activities
4.2.71 Even though, household resources and health and education infrastructure
are very important for the household's stability, it is important to also take into
consideration leisure activities. When asked about the household's main
leisure activities, the majority of the respondents answered that they spend
their free time in the house (43%), at the church (25%) and playing sports (14%) or at friend's house (12%). When comparing, the average time to get
to the place of leisure as well as the means of travel, 56% of the respondents
take less than 5 minutes to reach their destination and use walking as their
main mean of travel (90%).
4.2.72 Consequently, proximity to the neighbours and friends as well as sports fields
should be taken into consideration when looking at alternative locations.
Furthermore, the project will go through two football fields of which one belongs to a Public School in Fifinda 1 village and the other in Bivouba village both of which are in the KSD.
Scon Wilson December 2007
Page 65
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
4.2.73 It is recommended that AES SONEL compensate both fields in kind through improved football fields as an added benefit to the communities.
lndicator
4.2.74 When comparing, the average time to get to the place of leisure as well as the means of travel, 56% of the respondents take less than 5 minutes to reach their destination and use walking as their main mean of travel (90%'~). This is
in line with the Table above that demonstrates that the majority of leisure
activities occur in the house.
lndicator
4.2.75 Another very important indicator of the project impact on a household's
livelihood and standard of living is the expenditure on household resources.
For example, a project impact could maintain, decrease or increase expenditure on household resources. This could be deemed positive or
negative. It will be important to analyse what factors determined this increase, if these were due to a rise in income and better quality sources of household resources that require payment or greater distance to the resource source.
The baseline information for this indicator is given below by Subdivision:
EdCa Subdivision
4.2.76 According to the Graph below, the majority of respondents don't spend
anything for either water or fuel for cooking. This is due to the main sources of water and fuel being the river and forest. Both of these sources are normally
free. However, when looking at the fuel for lighting (mainly gas and
kerosene), the majority of the respondents in the ESD spend a monthly
average of between 1001 to 5000CFA (equivalent to US$2.1 to US$10.5).
Scotl UWson December ZOO 7
Page 66
Kribi Power Project - I5OMW Gas Plant and 225kY Transmission Line - Cameroon Resettlement Action Plan Final Report
Graph 4.2-15 - Expenditure on Household Resource in the ESD
Expenditure on Household Resources in the Edea Subdivision
Nothing Less than 500 Between 501 to Between 1001 to More than 5001 CFC 1000 CFC 5OOOCFC CFC
Kribi Subdivision
Expenditure
4.2.77 Following the same trends as the ESD, the Graph below illustrates that the
majority of the respondents incur a monthly cost between 1001 to 5000CFA
for the fuel used in lighting (equivalent to US$2.1 to US$10.5). However, the
ESD spends more on water and fuel for cooking when compared with the
KSD indicating among other things that the ESD has a higher expenditure
than the KSD.
W Water Fuel for Cooking Fuel for Llghtlng
Scott Wilson December 2007
Page 67
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Graph 4.2-16 -Expenditure on Household Resources in the KSD
Expenditure on Household Resources in the Kribi Subdivision
Nofhlng Lars than 500 CFC Betmren 501 to 1000 CFC Befmen 1001 lo 5000CFC More than 5001 CFC
Expenditures
1 W a t e r W Fuel for Cooking Fd Fuel for Lighting I
4.2.78 Summary of Key Project Impact Indicators of Household Well-Being
1. Wealth indicators 2. Time indicators
Household resources (water and fuel) Leisure activities
Health and education facilities
Expenditure indicators Household income indicators
Scott Wilson December ZOO7
Page 68
Kribi Power Project - 150MW Gas Plant and 225kV Transmission L~ne - Cameroon Resettlement Action Plan Final Report
5 Socio-Economic lmpacts & Respective Mitigation Measures
5.1.1 This Chapter will combine the information obtained from the socio-economic baseline of the project affected people, the inventory of land, crops and buildings done by the compensation commission with the potential project impacts to give a clear and concise picture of the potential socio-economic impacts as well as the respective mitigation measures.
5.1.2 The Kribi Power Plant Project has been designed to minimise the social and
environmental impacts. The location of the proposed plant site and power
transmission line route has been particularly sensitive to the prevention of unnecessary involuntary resettlement caused by the requirement for the land take.
5.1.3 A study of plant and site alternatives was carried out in 200514 where different
alternatives were discussed. For the plant site, alternatives regarding location,
plant types, fuels and gas sources were discussed and the conclusion that a
gas fired power plant located at Kribi with natural gas supplied from Sanaga Sud was the best, cost effective option.
5.1.4 For the transmission line, its route is dictated by the location of the plant and substations at Kribi and Edka and the need to minimise the overall length
wherever practicable. Nevertheless, various deviations along the route were
investigated to minimise, and where possible, avoid existing houses,
plantations and farmland falling within the ROW.
5.2 Project lmpacts
5.2.1 As stated in Chapter 1, the Kribi Power Plant Project will comprise of the following:
A 150 MW Power Plant at the Mpolongwe Site within an area of approximately 16ha;
A 225 kV double circuit transmission line between the plant and the existing Mangombe 225190 kV substation at Edka. The transmission line will be approximately 100km in length and a 30 metre wide corridor with 15 metres from either side of the main axis of the
14 Study elaborated by Power Planning Associates Llmlted (PPA)
Scoti Wilson December 2007
Page 69
Krlbi Po~ver Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
transmission line. This 30 metre wide corridor is called the right of
way (ROW).
5.2.2 Consequently, due to the land required for construction of the above, the project will have the following social impacts:
Permanent land acquisition
Permanent physical resettlement of houses, buildings, trees and crops
Permanent physical resettlement of businesses
Loss of cultural property
= Forest Loss
5.3 impact Overview & Mitigation Measures
5.3.1 The construction of the Power Plant and the transmission line will require
displacement of 16ha of land for the Power plant and a total area of 300ha for
the transmission line (given that the ROW will require an approximate length
of 100km and a width of 30metres)
5.3.2 This land acquisition will affect a total of 680 Households, a total of 84 buildings belonging to 83 households (including main houses, kitchen, toilets,
concrete, churches, storage houses)15, 55 land (with land title16 and belonging
to 54 households), and 985 crops (belonging to 623 households). A total
number of 386 people will need to be reallocated, as per the family survey.
See Table 5.3-1 below for the number of affected households.
Table 5.3-1 -Category of affected assets
Number of households with KS D
ESD Plant Entire affected: Site Route
Land 5 49 0 54 Crops 326 297 22 645 Buildings 18 57 8 83
I s Of a total of 84 buildings, 63 main houses will be affected 16 Or already in the process of obtaining land title
Scon Wilson December 2007
Page 70
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Note: The table above is according to individuals, which differ from crops/building/land owner since we can have for example 5 crops ownerslcrops
corresponding to 2 affected individuals.
5.3.3 Within the project area, crop owners will lose land that they cultivate as well as some crops, including the trees. Household owners will lose their residence or any other building that is part of their assets.
5.3.4 Category of Affected Assets
5.3.5 Loss of Land (titled and non-titled)
The majority of the respondents do not possess a land title for the land they
are currently on. However, they have purchased this land (usually from a
neighbour, the traditional chief or another community member) or been on it
for generations. Furthermore land availability near the existing community
facilities is also scarce as the land already has an owner, even though it is not
being exploited for any use. Land without owners exists but this is further
away from the community facilities and deeper into the forest. As a result, land is available within the vicinity of the original land but this land will need to
be bought.
For the land owners with land title, appropriate compensation will be given as
stipulated by Cameroonian law. However for those land owners without land
title Cameroon Law does not recognise the untitled land as land requiring
compensation. However given the circumstances of land availability, AES
SONEL should be assist them in the purchase of their new land.
5.3.6 Private Buildinas/Houses
5.3.7 Materials and design features of houses, out-houses and barns differ
significantly in the project-affected-area. Houses are constructed from a range
of materials, which can be divided into permanent material and temporary
material. Cement bricks are considered permanent material whilst mud, wood, stone or derivatives such as mud bricks are considered temporary material. The same applies to the roof material, which is usually constructed,
from Aluminium slates and timber. Adequate compensation will be provided and will take into consideration the type and size of the house. The statelquality of the house will be assumed as being brand new.
Scott Wilson December 2007
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5.3.8 Farmland and fruit trees
5.3.9 The main fruit trees cultivated are sweet banana, banana plantain, pineapple, orange, lemon, mandarins, mango, papaya, and avocado. Both crops and
fruits are not only an important source of household revenue when sold (as
well as a good bartering coin) but also a very important source of important
nutrients for the family. As such due compensation will be required.
5.3.10 Compensation will be made for the loss of crops during the construction and
operation phases of the transmission line and the power plant. The most
common cultivated crops in the project area are peanuts, maize, cassava,
beans, Soya, yams, potatoes.
5.3.1 1 Hardwood Trees
5.3.12 A few of the respondents have individual hardwood trees of a certain
commercial value. It is thus recommended that the owners of such trees be able to cut them and keep the timber and that AES SONEL provide them with
saplings of these trees.
5.3.13 Loss of forest and non-timber forest products
5.3.14 Forests provide both indigenous and non-indigenous groups with products
used for medicines, food (including protein), tools and materials for building. As a consequence, forest loss could have a direct impact on indigenous
groups and non-indigenous group's livelihoods, as it could reduce the
availability and quality of these forest products, which play a vital role in sustaining local lives.
5.3.15 Due to the nature of the impact being small and the fact that forests are
considered national land, no compensation will be made available for forest
loss.
5.3.16 Public Infrastructure
Scon Wilson December 2007
Page 72
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5.3.17 The project area is very poorly provided with service infrastructures such as
schools, hospitals, health and sanitation facilities (see Section 4.1.10).
However, no such structures will be affected by the project and therefore
these are not discussed further in this section. Nonetheless, two football fields
will be affected; one belonging to a school in Fifinda 1 and the other being of public domain in Bivouba. Both of these must be rebuilt before acquiring the
current fields.
5.3.18 Cultural Heritaqe
5.3.19 Five religious locations (2 missions and 3 churches) will be affected by the
project albeit in different degrees (two will have their crops affected whilst two
will have their main structure affected). Appropriate mitigation measures will
thus be undertaken with regards to the crops and the buildings ensuring that replacement buildings of at least an equivalent standard be constructed
before the destruction of the latter ones.
5.3.20 Business
5.3.21 The majority of businesses that will be affected by the land take for the ROW
are small-scale, informal and relatively mobile, such as kiosks selling fruits
and vegetables, tailors and drivers which can be therefore easily reallocated
with minimum impact and should not represent a significant loss of income for
the household.
5.3.22 The loss of income from selling of any household produced products will be
included in the calculations of the compensation of temporary and permanent
crops and will therefore be compensated at current market prices.
5.3.23 AES SONEL will provide assistance and incur the costs that might occur of
moving any businesses to the new locations.
5.3.24 TombslGraves
5.3.25 The majority of respondents that had tombslgraves within the ROW preferred
them to be left in the current location untouched. This is possible as the transmission line will go above and will not interfere with the tomblgrave
location. In addition, the construction teamlcontractors will be warned in advance of the location of the tombs and respective precautions and these
will be clearly identified so that they are not disturbed during the construction
of the line. For the few respondents that preferred the tombslgraves to be relocated with them, AES SONEL will provide the necessary experts and
Scotl Wilson December 2007
Page 73
Kribl Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
undertake the necessary pacification rites to enable relocation with the
minimum disturbance
Scott Wilson December 200 7
Page 74
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5.3.26 A summary of the types of losses from land acquisition is provided below.
Table 5.3-2 -Types of Losses from Land Acquisition
5.3.27 The entitlement matrix that follows summarises the main types of losses as described above and the corresponding nature and scope of entitlement,
Scott Wilson December 200 7
Page 75
Krrbi Power Projeci - l5OMW Gas Plant and 225kV Transmrssion Line - Cameroon Resettlement Action Plan Final Report
5.4 Entitlement Matrix
Direct Proiect Impacts
Table 5.4-1 - Entitlement Matrix for Direct Project lmpacts
Loss of land (equal
or more than 50% of
the existing land)
I I 1 APs, replacement land should be provided
Compensation Policy
Loss of less than
50% of land
I I I within the commune.
Definition of Entitled Person Types of Loss
Land located inside the
ROW of the transmission
line and Plant Site
Application
Land located inside the
ROW of the transmission
line and Plant Site
at full replacement costs.
AES SONEL assist in obtaining the land
title for the people without it.
Occupants with land title (or in
the process of obtaining) for the
land. Occupants that have proof of
purchase of the land
Loss of residential
land
Provide equivalent sized land nearby or
Provide cash compensation of the whole
land at full replacement costs at current
market value
Occupants with land title (or in
the process of obtaining) for the
land.
Occupants that have proof of
purchase of the land
Recommendations
Provide equivalent sized land nearby or
Provide cash compensation of the affected land area at current market
value
If remaining land is enough to absorb
Residential land located in
ROW and Plant Site
Loss of Primary
structures (shops,
houses) 8 secondary
The new land must be located as
close as possible to the affected
land
The new land must be located as
close as possible to the affected
land
Occupants of the land with land
title Occupants of the land with no
land title
Structures located in
ROW and Plant Site
The new land must be located
within the same community as the
previous structure
Must be close to essential
household resources such as
sources of fuel and water. If not,
these services must be provided as
part of the compensation package.
If remaining area is not enough an
alternative house-plot (if not land title) or
equivalent to the former plot (if has land
title) will be offered as close as possible
as the original plot, or cash compensation
The structures built by AES SONEL
must have similar or better
conditionslassets as the previous Legal owner of the structure
Scott Wilson December 2007
Page 76
AES SONEL builds an equivalent structure with better material andlor bigger
size.
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Types of Loss I Application I Definition of Entitled Person I Compensation Policy I Recommendations
structures (barns, garages, fences)
Cash compensation at full replacement costs with no deduction for depreciation or state of existing structure
Allowance for lost income in kind (with regards to businesses)
structures. All structures must be completed
before-destruction of the existing structure They must be located within the
same community as the previous structure Must be close to essential
household resources such as sources of fuel, water.
Relocation
Whenever possible and given the choice of the tomblgrave owner, leave the
the tombslgraves with minimum charge. disturbance.
People living in the structures located in the ROW and Plant Site
No compensation is given for the
Relocation of Tombs and Graves
All structures must be completed before destruction of the existing structure
Legal owner of the structurelpeople renting the structure
Gravesltombs located in the ROW and Plant Site
Loss of Cultural Structures (E.g. Church)
" Reconmend an additional bonus payment if the affected person clears the area on time
Scoti Wilson December 2007
Page 77
Allowance for transportation of all
household effects (Through assistance or additional payment) l7
Owners of tombs and graves
Structures located in ROW and Plant Site
Additional assistance to households
that are more vulnerable such as female headed households and households with disabilities
tombslgraves in the existing location. When required. AES SONEL to provide technical assistance in the relocation of
Legal owner of the structure
relocation of the tombslgraves as AES SONEL will provide this service when necessary and free of
AES SONEL builds an equivalent structure with better material andlor bigger
size
Krrbl Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Types of Loss
Loss of Public
Structures
Standing Crops
Trees
Loss of forest
resources (timber and non timber
forest products)
Application
Structures located in
ROW and Plant Site
Crops located in the ROW
and Plant Site
Trees located in ROW and
Plant Site
Forest resources located in the ROW of the transmission line and
Plant Site
Definition of Entitled Person
Legal owner of the structure
Farmers who cultivate the land
People who utilize the land
where trees are located
Hunter-gatherers with customary rights to the resources (e.g. Kola People) and non indigenous
groups that use the resource
Compensation Policy
AES SONEL builds an equivalent
structure with better material andlor bigger
size
Compensation in cash for crops based on the existing pattem of productivity as well
as average yield and current average
market price.
Compensation in cash based on type of
tree, gross market value, and loss of production based on yield at full maturity, market price of crop and number of years
required for a replacement planthree to
reach a similar level of maturity.
Due to forest being considered as national
land with no legal owners, there will be no
direct compensation, however compensatory measures will be
implemented as presented in the Community and Indigenous Peoples Plan.
Recommendations
All structures must be completed
before destruction of the existing
structure
APs will be given sufficient advance
notice regarding evacuation. Crops grown after the CEC census
will not be compensated.
The work schedule has to take into account the crop seasons to avoid work, if possible, during the harvest
season.
Only private owners of the trees shall be compensated for them.
It's recommended that indigenous groups are given priority regarding
employment in the project, and
support in getting their ID cards.
Scon Wilson December 2007
Page 78
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5.4.1 Additional Recommendations Reqardinq the Compensation Process
5.4.2 According to the SEB survey undertaken, the main preference of respondents in the
project area there is for compensation to be payment in cash instead of payment in
kind'' (see chart below). However, given the low average monthly income of
respondents, it is assumed that the PAP are not used to managing such large
quantities of money as to be provided as part of the compensation package. As such,
it is recommended that whenever possible (particularly with the compensation of
structures) that AES SONEL provides payment in kind which also guarantees that the
PAP will get a replacement property. .
- -
97%
I 1 H Payment in cash HAES SONEL to buylconstruct the landlhouse Mixture of both
5.4.3 With regards to the project affected people that will receive some or all of their
compensation in cash, it is important to note that only 16% of the respondents stated
they had a bank account whilst 84% stated they didn't. As such, it is recommended
that AES SONEL provides the following services:
a) Encouraging and supporting the PAP in opening a bank account (33% of the respondents with no bank account stated they would like AES SONEL to help them open a Bank Account). An incentive, such as an extra payment, could
be provided to the PAP if they choose to open a bank account.
b) Training before the compensation process starts, for PAP'S on using bank accounts and managing money, as well as on the different options of receiving moneys (see section 5.4.4 below)
'"ayment in kind is normally defined as payment for a good or service with a medium other than the legal tender (i.e money). E.g. building a new house instead of giving the money equivalent to the house.
Scon Wilson December 2007
Page 79
Kribi Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
c) Provide assistance to the PAPS that did not want to open bank accounts in cashing the cheques
5.4.4 Furthermore, it is recommended that AES SONEL should set up a long-term compensation process where the compensation package is made up of assets and
cash:
Whenever possible, AES SONEL should provide compensation in kind,
especially with regards to land acquisition, building of structures, provision of seeds, clearing and preparation of land for crop production.
With regards to compensation for crops and trees, it is recommended that
AES SONEL give the option of one-time lumpsum compensation or a periodic compensation (i.e. seasonally or annually). The periodic compensation would
be in line with the production cycles of the crops. E.g. a PAP that is expected
to receive compensation for lost production of a period of five years could get
the option of receiving the compensation annually over an equivalent period of
five years or a lump sum fee equivalent to the five years. This will not only reduce the amount in cash being given to the household but it will allow the household to make its adjustments every month with relation to money management.
5.4.5 Additionally it is recommended that AES SONEL create a RAP fund comprising of
25% of the total budget (25% contingency) as well as human resources and technical assistance, for community based livelihood restoration efforts as well as the
resolution of any conflict that may arise. This fund should assist PAP in:
I. Clearing and preparing the new land for construction orland planting
II. The reallocation (e.g. through provision of transport, medical team, etc)
especially if the household is deemed vulnerable (i.e. female head households, households with elderly, diseased or disabled members).
Ill. Visible demarcation of the current graves and tombs. Improvement of the current graves with more durable material.
Scon Wilson December 200 7
Page 80
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
IV. Providing extra payments for people that left the affected landlstructure at the
pre-agreed time.
V. Providing incentives, such as extra payments, for receipt of the cash payment into a bank account
VI. Providing payment for loss of income that occurred between the time the
activities stopped due to the project and the commencement of those same activities, upon delivery of evidence of loss income.
VII. Providing payment for additional payments that are required as a result of the requirement for relocation (E.g. Requirement for households being resettled to
move children during the school year and therefore needing to pay additional
school fees
5.4.6 With regards to the timing of the compensation process it is important that AES
SONEL that it takes into consideration the different seasons of the year in order to
allow for sufficient time for the PAP to re-establish themselves (e.g. construction of a
property in the rainy season can take longer than 6 months to complete).
5.4.7 Moreover, when providing new land for the structure, it must take into consideration the existing services such as education and health facilities, water and fuel sources,
markets, electricity, access to roads, among others. Consequently these should be
available in the new location.
5.4.8 Furthermore to mitigate impact regarding loss of forest resources, small trees and
branches that are cleared from the ROW should be made available at no cost to local
communities for firewood.
5.4.9 Finally, AES SONEL should provide the unused construction material obtained from
the destruction of the existing structures to the communities at no cost.
Scon Wilson December 2007
Page 81
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5.5 Project Attitudes & Concerns
5.5.1 The questionnaire used for the census included a series of open-ended questions regarding the household's attitudes, perceptions, choices and concerns regarding the
project. The answers given were assigned to different categories and an analysis of the data was conducted. The definition of the different categories is given before each
analysis illustrated below.
5.5.2 In order to better understand people's potential choices and respective reasons as a
result of the project, the questionnaire asked the head of the household where they
would reallocate to and why, if the project proceeded. The various open-ended answers obtained were categorised and analysed as seen in the Graph belowlg.
5.5.3 The majority of respondents from the ESD (46%) chose a location near the original area with the second largest choice (27%) being a location further from the original area.
5.5.4 The respondents from the KSD however, chose a location further from the original
area (53%) mentioning always the forest as their preferred location, however over a third (36%) chose a location near the original land.
Graph 5.5-1 - New Location After Resettlement
Furiherfromthe Near to origiml A w h e r e Refuseto m v e Another Village Don't know Original l o M i o n ( E g location
ForesllBush) Locations rn Littoral Province mSoulhern Province
5.5.5 When looking at the different reasons mentioned regarding their choices illustrated above, the main reason for both the ESD and KSD was land availability (32% and
30% respectively) as land usually has an owner even if this is traditional chief (see section 4.1.18). This concern was followed by proximity of new land to the original
19 For more detail on the different categories and their respective definitions. please see Appendix 9.4
Scon Wilson December ZOO 7
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
land (25%, 24% respectively). This is in line with the fact that the ESD is more
urbanised and basic services are located closer to their current location. As such,
people are less willing to move further from their current location and the services
they already enjoy.
Graph 5.5-2 - Reasons given for the location chosen above
- Reasons for choice of new ocation 1 OEdea Subdivision K r i b i Subdivision 1
5.5.6 When asked what was the main concern that the household had with the relocation,
several concerns and frustrations were mentioned. These were again put into
different categories and analysed. For further information and definition of the
categories see Appendix .
5.5.7 The main concern/frustration mentioned was disappointment at being forced to move
from the current location to the new location. A majority of respondents in both
Subdivisions stated that they did not have any great concerns. Availability of food - during the period of reallocation and until they can collect food from their new crops - as well as and the compensation package were also mentioned by a significant
number of respondents in both Subdivisions.
Graph 5.5-3 - Main concerns regarding the project
Scon Wilson December 2007
Page 83
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
.- - a a Z "-
C C .- to Main concerns 6
El Edea Subdivision W Kribi Subdivision -
5.5.8 Main Concerns and Attitudes from Land, House and Tomb Owners
5.5.9 The attitudes of respondents with respect to the type of compensation they can receive are split fairly equally between those who request solely cash compensation
(41 % of respondents) and those who prefer that AES SONEL take responsibility for
the construction of the new house (51 % of respondent^)^'. Each of these two groups
has raised distinct issues and concerns. Some of the issues raised, however, are
common to both groups.
5.5.10 All respondents raised as a main concern, the fact they want a house that will be
better, or at least as good as the one that they have at present. This includes not only
the size of the house and the building materials used, but also existing or additional
assets andlor services which can include, inter alia:
Annexes to the house, such as kitchen;
Proximity to sources of water;
Access to electricity;
Proximity to jobs and schools;
Size of land to be lost;
'O The remaining 8% of respondents wanted AES SONEL's help with building a church (2.5%) or wanted to choose their own technicians, but would like AES SONEL to supervise and coordinate the construction works (5%).
Scoii Wilson December 200 7
Page 84
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Crops and/or flower beds;
Financial damages from crop/business loss or interruption
5.5.1 1 Furthermore, respondents wanted to ensure that the compensation they will receive
(whether it is in cash or assets) will reflect the real value of their property, as well as the time and money already spent in acquiring it and developing it. A proportion of the residents who requested cash compensation were concerned that due to current local land prices, they may not be able to afford land in the vicinity of their current homes,
which demonstrates that land is available but has an owner. They would therefore
have to relocate to distant areas with less access to services, which would cause
even greater disruption to their lives. The majority of respondents mentioned that they would like to minimise, as far as practicable, the distance between the existing and new housing.
5.5.12 In addition, all respondents were concerned with the timing and phasing of the
project: the majority wanted to know exactly i) when would the compensation be received, ii) what were the planned dates for the destruction of their existing homes,
and iii) would the new homes be ready before the destruction of the existing ones.
5.5.13 For those respondents requesting compensation in cash, knowledge of the above
was considered very important as they needed to time the construction of their new
homes according to both the destruction of the existing ones, and other factors such
as weather and distance to the new location (estimated time for the construction of the new home ranged approximately between 3-12 months).
5.5.14 For those requesting that AES SONEL build their new house, they needed the knowledge of the above to prepare their move to the new home (estimated time
needed to relocate to the new home ranged approximately between 3-5 weeks). The majority of respondents also mentioned that knowing the date as soon as possible was essential, so that they could minimise disruption to their personal lives by
planning e.g. changes to their professional activities or registering children in a new local school.
5.5.15 A number of respondents mentioned that they are, or have in their household, people
with impaired mobility. This includes disabled and/or elderly people as well as young children. These people would have difficulty in relocating to their new homes, and therefore would need AES SONEL to assist them in doing so.
5.5.16 Some respondents already possess an additional land where they would like their new house to be built. Of this group, the majority need AES SONEL to help them prepare the land for construction (independently of whether they will build it
themselves or get AES SONEL to do it). Additionally, the remaining respondents that
Scon Wikon December 2007
Page 85
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
do not possess land nor have land title for their current land would like AES SONEL
to support them, not only financially, in the acquiring of the land but also in its
preparation.
5.5.17 Most respondents have tombs that will be affected by the proposed relocation. Of these, a significant proportion does not want their tombs to be removed, and would like AES SONEL to help make them more "visible" (e.g. by providing cement covers and signs around them), in order to avoid damage during demolition and reconstruction activities. Those respondents that would like their tombs to be moved to a new location request that this is done appropriately. In these cases AES SONEL
would provide all the resources necessary to move the tombs with minimum
disturbance whilst following traditional pacification rites but it would not provide any financial compensation. Additional details regarding the focus groups and a list of
frequently asked questions is presented in Appendix 9.7.
5.5.18 Information Provision and Conflict resolution
5.5.19 The study showed that for the majority of respondents in both Subdivisions, the most
reliable source of information was the radio (average of 58.7% respondents in the project area), followed by friendslfamily (18.6%). In addition, when asked whom the respondents would turn to in order to solve a community conflict, the majority of respondents (93.6%) mentioned their traditional leader.
Scoti Wilson December ZOO7
Page 86
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
5.6 Perceived Project Benefits
5.6.1 When asked what were the main benefits the household thought the project would bring, the majority of respondents of both Subdivisions mentioned the connection of
electricity to their houses and villages. When asked if they would be prepared to pay for the electricity, they respondents all said yes.
5.6.2 The overall development of their own villagelcommunitylcountry was also frequently mentioned. When asked to be more specific about the type of development, the
respondents mentioned mixture of factors such as other employment opportunities
brought about by the electricity, better markets and commerce and more tourism, among others.
5.6.3 As significant number of respondents mentioned work and employment as a specific
benefit of the project and urged AES SONEL to give the affected people priority with regards to employment.
5.6.4 Finally a significant number stated the project would not brirrg any benefits to them per se. This was particularly evident in the ESD.
Graph 5.6-1 - Project Benefits
Scot7 Wilson December ZOO7
Page 87
Krib~ Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
6 Budget and Costs
6.1 Compensation Framework
6.1.1 As defined in Section 2 (Legislative Framework) the main Cameroonian legislation relating to compensation for resettlement are:
Law No. 851009 of 4/07/1985 on expropriation for purposes of public utility,
Ministry of Town Planning and Housing (MINUH)
Decree No 20031418 of the 25th February 2003 defines the entitlement values
for crops and trees to be removed or destroyed by a public utility
Decree No 200613023 of the 29th December 2006, Fixing the modes of Administrative Evaluation of 'The buildings in Fiscal Matters. Although
not in force yet, this decree has been utilised to evaluate building
compensation where no agreement between PAP and CEC on building price
has been reached, as it takes into account land, construction, and rental
markets, of the infrastructures as well as the urban services level, which the
building benefits from due to its geographical location.
6.1.2 This legislation defines the framework and requirements for compensation for
expropriation of land andlor assets for a public utility (in this case the Kribi to Edea
Power line and Kribi Gas Power Station). Decree No 20031418 and Decree No
200613023 define the value of crops and buildings to be expropriated by the Public Utility respectively.
6.1.3 In line with Ministerial Order No 0136N. 14.4/MINDAF/D220 and
0137N. 14.4/MINDAF/D220 of 26'h ~ u g u s t 2005, The Compensation Evaluation
Commission established for project has undertaken the following works:
Completion of a survey report signed by all the members of the CEC.
Completion of a bordering report and concerned lands plan showing the
available land titles, the lands in the process of obtaining titles, plots of public
property and the lands of state private property;
Details of the various state of constructions, crops and other valuable goods
found in the different plots signed by the technical sub-commission members
and countersigned by the commission members (the value of which have been defined by Decree No 20031418 and Decree No200613023);
Scott Wilson December 200 7
Page 88
Kribi Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Rectification plans and reports of lands bordering of partly affected lands
detaining a land title or that are in the process of obtaining titles;
Copies and lands titles to be partially or entirely expropriated and the files of those who are in the process of obtaining titles.
6.1.4 Bridging the Gaps
6.1.5 Gaps identified between the Cameroonian Legislation and OP 4.12 are defined in
Section 2 and include provisions such as compensation to full replacement cost of
lost assets, moving allowances, income restoration and assistance to displaced
persons with their efforts to improve their livelihoods and standards of living and the
implementation of sustainable development programs to enable PAPS to share the
benefits of the project and not be worse off as a result of the project, which are not
covered under Cameroonian legislation.
6.1.6 As AES Sonel intends to attain funding from the IFC, the mechanisms outlined in
Section 7.8 will be utilised in order to bridge the gaps between PS 5 and
Cameroonian legislation.
6.1.7 The following section provides a summary of the estimated budget and costs required
to fulfil the requirements of OP4.12.
6.2 Financial Responsibility and Authority
6.2.1 All costs for resettlement, and implementation of the RAP will be the responsibility of
AES SONEL.
6.3 Compensation Budget
6.3.1 For the purposes of this RAP the Displaced persons have been defined (in line with
IFC PS5) in Section 2 and include Physically Displaced Persons and Economically
Displaced persons.
6.3.2 From the survey carried out by the CEC 75 households have been identified with
building within the proposed ROW for the project and have been classified as
Physically displaced, and a total of 596 have been classified as requiring compensation for economic displacement.
Scoff Wilson December ZOO7 Page 89
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
6.3.3 Physically displaced people will be entitled to a choice of feasible options for resettlement including adequate replacement housing or cash compensation and are
provided with resettlement assistance in addition to any compensation arising from
any economic displacement.
6.3.4 Economically displaced people regardless of whether or not they are physically
displaced or not will be entitled to compensation to loss of assets at full replacement
cost.
6.4 Physical Displacement
6.4.1 As outlined in Section 2 any PAPs that (i) have legal rights to the land they occupy,
(ii) who do not have formal legal rights to land, but have a claim that is recognizable
under the national laws or (iii) who have no recognizable legal right to the land they
occupy (but have moved to the area prior to the cut off date). Will be entitled to
choice of adequate replacement housing with security of tenure or cash
compensation and provided with resettlement allowances.
6.4.2 For PAPs who have recognizable legal rights to the land they occupy (i) and (ii),
resettlement property or land will be equal to or higher value than the current property
or land from which the PAPs are required to move away from.
6.4.3 Private Land
6.4.4 In line with Law No. 851009 of 410711985 Compensation for non-serviced land
acquired under customary law that enabled the holder to obtain a title, will be no more
than the minimum official rate for non-serviced state-owned land situated in the area
the land title was issued and compensation for land (Private Land) acquired by
normal legal transaction, shall be equal to the purchase price including costs incurred
in the transaction.
6.4.5 For this RAP any displaced person that has either full formal rights to the land they
occupy or have a claim to the land that is recognizable under the national laws will be provided with replacement property of equal or greater value or cash compensation at
full replacement cost of the land.
Scott Wilson December ZOO7
Page 90
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
6.4.6 Fifty-four PAPS have been identified as holding titles to land required for the project or
as having applied for land titles to their land. The total titled area affected by the project is 354, 560m2 (as evaluated by the CEC)".
6.4.7 No official government rates for land exist and the CEC has not evaluated the existing
land. As such, it is recommended that AES SONEL obtain information relevant to the
development of a fair market value for land. The rate currently used as an indication
was obtained from the Limbe Compensation Action Plan where the purchase prices
per square meter of land in the area ranged from 750 CFCA to 2000 CFCA. As such,
an average of 1,375 CFCA was used as an indication of possible costs.
6.4.8 The total estimated cost of fully replacing the titled land is 487,520,000.00 CFCA or
1,000,613.69 US$.
6.4.9 In addition AES SONEL will also support the PAP, which do not have land titles in
negotiating any new lands as well as incur any costs such as traditional gifts, needed
to obtain the land.
6.4.10 Buildings
6.4.1 1 Based upon the methodology adopted for evaluating building values adopted for this
RAP which is based upon Decree No 200613023 of December 2006 which values
buildings for tax purposes (this is only applied when no negotiated value has been
derived by the CEC and the PAP). The methodology for evaluating Building
compensation is summarised in Appendix 9.5.
6.4.12 The total estimated cost for building compensation is 193,348,243.62 for ESD,
64,751,798.57 CFCA for KSD (Transmission Line) and 27,483,700.00 CFCA for the
Power Plant in KSD. This amounts to a total of 285,583,742.19 CFCA or
593,214.91 US$.
6.4.13 Relocation Assistance
6.4.14 Relocation Assistance will be provided to all displaced persons. Assistance will be in the form of:
Land Clearance - AES SONEL will pay for local labour to clear new land for
displaced people. This will enable local people to benefit from wages due to
land clearance.
72,329 m2 of land titled in Kribi Subdivision and 282,23 1m2 in EdCa Subdivision
Scott W o n December 2007
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Negotiations in obtaining new land - AES SOIVEL must provide assistance to
all PAP'S in obtaining the new land as well as incur any costs that may arise
from this negotiation. It is important to note however that the negotiation will be between the PAP and the owner of the land.
Transportation of Property - AES SONEL will make transportation available for
Displaced Persons Free of Charge.
Transportation of businesses - AES SONEL will assist in rebuilding any
businesses that might need to be reallocated, e.g. fruit stalls
6.4.15 As choices are given to PAPS in terms of cash compensation or replacement, the costs of relocation assistance are difficult to quantify, as the total number of displaced people that will opt for cash compensation is not currently known. Assuming that
there will be the requirement of 6 months of support. An estimate of
17,681,000 CFCA or 36,289.49 US$ has been developed based on costs for
developing an assistance team with transportation as well as a budget for land
clearance based (see Table 6.4-1 below).
Table 6.4-1 : Relocation Assistance Costs
6,s Economic Displacement
Activity
Truck Use
Land Clearance
Relocation Assistance Team
6.5.1 Community Land
6.5.2 Five Churches have been identified along the ROW which will have their assets
affected (crops and buildings). AES SONEL will provide the Congregation of each
affected church with a choice of cash compensation. For the two churches, which will
have their building, affected, AES SONEL will provide the construction of a new
Church or provision of an alternative structure better than the affected building. The Compensation value is based upon the tenets of Decree No 200613023 of the 29'h
December 2006 relating to the condition of the building involved and the surface area
of the building. In this case the total estimated compensation for replacing the churches is 27,000,600 CFCA or 55,417.56 US$ (13,854.39 US$ per Church).
Number
2
6881 5
Scoff Wilson December 200 7
Page 92
TOTAL
Rate
5000lday each
1000
5000lday each
17,681,000
Quantity Duration
180
180
36,289.49)
Total CFCA
1,800,000
6,881,000 9,000,000
Total US$
3,694.42
14,122.95
18,472.1 1
Kribi Power Project - I5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
6.5.3 Two-football pitches have been identified as belonging to a school in Fifinda 1, and to
the community in Bivouba along the proposed power line. AES SONEL will build replacement pitches in the vicinity of the old pitches to a better standard and provide
football equipment to the community. The cost of undertaking this is estimated at 5,000,000 CFCA or 10,262.28 US$ per pitch, with a total of 10,000,000 CFCA or
20,524.57 US$.
6.5.4 Businesses
6.5.5 In line with the principles of OP 4.12 (to ensure PAPS are made no better off as a
result of the project) any person owning a small business that w~l l result in loss of
income or sources of income as a result of the project will be provided with options of
full replacement cost for businesses and loss of income and provided with alternative
locations situated in areas with similar infrastructures and access to markets and
demand.
6.5.6 From the Socio-economic Survey carried out by Scott Wilson in May 2007 and the
CEC Survey the majority of occupations recorded in the project area are agricultural,
and provisions for income restoration have been made within the methodology for
crops compensation.
6.5.7 Crops
6.5.8 Decree No 20031418 of the 25'h February 2003 defines the entitlement values for
crops and trees to be removed or destroyed by a public utility (See Section 2 - Legal
Framework). During the survey of crops affected by the proposed project undertaken
by the Compensation Evaluation Committee (CEC). CEC utilised Decree No
2003141 8 to evaluate total compensation values for PAP'S.
6.5.9 Decree No 20031418 defines prices for crops based on values established by the Prime Minister in 2003. The Decree does not indicate the methodology utilised for
arriving at these values and as such it is assumed that these prices were obtained based upon market conditions during the 2002 farming season.
6.5.10 In order for compensation values for crops to be inline with OP4.12 by restoring
incomes and compensating for crops at full replacement value, the following factors were taken into consideration;
For leguminous plants and cereals - Current (2007) market prices for
crops, average yields per hectare, price of seeds required for planting per hectare and number of farming seasons per year
Scon Wlson December 2007
Page 93
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
For Trees - Years required for growth prior to production, average production
per tree per year, price of tree products and price of a nursery tree,
6.5.1 1 All prices were determined through consultation with the Department of Agriculture in Kribi and Market Traders at Kribi market during field visits undertaken in May 2007,
as well as reviews of Voice of the Farmer publications which outline market prices for
a number of crops every month.
6.5.12 By taking into account the above factors in the methodology to determine
compensation values for crops. Due consideration was given to ensuring PAPs are
compensated for lost potential revenue from any agricultural activities using fair and up to date market prices and are provided with the full replacement cost of a
particular crop using the assumption that it will take 1 year for PAPs to be fully resettled and producing crops to the same level prior to resettlement.
6.5.13 The methodology utilised for determining compensation values for this project is outlined in Appendix 9.5
6.5.14 In some cases the value determined for this RAP is below the values defined in Decree No20031418. This may be due to the negative changes in market values for
certain types of crops. In the cases where the methodology utilised obtains lower values compared to the Decree or data about a certain plant is unavailable, the
values outlined in the Decree will be utilised as PAPs are entitled to these values by
law.
6.5.1 5 The Compensation Evaluation Commission has estimated the total cost for
compensation for Crops at 667,190,402.50 CFCA (1,369,379.40 US$). Using the methodology established for this RAP the total full replacement cost for crops lost for the project is 1,396,442,591.50 CFCA (2,866,137.94 US$)
6.6 Inflation and Currency Variations
6.6.1 All values detailed in this section have been converted into the United Sates Dollar (US$) using the average official exchange rate from the Cameroon CFCA to US$
dated theloth August 2007 of 1 US$ to 487.221 CFCA.
6,7 External Monitoring and Evaluation
6.7.1 Estimated cost of undertaking External Monitoring and Evaluation in line with the provisions highlighted in Section 7.9 is 72,790,817.40 CFCA or 149,400.00 US$ (See appendix 9.5 for estimated budget).
Scon Wilson December ZOO7
Page 94
Kribi Power Projecf - 150MW Gas Plant and 225kY Transmission Line - Cameroon Resettlement Action Plan Final Report
6.8 Total Compensation Costs
6.8.1 The total estimated costs for compensation are detailed below
Table 6.8-1 - Total estimated costs for compensation and associated relocation activities
Affected Assets & Associated Relocation Rate Total (CFCA)
Activities
( 1 l~rivate Land I@1,375C~CA/m21 487,520,000.00 1 $1,000,613.69 1
Lump Sum 3 Relocation Assistance Estimate I I 1 17.681.000.00 1 $36.289.49 I 2
1 4 Community Buildings
--
Buildings b s per Census 1 285,583,742.19 1 $593,214.91 1
1 5 community Land / 1 0 0 0 ~ ~ ~ A / r n 2 1 10,000,000.00 1 $20,524.57 (
I I I I
External monitoring and Lump Sum Evaluation IEstirnate 1 72,790.817.40 1 $149.400.00 1
I
6
6.8.2 The total Budget for implementing this RAP is estimated at Five Million, Nine Hundred and One Thousand, Nine Hundred and Ninety Seven American Dollares and Seventy Pence ($5,901,997.70) including a 25% Contingency
($1,180,399.54).
I I I I
Crops
Contingency (plus 25%)
Total RAP Budget
Scoti Wilson December 2007
Page 95
As per Census
574,254,687.77
2,871,273,438.86
$1,180,399.54
$5,901.997.70
1,396,442,591.50 $2,866,137.94
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7 Institutions and Implementation Arrangements
7.1 Introduction
7.1.1 According to the World Bank, the failure of many resettlement operations is more due
to the inability to implement the RAP adequately in order to attain the project
objectives, than the quality of the RAP itself. This is particularly true when the
organisations responsible for the implementation do not understand the RAP, as they
were not involved in its preparation and may lack an understanding of its objectives.
7.1.2 This chapter thus provides guidance on the roles and responsibilities of institutions
implementing the RAP as well as the schedule of the implementation. It will follow the
World Bank's Operational Policy on involuntary resettlement, OP4.12, which
stipulates that the analysis of the institutional framework must cover the following
areas:
Identification of agencies responsible for resettlement activities and NGOs
An assessment of the institutional capacity of such agencies
Any steps proposed to enhance the institutional capacity of agencies and
NGOs responsible for implementation.
7.2 Orgariizational Units
7.2.1 The Kribi-Edea Power Line Project goes through two politically and financially
independent Subdivisions. As such, the RAP followed the same structure and
analysed the PAP'S socio-economic characteristics and compensation requirements
by Subdivision.
7.2.2 Consequently, as the implementation of the RAP will be done by subdivision, the organisational units working in each subdivision will have the same AES SONEL
actor's but different government officers.
7.2.3 As a result, central coordination is key in maintaining the quality and the management
of the resettlement, as these can differ in each Subdivision depending on the actor's
knowledge and understanding of the RAP'S objective.
7.2.4 Furthermore, monitoring and supervision during implementation is also key to the success of the RAP.
Scon Wilson December 200 7
Page 96
Kribi Power Project - 150MUr Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Reoort
7.3 Overview of Implementing Orgar~isations
7.3.1 In Cameroon, there is no single agency that has the mandate for the planning and
delivery of resettlement and compensation in cases where people are involuntarily displaced. It is however, agreed in principle that the developer (AES SONEL)
assumes the responsibility for delivery of entitlements even though a number of other
organisations may be involved as described below.
7.3.2 The implementation of the RAP will involve the combination of the following
organisations:
ESlA and RAP Coordination Unit (ERCU)
AESS Finance Department
AESS Environmental Department
Local Government Offices of Edka and Kribi Subdivisions
Grievance Redress Unit and
Other service agencies (responsible for delivering entitlements and conducting
activities specified in the RAP such as relocation, income restoration and
monitoring)
Scott Wilson December 2007
Page 97
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Reoort
Diagram 1 - Overall Implementation Structure
PropertylLand Legal Team Community Liaison Team (& Grievance redress
officer)
Scott Wilson December 2007
Page 98
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7.3.3 AES SONEL's Edea - Kribi Power line Project Department
7.3.4 AES SONEL has a department for the management of the Edea - Kribi Power line
Project including the construction and operation of the power line as well as the implementation of the Environmental and Social Impact Assessment. This department
will take on the responsibilities of supervising and managing the resettlement activities. It will further create a unit inside the department specialised in environmental and social impact mitigation and resettlement activities of the project.
This will be called the project ESIA and RAP Coordination Unit (ERCU). In addition to
the ERCU, two additional departments will support the implementation of the RAP.
These will consist of the AESS Finance Department and the AESS Environment
Departmen t.
7.3.5 AESS Finance Department
7.3.6 This unit will be responsible for the overall RAP budget management and payment
activity financing. It will work in close collaboration with the ERCU as well as with the
compensation team during the payment of compensation period.
7.3.7 AESS Environment Department
7.3.8 This unit will be responsible for the implementation of the ESlA and will therefore
provide any technical support the ESlA and RAP implementation team might need.
7.3.9 ESlA and RAP Coordination Unit (ERCU)
7.3.10 This unit will be based in the Kribi Power line Project Department and have the role of
implementing the resettlement through its own network of field teams described
below:
ESlA and RAP implementation Team Compensation Team
PropertylLand Legal Team
Community Liaison and Grievance Redress Team
7.3.1 1 In addition, it will be responsible for the:
Scoti Wilson December 2007
Page 99
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Effective coordination and timely delivery of outputs in the RAP
implementation Problem solving related to coordination of field teams.
Responding to implementation problems identified in internal and external monitoring reports
Ensuring adequate consultation of all stakeholders Ensure that grievances that could not be solved at the field level be solved at the ERCU level. If this is not possible, ensure that the grievance is re- directed to the appropriate government bodies for the appropriate legal action.
7.3.12 Furthermore, for the ERCU office to achieve a successful implementation of the RAP
it must have the necessary knowledge, skills and decision authority. In this regard, a few suggestions are given below:
The establishment of a good communication structure between the AESS Finance Department, the ERCU, the AESS Environment Department and the field teams
in order for allow for a good information flow, support and guidance to be given to
the field officers in a timely and efficient manner.
Adequate transportation and office facilities to facilitate the communication
between the PAPS and the local field offices
The ERCU should have their own smaller budget for purchases and operational
expenses in order to avoid time consuming and inefficient institutional procedures. However larger amounts dealing with the main compensation payments (e.g. buildings and lands) will go through the AESS Finance Department budget for
better monitoring.
7.3.13 Furthermore as the local field offices are not only the direct implementers of the RAP
but also the primary contact points for the PAP, these should be equipped with the following skills:
Knowledge of the RAP and its main objectives
Participatory methods and consultations Knowledge of financial accounting and budget management
Scott Wilson December ZOO 7
Page 100
Kribi Power Project - l50MW Gas Plan! and 225kV Transmrssion Line - Cameroon Resettlement Action Plan Final Report
7.3.14 The ERCU Teams
7.3.15 As mentioned above, the ERCU will be composed of four teams with very specific
roles in the implementation of the RAP.
A) ESlA and RAP implementation Team
7.3.16 The ESlA and RAP implementation Team will work in close collaboration with the
remaining teams and will be responsible for the overall implementation, management
and coordination of the RAP activities in the field. It will also act as the management
arm of all teams and will be responsible for all reporting to the ERCU.
7.3.17 In addition, it will be responsible for the overall RAP budget management and
payment activity financing.
6) The Compensation Payment Team
7.3.18 The World Bank 12004: involuntary Resettlement Sourcebook: Planning and Implementation in Development Projects, ~2591 suggests the following measures for
payment of compensation. The implementation schedule and process has used these
measures as a basis for the practical application of the RAP.
Pay compensation into bank accounts and not directly to PAPs;
Involve local nongovernmental organisations in the compensation process;
and
Inform all household members about compensation payments
7.3.19 The main objective of the compensation payment team is to make compensation
payments to the PAPs. This team will have three main functions: (i) to keep records of
money paid (AESS Finance Department); to issue compensation payments and bank them (AESS Finance Department) and to resolve any disputes (AESS legal
Department and the Grievance Redress Officer). The Grievance Redress Mechanism
will be discussed in more detail in section 7.3.29.
7.3.20 The Compensation Team will make payments on location where there are no accessible banking facilities. All payments should be made by cheque. If possible full-
banking services should be made available on location. The accounting group will
ensure that all payments are made and that all legal documents are signed and witnessed. The Compensation Team will brief PAPs on the payment process and following the briefing go through the documentation. In the presence of the village
Scoit Wilson December 2007
Page 101
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
leader the accounting group must confirm that the PAP is satisfied with the payment
to be made. If the owner is dissatisfied with the payment the Compensation Team will need to refer them to the grievance redress group. The Compensation Team needs to ensure that 'photographs are taken of the PAPS receiving the cheque to guard
against fraud or future fraudulent claims.
7.3.21 The compensation team will also be in charge of collecting and recording all
compensation related reports and activities, which will then be passed on to the
ERCU for record keeping.
7.3.22 The compensation team will consist of an officer from the AESS legal department, a
community liaison officer, a local government authority and the traditional chief of the
village being compensated. The compensation team will be coordinated and managed by the ESlA and RAP implementation team.
7.3.23 The officer from AESS legal department will be present to ensure that the process is
done according to best practices and the Cameroonian law.
7.3.24 The Local government authority and the traditional leader will act as observers in
order to ensure that the process is conducted well and within the law.
7.3.25 The community liaison officer will act as an observer and will receive any
grievancestdisputes that may arise during the process.
C) 'The Property1 Land and Legal Team
7.3.26 The propertytland and legal team will be responsible for verifying the identity of the
PAPS listed in the resettlement action plan as well as dealing with any legal issues
that may arise from disputes mentioned by the grievance redress team. This team will
work closely with the AESS Legal Department as well as the other field teams.
Scon Wilson December 200 7
Page 102
Kribi Power Project - 150MW Gas Plant and 225kY Transmission Line - Cameroon Resettlement Action Plan Final R e ~ o r t
D) The Community Liaison Team (including the Grievance Redress Officer)
7.3.27 The key objective of this team is to ensure good project relations with both the PAPs
and local residents of the affected areas. The community liaison team will be
responsible for organizing meetings with PAPs in the locations to be resettled. This team will inform the PAPs and local residents about the resettlement and
compensation process.
7.3.28 The detailed tasks of the community liaison team will be to:
Prepare and distribute notices of meetings at least one week prior to the
meetings to local leaders and media such as radio, TV and newspapers.
Notices should be distributed in the local languages as well as in French;
Organize meetings with local government leaders at the village level and
distribute notices for general meetings to local government leaders, NGOs
and villagers;
Distribute notices, press releases at various points (such as at local
government offices, markets, schools, churches and mosques) with
summaries in local languages;
Meeting with village leaders to explain the land acquisition process and to
answer questions about the process;
Select appropriate locations for use as payment centres for compensation
payments;
Explain the compensation payment process including the benefits of using a
bank and the role of the bank.
Explain methodology used to calculate compensation values;
Present a summary of the Resettlement Action Plan to PAPs, local residents and other project stakeholders, its role and process. This must be done in
both the official and local languages.
Explain the process for resolving disputes that may arise during the compensation payment process. This will include the explanation of residents'
Scon Wilson December ZOO7
Page 1 03
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
legal rights and how to file a dispute in the legal system should they wish to
lodge a legal complaint; and
Discuss any socio-economic issues regarding the RAP that are raised by the
community.
Collecting and recording all community consultation and community related
activities (including any grievances they may encounter), which will then be
passed on to the ERCU for record keeping.
Be involved as an AES SONEL observer in the compensation payment
process.
7.3.29 Grievance Redress Officer
7.3.30 In addition, the Community Liaison Team will also be responsible for capturing and
solving any grievances and disputes that may arise from the RAP.
7.3.31 Even with an adequate implementation of the RAP and a fair compensation, some PAP will still believe they were treated inadequately or unfairly. As a result, it is
necessary to provide an accessible and credible means for PAPs to pursue any
grievances, which will then decrease the likelihood of overt resistance to the project.
This should be done through a grievance redressing mechanism.
7.3.32 This mechanism will be present at the time of payment at the payment centres and
address any disputes that may arise. 'The proposed RAP includes a mechanism to
ensure that entitlements are effectively transferred to the PAPs and there is proper
disclosure of information and consultations with the affected community. However
there is an additional need for an effective and efficient grievance redressal
mechanism, which will respond to people's queries and problems and address key
issues, concerns and complaints.
The Leqal Procedure
7.3.33 On Section Ill, Article 12 of Law number 851009
In case of dispute over the amount of compensation, the expropriated party shall lodge its complaint with the Ministry in charge of land
Scotl Wilson December 200 7
Page 104
Kribi Power Project - ISOMW Gas Plant and 225kV Transmissron Line - Cameroon Resettlement Action Plan Final Report
Where its request is not satisfied, the expropriated party shall refer the matter
to the appropriate court of the area of the property concerned within a month, as from the date of notification of the disputed decision
Pursuant to the procedure and subject to the normal course of appeal, the
court shall either, confirm, reduce or increase the amount of the compensation
in accordance with the evaluation terms laid down in this law and its implementation instruments.
7.3.34 In section IV under miscellaneous provisions, Article 14 states: Any cases pending
ruling or subject to dispute, and any other real actions shall neither halt the
expropriation process nor prevent its effects. The complaint shall be transferred onto
the compensation and law concerned relaxed.
7.3.35 The usefulness of the grievance mechanism is dependent on how swiftly the issues
can be resolved. Therefore at the first tier the PAPs must be informed of the
existence of the grievance mechanisms and even more important, understand how the mechanism works. As such, it is suggested that the PAPs be notified and
explained about their grievance redress options before the commencement of the
resettlement during the public consultations and that the name of the officer in charge
be presented.
7.3.36 It is expected that various types of grievances will be brought to the attention of the
grievance team from various types of PAP. As such, the mechanisms in place must
be able to reach all PAPs.
7.3.37 Under the proposed grievance procedure if a PAP is dissatisfied with any
resettlement issue, resettlement or compensation measure, the delivery of entitlements or even dissatisfied with the project he or she could voice a complaint in
the first instance to the Grievance Officer of AES SONEL (or the Community Liaison
Officer) which would also inform the traditional leader, and the local government
officer. The grievance officer together with the local government officer and the
traditional leader will try and solve the grievance within a period of seven working
days (All complains and respective actions must be recorded).
Scott Wilson December 2007
Page 105
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7.3.38 If the problem is not solved within the stated period it can then be referred to the
Senior Officer at the ERCU where amicable resolution will be sought between the
ERCU and the PAP within another established period - say fourteen days - (see
diagram below). Whenever the PAP has a land title and its dispute involves his land, if the complaint cannot be resolved within the time established, then the grieving party
is free to take the matter to court as a final resort. Compensation will be paid upon
resolution of the grievance or dispute
7.3.39 The grievance team must keep a database of all grievance claims as well as the
period if took to resolve the disputes which will then be passed on to the ERCU for
record keeping.
Scott Wilson December 200 7
Page 106
Kribr Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Diagram 2 - Grievance Redress Mechanism
Scott Wilson December 2007
Page 10 7
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7.4 Management Information System
7.4.1 AES SONEL will keep specified project related records pertaining to the
compensation.
7.4.2 Record Keeping
7.4.3 Records of all public consultations, surveys, grievances, disputes and resolutions will be kept on file at the ERCU offices. An electronic database will be created capturing information specific to each PAP as well as the lost assets, rates of compensation and total compensation figures, as well as data captured in the household survey and
any grievances.
7.4.4 In addition, the ERCU will also maintain records of project documents and technical
studies as well as all monitoring and evaluation reports
7.4.5 Identity Cards
7.4.6 During the Resettlement implementation, Cameroonian identity cards will be used to verify PAP. In cases were the person does not have an ID card, the project will verify the signature obtained during the Commission census with the current signature in
order to avoid any fraud. Digital photographs will be taken of all PAPs with their
compensation package for future reference and to avoid fraud claims of no
compensation.
7.5 Community Participation
7.5.1 During the RAP implementation the ERCU will adopt a more systematic public consultation process. It will seek participation of not only of PAPs, but also representatives of local authorities, community leaders, NGOs and other community/religious organizations.
7.5.2 As a first step, the consultation process will seek contribution of the affected communities in formulation and finalisation of the resettlement plan. Overall the main purposes of the participation and consultation process are to:
Provide complete and timely information to PAPs about resettlement stages, land clearance and related activities;
Scott Wilson December 200 7
Page 108
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Obtain the cooperation and participation of PAPs and other stakeholders in
resettlement planning and implementation;
Understandirlg the needs and priorities of PAPs regarding compensation, relocation and other activities to be undertaken
Obtaining reactions of PAPs and other stakeholders on regular basis specially on the effectiveness of policies and implementation process
Reduce the potential for conflicts, as well as the risk of project delays through the grievance mechanism
Enable the project to design the resettlement and rehabilitation program in a
manner to fit the needs and priorities of PAPs.
7.5.3 During the Commission census and the SEB survey a few consultations were held
with the PAPs and other stakeholders. Further consultations will be undertaken to ensure that information on the overall resettlement plan, implementation schedule, eligibility, entitlements and grievance mechanisms are properly understood and accepted by the affected communities.
7.6 Capacity Building
7.6.1 Considering the lack of experience of AES SONEL in resettlement implementation programmes it is recommended that its officers undergo a set of training programmes to help them implement the resettlement programme. AES SONEL can access
resource people from WB or other national agencies/universities for organising such training programmes for its officers and implementation team. Some of the key training inputs required for successful implementation of the RAP should be on the
following themes.
Resettlement policies and principles - WB policies and provisions of AES SONEL's RAP
Social survey skills, rapport building with communities and methods of assessing project impacts
Documentation and record keeping of resettlement process and disbursement of compensation and other benefits
Scoff Wilson December 200 7
Page 109
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Training should include shadowing resettlement experts working on the RAP implementation.
Conflict resolution & participatory methods of public consultation
7.6.2 The training programmes should be timed well before the implementation process and at critical stages during the RAP implementation to equip the implementation
team for the programme.
7.7 Vulnerable People
7.7.1 Special assistance must be given to the vulnerable project affected people during the resettlement plan implementation. This group includes households headed by
women, households with disabilities, child headed households, households made up of aged members or households whose members are socially stigmatised and/or
economically marginalized households.
It is recommended that the wives accompany their husbands in all sensitisation meetings and receive compensation jointly. In case of femalelchild headed households, these should be given priority in receiving their compensation package and assistance in reallocation. With regards to the child headed households, these will be required to identify a guardian which will have to open a bank account in the name of the children. With regards to households with disabilities or aged members,
all efforts must be made so that they are able to attend all meetings and private consultations will be given when and where necessary. In addition, special care will
be given during the reallocation/moving process.
Scoff WiLFon December 200 7
Page 11 0
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7.8 Implementation Schedule
Scoll Wilson December 2007
Page 111
1
2
3
4
5
6
7
9
10
11
12
Completion of Draft RAP
Approval of Draft RAP
Training of AES SONEL staff in
RAP
implementation (ongoing) --- PAPIcommunity consultation
(ongoing)
Notification of
entitlements
Payment of compensation (including
construction of buildings)
Notification to
PAPsIcommunity of
demolition of
structures and land
Demolition of old
structures and land
Replace any community facilities
(i.e. water taps) destroyed as part of requisition
Set up and
implement community
schemes (ongoing)
Grievance mechanisms and
procedures (ongoing) Performance monitoring (Ongoing)
External evaluation (bi-annual for three years)
X
X
Scott WlsonIAES SONEL
AES SONEL & World Bank
BankIResettlement
x
X X
X
X
X X X X X X
X
X X X X X X X X X X
X
X X X X X X X X X X
X X X X X X
X X X X X X
X
X X X X X
X X X X X
Community Liaison TeamIRAP
Coordinating Unit
Community Liaison TeamIRAP Coordinating Team
Compensation &
Payment Team
Community
Liaison TeamIRAP Coordinating
Team
AES SONEU Contractors
AES SONEL
Community LiaisonTeamI Project Coordinating Team
Community Liaison Team
X E R C U
Independent Evaluator
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7.9 Monitoring and Evaluation
7.9.1 Introduction
7.9.2 Monitoring is a crucial element for the success of any resettlement project as it is
important to accurately verify the information related to implementation of the
Resettlement Plan, and should be planned and costed as early as possible in the
project. The monitoring will provide feedback to project management which will help
keep the programs on schedule and successful. A monitoring schedule is presented
below in section 7.9.14.
7.9.3 Monitoring Process
7.9.4 In order to comply with World Bank requirements the overall internal monitoring
procedures will be as follows:
7.9.5 Internal performance monitoring
7.9.6 This monitoring will be based on the resettlement implementation plan and will check
that physical progress has been made in execution of required actions. Narrative
reports on progress should be produced on a monthly basis. The main performance milestones to be checked will be:
Public consultation meetings held;
Census, assets inventories, assessments and socio-economic studies
completed; Grievance and redress procedures in place and functioning;
Compensation payments disbursed;
Relocation of people completed;
Income restoration activities initiated; and
Monitoring and evaluation reports submitted.
7.9.7 Impact monitoring
7.9.8 The impact monitoring will be used to assess the effectiveness of the RAP and its
implementation in meeting the needs of the affected population. It will use socio-
economic data and census information gathered at the beginning of the project as
baseline information. Reporting should be conducted on an annual basis. The methodology for impact monitoring should involve:
Field checks of:
Scon Wilson December 200 7
Page 112
Kribi Power Project - 15OMW Gas Plant and 225kY Transmission Line - Cameroon Resettlement Action Plan Final Report
Payment of compensation and timing of payments;
Preparation and adequacy of resettlement sites;
Housing construction;
Provision of employment and income levels;
Adequacy of training and other support provided;
Infrastructure relocation or replacement;
Enterprise relocation, compensation and its adequacy;
Interviews with a random sample of affected people from different sites to
assess their knowledge and concerns regarding the resettlement process, their entitlements and rehabilitation:
Observer at public consultations with affected people and observe function of resettlement operation to assess compliance with RAP. Check the type
of grievance issues and the effective functioning of the grievance redress
mechanisms by interviewed aggrieved affected people and reviewing grievance and appeals processing;
Survey the standard of living of the affected people after the
implementation of Resettlement to assess whether the standards of living of affected people have improved or been maintained, using key indicators
from baseline information for comparison; and
Advise project management of changes necessary to improve
implementation of the RAP.
7.9.9 Final External Evaluation
7.9.10 According to the World Bank OP4.1 AES SONEL must supplement its internal
monitoring with an "independent monitors as considered appropriate by the Bank.
7.9.1 1 This external evaluation will assess whether compensation and other measures to restore the living standards of project-affected persons have been properly designed
and carried out. It will verify in the field some of the quantitative information submitted by the internal monitoring agency as well as using some of the impact indicators. Due
Scott Wlson December ZOO7
Page 113
Krrbr Power Project - 150MW Gas Plant and 225kV Trammrssron L~ne - Cameroon Resettlement Action Plan Final Report
to the vested interest in reporting smooth implementation by the internal monitors, an
external independent third party should be responsible for this evaluation.
7.9.12 There are various entities such as NGOs, research institutions, consultancy firms and others that qualify as an appropriate external monitoring agency, however these must
have the following essential requirements: (i) Experience in World Bank and/or IFC
projects dealing with resettlement issues (ii) Monitoring and evaluation of socio-
economic projects (ii) experience in socio-economic studies using quantitative and
qualitative methods (iii) experience in livelihood restoration with particular focus on
vulnerable groups. Experience in working in Cameroon is preferable but not essential.
7.9.13 The RAP Team and the monitoring agency will discuss and agree upon a
methodology for the external monitoring for the RAP.
Scon Wilson December 200 7
Page 114
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
7.9.14 Internal Monitoring Schedule
Activities
Monitoring
Monitoring
Audit
Objective
Assess the progress of the RAP implementation in terms of the executions of the recommended actions. Measurement of input
indicators against proposed timetable and
budget.
effectiveness of the RAP and its implementation in
meeting the needs of the affected population including PAP satisfaction with inputs.
Measurement of output indicators such as
restoration of living standards and the development impact
against the baseline. Verification in the field of some of the quantitative information submitted by the internal monitoring.
Source of information
Consultation with affected people. Narrative reports on progress of RAP implementation. Financial reports
regarding RAP implementation.
Qualitative and
quantitative surveys of PAPS
Review of grievance mechanism reports. Regular public
consultation Main performance reports
Main performance
reports lmpact monitoring
reports, independent
surveys and consultation with affected people
Responsibility for Data
collection, analysis and
reporting
ESlA and RAP Coordination Unit (ERCU)
ESlA and RAP Coordination
Unit (ERCU)
Contracted external agency
1 Frequency of Reports
and Audience of Reporting
1
Monthly narrative reports Monthly financial reports Two main performance
reports per year. Audience: Top Management of Kribi
Project
ERCU Lenders
Annual Reports Audience: Top Management of Kribi
Project
ERCU Lenders
I
Twice a year for the next 1 three years after the RAP
has been completed,
starting upon completion of the RAP.
Audience: Top Management of Kribi Project ERCU
1 Lenders
Scoff Wilson December ZOO7
Page 115
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
8 References
AES SONEL. 2003. Cameron Limbe Power Project - Compensation action plan. wbln0018.worldbank.orql,..l779b7621 dd00f96085256dc70079b5aal$FILEICAP%20Mainoh2ORe~ort%2O-
%20Final.pdf
Baka Pygmies htt~:Ilwww.p~qmies.infol
Centre for International Forest Research (CIFOR) "Forest Dwellers on the Brink"
http://www.cifor.c~iar.orq/Publications/Corporate/NewsOnlinelNewsOnline34ldwellers. htm
Chad Export project. Cameroon Report of the External Compliance Monitoring Group.
htt~://www.if~.orq/ifcext/enviro.n~f/AttachmentsByTitle/ecmq3 enq/$FILE/3enqlish.pdf
Country Analysis Brief, 2007, "Chad and Cameroon" www.eia.doe.qov
DSCN. 1997. ECAM 1 1996,Yaounde, MINEFI.
DSCN.1998. Annuaire statistique du Cameroun 1997,Yaounde, MlNEFl
DSCN. 2001. Annuaire statistique du Cameroun 2000,Yaound6,MINEFI.
DSCN. 2002.ECAM II Rapport principal 2001 ,YaoundB,MINEFI
Dugast I, 1949."lnventaire ethnique du Sud Carneroun". Yaounde, Centre IFAN du Cameroun,l49 p. mem.
IFAN,N01
Hand on/lVE/ITDG.2004. "Money Grows on Trees". htt~://www.tve.orq/ho/doc.cfm?aid=l524&lanq=Enqlish
Hathaway, Terri, 2005, "Lom Pangar Dam, Cameroon"
htt~://www.irn.orqlproqramsllompanqar/pdf/O50105lpfact.pdf'
INS. 2004. Annuaire statistique du Cameroun. 2003. Yaounde, MINEPAT
lnstitut National de la Statistique. 2005. Enquete Demographique et de Sante, Cameroun 2004. Ministere de la Planification, du Developpement et I'Am6nagement du Territoire
lnstitut National de la Statistique.2006. lndicateur socio - demographique de base au Cameroun, Projet donnees
actualisees CMR/04/02/04.
FAO, "Cameroon and the Organic Sector"
http://www fao.org/DOCREP/004/Y 1669E/yl669eOi. htm
FAO. 2004. "Land Reform- Land Settlement and Cooperative: A survey of indigenous land tenure in Sub-Sahara Africa". Volume 1. ft~://ftp.fao.orq/docrep/fao/007/v5407t/y5407tOO.~df
Scott Wilson December 2007
Page 11 6
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
MINPAT. 2000. Etudes socio-bconomiques rbgionales au Cameroun. Province du Littoral, Yaoundb. Projet
PNUD-OPS CMR/98~005/01199.92 P.
MINPAT (2000) Etudes socio-bconomiques rbgionales au Cameroun,Province du Sud,Yaoundb, Projet PNUD-
OPS CMR/98//005/01/99,89P.
Ministry of Environment and Forestry of Cameroon. "lndigenous People ("Pygmies") Development Programme for
the Forestry and Environment Sectoral Program." (IPP86)
Ministry of Finance of Cameroon. 2002. ""Conditions de vie des populations et profil de pauvretb au Cameroun en
2001 - Rapport Principal de I'ECAM 2".
PlanningIResettlement Solutions. 2002, "Resettlement Action Plan for the BTC Pipeline in Azerbaijan" http:11ww.bp.com/qenericarticle.do?cateqold=9006631 Bcontentld=7013911
Perenco Cameroun S.A. 2006. EIE Projet de dbveloppement du gaz du champs Sanaga Sud.
Rupp, S. 2003. "Interethnic relations in Southeastern Cameroon: challenging the "hunter-gatherer" - "farmer"
dichotomy" African Study Monographs, Supp1.28: 37-56.
Scott Wilson, 2007, "Environmental and Social Impact Assessment Report for the Kribi Power Project. Cameroon"
Scott W~lson, 2007, "Resettlement Action Plan for the Tanzania Railways Cooperation"
Schreckenberg. K; Awono, A; Degrande, A; Mbosso, C; Ndoye, 0 ; Tchoundjeu, Z. 2006, "Domesticating
lndigenous Fruit Trees as a Contribution to Poverty Reduction". Forests, Trees and Livelihoods Journal. Vol. 16, pp. 35-51.
SMEC, 2006. "Resettlement Action Plan for the "Ethiopia-Sudan Power System Interconnection ESIA"
Njifondou, D., Folack J., Njock J. C ., Bondjia M., Njamen D., 1985.Enquete-cadre et btude socio-economique de la peche artisanale maritime au Cameroun.Rapp.Contrat de service DIPAIFAOICRHOUDIRPECH T I resultats 4
pp+ annexes T2, rbpertoire des campements et villages de peche,l93 pp.
Stone, J. 2006, "The Baka Pygmies of Cameroon" http://www.articlecity.com/articles/travel and leisurelarticle 2651 .shtml
Soltau. K.S. 2003. "Plan de developpement des peuples pygmbes pour le programme national de dbveloppement participatif ( PNDP)" ww.wds.worldbank.orq/ ... /WDSP/IB/2003/07/12/000094946 03070712233780/Rendered/lNDEX/multi0paqe.txt
Tamache J.2000. "Population et dbveloppement dans la province du Littoraln.Rapport d'analyse.
World Bank "Life Expectancy" http://www.worldbank.orq/depweblenqlishlmodules/social/life/index.html
World Bank. 2004. "Community Development Program Support Project - AC127. h t t p : / /W- wds.worldbank.orqlse~let/WDSContentSe~er~DSP/lB/2004102/19/000104615 2004021 909201 3IRenderedlPD FllSDSOP073629.pdf
Scort Wilson December ZOO7
Page 11 7
Krrb~ Power Project - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9 Appendix
9."tpiperldix A: Photos and Maps
Scoti Wilson December 2007
Page 118
Kribi Power Project - I5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.2 Appendix B: The Selection Process
C.l The Selection Process
9.2.1 The Compensation census provided information regarding the project affected people
and their respective affected assets. This information was split into the different villages and the different categories of affected assets as seen in the Tables below
(See Table 9.2-I& Table 9.2-2 below).
9.2.2 Note that these tables are currently outdated as more information was obtained
during the SEE survey, which have decreased the number of affected people.
Table 9.2-1 ESD - Number of Affected Households per Village
Table 9.2-2 KSD - Number of Affected Households per Village
Scott Wilson December 2007
Page 11 9
Kribi Power Projecf - 150MW Gas Planf and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.2.3 The selection of the 250 affected households required for the SEB survey was done
following the same proportion of the categories of affected asset per village. In other words, the same numbers above were used and applied with a 0.36 ratio, which was
obtained from dividing 250 households with the existing 703 affected households (see
Table 9.2-3 & Table 9.2- below).
Table 9.2-3 ESD - Number of Affected Households per Village selected for the Socio-Economic Survey
1. Has land title . Has land title and crops I 1 I 1 I 0 I 1 1 1 1 0 1 I 1 3 1 1 1 10 1 2.74 1 3.92
13. HasLandtitleand house I 0 I 0 I 0 I 0 I 0 I 0 I 0 I 0 I 0 I 0 1 0.10 1 0.15
lhas crops and house L I U u
otal HH per Village
hota~ HH per province I 130 I I 1 I
Table 9.2-KSD - Number of Affected Households per Village selected for the Socio-Economic Survey
9.2.4 Once the exact number of households was obtained per village, a random selection of households per category was done. The names of the head of the households were sorted alphabetically and every third name was chosen starting from the first
name. Additional names were also chosen in case the first chosen households were not available or did not want to do the SEB survey. This additional list was obtained
following again the three-name procedure but started from the second name on the list.
Scon Wilson December 200 7
Page 120
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.3 Appendix C: Additional Socio-Economic characteristics of Project
Area
C.l Relationships between ethnic groups and linguistics features of some provinces in Cameroon
I Province of origin I Ethnic grol
1 WEST
1 Mbatcharn I 1 1 1 Mbabadjou
Bafang Balefok Bafou Bulu
SOUTH
LITTORAL
I 1 1 Fang
Beten Binoho
Evouzok
BATANGA
BAKA
MAB l
BASSA
Mabi Mabi Mabi kwaschior
Baka Baguiele Badjele
Bassa
Bakoko
MPO'O BASSOBALIKOL BAVEC ND JABAN E NYABl OKAK MALIMBA
Scott Wilson December 2007
Page 121
Bassa babirnbi Bassa bilteg Bakoko adie Bakoko yakalack Bakokoyassoukou
Sonkouri Elongasse Mpo'o Bassobalikol Bavec Ndjabane Nyabi Okak Malirnba
NORTH
CENTRE
1
SAWA
FOULBE
BANENG
BAFlA
Yabassi Yernba Foulbe Baneng Bapougou Bafia
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
C. 2 Additional Information regarding the main ethnic groups found in the Project
Area
Bassa ethnic aroup:
Bassa babimbi means Bassa people from babimbi village and they speak the Bassa
language.
Bassa bilteg means Bassa people from Bilteg village and they speaking the Bassa
Language.
Bakoko adie, Bakoko yakalak, and Bakoko yassoukou are languages of the Bassa
ethnic group and they can be grouped into Bakoko as their main language. In
addition, the second name after Bakoko is a Bassa village so for example Bakoko
adie or Bassa Babimbi means Bassa people from Adi6 village or Bassa People from Babimbi village.
Bamileke ethnic group:
Mbouda and Mbandja are Bamileke villages speaking respectively Mbouda and
Mbandja languages. They are part of the Bamileke ethnic group.
Mbeti ethnic group:
Bulu, Eton, Ewondo, Evouzok, Fang, belong to Mbeti ethnic group.
Mabi, and Mabi kwaschior can be grouped into Mabi as a main language.
Mbeti is not a language, but an ethnic group of South province.
Scott Wilson December 2007
Page 122
Kribi Power Project - 15OMW Gas Plant and 225kV Transrnrssion Line - Cameroon Resettlement Action Plan Final Report
C.3 Income Levels
Income levels by Province and Village
Scoti Wlson December 200 7
Page 123
Kribi Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
C. 4 Education
Schools Attended by ESD and KSD Respondents
Scon Wilson December 200 7
Page 124
Kribi Power Project - I5OMW Gas Plant and 225kY Transmission Line - Cameroon Resettlement Action Plan Final Report
Ecole Pilote de Edea Ecole Pilote d'Ekite 21 Ecole Pilote d'Ekite Edea Ecole Primaire de Beon
3, 11
7 Ecole Prive Mme Moukoko d 1 1
Ecole Primaire Mekoko
IEcole Saint Martin de Pongo
ol 1
Ecole Superieure de Technologie
EP de Bonguen 2 EP de Centre 1
Ecole Principale de Koukoue
IEP de Dehane d
1
EP de Dombe 1 EP de la aare 1
EP de Malimba urbain EP de Mbanda EP de Nriou
IEP d'Ekite Pilote 4
EP de Pilote
0 0 0
-
2
EP Ekite EP Elogbatindi
2 4 2
EP d'Ekite 4 13
EP dlElogbatindi 321
- -- -
/EP Koukoue , 1 111
EP Fifinda 1
EP Londji 91
EP Edea
121
I ~ ~ ~ b a n d a Bisseke 4
I I
[S;O d'Edea Fo e Presbiterienne d'Edea Fo er Kantel Fo er Tanier d'Edea Institute Pasteur d'Edea 0 I ST 0 1
EP Fifinda 2
l~ycee Bilingue de Ekite 01
d
Scon WiLson December ZOO7
Page I25
cee Bilingue de Kribi d cee Bilingue d'Mea I d 1
Krib~ Power Project - l5OMW Gas Plant and225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Unfortunately no information was obtained regarding the school's education level or their location.
Scott Wilson December 2007
Page 126
Kribi Power Project - ISOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.4 Appendix D: Definition of categories in open-ended questions
D.l Question: If you have to be resettled by the project where would you go?
The main locations categories mentioned were:
Further from the oriqinal location: The respondent will look for land in the forest to move into, which implied a certain distance from hislher original location
Near to oriqinal location: The respondent will look for land to move into, near the original location of hislher houseldestroyed fieldslcurrent fields
Anywhere: For the respondent it is not important where he will move into
He refuses to movelhe will not move anywhere else
Another Villaae
D.2 Question: Why did you choose the above location?
The main reasons given for the above choices were divided into the following 12
categories as summarised below:
Good conditions: The new location has fertile land, sufficient rainlsun to obtain the same quality and quantity level cultures he lost
Lack of Monev: The respondent has no money to get a better locationlto prepare the fields in time for the farming seasonlto feed his children
Safetv: The respondent is worried about the safety of his family due to the high power tension cables that will be constructed, or he is worried that he will be moved again.
Proximity of previous location: The respondent prefers to stay close to his original fieldlhouselpropertyll is staying in his own fields/house/property/forest/ land
Compensation ~ackaae: Once the respondent has received the compensation for his loss, he will be able to move in and start the farming operation;
Land availability: The respondent cannot find a suitablelfertilelfree land in the location he prefers. Only land available is where he chose
Own Villaae: The respondent will return to his own village to find a suitable IandIHe will stay in his own village
Scon Wilson December ZOO7
Page 127
Kribi Power Project - I5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Healthlold aae: The respondent suffers from lack of strength1 health conditionslold ageldisability which affects his agriculture productivity
Owns the LandIHouselPropertv: The respondent owns the landlhouselproperty he is going to move into
Employment: The respondent is going to look for employment
Will not cultivate: The respondent chooses not to cultivate again and do another activity
Availability of land space: The respondent is looking for land with enough space to cultivate
D.3 Question: What concerns do you have about being resettled?
Main concerns mentioned:
Fertile land: The respondent's main concern is that the new land needs to be
fertilelgood land
Availabilitv of food: The respondent's main concern is the availability of the food
between the period of reallocation and until he starts collecting the produce.
Cultures produced cannot be conserved for that long.
Safetv: The respondent's main concern is regarding hislhis family's safety due to
the high-tension power line being constructed
Disappointment: The respondent has feelings of disappointment, discontent and
frustration mainly due to the fact that his fieldslpropertylhouse are going to be
destroyedlloss of income that will affect his daily activities1 has to leave his family
land1 tombs. He can also be disappointed due to the time it takes to start a new
plantationlbuilding a new house
No Concerns: The respondent does not have any concerns regarding the
reallocation
Similar Conditions: The respondent's main concern is that he will not have the
same conditions regarding his fieldslcultures produced and respective quantities1 treeslhouselproperty as he has now
Land title: The respondent's main concern is that he will not be compensated for his cultures due to the fact that he doesn't have a land title or that his land title will not be recognised nor considered.
Scott Wilson December 2007
Page 128
Kribi Power Project - ISOMW Gas Plant and 22SkV Transmission Line - Cameroon Resettlement Action Plan Final Report
Religious places: The respondent's main concern is that he is unclear about the
situation regarding the fieldslcultureslproperty of the religious places
Evaluation of crops: The respondent's main concern is that the evaluation of the cropsllandlbuildings was not done properly
Construction of houses: The respondent's main concern is that AES SONEL will not build his house
Sacred ulacesltreesltombs: The respondent's main concern is regarding what will
happen to his (access to) sacred placeltreesltombs
Distance of new land: The respondent's main concern is the distance of the new
land as they prefer to be closer to their current fields/house/villagelschoolslheaIth centreslroads
Compensation: The respondent's main concern is when they will receive their compensation package. Some add that they need it to start the preparations for
the reallocation. The compensation process must be done well with no corruption.
HealthIOld Aqe: The respondent's main concern is how he will reallocate and prepare his new land/house/property due to lack of strength1 health conditionslold
ageldisability
Medicinal plantslherbs: The respondents main concern is the lack of certain
medicinal plants and herbs he uses in his new location
Constructionlend of project: The respondents main concern is that he must wait for the construction of the line to finish in order to choose a nearby land to start preparing. But so far the construction has not started.
Field split: The respondents main concern is that his field will be split into several
parts as the line goes through it. This is connected with safety of the respondent, as he must cross the line to go from one field to another.
Pavments overdue: The respondent's main concern is that his payments will be overdue between the time he has to stop cultivating until he receives money to start cultivating again and get the returns from it
Unknown location of the new landlhouse: The respondent's main concern is that he doesn't know where he will move to.
Scott Mlson December 2007
Page 129
Kribi Power Project - 150MW G a s Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.5 Appendix E: Methodology used for Compensation Calculations
Buildings
Crops
External Monitoring and Evaluation
Scon Wilson December 2007
Page 130
Kribi Power Projecl - 15OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.6 Appendix F: Database of affected people
Database of Affected people without Costs
Database of Affected people with Costs
Scon Wilson December ZOO7
Page 131
Kribr Power Project - 150MW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.2 Appendix G: Focus group transcripts
Scoti Wilson December 2007
Page 132
Kribi Power Project - l5OMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
9.8 Appendix H: Questionnaire
Scoff Wilson December 200 7
Page 133
Kribi Power Project - lSOMW Gas Plant and 225kV Transmission Line - Cameroon Resettlement Action Plan Final R e ~ o r t
9.9 Appendix 1: Terms of Reference for the RAP
Scon Wilson December 2007
Page 134
Krrbi Power Projecl- 15OMWGas Plan1 and 225kV Transmission Line - Cameroon Resettlement Action Plan Final Report
Scott Mlson December ZOO7
Page 135
Note from World Bank to be inserted after page I35 o f Kribi Resettlement Plan
Chapter 9 - The Appendix of the Kribi Resettlement Action Plan, which is being disclosed in the World Bank's Infoshop, shows blank pages for Appendices A, E, F, G, H and I. These appendices were prepared and submitted to the World Bank in separate ,files.
The World Bank has added the following Appendices back into the document, after page 135 o f the Kribi Resettlement Plan:
Appendix A: Photos and Maps
Appendix E: Methodology used for Compensation Calculations
Appendix G: Focus group transcripts
Appendix H: Questionnaire
Appendix I: Terms of Reference for the RAP
The World Bank did not add appendix F, the database of affected people, to the Kribi Resettlement Action Plan because it contains personal data. This data is available for public viewing at the World Bank Public Information Center in Yaounde, Cameroon, and AES Sonel offices in Kribi and Douala, Cameroon.
Scott Wilson www.scottwilson.com
AES SONEL
KRlBl POWER PROJECT ESlA
PROJECT LOCATION PLAN D110687-101-1
LllTORAL PROVINCE
Ropwed Powerline
Rovincial Boundary
AES SONEL KRlW POWER PROJECT
UTML'JGS 1964 MllE 32R RESSETLEMENT ACTION PLAN
AES Sonel Kribi Power Project
Cameroon Resettlement Action Plan
PHOTOGRAPHS
AES Sonel Kribi Power Project
Cameroon Resettlement Action Plan
Figure 2 Surveyor conducting questionnaire
Figure 3 Anglican Church
Scott Wilson Ltd
AES Sonel Camer Kribi Power Project Resettlement Action 1
Figure 4a 7th Day Adventist Church - EBE LO 010 80 009
Figure 46 7th Day Adventist Church - EBE LO 010 BO 009
Scott Wilson Ltd
AES Sonel Kribi Power Project
Cameroon Resettlement Action Plan
Figure 5 Kola Women
Figure 6 Kola House
Scott Wilson Ltd
AES Sonel Kribi Power Project
Cameroon Resettlement Action Plan
Crop Price Evaluation at Kribi Market
Bananas for Sale at Kribi Market
Scott Wilson Ltd
AES Krib
Sonel i Power Project
Camc Resettlement Action
?roan
Plan -
Existing Power Line at Mpolongwe
Road Between Kribi and Edea
Scott Wilson Ltd
AES Sonel Kribi Power Project
Cameroon Resettlement Action Plan
Bridge over the Nyong River
Scott Wilson Ltd
1 Methodology used to calculate the value of Temporary Crops
In order to evaluate the amount of compensation to be provided to PAPS as a result of land
take due to the project. The following methodology was utilised for Temporary crops.
4.1 Temporary Crops
Temporary crops include Leguminous cereal and garden crops such as Maize, Soya, Cassava, potato, and sweet potato which are typically sown and harvested during the same agricultural year, sometimes more than once. These constituted the main primary crops'
produced in the project area.
Assumptions:
As leguminous, cereal and garden crops are typically both sown and harvested during the same agricultural year, sometimes more than once and due to the density of planting
regimes. These crops are extremely difficult to count on a plant-by-plant basis, making
compensation by plant extremely difficult.
Due to these two factors the following assumptions have been made:
Given that the reallocation time, upon the publication of an expropriation decree
(Arficle 3 Law No. 85/009 of 4/07/1985) is 6 months, and the different number of farming seasons for the different crops that occur in the year. It is practically impossible to time the reallocation with the commencement of one season for all the
different crops. As such, the value of the compensation will be calculated assuming a one-year impact on the household crop production.
Due to the density of planting regimes, average crop densities per hectare and their
production potential have been established by the Department of Agriculture in Cameroon and by Voice of the Farmer Publications on yields for crops. This information has been utilised to establish the compensation value for these types of crops per hectare taken for the project.
Methodolonv:
The value of temporary crop production per household was calculated using the following methodology:
I Primary crops are those, which come directly from the land and without having undergone any real processing, apart from cleaning. They ma~ntain all the biological qualities they had when they were still on the plants. (FAO: http:llwww.fao.or~es~ess/rmcrops.asp)
1. The area of land utilised for each crop produced (AC) per household was surveyed and recorded - this was undertaken by the compensation commission during the first
census
2. The average yield per hectare (Y) for each crop was established through liaison with
the Department of Agriculture and publications from the voice of the ~ a r m e P
3. The potential production of a particular crop for a particular household was established by multiplying the area utilised for that crop (AC) by the average yeild of
the same crop per hectare (Y).
Crop Production per household (CP) (z)= AC(z) x Y(z)
4. The price of the crop per Kg/g/ton/cup/bag/unit was established through liaison with
the Department of Agriculture, review of publications from the Voice of the Farmer
Magazine and through consultation with marketeers in Kribi. The price of the crop
per Kg/g/ton/cup/bag/unit was then multiplied by the total production expected from
that particular crop by that household (CP) to get the value of the crop for that
household (VP).
Value of Crop (VP)(Z) = CP(Z) x P(z)
5. Depending on the number of seasons (S) that might occur for each type of crop in
one year. The number of seasons per year were multiplied by the value of the
production to give Total Value of Production for theCrop(TVP):
6. Through liason with the Department of Agriculture and the Voice of the Farmer, the
quantity (QS) and cost of seeds (CS) required per hectare for each crop was defined. Therefore per hectare lost to the project the follwoing calculation was used and the result added onto the Total Value of Production based on the assumption that PAPS will require new seed to plant in ressettled areas.
Planting Cost (PC) (Z, = CIS(^, x CS(z,) x No of hectares(Ha,~) x Seaons in one year (S)(Z)
7. Therefore the Grand Total Value of Compensation per hectare (GTVC) is equivalent
to the Total value of lost Production for 1 year per hectare plus the Planting Cost for
one year per hectare.
GTVC = TVP+ PC)
La Voix du Paysan - Recueil de Fisches Techniques Pour L 'Entrepreneuer Rural Tome 2 Edition 2001
8. Given that one household might have different crops (in the same or different plots),
the grand total value of the crop production per household is a simple addition of all
the GTVC's for each crop.:
1.2 Methodology used to calculate the value of Permanent Crops
Permanent Crops
Permanent crops are sown or planted once and will not be replanted after each annual
harvest. The main permanent crops in the project area were fruit trees and medicinal plants. Main fruit trees include citrus trees (orangellemon), mango, and guava trees. The majority of medicinal trees were not identified in terms of their common name.
Assumptions:
Due to the lack of information regarding the actual age of the existing trees, and given the fact
that mature trees are considered slightly more valuable by Decree No 20031418 of the 25th February 2003, the same logic was applied in the calculations. As such, young trees were
considered as being in their first year of production (as these produce considerably less in the
first year of production then when they are in full production3), whilst adult trees were
considered to be in their second year of production.
Methodoloqv:
With regards to the calculations used to obtain the current value of permanent crops, information was obtained from the compensation commission census, department of agriculture in South Province and local markets.
The compensation commission census provided the following information per household: Type of tree (Local name)
Maturity of tree (Adult or young) Condition of tree (Wild, local, improved) Quantity of tree (number of individual trees)
The department of agriculture in the South Province provided the following general information for both the South and Littoral Province and for each type of tree:
Number of growth years until it reaches production Number of production years
3 According to the department of Agriculture in the South Province
Cost of a small plant (including the cost of labour, fertilisers, water, to reach the size of a small plant) Annual Yield per tree Average market price per Kg/g/ton/cup/bag/unit
In order to determine the value of the permanent crops, the following methodology was used:
1. Given that permanent crops take longer to achieve the production stage, these "waiting years" must be taken into account as lost production, assuming that if the tree was not destroyed, it would be producing for those years. The waiting years for tree A = W(A)
2. Given the difference in tree maturity (young or adult), one or two years must be added to the waiting years as such:
Young Tree A: Young years (w)= W(A)+ 1 Adult Tree A: Adult years (ay) = W(A)+ 2
3. Once the overall number of years have been obtained, the total yield (TY) for tree A
must be calculated:
Total Yield (TY(,)) = Average Yield,~)x W(A) or ay(A)
Note that even though the first year of production has a lower yield, it was assumed for the calculation that it had the same yield as the remaining years. As such, the only difference between a young and an adult tree is an additional production year.
4. The production cost (PC(A)) of tree A is obtained by multiplying the TY,,) with the
average market price (P(A))
5. In addition, to the PC, the household should also receive a similar quantity of plant trees (QP) in saplings to get the Grand Total Production Cost (GTPC)
GTPC (A) = PC (A) + QP (A,
6. Given that one household might have different trees (in the same or different plots), the grand total production cost (GTPC) per household is:
GTPC (A) + GTPC (B) + GTPC (c) +... = GTPC (A+B+c+...)
"1.3 Further Assumptions for both Temporary and Permanent
Crops:
Due to the fact that some temporary and permanent crops are indigenous trees and crops, there is very limited information regarding average production yields, market
prices, years of production, etc. As such, for the crops that information is lacking, the
consultants :
1. put the crop into their respective category, e.g. cereals, legumes, tubercules, medicinal plants, fruit trees, etc..
2. Obtained the average percent increase or decrease per category, when compared to the 2003 decree prices per crop
3. Applied the same average increaseldecrease to the average 2003 decree prices for the crop
2 Compensation Methodology for Buildings
Building compensation values were determined in line with Decree No2006130231PM of
December 29,2006 (Fixing the modes of Administrative Evaluation of The buildings in
Fiscal Matters) or through negotiated agreements between the CEC and PAPS.
Principles of Decree No 200613023
The main principle of Decree No 200613023 is that the determination of value of
buildings is undertaken by taking into account the land, construction, and rental
markets, of the infrastructures as well as the urban services level, which the
building benefits from due to its geographical zone.
'The Decree defines ten geographical Zones listed below:
- Zone 1 : Douala and Yaounde very smart districts;
- Zone 2: Douala and Yaounde smart districts; - Zone 3: Douala and Yaounde other city centre districts;
- Zone 4: Other districts on the close periphery of Douala and Yaounde; - Zone 5: Other districts on the distant periphery of Douala and Yaounde; - Zone 6: City centre districts of the provincial big cities;
- Zone 7: Districts on the periphery of the provincial big cities; - Zone 8: City centre districts of the small and medium provincial cities; -Zone 9: Districts on the periphery of the provincial medium and small cities;
- Zone 10: Inhabitant rural zones.
The buildings found in the ROW are located in Zones 9 and 10 and are subject to the provisions of Section 4 of Decree 200613023.
Under Article 8 (Decree 200613023) For the determination of the administrative monetary values of imposition of the constructed buildings, the criteria and parameters evaluation are as follows:
- Type of construction;
- Construction values per type; - Balancing coefficients of the constructions value per construction type;
A - Types of construction
The buildings are classified in five (5) types as follows, according to their architecture, of the quality of the material used and of the level of the completion observed:
Type 1: High Standing - Constructed building on level, villa or apartment built of high standards with definitive completion materials.
Type 2: Standing - Constructed building on level, villa or apartment in built of comfortable
definitive completion materials.
Type 3: Standard - Villa or apartment built of definitive standard completion materials.
Type 4: Semi Hard - Constructions built of semi-hard middle completion materials.
Type 5: Temporary - Construction built of temporary completion materials.
B. Values for each type of Construction
The average price of the square meter built for each constructional type has been determined through the observation of market values as follows:
- type 1 more than 145 000 Flm2
- type 2 from 90 001 to 145 000 Flm2
- type 3 from 45 001 to 90 000 Flm2 - type 4 from 20 001 to 45 000 FIm2 - type 5 from 7000 to 20 000 FIm2
The gross administrative monetary value of the constructions is calculated by applying to the built surface, the price of the square meter according to the constructional type.
The majority of Buildings within the ROW are defined as type 3, 4 or 5 and where no
agreed value has been determined between the CEC and PAPS, these values have been
utilised.
C -The pondering coefficients of the construction value
Under Section C of the Decree the gross administrative monetary value calculated as mentioned above, can be reduced by the following coefficients, to obtain the administrative monetary value of imposition for the constructed buildings:
A) The depreciation coefficient for absence of connection to the water adduction networks = 0,10
B) The depreciation coefficient for absence of connection to the electric network = 0,05
c The depreciation coefficient for absence of the telephone network = 0, 02
D) The depreciation coefficient for accessibility = Good: 0, Average: 0, 1 and Bad: 0,2
E) The depreciation coefficient for state of appearance = Good: 0,Average: 0, 3 and Bad: 0, 5
In summary the calculation for Buildings Compensation is as follows
Area of Building (width x length) m2 X Type of Construction (Type 1 -5) X (1- (Coefficient A+B+C+D+E)) = Total Compensation Value
3 Budget Estimate for the External Monitoring and Evaluation
Activity
Evaluator's Fees
Travel
Per diems
Miscellaneous (Communicationslprintinglp hotocopying)
Total(CFCA)
58,466,520.00
5,554,319.40
5,846,652.00
2,923,326.00
Unit
Day
Trip
Day
Trip
Quantity
I 2 O
6o
72,790,817.40
Unit Price (USD)
1,000.00
1,900.00
200.00
1,000.00
(USD)
120,000.00
11,400.00
12,000.00
6,000.00
Grand Total 149,400.00
OSLLP IOSSL1, I elude8 104 l V 1 0 1 l I
0519 OOSLOZ OOSLLL OOOSE ooosc
0005F
uotle.ueduro3 OOOL
056P IOS6P Iala~uldadreoud.uownpo~d) = uaneruaducg
u n p - u q p s u w l u o j 005 OSLS OSPL
0091 IOSL
OSL9 OOSLOL OOSLZL 00597. o o s x
OOS9Z
OOCL (~~lld.pald/UO!Pnpold. (!inp'djl L+ lo A,! ~+ )uopnpa~d 04 n e s l ) = uqsruadwog g
IlunoA -uo!lrsuaduo3 00s 0525 OSPL
I barno, e raaenleha hfiolopoqlaui d v u j l COOL aal==a 01 lmba =q llu uoae5uadruo31 I
002
n u d dam01 rn ralenlene lSolopoq+w d v 8 ~ COOL -L"aa ol lanba aq I,M "iuoneruaduog
eel1 b n o l jo a~lld+a3ud.pldpolpnpo~d. uotpnpa~d ol n o e l = uo~~e ruaduog
OOL
IUW~O)
a n l 6unoljo e3ud+a3ud.psld(uolpnpo~dd uoipnpo~d o l weal = uoaenuadluo3
L 5 5 S 5
s
~ u ( uapsuedwo3 ( rq l a d uo1psuadwo31 s u n u o 3 l uotpnpordolnra~l %u V3j.Wd
OOOOLLi
OOE 008 OOP 00s 00s
00s
u o l p n w d 01 u w a ~ L 5 L
%u V34aWd OOP 0001 0021
2. eq/ )uqd or swd+ suolear 6ulmo~6 L . mud. eq/&lluenb suoseof = uollesuadwo3 6uwio~6 OSE
D.2 Transcripts
Village: Malimba Urbain 1
Date: 05.06.07 Time: 13:45 - 16:OO
Number of participants: 12
Question I
Five out of 12 participants requested the option of receiving money from AES SONEL instead of being reallocated and their house constructed for them by AES SONEL. The remaining participants all
expressed that they would like AES SONEL to build them a new house with better material. However one person requested the house to have the same dimensions as the current house. The remaining
expressed their desire to have a bigger family house. Some participants even mentioned the number of rooms that they would like and these ranged from 6 to 12. All the participants that chose the construction instead of the money, stated that their new house should have all the comforts that their current house has, this meant that if the house to be destroyed had electricity, water, TV reception.
phone network, proximity to roads, proximity to their children's schools orland their work then the new house should also have the same thing. In addition, some expressed their desire to remain close to the
previous house.
Question I I
When asked the location of the new house, the people that asked for money instead of the construction
of their new house by AES SONEL stated that they would find their own land somewhere else and that
AES SONEL did not have to do anything in this regard. The remaining participants stated that if there was no compensation for the land, and then they would require AES SONEL's support in finding the land, negotiating and preparing if for construction. Some participants had the idea that this new land
would be purchased by AES SONEL as they had also purchased the previous land, even though they had no land title. Finally, these participants also expressed their wish that AES SONEL find them a land
not very far from their current activities such as children's school, work, road, and others.
One participant said that his house that was going to be destructed was not the house he was living in
and therefore he would remain in that house and use the money for something else. AES SONEL did
not have to find him another land.
Question Ill
All participants expressed their willingness to know exactly when AES SONEL would give the compensation, as that would determine the period for their reallocation. However, when they received the information that according to the Cameroonian law, they had a maximum period of 6 months to reallocate from the moment they received the compensation, all said that they would respect the time stipulated by the law. Nevertheless, there was some concern regarding the weather season, as that would affect the construction time. In other words, if they received the compensation during the raining
season, the construction time would not be possible during the six months predicted due to the constant
rain.
Question IV
When asked about any possible disabilities that they would like AES SONEL to pay particular attention
to, many of the participants mentioned their own old age as a physical problem. More specifically there were four people with physical handicaps out of 12 respondents. And four people mention that they had family members that were very old and had difficulty moving and therefore would require special assistance. It is important to note that some of the old family members mentioned were not permanent
members of the household.
Question V
When asked about any concerns they might have due to the reallocation, the main concern were about the location of the new land. Their main worry was that this would affect their daily activities and even
increase their daily expenditures. As such participants mentioned the proximity to their children's
schools, their place of work, their access to the road, electricity and water as some of the factors that should be taken into consideration when choosing the new land.
One person was concerned about when they would receive the compensation or know the new land
they would be reallocated too, as he needed to matriculate his children in the school and could not wait for too long otherwise their children would loose their place in the current school. In addition, if he did
matriculate them and then was reallocated to a much further location, their children would need to change schools and he would need to pay again.
Some people were also concern if the compensation for their houses would reflects the prices of today's material.
One particular person was concern about the affected people's mental stability during the reallocation process and believe that the reallocation should be accompanied by a certain moral assistance that could be given in the form of additional material goods necessary for their well being.
Question VI
The majority of the participants stated they would prefer to leave their graves untouched where they were. In addition, they would like AES SONEL to demarcate them in order for them to be visible during
the construction period and therefore minimise the risk of being tempered with.
Only one participant expressed his wish to have his grave reallocated to the new site and was happy to receive AES SONEL's assistance in this reallocation
All participants understood that they would not receive any compensation for their graves if they were to be reallocated, as AES SONEL would provide this service.
Question VII
= The participants were given time to answer any questions that they might have regarding the reallocation. To some of these questions the team was able to provide an adequate answer however to others, these were only noted down. All of the questions posed are expressed below.
When will they receive their compensation package?
Would AES SONEL compensate them for additional costs that came about due to the reallocation
such as the matriculation of their children in a different school due to the position of the current location after being matriculated in one school?
Will there be any more studies after this one? Will there be a new commission coming?
Will AES SONEL provide them with transport for them to move their material assets from the
original house to the new house?
One respondent mentioned that he had two houses that were going to be destroyed and was
wondering if AES SONEL could build his two houses instead of one.
Could they use the material from their houses to help them build their new house as AES SONEL
was going to destroy the house and had no need for this material?
= Will their new house have the same quality as the previous house with regards to water, electricity,
TV network, phone network, etc.
Observations from the moderator
People seem to be impatient to receive their compensation and are tired of being surveyed. They have expressed the need to have a detailed plan of all activities that will occur with set times and dates and
also asked to be considered a priority during the recruitment process for the construction of the line. The meeting was conducted without any particular incident. Their relatives represented participants who
could not attend the meeting. The concerns show that the participants want AES SONEL to respect their
wishes and take into account their concerns. No one seemed to object the project.
List of ~ a r t i c i ~ a n t s
1 NO ( Last Name, First Name 1 contact I 1
2
3
4
5
6
Achuache John
Hambem J. Jacques
Fansi Toko Desire
7
8
9
10
11
12
96650773
75701398 1
Otto Marie Noel
Ngono Hypolite
Mapout Bienvenu
99465391
7797821 5
99603066
lmandi Nicolas
Ebobane lseac
Nang Babes David Aime
lsson Daniel Martin
Lissom Joseph Blaise
Billong N. Paulette
99997936
77854928
9631 3204
Village: LONDJI 2
Date: 04/06/07 Heure: 8.30 10.10
Nombre de participants: 4
Question I
Dans ce village I'option proposee par AES SONEL a arrange la moitie des participants. Ils
souhaiteraient que AES SONEL leur construise une maison meilleure que celle actuelle. Les cles doivent leur dtre remises. Les autres ont opte pour une solution differente qui est celle de chercher leurs
propres techniciens, mais que AES SONEL finance et cordonne les travaux de construction. La raison
est la lutte contre la pauvrete et le chbmage des jeunes dans le village. Ils estiment que les jeunes du village sont qualifies et aptes a faire ce travail.
Question II
Deux participants affirment avoir du terrain pour la reconstruction de leurs maisons. Un autre dit avoir du
terrain mais sur lequel se trouve sa palmeraie or il voudrait que sa maison soit construite sur cette parcelle. Sa preoccupation est que AES SONEL revienne sur le terrain voir sa palmeraie,car il estime
qu'il merite une indemnisation pour cette palrneraie qui constitue son activite principale. Le dernier ne possede pas de terrain et ne veut mdrne pas chercher. II laisse cette responsabilite a AES SONEL.
Question Ill
Sur cette question les avis sont differents. Pour ceux qui attendent les maisons de AES SONEL, le demenagernent prendra une semaine parce qu'ils estirnent qu'ils ont une nouvelle maison et n'ont plus
rien a faire dans I'ancienne qui sera d'ailleurs detruite. Pour les autres, un mois suffirait A construire une maison et a y amenager. Ils ne voudraient pas trainer de peur de depenser I'argent a d'autres fins.
Question IV
Une personne declare un cas d'irresponsabilite dans son menage. Madame BILONGO en I'occurrence
souhaite que AES SONEL lui construise une maison parce qu'elle estime que remettre de I'argent a son fils causerait des problemes. pour les autres il n'y a pas de probleme
Question V
Les gens sont inquiets parce qu'ils laissent tout derriere eux et ils doivent recommencer a zero. Arriveront I-ils a s'integrer facilernent dans le nouveau milieu ? AES SONEL les mettra t-ils dans les
meilleures conditions de vie ? Auront-ils des points d'eau ? Pour ceux qui ont leur puits dans la
cour AES SONEL pourra t-elle les aider a creuser un autre ?
Question VI
La majorite des participants n'a pas de tornbe. Pour ceux qui en ont une partie souhaite que AES SONEL les aide a les recaser mais dans les m8rnes conditions qu'actuellement. L'autre partie restante souhaiterait que les tornbes restent sur place.
Question VII
Les participants se demandent a quel moment AES SONEL construira les maisons pour le recasement. Ils aimeraient savoir s'ils peuvent rkcuperer les materiaux provenant de la destruction de leur maison et
si AES SONEL peut les aider A ouvrir un compte bancaire pendant la periode des indemnisations.
List of Participants
Contacts
96 01 65 49
99 62 21 83
99 65 93 35
99 1 1 98 59
No.
01
02
03
04
Noms et prbnoms
BOKALY SAMUEL
NZOUANGA JEAN PIERRE
BlLONGO represente par sa veuve NDOMO
MISAGU represente par NYARl JEAN CLAUDE
Village: ELOGBATINDI
Date: 04 juin 2007 Heure: 12.20 14.05
Nombre de participant: 2
Question I
Les participants souhaitent tous que AES SONEL leur construise une rnaison rneilleure que I'actuelle.
Leur inquietude est de savoir s'il y aura des habitations provisoires parce qu'ils estirnent que AES SONEL doit prendre un certain temps pour construire de bonnes maisons. ils ne voudraient pas des rnaisons faites a la hate.
Question II
Ces personnes ont du terrain rnais c'est dans le rnarecage. ils souhaiteraient que AES SONEL les aide
a degager ce rnarecage
Question Ill
Les participants pensent que trois sernaines suffiront pour arnenager dans la nouvelle rnaison des que
celle-ci est prete. Cet intervalle leur perrnettra de planter quelques fleurs et de quitter celle qui sera detruite pour que AES SONEL fasse aisernent son travail.
Question IV
Un des deux participants dit qu'il est vieux et il estirne qu'il lui faut une voiture pour son dernenagernent. AES SONEL devrait leur envoyer des specialistes en arnenagernent et la rnanutention. L'autre
participant n'a pas de problerne.
Question V
Quelques soucis ont ete releves. Etant donne que ces deux participants habitent une rn&rne concession ils voudraient savoir si AES SONEL va rernplacer tout ce qui sera detruit. Par exernple le puit, la barriere naturelle( fleurs). Ils souhaitent avoir la lurniere avec une facturation speciale, et les forages
pour avoir de I'eau potable.
Question VI
Un des deux participants n'a pas de tornbe. Pour celui qui en a, il souhaite que AES SONEL I'aide a recaser ses tornbes parce qu'il estirne que ses rnort doivent etre a cote. Pour celles qui sont dans la
rnaison, il voudrait qu'il y ait un caveau familial a cote de la nouvelle rnaison. Pour celles qui sont dehors, il voudrait qu'elles soient recasees si possible avec les rngrne monuments.
Question VII
Trois questions ressortent ici. Est-ce que AES SONEL nous aidera a financer les rites qui accornpagnent le recasernent des tornbes ( reorganiser toutes les &r6rnonies liees au deuil et a
I'inhurnation) ? Toutes les rnaisons seront-elles faites en rnatkriaux dbfinitifs ? Quand est-ce que nous serons indernnises ?
List of Participants I No I Norns et prbnoms Contacts
01
02
MEDJO MARCEL MYNYINGA TONYE
77 42 46 821 99 99 07 82
99 12 36 94
Village: BIBABWE
Date: 04/06/07 Heure: 15.10 - 16.45
Nombre de participants: 4
Question I
Trois participants sur quatre souhaitent que AES SONEL leur remette de I'argent pour construire eux meme leurs maisons. Etant donne qu'ils sont sur une cote, ils estiment qu'ils sont mieux places pour choisir les materiaux de construction capable de resister aux intemperies (coup de vent, pluies. Le quatrieme voudrait que AES SONEL lui construise une maison meilleure avec de bons materiaux.
Question II
Sur cette question, tous ont un terrain ou ils pourront etre recase.
Question Ill
Pour ceux qui doivent construire, les reponses varient de trois a six mois. Ils estiment que s,ils ont de I'argent, I'achat des materiaux sera facile et les travaux prendront trbs peu de temps parce que I'un
deux est du metier. pour celui qui souhaite qu AES SONEL lui construise une maison, trois mois lui seront suffisant pour demenager parce qu'il doit se preparer a quitter sa maison qui regorge beaucoup de souvenir pour lui et il faut le temps de planter les fleurs dans la nouvelle maison.
Question IV
Tous afirment qu'ils n'ont pas de handicaps a signaler.
Question V
Leur principal soucis concerne la proximite avec la ligne haute tension. Ils estiment qu'ils seront en
danger en restant t k s proche de la ligne or c'est a ce niveau que se situent leurs terrains.
Question VI
Pour ceux des participants qui ont des tombes, ils souhaiteraient qu'elles ne soient pas deplacees parce
que du vivent des defunts ils avaient eux-m8mes choisis le lieu ou ils seront enterre.
Question VII
Ces participants demandent pourquoi AES SONEL n'a pas repris I'ancienne ligne ?
Observation :
Les participants dans ce village n'ont pas ete cooperatifs des la reponse a la premibre question qui est d'avoir de I'argent, ils ont estime que le reste des questions n'etait plus important d'ou leur reponse evasive.
List of Participants Contacts No.
01
02
03 04
Noms et prbnoms
NABVOUO JULIENNE
BlKlEPTOU EMMANUEL
NANDANG THERESE
NGONOROSE
Village: APOUH Date: 05-06-07
Heure: 08.20 - 10.30
Nombre de participants: 5
Question I
Tous les participants ont souhaite que AES SONEL leur donne I'argent pour qu'ils construisent eux meme leurs maisons.ils estiment qu'ils ne peuvent &re mieux servis que par eux-m8mes que compte
tenu des delais AES SONEL risque de construire des maisons a la hate et cela ne refletera pas I'image
qu'ils attendent de leur maisons. Ils ont deja construit celle qui est la et ils ne veulent aucune intervention externe ils pensent enfin que AES SONEL peut ne pas respecter les dosages de ciment et
surtout elle ne tiendra pas compte de leurs plans.
Question II
Pour ce qui est d'avoir une parcelle de terrain ou se recaser, la majorite des participants affirme que
I'achat d'un terrain est tres difficile parce que la ferme Suisse a occupe tout I'espace et plus personne ne vend le terrain. Mais a la fin plusieurs ont affirme avoir une parcelle ou reconstruire leurs maisons,
mais seulement ce terrain est accidente. II y a des rochers et cela va necessiter un terrassement, ils
sollicitent I'aide de AES SONEL pour cela. Une seule personne a dit n'avoir pas de terrain mais est sur
d'en trouver a EDEA.
Question Ill
Pour ce qui est du temps necessaire pour le recasement, les reponses varient de trois a six mois. Certains pensent qu'ils ne faut pas se precipiter pour faire une maison solide. II faut calculer la periode
de sable, trouver les techniciens capables de reproduire ce qui leur est demander. D'autre affirment se connaitre en construction ils savent exactement ce qu'il y a a faire. Le tout est d'avoir de I'argent en
main.
Question IV
Aucun participant n'a signale un cas d'incapacite ou de handicaps quelconques
Question V
Tous les participants sont inquiets des troubles que ce recasement va causer dans leur famille.
Notamment pour ce qui est de la scolarisation des enfants qui seront eloigne des etablissements qu'ils
frequentent maintenant. Pour celui qui va chercher son terrain a Edea, il se demande si AES SONEL recreusera ou alors lui donnera une indemnisation pour son puit qui sera detruit. Y a t-il une indemnisation pour le prejudice moral cause par la destruction de son commerce qu'il tenait a la ferme
suisse? Les participants voudraient savoir si les sacrifices qu'ils ont accompli jusqu'ici, a savoir acheter le terrain sur lequel ils ont construit et tous les travaux effectues sur ce terrain, seront pris en compte
lors des indemnisations. Une autre personne est inquiete de savoir comment gerer ses differentes maisons etant donne que sa concession a Bte divisee en deux, et la nouvelle maison sera construite deux kilometres plus loin. La dernikre inquietude est de savoir a quand I'indemnisation?
Question VI
Aucun des participants n'a de tombe affectee
Question VII
Plusieurs questions ressortent. Qu'arrivera t-il si nous trouvons du terrain dans une zone non klectriske alors que nous avions la lumibre dans I'ancienne maison? AES SONEL va t-elle nous rembourser I'argent que nous avons dkpense pour acqubrir le terrain sur lequel nous avons construit? Aurons-nous le temps suffisant pour reconstruire avant que nos maisons soient dbtruites? La question de I'indemnisation est encore revenue A ce niveau. Les participants trouvent que le processus prend plus
de temps qu'il n'en faut, et certains sont entrain de mourir. Ils ont peur de ne pas toucher leur argent.
List of Participants
Contacts
99 78 60 82
9964 14 10
96 37 61 18
99 79 08 77
99 55 92 64
No
01
02
03
04
05
Noms et prknoms
ETAMANE ETAMANE JEANVIER
LOME JOSEPH
EPOULA PIERRE
NDONG SERGE
BOUYAME LOUIS
Village: MALIMBA URBAIN Date: 05/06/07
Heure: 13h30 15.05
Nornbre de participants: 10
Question I
Sur les dix participants, huit ont demande que AES SONEL leur donne leur argent pour pouvoir
construire eux meme leurs maisons. 11s estiment qu'ils sont mieux place pour savoir ce qu'ils veulent, construire selon leur plan, choisir tout seul le materiel de construction. Une personne dit qu'il est du
domaine et qu'il peut tout seul se charger de construire sa maison. Les deux autres personnes ont sollicite que AES SONEL leur construise des maisons meilleures. L'une dit qu'elle est veuve et ne sait pas ou aller et I'autre dit que AES SONEL doit restituer sa maison.
Question II
La plus part des participants sont des allogenes donc n'ont pas toujours la possibilite d'avoir plus d'un terrain parce que nous sommes dans une zone urbaine et les terrains cootent excessivement chers
c'est pourquoi la majorite ne possedent pas de parcelle de terrains ou reconstruire leurs maisons.
Certains pensent qu'avec de I'argent en main ils serait facile de trouver et de negocier une parcelle de terrain. D'autre souhaiteraient que AES SONEL les aident a trouver et a negocier le terrain. Quelques-
uns ont le terrain mais qui va necessiter un terrassement, et il sollicite I'aide de AES SONEL pour cela.
Ils souhaiteraient que ces terrains ne soient pas eloignes de leur lieu d'activite.
Question Ill
Pour les participants qui veulent construire eux mgme leurs maisons, le temps du recasement varie entre six et douze mois. Plusieurs raisons ont ete avancees, pour construire une maison ils ne vont pas
utiliser des machines mais des personnes qui peuvent se fatiguer et prendre du repos. II faudra attendre que les enfants soient en vacances pour demenager, il faut calculer avec les intemperies, notamment les pluies, la rupture des stocks sur le marche, et enfin ils estiment que pour faire quelque chose de
solide ce n'est pas a la hate. Pour ceux qui attendent des maisons de AES SONEL, ils estiment que deux ou trois mois seront suffisant pour demenager, parce qu'ils auront deja une nouvelle maison et
qu'il n'y aura plus de raison de rester dans I'ancienne
Question IV
Aucun cas de handicap n'est signale ici.
Question V
Les participants sont preoccupes par le fait qu'ils vont laisser toute leur vie derriere eux et recommencer a zero, or I'insertion dans un nouveau groupe n'est toujours pas facile. Certain sont inquiet de savoir s'ils auront la lumiere, I'eau, si la main d'c~uvre qui sera utilisee pour construire leurs nouvelles maisons
sera pris en compte lors du calcul des indemnisations, ils veulent savoir comment et sur quelle base se fera le calcul des indemnisations, sera t-il objectif? Enfin ils souhaiteraient que le gouvernement ne soit pas mble dans les transactions financiers. Que cella soit fait entre AES SONEL et les affectes !
Question VI
Parmis les participants, la majoritk n'a pas de tornbe. Une seule personne en a et souhaite que AES
SONEL I'aide a recaser cette tombe si possible.
Question VII
Deux questions ont kt6 posees, celle de savoir a quand le financement? Comment auront-ils des
rkponses a leurs prkoccupations ?
List of Part ici~ants
No.
01
02
03
04
05
06
07
08
09
10
Noms et prbnoms
BlKAT BAHOYA REYMOND
KOUMOUKAN EPSE MAHOP ANASTASIE
SUUM EWONGO PASCAL
HlNAGSlKE SEVERAIN
NGUENA BATOUM MAURICE
BlERAl DIEUDONNE JOSEPH
BIEGWA EPSE BELL ESTHER
NSONGO EDlMO ETIENNE
NGOULEKANG MARCELINE
LISSOM JOSEPH BLAISE
Contacts
7792 11 78
96 40 39 12
96 69 88 46
99 38 50 77
99 28 51 42
96 23 54 70
75 90 28 51
74 65 44 08
75 44 46 82
77 87 49 28
Village: Malirnba Urbain Date: 06-06-07
Heure: 09.10 - 1 1.30 Nombre de participants: 10
Question 1
Les participants ont eu de la peine a repondre a cette question car ils ont estimes que le terme meilleur
etait un pigge. Apres mainte explication Six participants ont finalement souhaite que AES SONEL leur construise une maison meilleure et le reste voudraient que AES SONEL leur remette de I'argent afin
qu'ils construisent eux meme leur maisons parce qu'ils estiment qu'ils sont mieux places pour savoir ce
qu'ils veulent comme maison( le plan de la maison, rnateriaux de construction, meilleurs techniciens)
Question II
En ce qui concerne la parcelle de terrain ou construire la maison, un seul des participants avoue avoir une parcelle. Cette question reste la principale prBoccupation des autres participants, qui pensent qu'il
est difficile de trouver du terrain dans le village parce que c'est une zone urbaine et lorsqu'il est possible d'en trouver, celui-ci coirte excessivernent cher. Voila pourquoi leur souhait est que AES SONEL les aide a trouver et a nBgocier le terrain. Un des participants propose que AES SONEL utilise une partie
de I'argent qui doit leur Btre remis pour leur acheter du terrain et utiliser le reste pour la construction. En ce qui concerne cette question, plusieurs personnes ont pense que AES SONEL devait acheter du terrain a tous les recases parce qu'ils estiment que mBrne si leur terrain n'ont pas de titre, ils ont
debourse beaucoup d'argent pour I'obtenir.
Question Ill
Concernant le temps que mettrons les affectes pour se recaser, les rBponses varient de six a douze mois pour ceux qui prBferent construire eux rneme leur rnaisons. Plusieurs raisons ont ete Bvoquees. La plus importante concerne les intemperies (pluies, rupture de stock de materiaux sur le marche)
certains ont evoque le probleme d'ecole, il souhaiteraient que le dernenagement se fasse pendant les vacances pour leur permettre de rnieux choisir les Btablissements scolaires en fonction des distances et
de la qualite d'enseignement dans ces etablissernents. D'autres enfin ont parle de la periode des recoltes parce que les nouvelles maisons risquent d'etre loin de leurs champs. Pour ceux qui attendent des rnaisons de AES SONEL ils pensent que un a deux rnois seront suffisant pour dernenager parce
qu'ils auront a ranger leurs affaires sans prbcipitation, a bien arnBnager la nouvelle maison( planter les fleurs, planter les arbres fruitiers).
Question IV
Aucun cas de handicap ou d'incapacite n'a ete souleve par les participants, parce qu'ils pensent qu'a
partir du moment ou ils ont de I'argent tout est possible
Question V
Plusieurs inquietudes ont BtB soulevBes. Les participants voudraient bien savoir s'ils auront de I'eau. des hapitaux, de I'dlectricitB, si les enfants auront des Bcoles tout proche, si les droit des populations seront respectes a la lettre. Y aura t-il un financement pour le dBrnBnagernent ? Recevront-ils une compensation pour la perturbation de la vie sociale des enfants, qui vont laisser derriere eux leurs amis et leurs habitudes ? AES SONEL va t-elle engager leurs enfants pour les travaux? Ils souhaiteraient
enfin que le gouvernement n'intervienne pas dans les transactions financieres. Que cela se fasse
directement entre la SONEL et eux, parce qu'ils risquent ne pas avoir la totalitb de leur indemnisation.
Question VI
Parmis les participants, une seule penonne a une tombe affectbe, et elle souhaite que celle-ci reste sur
place.
Question VII
Plusieurs questions ont btb posbes a savoir s'ils pourront recupbrer les matbriaux des maisons a
dbtruire ? AES SONEL prendra telle en compte leurs terrains non titres parce qu'ils estiment qu'lls les
ont achetbs et ils doivent &tre rembourses.
List of Participants
Contacts
99 46 53 91
96 42 31 15
74 02 62 92
99 39 32 55
752469 12
99 43 69 83
77 04 73 84
7768 1823
96 21 18 69
No.
01
02
03
04
05
06
07
08
09
10
Norns et prbnorns
OTTO MARIE NOELLE
NGO NOLBA MARIE LUlSE
DENIS TAMACK
TCHASSONG TAGUETIGOUNG ANDRE MARIE
DZIZZANG APPOLLINAIRE
SEGNOU PASCAL
BATAYA HEUBTHE JEANVIER
ESSOGO CECILE EPSE ELOUNDOU
KEMCHE FEZE NESTOR
HONLA NOM MOUTLEN
Village: Malimba Urbain 1 Date: 06.06.07
Time: 08:OO - 11:OO Number of participants: 8
Question I
Only one person requested the money, giving the reason that he would like to find a land closer to his affected house and construct it himself even if he could only afford to construct a smaller house.
The remaining participants chose the construction instead of the money. These stated that their new house or foundation should be similar to the one destroyed but better quality and bigger. In addition, the people with houses to be constructed requested these to have all the comforts that their current house has, this meant that if the house to be destroyed had electricity, water, TV reception, phone network, proximity to roads, proximity to their children's schools orland their work then the new house should also have the same thing. Furthermore, all participants requested AES SONEL to construct their house in a location close to the previous location in order to minimise the impact on their daily lives.
Question II
All participants asked support from AES SONEL in clearing their new land and preparing it for construction. This included the person that requested the compensation in money. Only one person mentioned the existence of another land where AES SONEL could build her house. The remaining people stated they would require support in finding another land in a location close to the previous location as well as in buying the land, as they did not have enough money to purchase the new land. None of these people have land title for the current land.
Question Ill
All participants expressed their willingness to know exactly when AES SONEL would give the compensation, as that would determine the period for their reallocation. However, when they received the information that according to the Cameroonian law they had a maximum period of 6 months to reallocate from the moment they received the compensation, the person that chose the option of receiving money said that he would respect the time stipulated by the law. Nevertheless, he expressed the concern regarding the weather season, as that would affect the construction time. In other words, if he received the compensation during the raining season, the construction time would not be possible during the six months predicted due to the constant rain. The remaining participants mentioned that the time of reallocation would depend on AES SONEL as they chose their house to be constructed by them.
Question IV
When asked about any possible disabilities that they would like AES SONEL to pay particular attention to, the majority of the participants mentioned that they did not have major disabilities or older people in their households that would require special assistance. Only one person mentioned that her husband was blind and would need special attention and another that mentioned that she was a recent widowed with small children.
Question V
When asked about any concerns they might have due to the reallocation, the main concern were about the location of the new land. Their main worry was that this would affect their daily activities and even increase their daily expenditures. As such participants mentioned the proximity to their children's schools, their place of work, their cultures, their access to the road, electricity and water as some of the factors that should be taken into consideration when choosing the new land.
A couple of people stated they were very unhappy and irritated about having to reallocate because they had been living in the land for many, many years and now because the government wants the land, they must leave.
One concern was expressed was the finding a new land that was as big as the land they currently possess.
Another concern mentioned was the transport of their house assets to the new reallocation, as they were afraid these could be damaged during the trip and there would not be any compensation for that.
One person was concerned about the current material (blocs) in the house that was in the process of construction and asked if AES SONEL could help her to transport those blocks to the other land. In addition, she mentioned that she had bought sand for the construction and when AES SONEL asked her to stop the construction due to the reallocation, the rain that occurred during the time she was waiting for the reallocation washed the sand away.
One person was concerned about when they would receive the compensation or know the new land they would be reallocated too, as he needed to matriculate his children in the school and could not wait for too long otherwise their children would loose their place in the current school. In addition, if he did matriculate them and then was reallocated to a much further location, their children would need to change schools and he would need to pay again.
One person stated that she had already started looking for a land in the vicinity but could not find any.
The final concern was regarding the land title. One respondent mentioned that he purchased a portion of land from a neighbour that had a big land with land title, but that for his portion of land the neighbour did not give him the land title. As such, the neighbour will receive the compensation for the land and he is concerned that he will not get any compensation.
Question VI
With the exception of one participant, no other participant had tombs that could be affected.
With regards to the participant that had the tomb, he understood that he would not receive any compensation for their graves if they were to be reallocated, as AES SONEL would provide this service. Nevertheless, he still expressed his wish to have his grave reallocated to the new site and was happy to receive AES SONEL's assistance in this reallocation (EYOCK Philipe).
Question VII
The participants were given time to answer any questions that they might have regarding the reallocation. To some of these questions the team was able to provide an adequate answer however to others, these were only noted down. All of the questions posed are expressed below.
When will they receive their compensation package? If they had cultures that were going to be compensated, would that compensation occur at the same time as the reallocation date, if they chose their house to be reconstructed?
Would AES SONEL compensate them for additional costs that came about due to the reallocation such as construction material that was destroyed due to the long waiting time for the reallocation?
The people that have tombs constructed with more permanent material, will these be compensated during the reallocation as they will be destroyed or will AES SONEL also build the same quality tomb?
Will there be any more studies after this one? Will there be a new commission coming?
Will AES SONEL provide them with transport for them to move their material assets from the original house to the new house?
= One respondent mentioned that he had two houses that were going to be destroyed and was wondering if AES SONEL could build his two houses instead of one.
Could they use the material from their houses to help them build their new house as AES SONEL was going to destroy the house and had no need for this material?
Will their new house have the same quality as the previous house with regards to water, electricity, TV network, phone network, etc.
Observations from the moderator
People seem to be impatient to receive their compensation and are tired of being surveyed. In addition, people were not happy about not receiving any monetary help to purchase their new land. The meeting was conducted without any particular incident and the participants who could not attend the meeting were represented by their relatives. Some people were not happy about being reallocated and expressed this sentiment clearly.
List of Participants
Household Questionnaire used in Socio-Economic Baseline Survey
Social Assessment for the Construction of the Edea-Kribi Power Line
I ~ u m e r o d'ordre de chaque menbre du I Imenage/~umber of household members 1 2 3 4 5 6 7 8 9 10 1
8.3. Comment aimeriez vous etre indemmnise?choisir par ordre de preference dans les 3 cas suivantsl How would you want to be compensated? Choose three in order of preference
01 Payer ma compensation en especelPayment of the compensation in cash
02 AES doit m'acquerir un terrain nouveaulme construire une maisonl AES to buy your landlhouse on your behalf
03 Associer les deuxl Mixture of the two above Lu 98 Autre moyen a specifierlother specify 99 Ne sait pas1Don't know
B.4 Est ce que vous avez un compte banmire?( a poser au chef de menage uniquement)/ Do you have a bank account (ask the head of household only)
01 OuiNes 02 NonlNo
01 OuiNes 02 NonlNo
01 OuiNes 02 NonlNo
Si non,passer a la question B7Af No, go to question 87
8.5 Preciser le nom de votre banque SVPI. Please specify the name of your bank
B.6.Etes vous en mesure d'effectuer une transaction bancaire en espece ou par cheque? Are you able to deposit and withdraw cash or cheques?
B.7.Aimeriez vous que AES SONEL vous aide a ouvrir un compte bancaire pour recevoir votre compensation? Would you like AES SONEL to assist you in opening a bank account to receive
Section 1 - 4 Scott Wilson
Social Assessment for the Construction of the Edea-Kribi Power Line
Numero d'ordre de chaque menbre du menagelNumber of household members 1 2 3 4 5 6 7 8 9 10
D.3 Est ce I'enquete frequente actuellement?/Are any of the household members currently studying
01 < 5 min. 02 De 5 a30 mn 03 De 30 mn a 1 h 0 4 > l h
01 A piedlBy foot 02 A velo1By bicyde 03 Par minibuslby mini bus 04 Par taxilBy Taxi 05 Par vehicule personnelllprivate car
D.4 -Quelle ecole frequente les enfants en age scolaire(preciser pour chaque enfant) Which schools do the children in the house go to (Write down per child)?
D.5 -Quelle duree met les enfants pour aller de la maison a I'ecole? How long do the children take from the house to get to the school?
J.3 -Quel moyen de deplacement utilisent les enfants pour se rendre a I'ecole? How do the children of the household travel to school? (Repondre en respectant I'ordre des questions precedentes)(Register using the same order as the previous question)
1. u 5 w
98 Autre moyen a specifierlother specify
Section 1 - 7 Scott W~lson
Social Assessment for the Construction of the Edea-Kribi Power Line
Numero d'ordre de chaque menbre du menagelNumber of household members 1 2 3 4 5 6 7 8 9 10
E- Activites generatrice de revenus par chaque membre du menagellNCOME GENERATING ACTIVITIES PER HOUSEHOLD MEMBER
E.l - Est ce que chaque du menage contribue au revenu du menage?lDoes the household member contribute to the household income?
E.2 -Quelle est I'activite principale de chaque membre de menage?/ What is the main occupation of the household member?
01 CultivateurlFarm~ng 02 Agent de I'EtatlGovemment Em~loyment
W I I U W W U I U W 03 Employe du secteur privel~mplbyment in the Private Sector 04 Auto employe1 Self employed: a- Vendeur ambulant (fruits,culture vivnere,lroad side selling of products (e.g. fruits, crops and food) b - Barlrestaurant c - Pechelfishing d - Commerce e - MawnlConstruction f - MechanlcienlMechanic h - Taximanhaxi drivers I - Vendeur de sablelselling of sand
I 1 98- Autre a specifierlother specify I I 06 EtudiantlStudent 07 Homme de maison /Femme de rnenageNousekeeperlcleaner 08 RetraitelRetired 09 Sans emploilUnemployed 10 EnfantlChild 11 HandicapelDisabled
Section 1 - 8 Swtt W~lson
Social Assessment for the Construction of the Edea-Kribi Power Line
---- Numero d'ordre de chaque menbre du menagelNumber of household members 1 2 3 4 5 6 7 8 9 10
E.3 - Quelle autre activite exerce chaque membre du menage?/\l\lhat other acitvities does the household member practise? (maximum of 3)
01 CommercanUFormal Commerce I l - u I u-l Lu L - u U l-u u - l u - l
E.4 - Specifier SVPIPlease specify (maximum of 3)
98 Autre moyen a specifierlother specify
E.5. Est ce que vous avez un parent qui vous envoie de I'argent d'ailleurs?lDo you receive monetary assistance from familiy members living in other places?
E.6 - Quel est le revenu total mensuel des activites pratique par chaque membre du menage (y compris I'argent venu d'ailleurs)?l\l\lhat is the total monthly income of all activities practised by the household member (including money from outside)?
E.7 - Quel est le moyen de deplacement utilise par chaque membre de menage pour de rendre au travail?lHow does the household member travel to hislher main working location?
II I UI u ULU LU uu 01 A piedlBy foot 02 A velolBy bicycle 03 Par minibuslby m~ni bus 04 Par taxilBy Taxi 05 Par vehicule personnelllprivate car
98 Autre moyen a specifier1Other specify
Section 1 - 9
Social Assessment for the Construction of the Edea-Kribi Power Line
Numero d'ordre de chaque menbre du menagelNumber of household members 1 2 3 4 5 6 7 8 9 10
E.8 -Est ce qu'on pratique I'elevage dans le menage?/ Does the household raise or sell animals ?
u If non go to F
E.9 - Que fait le menage des animaux eleves?specifier par type d1animaux.What does the household do with the animals it raises? Specify per animal
01 Eleve pour autoconsomationlraise for own consumption VollailelChickens OZEleve pour vendrel Raise and sell 03 N'eleve padDoesn't raise CanardIDucks 04Vend uniquementl Just Sells
u ChevrelGoats l-u
Section l - 10
Chicks
Ducks
Goats
COWS
Scott W~lson
Social Assessment for the Construction of the Edea-Kribi Power Line
l ~ u m e r o d'ordre de chaque menbre du 1 lmenagelNumber of household members 1 2 3 4 5 6 7 8 9 1 O A
F.l - Quel est le loisir favori de chaque membre du menage?lNVhere does the household member go during hislher free time?
01 A la rnaison1At home 02 Chez les amidat friends houses 03 Le sporVPractising sport 04 Au culte1At the church 05 Dans les debits de boisson du village1At barslstalls in the village 06 Dans les debits de boisson le long des routedAt bars next to the road 07 Dans les boites de nuit hors du villagelln night clubs outside the village 98 Autre rnoyen a specifierlother specify)
01 < 5 rnin. 02 De 5 a30 rnn 03 De 30 rnn a 1 h 0 4 > l h
01 A piedlBy foot 02 A velolBy bicyde 03 Par rninibuslby rnin~ bus 04 Par taxilBy Taxi 05 Par vehicule personnelllprivate car 98 Autre rnoyen a specifierlother specify
F.2 - Quelle est la duree que met chaque membre du menage pour se rendre a son lieu de loisir favori?lHow long does it take the household member to get to the place of leisure helshe frequents the most?
F.3 - Quel est le rnoyen de deplacement utilise pour se rendre a son lieu de loisir favoriMow does helshe go to the place of leisure helshe frequents the most?
Section I - 1 1 Scott Wilson
Social Assessment for the Construction of the Edea-Kribi Power Line
Numero d'ordre de chaque menbre du menagelNumber of household members 1 2 3 4 5 6 7 8 9 10
G - ETAT DE SANTE DE CHAQUE MEMBRE DU MENAGEIHEALTH PER HOUSEHOLD MEMBER
G.l - Y'a t-il dans le menage quelqun qui soufre d'un handicape mental ou physique?lls there anyone in the household with a mental or physical disability?
G.2 - Specifier I'handicapelSpecify the disability
04 PsychologiquementallPsychological/Mental 05 MultiplelMultiple 98 Autre moyen a specifierlother spec~fy
G.3 - Y'a t'il dans le menage quelqun qui a soufert de I'une des maladies suivantes les trois dernieres annees?l Has the household member suffered from any of the following diseases in the last three years?
02 PaludismeIMalaria 03 PiarrheelDiarrehea
I I Iuuuuuuu 04 Tuberculose~uberculosis 05 HepatitelHepatitis II I I u UILL u uu
06 Fievre jauneNellow Fever 07 Toutes les maladies sus-citeeslall of the
I I I U U I U ~ U L - U above
Section 1 - 12
98 Autre moyen a spec~fierlother specify
Scott W~lson
1
Social Assessment for the Construction of the Edea-Kribi Power Line
Numero d'ordre de chaque menbre du menagelNumber of household members 1 2 3 4 5 6 7 8 9 10
01 S'est rendu dans le centre de sante du villageMlent to the local hospital
G.4 - Dans quel centre de sante a t-il recu des soins?NVhere does helshe go to get treatment?
a - Aspecifier SVPlplease specify
02 S'est rendu dans un hopital Departemental- ProvincialMlent to the bigger hospital in the city I I
a - Aspecifier SVPlplease specify I 03 S'est rendu chez le tradi praticienMlent to the traditional doctor 05 S'est traite a la maison sans medicamentltreated at home without medication 06 S'est traite a la maison avec des medicaments achetes au marcheltreated at home with medication got from the market 07 S'est traite a la maison avec des medicaments traditionnelsltreated at home with traditional medication 98 Autre moyen a specifierlother specify
G.5 - Ya t-il eu dans le menage le deces d'un enfant de moins de cinq ans durant les trois dernieres anneeslHas any child in the household under the age of five died over the last three years? Si non aller a la section suivantehf no go to next section
G.6 - Quelles ont ete les raisons de son deces?NVhat were the main reasons
98 - Aspecifier SVPlplease specify
Section 1 - 13 Scott Wilson
AES SONEL
KRIBI POWER PROJECT
TERMS OF REFERENCE FOR A DETAILED SOCIO ECONOMIC SURVEY, RESETTLEMENT ACTION PLAN
AND INDEPENDANT VALUATION
. I8 KPP ToRjbr RAP.Decernher 06
PROTECT BACKGROUND
1 INTRODUCTION
AES SONEL, the national power utility in Cameroon, is currently developing a 150 MW gas-fired power plant in order to meet the expanding electricity requirements of the country over and as part of the medium-term strategic development programme.
In the course of development of the project, the company hired in December 2005 after an international competitive bidding process, an environmental consulting firm to conduct an Environmental and Social Impact Assessment (ESIA) necessary to obtain both national authorisations and multi-lateral approval for the construction and operation of the proposed power plant and associated facilities for the project. This study is complete and the ESIA report shall be issued and submitted to approval in the next few weeks.
One of the major impacts identified during the ESIA is the necessity the resettle a number of Project Affected People (PAPs) with regards to their properties identified on the plant site and within the transmission line corridor, particularly:
the land (titled or not) the crops the other properties (houses, ...)
In parallel to the ESIA, AES SONEL jointly with government commissions appointed by Divisional Officers decrees in the project area carried out a survey, based on the Public Utility Decrees (PUD) obtained, whose task was to identify namely all the PAPs and record in details the nature of their affected belongings (lands, properties, crops, . . .). These commissions completed their task in July 2006, and detailed reports will be available in the next few weeks. AES SONEL also hired a company to work with the commission and issue maps of all affected properties, with inclusion of all identification details on their owners.
AES SONEL is now seeking a reputable consulting firm to carry out a detailed Resettlement Action Plan (RAP) that will include the Independent Valuation of properties affected by the Project for the sake of compensation as well as a socioeconomic impact assessment of the losses on the affected parties.
The detailed scope of this assignment follows.
2 PROJECT BRIEF
The Kribi Power Project, scheduled to be commissioned during the second half of 2008 comprises:
JR-KPP-%l< for RAPlDecernher 06
The construction of a 150 MW power plant fuelled with natural gas;
The construction of energy transmission facilities comprising: a step-up substation at the plant site;
- a 100 km, 225 kV transmission line between the step up substation and the Mangombe 225190 kV substation at Edka;
- the connection of the transmission line at the Mangombe substation with addition of new 225 kV bays.
The power plant will be located at MPOLONGWE, a village situated 9 km north of the coastal city of Kribi, in the southern province of Cameroon. Its area is almost 16 hectares.
This power plant will be equipped either with simple cycle gas turbines or reciprocating gas engines. The plant will be owned by AES SONEL through a subsidiary.
The energy produced will feed the Southern Interconnected Grid (SIG) via a double circuit 225 kV transmission line constructed on steel towers in a 30 m way leave. The connecting point shall be the Mangombe 225190 kV substation at Edka.
Both the power plant site and the transmission line corridor were declared of public utility through Public Utility Decrees (PUD) signed by the Minister in charge of land affairs in August 2005.
3 PROJECT DOCUMENTATION
Inventorv of Project Affected People
During the census of Project Affected People (PAPS) led by the divisional commissions, following numbers were recorded:
On the power plant site: Property owners: 8 Crops owners: 17 Titled lands: 0
On the transmission line corridor: Property owners: 86 Crops owners: 665 Titled lands: 34
The following documents were issued and shall be at disposal of the consultant: o the detailed list of land owners, their location and details of affected area; o the detailed list of crops owners and types of crops affected; o the detailed layouts of all affected lands (farmed, titled or not);
3 .JB KPP-ToR,for RAP/Decrrnber 06
Additional documentation
In addition, following documentation shall be provided:
layouts of the plant site and transmission line route; the ESIA report; the Decree No 2003/418/PM dated on the 25th February 2003 relating to the valuation of crops for compensation purposes.
4 SCOPE OF THE STUDY
The scope of the study contemplated in these Terms of Reference shall include but not limited to:
a Detailed household survey to cross check the information gathered by the divisional census commissions, and identify, interview and validate all Project Affected People (PAPs) and their relevant affected properties; Detailed socio-economic survey of all validated PAPs; Detailed Resettlement Action Plan (RAP) for all affected properties; Independent valuation of the PAPs belongings and properties for the sake of compensation;
a. Detailed Household and Socio-economic Survev of validated PAPs
The detailed household and socio-economic survey objective is, for all Project Affected People (PAPs) to:
i. Cross check the available information gathered during the census of the divisional commissions in order to confirm the data collected (list of Project Affected People (PAPs) and their properties) ;
ii. Establish a Baseline Information (quantitativelqualitative) on affected families including spouses, children/dependants/relatives, health, land, religions, and economic and social data (sources of income and livelihood);
iii. Determine impact (quantitativeJqualitative) of the project on the family unit, health, land, and economic situation;
iv. Assess impacts of losses incurred on the affected households and individuals, and identify accompanying or bonification measures for affected communities orland socially vulnerable households
v. Question the PAPs individually and record their preferred means of compensation (money or in-kind).
b. Resettlement Action Plan (RAP)
Based on the validated census information on the affected crops, land and properties:
Prepare and Formulate a Resettlement Action Plan (RAP) consistent with national and international standards, particularly IFC standards; Formulate a resettlement framework and implementation plan for the management of resettlement actions; Propose a Monitoring and Evaluation plan including indicators to monitors and baseline information to assess the successful implementation of the RAP. Include the budget for the RAP.
c. Independent Valuation
The objective of the independent valuation is to provide a database in an agreed software package that will enable AES SONEL, Government authorities and potential Lenders to, by using 'Fair Market Value' process (as defined in the Standards and Procedure of Assessment Valuation), determine for each of the PAPS the amount of compensation to be paid either in cash or in kind.
The Independent Evaluator will analyse the rates published in the decree mentioned here up and, in accordance with registered Standards and Procedures of Assessment Valuation propose a fair market value for each crop (depending on its maturity) and each property (land, house ...) for compensation purposes. The details of the valuation methodology and calculation shall be provided;
In case the property is of a sensitive or cultural nature, it shall be assessed and valued and appropriate in-kind, compensation or migration/offset be proposed based on the will of the owner;
The Independent Evaluator shall, where necessary, identify potential project related litigation issues and immediately inform AES SONEL, with proposal of possible solutions.
A Claims Dispute Resolution Committee (CDRC) shall be set up (with participation of government representatives, Independent evaluator and AES Sonel).
5 EXPECTED OUTPUT
The expected output shall be a report written in English, with executive summary in English and French. Five (5) hard copies and an electronic copy will be provided.
6 PROPOSAL REQUIREMENTSIIMPLEMENTATION DELAY
The technical and financial offers are expected within Two weeks from issue of these TORS. The expected implementation delay is 3 months from contract signature.
.IB-KPP ToRfor RAP December 06