AEO Authorisation Requirements

T MU MD 00009 ST

Standard

Version 3.0

Issued date: 08 May 2017

© State of NSW through Transport for NSW 2017

Page 2: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Important message

This document is one of a set of standards developed solely and specifically for use on Transport Assets (as defined in the Asset Standards Authority Charter). It is not suitable for any other purpose. The copyright and any other intellectual property in this document will at all times remain the property of the State of New South Wales (Transport for NSW). You must not use or adapt this document or rely upon it in any way unless you are providing products or services to a NSW Government agency and that agency has expressly authorised you in writing to do so. If this document forms part of a contract with, or is a condition of approval by a NSW Government agency, use of the document is subject to the terms of the contract or approval. To be clear, the content of this document is not licensed under any Creative Commons Licence. This document may contain third party material. The inclusion of third party material is for illustrative purposes only and does not represent an endorsement by NSW Government of any third party product or service. If you use this document or rely upon it without authorisation under these terms, the State of New South Wales (including Transport for NSW) and its personnel does not accept any liability to you or any other person for any loss, damage, costs and expenses that you or anyone else may suffer or incur from your use and reliance on the content contained in this document. Users should exercise their own skill and care in the use of the document. This document may not be current and is uncontrolled when printed or downloaded. Standards may be accessed from the Asset Standards Authority website at www.asa.transport.nsw.gov.au

© State of NSW through Transport for NSW 2017

Page 3: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Standard governance

Owner: Manager Authorisation, Asset Standards Authority

Authoriser: Principal Manager, Authorisation and Audit, Asset Standards Authority

Approver: Executive Director, Asset Standards Authority on behalf of the ASA Configuration Control Board

Document history

Version Summary of Changes

1.0 First issue under standard number TS 10502

2.0 Version 2.0 issued 1 December 2014, effective date 5 January 2015

3.0 Third issue

For queries regarding this document, please email the ASA at [email protected] or visit www.asa.transport.nsw.gov.au

© State of NSW through Transport for NSW 2017

Page 4: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Preface The Asset Standards Authority (ASA) is a key strategic branch of Transport for NSW (TfNSW).

As the network design and standards authority for NSW Transport Assets, as specified in the

ASA Charter, the ASA identifies, selects, develops, publishes, maintains and controls a suite of

requirements documents on behalf of TfNSW, the asset owner.

The ASA deploys TfNSW requirements for asset and safety assurance by creating and

managing TfNSW's governance models, documents and processes. To achieve this, the ASA

focuses on four primary tasks:

• publishing and managing TfNSW's process and requirements documents including TfNSW

plans, standards, manuals and guides

• deploying TfNSW's Authorised Engineering Organisation (AEO) framework

• continuously improving TfNSW’s Asset Management Framework

• collaborating with the Transport cluster and industry through open engagement

The AEO framework authorises engineering organisations to supply and provide asset related

products and services to TfNSW. It works to assure the safety, quality and fitness for purpose of

those products and services over the asset's whole-of-life. AEOs are expected to demonstrate

how they have applied the requirements of ASA documents, including TfNSW plans, standards

and guides, when delivering assets and related services for TfNSW.

Compliance with ASA requirements by itself is not sufficient to ensure satisfactory outcomes for

NSW Transport Assets. The ASA expects that professional judgement be used by competent

personnel when using ASA requirements to produce those outcomes.

About this document

A principle function of the ASA is to set, maintain and administer the framework for assessment,

authorisation, surveillance, review and audit of organisations that provide engineering services

in relation to the asset life cycle of TfNSW assets.

This is the third issue of this document. The changes to previous content include the following:

• restructuring of the requirements and guiding information to remove overlaps in

requirements causing duplications in answers, to add clarity and to provide more

information on the expected evidence

• new grouping of requirements to make some important requirements more prominent and

to better align the requirements structure with the engineering assurance and contract

performance evaluation frameworks

© State of NSW through Transport for NSW 2017 Page 4 of 65

Page 5: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Table of contents 1. Introduction .............................................................................................................................................. 6

2. Purpose .................................................................................................................................................... 62.1. Scope ..................................................................................................................................................... 62.2. Application ............................................................................................................................................. 6

3. Reference documents ............................................................................................................................. 7

4. Terms and definitions ............................................................................................................................. 8

5. Assessment of suppliers ...................................................................................................................... 10

6. Contractual obligations ........................................................................................................................ 10

7. AEO authorisation requirements ......................................................................................................... 107.1. Engineering management process and planning ................................................................................ 127.2. Requirements management ................................................................................................................ 177.3. Service or solution engineering ........................................................................................................... 207.4. Assurance, verification and validation ................................................................................................. 377.5. Configuration management ................................................................................................................. 517.6. Competence management .................................................................................................................. 547.7. Stakeholder management .................................................................................................................... 607.8. Resources management ...................................................................................................................... 617.9. Supplier management .......................................................................................................................... 637.10. Performance measurement and evaluation ..................................................................................... 647.11. Continual improvement management .............................................................................................. 65

© State of NSW through Transport for NSW 2017 Page 5 of 65

Page 6: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

1. Introduction Transport for NSW (TfNSW) is collaborating with industry to improve engineering governance of

transport projects and to use the skilled resources from both government and industry

organisations to greatest effect. One of the key initiatives is the process for enabling Authorised

Engineering Organisations (AEOs) to manage the competence of their engineering staff

internally and to manage the assurance of their engineering services in relation to the asset life

cycle of NSW Transport Assets on behalf of TfNSW.

2. Purpose This standard provides information outlining engineering management system capabilities and

practices that an engineering organisation is required to demonstrate to be engaged to provide

engineering services in relation to the asset life cycle of NSW Transport Assets on behalf of

TfNSW.

2.1. Scope This standard sets the common expected organisational engineering management capabilities

and practices (requirements) that underpin a robust system of delivery and assurance

engineering services that are correct, integrated and delivered in a manner which is compliant

with relevant standards and which satisfies TfNSW requirements. The requirements tables

include a rationale for each requirement group, a statement of one or more requirements that

AEOs shall comply with and guidance notes elaborating requirements to assist in interpreting

applicability to the AEO and demonstration of adequate compliance, providing references to

other relevant documents for further details.

This document also includes information on typical evidence that can demonstrate meeting

requirements depending on the type of engineering services (engineering discipline and

lifecycle phase) the organisation provides.

Requirements in this document are independent of any TfNSW tender or contract requirements.

2.2. Application This standard applies to engineering services suppliers applying for authorisation to provide the

services defined in T MU MD 00009 SP AEO Authorisation Model and T MU MD 00009 F1 AEO

Engineering Services Matrix Template in relation to the asset life cycle of NSW Transport

Assets.

The intended audience for this standard includes TfNSW, TfNSW transport infrastructure

managers, TfNSW Transport Assets operators and suppliers of engineering services to TfNSW

in relation to transport assets.

© State of NSW through Transport for NSW 2017 Page 6 of 65

Page 7: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

The requirements contained in this document may be used by an AEO to self-assure

engineering outputs under its own engineering assurance system and to manage the

competence of its staff under its own competence management system.

3. Reference documents The following documents are cited in the text. For dated references, only the cited edition

applies. For undated references, the latest edition of the referenced document applies.

International standards

IS EN 50121 Railway applications - Electromagnetic compatibility series

ISO/IEC 26702 Systems engineering - Application and management of the systems engineering

process

ISO/IEC/IEEE 15288 Systems and software engineering - System life cycle processes

ISO/IEC/IEEE 29148 Systems and software engineering - Life cycle processes - Requirements

engineering

ISO 9001 Quality management systems – Requirements

ISO 55000 Asset management - Overview, principles and terminology

Australian standards

AS ISO 55000 Asset management - Overview, principles and terminology

AS ISO 55001 Asset management – Management systems -Requirements

AS ISO 10007 Quality management systems – Guidelines for configuration management

AS/NZS ISO 9001 Quality management systems - Requirements

Transport for NSW standards

Safety Change Management Standard 20-ST-006

T MU AM 04001 PL TfNSW Configuration Management Plan

T MU AM 04003 GU Configuration Management Guide

T MU AM 06001 GU AEO Guide to Systems Architectural Design

T MU AM 06002 GU AEO Guide to Reliability, Availability and Maintainability

T MU AM 06004 ST Requirements Schema

T MU AM 06006 GU Systems Engineering

T MU AM 06006 ST Systems Engineering

T MU AM 06007 GU Guide to Requirements Definition and Analysis

© State of NSW through Transport for NSW 2017 Page 7 of 65

Page 8: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

T MU AM 06010 GU Business Requirements Specification

T MU EN 00003 GU AEO Guide to Sustainability in Design

T MU MD 00003 GU Guide to Independent Safety Assessment

T MU MD 00009 F1 AEO Engineering Services Matrix Template

T MU MD 00009 F2 AEO Self-Assessment Checklist Template

T MU MD 00009 F3 Self-Assessment Tool Template

T MU MD 00009 SP AEO Authorisation Model

T MU MD 20001 ST System Safety Standard for New or Altered Assets

T MU HF 00001 GU AEO Guide to Human Factors Integration

T MU HF 00001 ST Human Factors Integration – General Requirements

TS 10503 AEO Guide to Engineering Competence Management

TS 10504 AEO Guide to Engineering Management

TS 10505 Guide to Requirements Definition and Analysis

TS 10506 Guide to Verification and Validation

TS 10507 Guide to Systems Integration

Other reference documents

TfNSW, NSW Sustainable Design Guidelines Version 3.0

4. Terms and definitions The following terms and definitions apply in this document:

AEO Authorised Engineering Organisation

ASA Asset Standards Authority

asset life cycle stages for an asset from recognition of need through to disposal and any

residual risks or liability period

assurance a set of structured and planned activities conducted through the asset life cycle

providing progressive justified confidence that objectives are being achieved and that the asset

is or will be fit for purpose

authorisation the conferring of authority, by means of an official instruction, and supported by

assessment and audit, to a supplier, to self-perform assurance of the competence of its staff

and the outputs of engineering processes

CCB configuration control board

© State of NSW through Transport for NSW 2017 Page 8 of 65

Page 9: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

CMAAC TfNSW Configuration Management and Asset Assurance Committee

compliance the state or fact of according with, or meeting, rules or standards

EMC electromagnetic compatibility

EMI electromagnetic interference

engineering assurance a sum of technical assurance activities along the lifecycle; includes

design assurance, construction assurance, maintenance assurance

framework a basic structure underlying a system, concept or text

hazard potential source of physical injury or damage to the health of people or damage to

property or the environment

HF human factors

HV high voltage

ISA independent safety assessment

JOS judgement of significance; an assessment of the technical risk introduced by the

implementation of the design and considers both the probability and consequence of partial

performance or failure of a design

RAM reliability, availability and maintainability

responsible a duty or obligation to satisfactorily perform or complete a task (assigned by

someone, or created by one's own promise or circumstances) that one must fulfil and which has

a consequent penalty for failure. Responsibility can be delegated.

SFAIRP so far as is reasonably practicable

SMS safety management system

staff all of the following employment categories: permanent or fulltime or fixed-term employees,

part-time or casual employees, shift workers, daily hire and weekly hire employees,

probationary employees, apprentices or trainees, employment agency staff or labour hire,

contractors or sub-contractors

supplier a supplier of engineering services or products

TfNSW Transport for NSW

TfNSW Transport Network the transport system owned and operated by TfNSW or its

operating agencies upon which TfNSW has power to exercise its functions as conferred by the

Transport Administration Act or any other Act

validation the process to ensure that the delivered system or asset meets requirements

verification the process to ensure that the output of each stage in the system life cycle meets

the stage input requirements

© State of NSW through Transport for NSW 2017 Page 9 of 65

Page 10: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

5. Assessment of suppliers A supplier of engineering services and products wishing to engage in work for TfNSW may be

assessed and audited against AEO requirements irrespective of contractual status. Contract

delivery evidence may be used to demonstrate compliance with AEO requirements.

6. Contractual obligations Compliance with the requirements of this standard by a supplier of engineering services or

products as part of achieving initial AEO status does not remove the responsibility of an AEO to

continually demonstrate compliance as part of the normal TfNSW tendering and contracting

arrangements.

Users of this standard are bound by all relevant requirements of the law, regardless of whether

or not there is any specific reference to them in this standard.

7. AEO authorisation requirements Sections 7.1 to Section 7.11 define the requirements AEOs shall meet to be accredited as an

AEO.

The requirements are accompanied by the following:

• requirement identification (Req ID) – identification of the related element in

T MU MD 00009 F3 Self-Assessment Tool Template and T MU MD 00009 F2 AEO Self-

Assessment Checklist Template

• other ASA standards and guides available on the ASA website.

• elaboration – supplementary mandatory information regarding the requirement

• evidence – elaboration on documentation and deployment evidence that AEOs are

expected to demonstrate and that must be relevant and cover the proposed scope of

authorisation

• documents – standards or documents that provide additional information

Requirements for AEOs cover organisational engineering management capabilities in the

following areas:

• engineering management process and planning

• requirements management

• service or solution engineering including the following:

o interface management

o integration management

© State of NSW through Transport for NSW 2017 Page 10 of 65

Page 11: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

o system architecture management

o sustainability in design

o reliability, availability and maintainability (RAM) management

o human factors (HF) integration management

o electromagnetic compatibility (EMC)

• assurance, verification and validation including the following

o judgement of significance (JOS)

o system safety assurance

• configuration management

• competence management

• stakeholder management

• resources management

• supplier management

• performance measurement and evaluation

• continual improvement management

© State of NSW through Transport for NSW 2017 Page 11 of 65

Page 12: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.1. Engineering management process and planning These requirements demonstrate engineering management activities and arrangements for the systematic execution of those activities that need to be performed to

ensure the delivery of services within the scope of authorisation is compliant with relevant standards whilst satisfying TfNSW needs.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM1

An AEO shall have engineering management processes and methodologies appropriate to its engineering services and suitably aligned with

ISO 9001 Quality management systems – Requirements, ISO 55000 Asset management - Overview, principles and terminology, AS ISO 55001

Asset management – Management systems – Requirements and AS/NZS ISO 9001 Quality management systems – Requirements.

Guidance Elaboration

An AEO shall perform systems engineering activities in accordance with the requirements of ISO/IEC/IEEE 15288 Systems and software engineering

- System life cycle processes or ISO/IEC 26702 Systems engineering - Application and management of the systems engineering process or

equivalent.

The level of systems engineering is scalable as relevant to the level of complexity, novelty and risk associated with its services.

An AEO should ensure that the technical processes covered in its documentation include all required processes as elaborated in this document as

applicable.

Guidance Evidence

AEOs shall have suitable plans, processes, procedures, guides or manuals (or a combination thereof) that demonstrate how th

out their services in the absence of, or in conjunction with, the contractually prescribed relevant processes.

ey consistently carry

An AEO that provides multi-disciplinary services should document its systems engineering approach in a systems engineering

manual.

management plan or

© State of NSW through Transport for NSW Page 12 of 65

Page 13: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

An AEO may choose to establish an enterprise level systems engineering management plan (SEMP), which is tailored and applied to each project,

rather than developing project-specific SEMPs without reference to an overarching standard SEMP.

An AEO may choose to embed systems engineering principles and processes within an engineering management plan rather than write a dedicated

systems engineering management plan. This choice will depend on the complexity and range of services offered by the AEO. Specialised

engineering services suppliers that have limited scope of authorisation, typically within the same lifecycle phase, and only for few disciplines may

choose this approach. AEOs may prepare a relatively simple engineering management plan for standard, single discipline engineering projects,

whereas AEOs engaged in complex, multi-discipline, multi-phase projects with significant levels of systems integration will likely need to prepare a

systems engineering management plan that covers all systems engineering areas, or have separate plans or manuals, including, but not limited to,

the following:

• requirements management plan or procedure or guide or manual • interface management plan or procedure or guide or manual • systems architecture management plan or procedure or guide or manual • systems assurance management plan or procedure or guide or manual • RAM management plan or procedure or guide or manual • verification and validation management plan or procedure or guide or manual • testing and commissioning management plan or procedure or guide or manual • EMC management plan or procedure or guide or manual • maintenance management plan or procedure or guide or manual • The relevant organisational procedures or project plans should meet the following requirements : • reflect all the requirements for the discipline or capability • be documented as suitable (standalone document or part of another document, hardcopy or softcopy organisational procedure or project

plan) • define the process (activities, applicable standards and rules) • provide evidence of its review

© State of NSW through Transport for NSW Page 13 of 65

Page 14: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

These demonstrated artefacts can be part of the integrated management system or similar and should be aligned with the AS/NZS ISO 9001 or

AS ISO 55000 Asset management - Overview, principles and terminology requirements as suitable.

Depending on the scope and complexity of engineering services, an AEO may incorporate some or all sub-plans within a single engineering

management plan. For example, a specialist supplier of geotechnical or potholing services will have a relatively simple engineering management plan

compared to a supplier of multi-discipline, multi-phase services covering systems integration.

Possible evidence for various engineering disciplines and lifecycle services or activities include the following:

• integrated management system (IMS) home page • design management plan, procedure, guide or manual • fabrication or manufacturing management plan, procedure, guide or manual • construction or installation management plan, procedure, guide or manual • testing management plan, procedure, guide or manual • maintenance management plan, procedure, guide or manual • plan, procedure, guide or manual associated with any other specialist services that are not specific to an asset life cycle phase (design,

manufacture, install, test and maintain)

The requirement evidence of documentation and deployment must be relevant and cover the proposed scope of authorisation as follows:

Design consultants need to document how they manage designs from start to finish, including design assurance, see Section 7.4, and design support

of post approved for construction (AFC) lifecycle phases. This may include options analysis associated with early concept designs and feasibility

studies.

Manufacturers of products and systems should document how they manage and assure the manufacturing process and products. This includes mass

public transport asset manufacturers.

Constructors, often principal contractors, should document how they plan, execute, coordinate and assure, see Section 7.4, construction phase

© State of NSW through Transport for NSW Page 14 of 65

Page 15: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

activities, including management of design sub-consultants, material suppliers, other construction sub-contractors and testers.

Testing organisations, often the constructor AEO, but sometimes a test specialist, should document how they plan, coordinate and assure all testing

activities.

Maintenance organisations should document how they plan, execute, coordinate and assure all asset maintenance activities.

The above should be directly relevant to the asset group (or multiple asset groups) for which the AEO is applying for.

AEOs applying for non-asset specific services provided as a specialist services directly to TfNSW or in relation to other service providers in the

interest of and, or on behalf of TfNSW that do not directly relate to an asset group (or multiple asset groups) should also document how they plan,

execute and assure those services.

Guidance Documents

TS 10504 AEO Guide to Engineering Management

As applicable Requirement – ENM2

Design AEOs shall have capability to provide design support during procurement, manufacturing, construction, integration, test and commissioning

stages.

Guidance Elaboration

This requirement is limited to design AEOs, who are expected to demonstrate that they have capability to provide post-AFC design support and

advice.

This includes responding to and clarifying requests for information (RFIs) raised by the constructor, reviewing and approving engineering changes

proposed by the constructor by assuring that the changes continue to meet the original design intent and comply with relevant standards, inspecting

the site and witness tests performed by others to ensure that the design intent is met.

© State of NSW through Transport for NSW Page 15 of 65

Page 16: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

The design AEO must also mark up all changes made during construction, integration and testing and prepare final as-built designs for handover to

the client.

Guidance Evidence

Possible evidence includes the following:

• design management procedure. • design management plan • design reports • RFI responses (during construction) • engineering change requests or notes • engineers advice notes (during construction) • site inspection records • witness records for factory or site testing • construction drawing mark-ups

Guidance Documents

TS 10504

Other standards:

ISO/IEC/IEEE 15288

T MU AM 06006 GU Systems Engineering

T MU AM 06006 ST Systems Engineering

© State of NSW through Transport for NSW Page 16 of 65

Page 17: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.2. Requirements management This requirement demonstrates engineering management activities and arrangements for systematic eliciting, defining, analysing and allocating service or solution

requirements as well as managing traceability and fulfilment of those requirements through the service delivery cycle.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM3

An AEO shall have requirements management arrangements that set out appropriate process, responsibilities, structure, tools and deliverables for

management of stakeholder requirements applicable to the scope of engineering services provided across the system life cycle.

Guidance Elaboration

An AEO should ensure that the technical processes or tool for service requirements management covered in its documentation (as appropriate)

include the following:

• identification • categorisation • allocation • analysis • tracing • prioritisation • agreement • documentation • management changes • communication • compliance demonstration

The requirements management tool or process should enable requirements information exchange as suitable to the nature and scope of services.

© State of NSW through Transport for NSW Page 17 of 65

Page 18: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

This could be addressed by using some common requirements interchange formats in accordance with relevant industry best practices.

It is not always necessary to implement a complex proprietary requirements management tool for simple services or projects. Depending on the

project or system complexity the AEO could manage requirements using a spreadsheet tool or other means.

Guidance Evidence

The requirement evidence of documentation and deployment must be relevant and cover the proposed scope of authorisation.

Possible evidence includes the following:

• requirements management plan • requirements database • stakeholder engagement plan (or similar) • stakeholder register (or similar) • stakeholder engagement meeting records • stakeholder needs statement (or similar) • business requirements specification • systems requirements specification • subsystems requirements specification • operational concept definition (or concept of operations) • maintenance concept definition

© State of NSW through Transport for NSW Page 18 of 65

Page 19: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Documents

TS 10505 Guide to Requirements Definition and Analysis

ISO/IEC/IEEE 15288

ISO/IEC/IEEE 29148 Systems and software engineering - Life cycle processes - Requirements engineering

T MU AM 06004 ST Requirements Schema

T MU AM 06006 GU

T MU AM 06006 ST

T MU AM 06007 GU Guide to Requirements Definition and Analysis

T MU AM 06010 GU Business Requirements Specification

TS 10504

© State of NSW through Transport for NSW Page 19 of 65

Page 20: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.3. Service or solution engineering These requirements demonstrate engineering management activities and arrangements that support application of the relevant engineering principles and practices

in developing engineering products, services or solutions as appropriate to the scope of authorisation.

7.3.1. Interface management The objective of interface management requirement is to ensure that an organisation has a systematic process for identifying all interfaces, defining and analysing

safety, functional and performance requirements of relevant products or service interfaces within the scope of authorisation, agreeing on primary and secondary

owners of such interfaces and managing those interfaces over the full system life cycle.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM4

An AEO shall have interface management arrangements that set out the processes, responsibilities, structures, tools and deliverables.

Guidance Elaboration

An AEO shall ensure that all interface requirements under the control of its engineering services are identified, captured and managed.

An AEO shall ensure that interface design reviews and checks are conducted at appropriate stages of the design process by competent subject

matter experts.

An AEO shall identify and manage interface risks and outcomes that may have a safety or other undesired impact.

© State of NSW through Transport for NSW Page 20 of 65

Page 21: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Evidence

An AEO should ensure that the interface management processes covered in its documentation include the following for internal and external system

interfaces:

• identifying • recording • tracking • interface specifications • interface control • inter-disciplinary checks if applicable • identification of interface risks and outcomes that may have a safety or other undesired impact • arrangements to plan and carry out the integration if systems integration capability is offered

Possible evidence for various engineering disciplines and lifecycle services or activities include the following:

• interface management plan or process (system) or section in an overall systems engineering management plan or engineering management plan

• interface meetings, interface design reviews and check records • interface matrix (system) • interface control documents (system) • interface requirement specifications • interface requirements in requirements database • managing safety risks at interfaces

The requirement evidence of documentation and deployment must be relevant and cover the proposed scope of authorisation.

© State of NSW through Transport for NSW Page 21 of 65

Page 22: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Documents

ISO/IEC/IEEE 15288

ISO/IEC/IEEE 29148

T MU AM 06006 GU

T MU AM 06006 ST

TS 10504

TS 10507 Guide to Systems Integration

7.3.2. Integration management

The objective of integration management requirement is to demonstrate the process that ensures that implemented sub-system elements are integrated into the final

system that is consistent with the architectural design and function as a coherent system.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM5

An AEO shall demonstrate that it has suitable management arrangements to plan and carry

systems as appropriate to the scope of authorisation.

out the integration of all the declared products or

Guidance Elaboration

System integration is bringing together component elements of the product or service into one system, ensuring that elements function together as a

complete system and ensuring the resultant system integrates within the existing system or systems.

Not all AEOs will be required to offer or demonstrate systems integration capability.

© State of NSW through Transport for NSW Page 22 of 65

Page 23: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Evidence

The requirement evidence of documentation and deployment must be relevant and cover the proposed scope of authorisation.

An AEO should ensure that the systems integration processes covered in its documentation include the following:

• planning • assembly • verification and validation • documenting • analysing results

Other possible evidence includes the following:

• systems integration plan • systems integration requirements • interface control documents • interdisciplinary design review records • system integration report

More examples are provided in TS 10507.

Guidance Documents

ISO/IEC/IEEE 15288

ISO/IEC/IEEE 29148

T MU AM 06006 ST

TS 10504

TS 10507

© State of NSW through Transport for NSW Page 23 of 65

Page 24: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.3.3. System architecture management

The objective of system architecture management requirement is to demonstrate the capability to synthesise or translate system level functional and performance

requirements into a framework architecture that provides a range of perspectives, which are then used for design decision making and detailed system design

development.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM6

A design AEO shall demonstrate that it has arrangements to manage the synthesis and development of system level requirements

system architecture.

into a credible

Guidance Elaboration

System architecture development and management is typically done by AEOs during the concept and development stages of the system or asset

life cycle in conjunction with system modelling and analysis.

For complex software programmable communications and control systems, evolving best practice is to use the unified modelling language (UML) or

systems modelling language (SysML) to define these systems using a range of standard architectural viewpoints and models.

An AEO may choose to procure established, validated, commercial architecture development and modelling tools to support this service. Generally

this is used for modelling complex systems. It is expected that AEO processes would have required triggers for this to occur and also the suitable

processes in place to ensure procurement.

Guidance Evidence

System architecture management arrangements are typically documented in a system architecture management plan, but may be included as a

section within an overall systems engineering management plan or engineering management plan depending on the scope and complexity of

engineering services provided.

Depending on the nature of the systems, the asset types involved and the level of detail abstraction the system architecture may be defined in

© State of NSW through Transport for NSW Page 24 of 65

Page 25: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

standards and general arrangement drawings.

Depending on the scope and nature of systems and elements involved, typical architectural viewpoints may include the following:

functional architecture, a representation of each function and its embedding or relationship to other functions within and outside the system

logical architecture, representing logical relationships between functional elements of the system

physical architecture, representing the physical hardware that actually contains the functions defined in the functional architecture

geographic architecture, allocation of physical hardware assets to geographic locations

operational architecture, operational processes and interactions with internal and external users

An AEO should ensure that the systems architecture processes covered in its documentation include the following:

• defining architecture • defining viewpoints • analysing • evaluating • documenting • maintaining • Possible evidence includes the following: • system architecture management plan • architectural framework • operator viewpoint • maintainer viewpoint • logical or functional architecture • physical architecture • geographical architecture

© State of NSW through Transport for NSW Page 25 of 65

Page 26: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Documents

ISO/IEC/IEEE 15288

T MU AM 06001 GU AEO Guide to Systems Architectural Design

T MU AM 06006 GU

T MU AM 06006 ST

TS 10504

© State of NSW through Transport for NSW Page 26 of 65

Page 27: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.3.4. Sustainability in design

The objective of sustainability in design requirement is to demonstrate the organisational capability to ensure that all relevant aspects of sustainability are considered

in the engineering activities applied across the full asset life cycle as relevant or impacted by the services within the scope of authorisation. Appropriate and timely

consideration of sustainability should aim to optimise the environmental, social and economic sustainability of the asset.

As applicable Requirement – ENM7

An AEO shall incorporate sustainability in design principles as relevant to the scope of the authorised engineering services.

Guidance Elaboration

For specific projects or issues, an AEO will often require specialist sustainability advice. This expertise may be in-house or contracted.

Sustainability in design should aim to provide the optimal design solution for the whole asset life cycle, by improving the environmental, social and

economic sustainability of the asset.

Key considerations for sustainability in design are as follows:

• inclusion of sustainability early in the planning and design process • inclusion of consideration of sustainability in engineering analyses. For example, in requirements definition, life cycle analysis, operational

concepts or risk assessment • determination and justification of the amount of sustainability work in line with the risk and complexity of specific projects • identification and recording of sustainability issues relevant to specific projects • analysis, management and control identified issues • inclusion of consideration of sustainability in engineering analyses. For example, in requirements definition, life cycle analysis, operational

concepts or risk assessment • provision of a mechanism for transferring sustainability requirements to subsequent life cycle stages, closing out issues, and capture and

recording of issues learnt at the conclusion of projects

The scale of the sustainability work required will vary from significant for novel and complex projects to minimal for like for like substitution of a piece

of equipment.

© State of NSW through Transport for NSW Page 27 of 65

Page 28: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Evidence

AEOs should demonstrate company commitment to sustainability such as company environment and/or sustainability policies; processes to integrate

sustainability into designs at an appropriate stage of the project, such as in a design management plan; and evidence of deployment such as

sustainability integration plans, sustainability workshops, or completion of a sustainability tool such as NSW Sustainable Design Guidelines published

by TfNSW.

The application of the sustainability in design process for a specific project would typically be described in a sustainability integration plan (SIP) or

relevant sections of the other planning documents, for example within the engineering management plan.

Guidance Documents

T MU EN 00003 GU AEO Guide to Sustainability in Design

7.3.5. RAM management The objective of this requirement is to demonstrate organisational capability to ensure that RAM properties of the impacted target system or asset can be achieved

by the evolving system architecture and design.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM8

An AEO shall demonstrate that it has RAM management arrangements in place, relevant to the engineering services or products provided.

Guidance Elaboration

An AEO providing fabrication, construction or installation services may need to demonstrate RAM management. An AEO offering system design or

systems integration services should have RAM management arrangements. Maintenance AEOs may need to ensure that the delivered asset or

system continues to meet its designed RAM targets over its operational lifetime.

However, if an AEO intends to engage in design or systems integration services involving development and delivery of novel systems in

© State of NSW through Transport for NSW Page 28 of 65

Page 29: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

configurations that are not covered by existing TfNSW standard configuration drawings, then the AEO will be expected to demonstrate that it does

have RAM management arrangements.

Validating RAM models may be done by the AEO, but also by the TfNSW accepting organisation during system acceptance and handback.

An AEO may choose to develop in-house RAM assurance tools, but their outputs must be demonstrated to have been validated against recognised

established benchmarks.

An AEO may choose to procure established and validated commercial RAM modelling tools to support this service.

Guidance Evidence

RAM management arrangements should be documented in a RAM plan or manual, but may be included as a section within an overall systems

engineering management plan or engineering management plan, depending on the scope and complexity of engineering services provided.

An AEO should ensure that the RAM management processes covered in its documentation includes the following:

• planning • requirements • modelling and analysis • documenting • failure recording

Possible evidence includes the following:

• RAM management plan • RAM requirements (including service availability) • RAM models • RAM reports • redundancy strategies

© State of NSW through Transport for NSW Page 29 of 65

Page 30: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, Requirement, elaboration, evidence or documents as applicable or guidance

Guidance Documents

ISO/IEC/IEEE 15288

T MU AM 06006 GU

T MU AM 06006 ST

TS 10504

T MU AM 06002 GU AEO Guide to Reliability, Availability and Maintainability

7.3.6. Human factors integration

The objective of this requirement is to demonstrate organisational capability to ensure that all relevant aspects of the human interaction within the system are

considered in the engineering activities applied across the full asset life cycle as relevant or impacted by the services within the scope of authorisation. The practical

application of HF knowledge contributes to enhanced design solutions and improved operational and safety performance.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM9

An AEO shall manage all HF relevant to the scope of the authorised engineering services

Guidance Elaboration

HF considerations form an integral part of the specification, desig

that it can be operated and maintained safely and efficiently.

n and development process ensuring that the asset is designed and delivered such

An AEO should ensure that engineering design decisions are properly informed by adequate information about human related issues and that

© State of NSW through Transport for NSW Page 30 of 65

Page 31: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

decisions relating to design alternatives or assessments consider HF data to provide the optimal design solution for the whole asset life cycle.

There are benefits that an organisation conducting post-design asset lifecycle activities from manufacturing and installation through to the

decommissioning and disposal can gain through the application of HF principles and knowledge to the organisation of the day-to-day operation or

maintenance of assets.

Application of the HF integration processes should identify HF issues such as physical, cognitive and organisational including the opportunities for

human error and their consequences.

HF integration is the process by which the application of HF is managed. An AEO is expected to have such a process, standalone or integrated into

the other product or service delivery processes. An AEO that delivers assets with complex human interactions such as rolling stock or control

systems interfaces is expected to have a standalone process.

Guidance Evidence

The application of the HF integration process for a specific project would typically be described in a HF integration plan (HFIP), although for simple

projects it may be contained within the engineering management plan.

The scale of the HF work required will vary from significant for novel and complex projects to minimal for 'like for like' substitution of a piece of

equipment. It also depends on the scope of services provided.

For specific projects or issues an AEO will often require HF specialist advice. This expertise may be in-house or contracted. It is expected that AEO

process would have the required triggers for this to occur and also the suitable process in place to ensure procurement of competent resources.

AEOs are expected to demonstrate that their HF integration practice contains the following as a minimum:

• identifies the various user groups, their attributes and requirements • identifies and records HF issues relevant to specific projects • determines and justifies the level of HF work in line with the risk and complexity of specific projects

© State of NSW through Transport for NSW Page 31 of 65

Page 32: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

• •

• •

analyses, manages and controls identified issues includes HF consideration in engineering analyses (for example in requirements definition, operational concepts, hazard identification, risk assessment, FMECA, FTA and so forth) provides a mechanism for closing out issues (such as within multi-disciplinary design reviews) captures and records lessons learnt at the conclusion of projects

Guidance Documents

T MU HF 00001 GU AEO Guide to Human Factors Integration

T MU HF 00001 ST Human Factors Integration - General Requirements

T MU MD 20001 ST System Safety Standard for New or Altered Assets

© State of NSW through Transport for NSW Page 32 of 65

Page 33: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.3.7. Electromagnetic compatibility (EMC)

The TfNSW operational transport environment consists of a large number of critical, electromagnetically emissive and sensitive systems co-located in close

proximity, including systems used by other transport operators and external organisations.

All electrical or electronic systems that are not correctly designed, manufactured or installed can cause electromagnetic interference (EMI) to other equipment or

services susceptible to EMI from a range of sources in the operational environment.

It is essential to manage EMC throughout the system life cycle, from concept to commissioning and ongoing maintenance, to achieve and maintain total system

functionality, performance and safety.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM10

An AEO engaged by TfNSW to undertake engineering activities involving the specification, design, integration, testing and maintenance of electrical

or electronic systems involving EMI emitters (threats) or receivers (victims) shall have arrangements for managing EMC.

An AEO engaged by TfNSW to undertake engineering activities involving the specification, design, build, integration or modification of electrically

conductive or magnetically permeative structures shall ensure that arrangements are in place for managing electromagnetic interference and

electromagnetic compatibility.

Guidance Elaboration

EMI can typically occur via four coupling mechanisms:

• conductive interference, for example, stray earth currents from the traction earth return circuit • inductive, for example, currents induced by near-field alternating current power circuits • capacitive, for example, static discharge from high voltage (HV) circuits and coupling to lineside fences • radiative, for example, radiated electromagnetic waves

Any electrically conductive or magnetically permeative structure near electrical or electronic equipment can excessively couple (transfer) EMI if it is

© State of NSW through Transport for NSW Page 33 of 65

Page 34: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

not correctly designed, manufactured, modified or installed. These structures typically include buried metal pipes, fences, towers and steel reinforced

concrete structures of appreciable length such as viaducts, bridges, tunnels, platforms and concourses.

An AEO responsible for design and construction of these electrically conductive or magnetically permeative structures, usually civil engineers,

should consult with the designers and installers of the electrical or electronic systems that may transfer EMI via these structures.

EMC is typically achieved on most TfNSW transport projects through the following:

• compliance to established standards and standard drawings for the configuration and relative positioning of electrical HV power feeders, overhead wiring (OHW) systems, low voltage (LV) power circuits and various signalling, telecommunication and control systems

• use of type-approved electrical and electronic systems and products such as radar, navigation, global positioning and radio communications systems

• compliance with established earthing, bonding, screening, segregation, immunisation and electrolysis standards and codes of practice

Engineering design and specification activities associated with EMC on transport assets include the following:

• earthing and bonding design for protection of both equipment and people • electromagnetic radiation analysis and design • electrolysis effects and their mitigation • lightning and other surge protection

An AEO engaged by TfNSW to undertake engineering activities involving the specification, design, integration or testing of electrical or electronic

systems involving EMI emitters (threats) or receivers (victims) shall have arrangements for managing EMC.

An AEO engaged by TfNSW to undertake engineering activities involving the specification, design, build, integration or modification of electrically

conductive or magnetically permeative structures shall ensure that arrangements are in place for managing EMI and EMC.

An AEO offering system design or systems integration services, either as a technical advisor during the development of the reference design or as

part of a design and construct contract during project implementation, should have EMC management arrangements.

An AEO that intends to engage in design or systems integration services on projects involving development and delivery of novel electrical and

© State of NSW through Transport for NSW Page 34 of 65

Page 35: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

electronic systems in novel configurations that are not covered by existing standards should demonstrate EMC management including systematic

analyses of the electromagnetic impact of any deviation from standard practice.

These arrangements should enable the planning, analysis, execution, assurance and reporting of all EMC-related activities on a project or system

and document this in an EMC management plan.

The level of EMC management is expected to be negligible where it can be demonstrated that a new system will be designed and implemented

using type-approved products in standard configurations.

An AEO providing fabrication, construction or installation services for non-electrical or electronic systems will not need to demonstrate full EMC

management arrangements.

The system design or systems integrator AEO may choose to sub-contract a specialist EMC consultant to support its EMC management

arrangements. It is expected that AEO process would have required triggers for this to occur and also the suitable process in place to ensure

procurement.

An AEO should ensure, if applicable to the AEO services, that the EMC management processes covered in its documentation includes the following:

• planning of EMC or related electrical immunisation activities • EMC hazard identification • electromagnetic radiation effects on people • reporting • An AEO should demonstrate that it has systematically analysed the electromagnetic impact of any deviation from standard practice if is

engaged to design, develop or introduce a new product or non-standard configuration is integrated into the above.

© State of NSW through Transport for NSW Page 35 of 65

Page 36: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Evidence

Possible evidence includes the following:

• design plan or procedure with EMC considered • EMC management plan • EMC procedure • EMC guide • EMC manual • earthing and bonding designs • EMC test records

Guidance Documents

T MU AM 06006 GU

T MU AM 06006 ST

TS 10504

International standards on EMC, in particular for railways (for example, IS EN 50121 Railway applications - Electromagnetic compatibility series)

© State of NSW through Transport for NSW Page 36 of 65

Page 37: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.4. Assurance, verification and validation These requirements demonstrate engineering management activities and arrangements that support the delivery of the quality engineering product, system or

service by providing confidence that relevant processes were followed, requirements are met and the final product or service meets its intended purpose.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM11

An AEO shall have arrangements for verification and validation management of the engineering services or products provided.

Guidance Elaboration

Verification and validation are processes that are used together for assuring that a product, service or system fulfils its intended purpose. The two

processes are seen as essential in the life cycle of any complex system. The development of any system is not complete without ensuring that the

implementation is consistent with the specifications.

Implementing verification and validation provides assurance that the product, service or system meets its required specifications, including any

safety requirements.

Guidance Evidence

Verification and validation management arrangements should typically be supported by the following evidence artefacts:

• organisation level verification and validation arrangements • Project-level verification and validation arrangements • verification and validation plans • verification and validation processes and procedures • verification and validation guides • verification and validation checklists or tools • verification and validation reports • other artefacts documenting or demonstrating how they will carry out verification and validation of systems on a repeatable basis

© State of NSW through Transport for NSW Page 37 of 65

Page 38: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

These artefacts should form part of an integrated management system or similar system at an organisational or project level, that is compliant with

either ISO 9001, ISO 55000, AS/NZS ISO 9001 or AS ISO 55000 as appropriate.

Verification and validation management arrangements are typically documented in a verification and validation plan. However, they may form a

section of a systems engineering management plan or overall engineering management plan, depending on the scope and complexity of

engineering services provided.

An AEO may choose to develop in-house systems verification and validation tools.

An AEO may choose to procure established and validated commercial verification and validation management tools to support this service. It is

expected that AEO processes would have the required triggers for this to occur and also suitable processes in place to ensure procurement.

An AEO should ensure that the verification and validation management processes covered in its documentation includes the following:

• design reviews • analysis • demonstration • certification • inspection and testing • commissioning • acceptance testing • maintenance

Possible evidence includes the following:

• verification management plan, procedure, guide or manual • validation management plan, procedure, guide or manual • testing and commissioning management plan, procedure, guide or manual • maintenance management plan, procedure, guide or manual

© State of NSW through Transport for NSW Page 38 of 65

Page 39: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Documents

ISO/IEC/IEEE 15288

T MU AM 06006 GU

T MU AM 06006 ST

TS 10504

TS 10506 Guide to Verification and Validation

Mandatory Requirement – ENM12

An AEO shall demonstrate engineering assurance based on progressive stage gateway reviews.

© State of NSW through Transport for NSW Page 39 of 65

Page 40: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Elaboration

This requirement is applicable to prospective design, manufacturing, construction and testing, and maintenance AEOs and must be fulfilled.

The baseline stage gateways to apply will depend on the scope of engineering services offered over the asset life cycle by the AEO.

The engineering methodologies and processes that an AEO applies will depend upon the scope of engineering services offered over the asset life

cycle.

Systems assurance brings together the elements of:

• quality assurance • verification and validation results • RAM assurance • system safety assurance (also see requirement ENM16) • compliance to procedures • compliance to standards • compliance to appropriate legislation

Guidance Evidence

For design consultants, the design assurance process should identify key stages where the design is reviewed prior to progressing to the next level

of detail. This may take the form of 30%, 70% or 100% gates or system definition review (SDR), preliminary definition review (PDR) or critical design

review (CDR) gates or something similar.

For construction contractors, the use of witness and hold points represents application of stage gates in the progressive assurance of the built asset

or system.

Possible evidence includes the following:

• design management plan, procedure, guide or manual • fabrication or manufacturing management plan, procedure, guide or manual • construction or installation management plan, procedure, guide or manual • testing management plan, procedure, guide or manual

© State of NSW through Transport for NSW Page 40 of 65

Page 41: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Documents

TS 10504

Mandatory Requirement – ENM13

AEOs shall apply a risk-based approach to engineering assurance.

Guidance Elaboration

This requirement refers to assurance of all engineering-related risks and while it includes safety risk, it is not limited to safety.

Management of engineering risk across the TfNSW Transport Network is a joint responsibility of all parties, including the AEO and TfNSW.

The level of risk associated with an engineering activity is related to technology, novelty, system size and complexity, amount of stage work and

quantity and type of system interfaces.

© State of NSW through Transport for NSW Page 41 of 65

Page 42: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Evidence

Design consultants should demonstrate how they assure risks introduced by their designs.

Constructors should demonstrate how they assure risks introduced by their construction methods, tools and equipment.

Maintainers should demonstrate how they assure risks introduced by their maintenance actions, methods, tools and equipment.

This requirement is applicable to all prospective AEOs and must be demonstrated including arrangements for acceptance of risks transferred from

preceding lifecycle stages.

Possible evidence includes the following:

• risk management plan, procedure, guide or manual • risk registers • risk matrix • risk assessment forms • risk workshops • risk reports • hazard logs

Guidance Documents

TS 10504

© State of NSW through Transport for NSW Page 42 of 65

Page 43: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.4.1. Judgment of significance (JOS)

All designs are required to be subject to a judgement of significance (JOS). This judgement is an assessment of the technical risk introduced by the implementation

of the design and must consider both the probability and consequence of partial performance or failure of a design. Subsequent to a JOS, all designs must be

classed as either significant or non-significant. Designs judged as significant are subject to a more rigorous design review and approval process.

Mandatory, as applicable or guidance

Requirements

As applicable Requirement – ENM14

An AEO shall establish arrangements for assessing the significance of proposed engineering changes arising from the delivery of its engineering

services.

© State of NSW through Transport for NSW Page 43 of 65

Page 44: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Guidance Elaboration

The JOS should assess complexity and effects, including safety risk, of the change.

In the absence of hands-on JOS decision making by the client, AEOs must demonstrate that they have a systematic and robust process for

assessing the impact of engineering changes.

These changes may arise during the design, procurement, fabrication or manufacturing, construction or installation, integration, testing and

commissioning phases.

The AEO responsible for assuring the engineering service in these phases must demonstrate how it will assess an engineering change against a set

of criteria, to assure that the change is safe, reliable, sustainable and value for money. Assessment of the change should be demonstrated on a risk-

basis.

For all works TfNSW undertakes an assessment of the significance of safety impact prior to awarding contract and informs the principal contractor.

The attributes of a suitable JOS related to a proposed engineering change include:

• assessment of the need for the change • risk level including safety risk • RAM impacts • updates to the configuration and technical data

Guidance Evidence

Possible evidence includes the following:

• engineering change request or note • risk assessment evidence • configuration change note

© State of NSW through Transport for NSW Page 44 of 65

Page 45: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.4.2. System safety assurance

The objective of this requirement is to demonstrate organisational capability to ensure that the operational safety risks associated with the impact of the AEO service

system or asset are identified, managed and reduced so far as is reasonably practical (SFAIRP) in all engineering activities and disciplines over the full asset life

cycle. Safety must be integrated into the design of assets and demonstrated to be safe SFAIRP in accordance with T MU MD 20001 ST.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM15

The AEO shall have system safety assurance arrangements in place relevant to the engineering services or products provided. These arrangements

must include suitable planning activities and deliverables. They must also demonstrate suitable and sufficient integration into the engineering

services.

Guidance Elaboration

The key objective of system safety is to ensure the integration of safety in operation into the design, construction, implementation and

commissioning of a change.

The TfNSW Configuration Management and Asset Assurance Committee (CMAAC) supports the acceptance of assets for the Transport Network. If

an AEO is authorised and planning to undertake the leading role in integrating and delivering change (product or service) directly to TfNSW,

including systems safety integration, then its own systems safety management system must be capable of ensuring alignment with the TfNSW

configuration management framework including the TfNSW Configuration Control Board (CCB) process.

System safety activities shall be planned so that they support the development of a suitably safe system and provide the assurance needed to

demonstrate the safety of the system.

The scope and depth of safety assurance arrangements should be scaled according to the range of engineering services and associated risk. A

large multi-disciplinary engineering organisation that performs or engages other AEOs to perform significant safety critical functions, including

construction, testing and maintenance affecting TfNSW Transport Network will require a more comprehensive set of system safety management

© State of NSW through Transport for NSW Page 45 of 65

Page 46: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

arrangements than a small niche consultancy providing single-discipline design services.

TfNSW undertakes an assessment of the significance of safety impact prior to awarding contracts and informs the integrating AEO.

Guidance Evidence

System safety assurance arrangements may be documented in a safety management system (SMS). The scope and depth of an SMS will depend

on the scope and depth of an AEO's engineering services. A small single discipline consultancy will have a small and simple SMS, whereas a large,

multi-disciplinary engineering services or construction company will have a large and detailed SMS.

The AEO shall have a process that plans all safety assurance activities in an auditable manner.

Where appropriate, the system safety activities should be aligned with the engineering life cycle.

A safety change management plan is typically used to document how the AEO will manage the safety risks associated with the changes that it

introduces to the TfNSW Transport Network and integrates safety into the design of the asset. This plan is alternatively referred to as a safety plan,

safety management plan or safety assurance plan.

For a safety significant change acceptance an AEO delivering services or products to TfNSW shall provide the following to the TfNSW CMAAC for

consideration:

• a system safety plan • an operational safety argument • an independent safety assessment (ISA) (may be delivered by TfNSW)

For minor changes, an delivering products or services can include safety risk management activities planning into its engineering management plan.

A risk summary report, with a description of the key residual safety risks that TfNSW or the operator will be exposed to during the operating life of the

asset and evidence of appropriate independent validation during the development and implementation of the change, shall be provided for

acceptance of minor changes and demonstration of SFAIRP.

© State of NSW through Transport for NSW Page 46 of 65

Page 47: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM16

The AEO's safety assurance arrangements must provide progressive assurance through the project or system life cycle.

Guidance Elaboration

As safety assurance is integrated with engineering assurance, this requirement means that AEOs shall continually demonstrate safety assurance for

each staged gateway review. It shall also develop the assurance level of details in line with the level of details of the design.

The approach to progressive safety assurance should be scaled to the scope and nature of services being provided and also consider the

overarching integral systems safety needs for the impacted TfNSW assets and services.

At each gateway an agreement shall be reached with all stakeholders that for that point in the system development where all reasonably practicable

activities and actions have been conducted to ensure safety.

Guidance Evidence

The safety assurance program may include safety assurance documents or safety cases at key project milestones including concept design,

detailed design and testing. In complex or novel projects these interim assurance documents representing a progressive assurance approach help

manage the risks associated with the asset and its delivery.

Mandatory Requirement – ENM17

The AEO shall have arrangements for the identification and management of safety risks associated with the changes to be introduced. The process

should follow a life cycle approach such that the granularity of risks and the level of analysis aligns with the progression through the engineering life

cycle. It shall also support risk-based decision-making with records to show traceability of all decisions made.

© State of NSW through Transport for NSW Page 47 of 65

Page 48: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Elaboration

AEOs and suppliers shall implement a level of safety risk management appropriate to the risks associated with the change.

The safety risk management process implemented by AEOs shall address the full intended operational life of the new or altered asset or system. It

should include an assessment of safety risk for each identified hazard against the appropriate risk criteria and provide a high degree of confidence

that the final residual risk can be demonstrated to have been reduced to tolerable and SFAIRP.

Guidance Evidence

AEOs shall employ suitable and sufficient hazard identification, hazard analysis and hazard management techniques and demonstrate this in the

safety argument, risk summary report or other safety assurance documentation. All analysis results shall be documented and referred to as

evidence.

Hazard identification and analysis techniques may include hazard identification (HazID), hazard and operability studies (HazOp), preliminary hazard

analysis (PHA), system hazard analysis (SHA), sub-system hazard analysis (SSHA) and operational support hazard analysis (OSHA).

The hazard log is the central repository of identified hazards. The hazard log is the primary artefact for providing traceability within the safety risk

management process and assurance of the effective management of safety.

The hazard log at the system level may be managed by a system integrator, however, it is still the responsibility of all AEOs to identify and manage

the hazards and risks for which they are responsible.

As applicable Requirement – ENM18

The AEO shall have arrangements for delivering safety assurance arguments and supporting evidence (or input to such documentation) that

describes how it has ensured safety SFAIRP and managed safety risks to tolerable and SFAIRP. The content of such documents should be aligned

with the requirements of T MU MD 20001 ST so that they meet the requirements of the CMAAC process.

© State of NSW through Transport for NSW Page 48 of 65

Page 49: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Elaboration

For safety significant changes an AEO shall deliver an operational safety argument which demonstrates the safety of the delivered system in

operation within the Transport Network.

For minor changes a risk summary report must be provided. AEOs are also required to deliver assurance against the requirements of the system

safety standard for new or changed assets.

Guidance Evidence

The safety argument should be structured using goal structuring notation or a similar approach and is included in a document referred to as a safety

assurance report or statement. An operational risk register should be included into the safety argument to document risks that have been identified

but not eliminated during the development and implementation phase and are thus carried over to the operate and maintain phase.

The argument should be scaled to the level of risk and follow the expected industry practice. For example, a safety argument for a station upgrade

should look very different to the one for a rolling stock fleet.

Guidance Documents

T MU MD 20001 ST

As applicable Requirement – ENM19

AEO safety engineering and assurance arrangements shall be subject to ISA, where it is responsible for the introduction of new or novel systems

that affect the operational safety of the network or where the general scope and complexity of the project requires it. There shall be arrangements in

place to support the appointment of an ISA organisation and to engage with an ISA organisation at all stages of the engineering activities being

undertaken when required and in accordance with the relevant standards and best practice for the scope of works.

© State of NSW through Transport for NSW Page 49 of 65

Page 50: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Elaboration

For changes determined to be safety significant by TfNSW an authorised ISA organisation will be appointed. The ISA organisation may be appointed

by an AEO that has a process in accordance with relevant standards or TfNSW may appoint an ISA organisation..

Guidance Evidence

An AEO should have a process for independent safety assessor engagement that would cover the following:

• scenario or circumstances when an ISA is to be conducted • function of an ISA • details and use of the expected outcome of the ISA

There also has to be a suitable process in place to ensure procurement.

Guidance Documents

T MU MD 00003 GU Guide to Independent Safety Assessment

Safety Change Management Standard 20-ST-006

T MU MD 20001 ST

© State of NSW through Transport for NSW Page 50 of 65

Page 51: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.5. Configuration management This requirement demonstrates engineering management activities and arrangements that ensure the integrity of network product or service being delivered and that

all changes to assets over the system life cycle are managed across a defined set of baselines, including all related information and records.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – CFM1

An AEO shall have a documented system that describes the management of the configuration of all proposed or existing configuration items under

its control as relevant to the scope of the authorised engineering service.

Guidance Elaboration

An AEO is required to have and apply documented arrangements that provide confidence that an appropriate systematic and comprehensive

approach is applied to the management of the configuration items the organisation is responsible for.

Depending on circumstances and the services or products being provided, configuration items may include any work products that are controlled,

produced and delivered as part of the engineering service delivery within the scope of authorisation.

Configuration items can be documentation such as various reports, specifications and designs, asset information or actual assets that will form part

of the TfNSW Transport Network, such as vehicles, physical structures and software.

Arrangements for configuration management should be tailored to be appropriate to the following:

• nature and complexity of the configuration items controlled or delivered by the AEO • complexity and role within the organisational environment in which the AEO will be providing services

Configuration management arrangements may exist as a specific system or be integrated into other business systems but must be appropriate. It

must also be clearly demonstrated how the AEO meets the configuration management requirements.

Configuration management involves a complete definition of the baseline, for example, considering whether the configuration items are classified in

© State of NSW through Transport for NSW Page 51 of 65

Page 52: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

discrete or grouped categories and taking into consideration the service or solution requirements and the management of the configuration items

over the asset life cycle.

An AEO that will be responsible for decisions to integrate new or modified transport assets into the TfNSW Transport Network is expected to have a

configuration management system that is capable of meeting the requirements of the T MU AM 04001 PL TfNSW Configuration Management Plan.

A configuration management system should allow the following to be clearly understood and appropriately applied:

• the scope of configuration items that will be controlled, for example engineering designs or assets being delivered or assets being managed • stakeholder identification and management applicable within the context of the services provided by the AEO • change control process that demonstrates full asset life cycle considerations (not just commercial or project delivery) have been considered • roles and responsibilities associated with maintaining the configuration items, approving changes and delivering configuration items • assuring that configuration items and associated information are checked and delivered such as transport assets, design drawings and other

documentation and data

An AEO produces various types of information (such as documents) that must also be kept under the appropriate level of work product control as

suitable to the scope of services.

Guidance Evidence

An AEO is to show evidence of a documented system for configuration management. The sophistication, detail and structure of the system may vary

depending on the complexity and nature of expected engagements. The system may be specifically identified as configuration management or be

part of other business systems.

The documentary evidence broadly falls into the following categories:

• a cohesive documented system • configuration items that are known and recorded • changes to configuration items that are appropriately controlled • information about configuration items that are available and assured as correct

© State of NSW through Transport for NSW Page 52 of 65

Page 53: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Where an AEO intends to be responsible for making decisions about the integration of assets into the TfNSW Transport Network or integrating

multiple components to form a complex solution, a configuration management plan or similar document is expected.

If the configuration items to be managed by an AEO largely consist of documentation it may be acceptable to demonstrate that appropriate

document control arrangements exist.

The evidence presented should demonstrate that the organisation understands configuration management in the context of the services the AEO

intends to offer. The evidence should reflect the principles of AS ISO 10007 Quality management systems - Guidelines for configuration

management. Various documents may be used as evidence but it must be clear that the configuration management requirement is met and it must

be cohesive.

Roles and responsibilities for configuration management should be clear within documentation.

Evidence of change control arrangements should include tools and processes that provide traceability of changes. Tools may vary depending on the

complexity of configuration items and changes being managed but may include change control forms, change control registers or configuration

management software. Evidence of arrangements for appropriate stakeholder engagement and approval should be included in the change control

arrangements.

Evidence of a system for recording and maintaining information about configuration items may include processes and tools. Suitable tools will vary

depending on the nature of the configuration items and the services being provided by the AEO. Tools may include simple registers or complex

databases.

Document control tools and processes may be adequate where the configuration items are only documents.

Depending on services being provided, processes for identifying and managing information about proposed or actual assets may be expected.

Processes should address the assurance that information is correct and appropriately structured before being delivered.

Documentation may include asset registers, approved designs, maintenance manuals or any other document that specifies the characteristics of the

© State of NSW through Transport for NSW Page 53 of 65

Page 54: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

customer asset. Arrangements for updating and confirming the accuracy of that information should be documented. Assurances that documentation

matches configuration items may be provided through configuration audits.

An AEO shall establish and maintain, as a minimum, records of the following:

• configuration data records, for example as-built drawings, manuals and training materials in a common format that can be exchanged with other parties

• quality assurance records, for example, inspections, audits and reports • safety assurance records, for example, hazard logs, safety plans and safety reports • competence management records, for example, assessments, development, logbooks and curriculum vitaes (CVs) • engineering assurance records applicable to the authorised services, for example, construction, manufacturing, integration, testing,

commissioning, maintenance and disposal

Guidance Documents

T MU AM 04003 GU Configuration Management Guide

7.6. Competence management These requirements demonstrate engineering management activities and arrangements that ensure that only engineering staff with the appropriate knowledge, skills

and behaviours are engaged to perform activities defined for a specific job role or function, within a specific engineering service area or discipline.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – CPM1

An AEO shall have comprehensive arrangements and systems for managing the competence of its staff, contractors, sub-contractors and other third

party suppliers, relevant to the engineering services provided.

© State of NSW through Transport for NSW Page 54 of 65

Page 55: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Elaboration

A system for managing staff competence must consist of the following:

• an unambiguous series of documented arrangements of the organisation’s roles, plans, processes, tools and records in relation to managing competence

• a recruitment process that clearly outlines how the organisation employs people that have the necessary knowledge, skills and attitudes to competently and safely discharge their duties in providing engineering services

• a process for assuring competence for all external parties, including contractors, sub-contractors and suppliers • existing job descriptions containing roles, functions and abilities before candidate assessment • defined skills and proficiency levels relevant to the tasks and activities used in the provision of engineering services to TfNSW • minimum acceptable competence requirements for positions carrying out key roles identified in the organisation

Guidance Documents

TS 10503 AEO Guide to Engineering Competence Management

Mandatory Requirement – CPM2

An AEO shall consider relevant external qualification standards to benchmark the skills to be assessed and maintain evidence that relevant industry

competence requirements, including TfNSW Standards, have been analysed and interpreted for the appropriate engineering services offered.

Guidance Elaboration

Benchmarking of skills must consist of the following where relevant:

• evidence of how technical assessments align with the industry and other standards • qualification or Australian Quality Training Framework (AQTF) reference in position descriptions • benchmark plans • references to international or national standards • references to TfNSW Standards • professional memberships

© State of NSW through Transport for NSW Page 55 of 65

Page 56: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Documents

TS 10503

Mandatory Requirement – CPM3

An AEO shall have arrangements in place to train, develop and assess the competence of staff using established methods and competence

standards, including establishing training and development needs for staff delivering engineering services.

Guidance Elaboration

Arrangements to train, develop and assess the competence of staff must include the following where relevant:

• processes to regularly assess competence of staff • staff development processes • log book reviews • training and development processes, including needs identification • training calendars • training forms

Guidance Documents

TS 10503

Mandatory Requirement – CPM4 An AEO shall provide for the planning, implementation, recording, assessment and recognition of relevant continuing professional development activities to enhance the knowledge and skills of staff and the organisation as a whole.

© State of NSW through Transport for NSW Page 56 of 65

Page 57: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Elaboration

Arrangements for the planning, implementation, recording, assessment and recognition of relevant continuing professional development activities

must include examples of the following where relevant:

• professional development processes • professional development plans • records of professional development • professional memberships

Guidance Documents

TS 10503

Mandatory Requirement – CPM5

An AEO shall maintain competence management records that contain appropriate and up-to-date information about all competence aspects of a

candidate. All records shall be maintained for audit purposes and must be stored in a secure location for the duration of the AEO certification validity

period.

Guidance Elaboration

Competence management records must include the following where relevant:

• processes for the maintenance and storage of records • management of expiry of competences and assessments • recruitment records • competence assessment records • training records • training registers • development review records

© State of NSW through Transport for NSW Page 57 of 65

Page 58: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Documents

TS 10503

Mandatory Requirement – CPM6

An AEO shall establish and maintain a register of all engineering and other engineering-related services provided by staff and their competences.

Guidance Elaboration

The register must consist of documentation that demonstrates which staff members have been assessed as competent to carry out required

functions or roles within the scope of engineering services, with assigned proficiency levels.

Guidance Documents

TS 10503

Mandatory Requirement – CPM7

An AEO shall maintain the competence of those managers and assessors implementing the competence management system and ensure that the

managers and assessors understand their responsibilities.

Guidance Elaboration

Arrangements for those involved in the management and implementation of the competence management system must include the following:

• defining competence management roles and responsibilities • assigning ownership and responsibility to suitably qualified and experienced individuals • processes to outline the procedures for conducting competence assessments • qualification or proficiency levels required for subject matter experts • competence requirements for assessors

© State of NSW through Transport for NSW Page 58 of 65

Page 59: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Documents

TS 10503

Mandatory Requirement – CPM8

An AEO shall demonstrate its knowledge management capability as suitable to the scope of services and the sharing of industry relevant lessons

learnt within the organisation and with the ASA.

Guidance Elaboration

The purpose of the knowledge management practice is to enable the organisation to use and re-apply existing internal and external knowledge.

This requirement also aligns with one of the ASA objectives to engage with industry to share lessons learnt and emerging best practice.

Guidance Evidence

An AEO should demonstrate its ability and arrangements for knowledge capture, storage and redeployment as appropriate for the organisational

scope of authorisation and business model.

This could be evidence of the following:

• planning to identify, obtain, retain and deploy knowledge, skills and knowledge assets • arrangements to qualify and control it • evidence of the knowledge sharing to have been occurring within the organisation and with the ASA

Guidance Documents

TS 10503

© State of NSW through Transport for NSW Page 59 of 65

Page 60: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.7. Stakeholder management This requirement demonstrates engineering management activities and arrangements to establish and maintain the stakeholders involvement for the work within the

scope of authorisation.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM20

An AEO shall have arrangements in place to identify and manage internal and external stakeholders as appropriate to the scale and scope of

engineering services being provided.

Guidance Elaboration

It is expected that AEOs be able to identify relevant internal and external stakeholders, establish appropriate levels of engagement and manage

stakeholder involvement, communication and consultation as suitable for the engineering service being provided.

Guidance Evidence

Evidence of documentation and deployment must be relevant and cover the proposed scope of authorisation.

The impacted assets and the solution for whole of life considerations should be demonstrated.

Typical evidence could be various organisational processes, plans that support stakeholder management, records of relevant activities such as

meetings minutes, communications, stakeholder registers, stakeholder engagement tracking tools and records.

Guidance Documents

TS 10504

© State of NSW through Transport for NSW Page 60 of 65

Page 61: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.8. Resources management This requirement demonstrates engineering management activities and arrangements that ensure that all tangible and non-tangible resources are in place to support

the engineering service provision within the scope of authorisation.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM21

An AEO shall have arrangements in place to ensure the required tangible and non-tangible resources are available as necessary for the provision of

the authorised scope of engineering services.

Guidance Elaboration

There may be a need for special facilities, and resources for the service delivery, solution or product design, implementation, installation or

maintenance. This may include the following:

• tools (for example, computer-aided design system or other specific tools) • methodologies (adequate lifecycles or relevant engineering methodologies) • infrastructure (work site or equipment) • materials • standards

Standards management ensures that AEOs are working to the latest approved versions of engineering standards that are relevant to engineering

services provided.

Human resources requirements are not included here, but elaborated in details Section 7.6.

© State of NSW through Transport for NSW Page 61 of 65

Page 62: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Guidance Evidence

An AEO should demonstrate understanding of what kind of resources are required for the service it provides and demonstrate that those resources

are available when necessary.

AEOs must demonstrate that they have ready access to all relevant engineering standards, that they are notified of changes to those standards, that

they brief their engineering staff on the changes to the standards and perform an impact assessment of the change and determine whether to

comply or seek a concession to the changes reflected in the standard.

Possible evidence includes the following:

• engineering intranet home page with links to standards • links to TfNSW and ASA standards • standards change briefing notes or emails • standards change impact assessments

Guidance Documents

TS 10504

© State of NSW through Transport for NSW Page 62 of 65

Page 63: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.9. Supplier management These requirements demonstrate engineering management activities and arrangements that enable management of acquisitions from internal and external suppliers

as necessary for the scope of authorised services.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

Mandatory Requirement – ENM22

An AEO shall have arrangements in place, appropriate to the scope of services, to manage selection, evaluation and monitoring of internal or

external suppliers and to assure selection and acquisition of required products and services.

Guidance Elaboration

Certain work products or services may be acquired to be used during the delivery of the authorised engineering services. These could be various

sub-systems, intermediate work products, elements of the solution that are used in the final product or service delivery. Suppliers may also be used

by the service provider for provision of some part of the service.

An AEO should be able to demonstrate its approach to the use of acquired products and services in its authorised engineering product creation or

service delivery. This includes demonstrating its relevant acceptance and assurance arrangements and transitioning of the required products into its

own product or service.

Guidance Evidence

An AEO should demonstrate that it has a process for managing suppliers and associated risks including selection, evaluation and monitoring of

supplier performance.

Evidence of process execution covering the scope of authorisation (disciplines and lifecycle phases) as suitable are also required.

Guidance Documents

TS 10504

© State of NSW through Transport for NSW Page 63 of 65

Page 64: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.10. Performance measurement and evaluation These requirements demonstrate engineering management activities and arrangements that support consistent repeatable service or product delivery by providing

objective quantitative information on the organisational processes performance and quality of the product or service.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM23

An AEO shall periodically review key service delivery processes using established measurement processes, methods and defined quantitative

performance criteria.

Guidance Elaboration

This requirement is implemented as suitable for the organisational business needs.

Typically, only a few core processes are managed using quantitative methods. These are selected based on associated risks and impact on

business objectives.

Some ad-hoc improvements are implemented through the special causes of variations identification and corrective actions implementation.

Guidance Evidence

AEOs are expected to demonstrate the following:

• relevance of the selected performance framework to business objectives • rationale behind the adopted measurement baselines • measurement models and methods being used • evidence of process execution and outcome use (collecting, storing and analysing the data) • evidence of organisational process support (availability of competent staff, appropriate tools and methodologies) • evidence of process review and calibration

© State of NSW through Transport for NSW Page 64 of 65

Page 65: AEO Authorisation Requirements · 2019-05-21 · This document is one of a set of standards developed solely and specifically for use on Transport Assets ... AEO authorisation requirements

T MU MD 00009 ST AEO Authorisation Requirements

Version 3.0 Issued date: 08 May 2017

7.11. Continual improvement management These requirements demonstrate engineering management activities and arrangements that ensure sustainable and growing organisational efficiency and

effectiveness through the deployment of measurable improvements.

Mandatory, as applicable or guidance

Requirement, elaboration, evidence or documents

As applicable Requirement – ENM24

An AEO shall have arrangements in place for continual and systematic process improvement based on measured processes performance.

Guidance Elaboration

This requirement is fulfilled based on the outcomes of the ENM23 requirement implementation and execution.

This practice includes the following:

• identifies common causes of variations in process performance using measurement data • identifies opportunity for improvements based on best industry practices • pilot improvements, quantitatively analyse the outcome • deploys improvements, monitor performance and compare with the expected values

Guidance Evidence

There should be evidence of improvement opportunities including the following:

• systematic identification • objective evaluation against business needs and best industry practices • prioritisation using established criteria or process as suitable • There should be evidence of established process of improvements implementation in a controlled manner. • There should be evidence of improvements performance measurement and review.