aemip year 5 quarter 1 (july-sept 2017) progress report
TRANSCRIPT
Winrock International
Agriculture Education and Market Improvement Program
(AEMIP)
AEMIP Year 5 Quarter 1 (July-Sept 2017) Progress Report
Submitted by:
AEMIP
Winrock International
ISAV/F Campus
Faranah, Guinea
October 30th, 2017
AEMIP is funded by USAID Cooperative Agreement No. AID-675-A-13-00003, as an Associate Award under the
Farmer-to-Farmer LWA Cooperative Agreement No. EDH-00-0900003-00.
Contact AEMIP
Andrew Kovarik,
Program Director
ISAV/F Campus
Faranah, Guinea
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | ii
TABLE OF CONTENTS
ACRONYMS .................................................................................................................................. iii
1. EXECUTIVE SUMMARY – QUARTER OVERVIEW ............................................................. 4
Discussion of Planned Activities that are Delayed, Postponed or Cancelled, or Unplanned
Activities that Took Place ..................................................................................................... 5
III. ACCOMPLISHMENTS ......................................................................................................... 5
A. Activities Implemented in Quarter 1 .................................................................................. 5
B. Success Story ......................................................................................................................... 7
A. Deliverables & Reports Prepared ......................................................................................... 9
III. PROGRAM MANAGEMENT ................................................................................................ 9
C. Key Stakeholder Meetings Held ........................................................................................... 9
D. Program Communications and Public Relations ................................................................ 9
E. Requested Adjustments to Approved Work Plan and PMP ............................................. 9
IV. WORK PLAN FOR NEXT QUARTER .............................................................................. 10
A. Activities Planned ................................................................................................................ 10
B. Volunteer Assignments Planned ........................................................................................ 10
C. Staff and Consultant Technical Assistance Planned ......................................................... 11
V. APPENDICES ......................................................................................................................... 12
Appendix 1: WORK PLAN PROGRESS –STATUS OF PLANNED ACTIVITIES ................ 12
Appendix 2 ................................................................................................................................... 19
Quarter Outputs ......................................................................................................................... 19
Appendix 3 ................................................................................................................................... 22
Y5Q1 Outputs Indicator Update Table ..................................................................................... 22
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | iii
ACRONYMS
AAPR
AET
Association des Animateurs Pisci-rizicoles de Guinée
Agriculture Education and Training
DPD AEMIP Deputy Program Director
F2F USAID’s Farmer to Farmer for Agriculture Education and Training
F2FCD
FEPAF-BG
F2F Country Director
Fédération des Planteurs de la Filière Fruitières de la Baisse Guinée
GAIN
GAS
GPS/GID
Guinean Agriculture Institutions Network
Guinean Agriculture Services
Global Positioning System/Global Information System
ISAV/F Institut Supérieur Agronomique et Vétérinaire de Faranah
JDR
LTTA
John David Rockefeller Grants
Long-Term Technical Assistance
M&E Monitoring and Evaluation
PD AEMIP Program Director
PMP Performance Monitoring Plan
PPP
PUP
SPSS
Public-Private Partnership
Private Utility Platform
Statistical Package for the Social Sciences
STTA Short-Term Technical Assistance
TA Technical Assistance
ToT Training of Trainers
USAID U.S. Agency for International Development
USG United States Government
VTA Volunteer Technical Assistance
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 4
1. EXECUTIVE SUMMARY – QUARTER OVERVIEW
This report is a synthesis of the major activities planned and implemented, and the results achieved
during the period from July-September. Below is a list and short summary of key project activities during
the quarter organized by major program component. A more detailed description of these activities is
available in the accomplishments section of this report.
Activity 1 – Curriculum Strengthening
• In September, AEMIP supported monitoring visits by ISAV/F faculty for internships for 3rd year
students established in the previous quarter with potential employers. AEMIP supported senior
ISAV/F faculty and the Deputy Chief of Party to conduct visits with 21 employers that provided
90 internships to ISAV/F students. Two teams of faculty met with all of the employers to
evaluate the students’ internships, facilitate future partnerships and understand employers’
needs for improvement of coursework and curriculum. Drawing on information gathered
during the field visits, ISAV/F and AEMIP are currently developing a job and internship readiness
training module that will be taught to 4th year students and future interns. Once students
return to ISAV/F in the coming quarter, AEMIP will facilitate a day of presentations whereby
interns will share their work experiences with faculty and student peers. This experience will
broaden student and faculty understanding of activities and actors in the Guinea ag-sector while
preparing subsequent classes for the realities of an internship. The knowledge collected from
both hosts and participants will allow ISAV/F faculty to refine and improve the delivery of
career-readiness training content for future internship cohorts.
Activity 2 – Faculty Strengthening
• In July, Dr. Michael Miller provided a ToT to 12 ISAV/F faculty and students on the use of
GPS/GIS technology for soil and land management. Dr. Miller instructed participants on usage of
software called QGIS. The training focused on online data, navigation points and downloading of
data into QGIS system. Additional training topics included use of Google Earth with QGIS and
use of land mapping databases. ISAV/F faculty participants were selected based on ability to
incorporate trainings into coursework on GPS/GIS.
• In September, Dr. Gonzalo Rojos-Cifuentes conducted a ToT on effective strategies for plant
selection and breeding. The training provided ISAV/F faculty and graduate students with
information on plant breeding and selection for yield, disease resistance, flooding and taste. Dr.
Rojos-Cifuentes also provided information on emerging diseases and common pest issues in rice
and tomato production. He thenled site visits to the ISAV experimental station and rice fields to
diagnose issues in local rice and crop production. On the final day of the training, rice varieties
purchased from the local market were used to demonstrate a sensory panel exercise.
Activity 3 – AEMIP Innovation Grants
• Grant activities during the quarter included submission of two innovation grants to USAID for
approval in July 2017; preselection of three JDR grants; and, participation of grant beneficiary,
Mamadou Tanou, at the Conference for the European Association of Potato Producers where he
presented AEMIP funded research on potato production in Guinea and met with contacts
involved in potato production from around the world.
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 5
Project Management
AEMIP and SMARTE received visits from home office management staff in June and July to support
operations assessments; develop communications materials; and, inspect the new office in Faranah.
During the quarter numerous staff took 1-2 week vacations in August and September.
Discussion of Planned Activities that are Delayed, Postponed or Cancelled, or Unplanned
Activities that Took Place
Below is a list of delayed or cancelled activities during the quarter as per Work Plan assignments.
Activity 3 – AEMIP Innovation and Challenge Grants
3.2 Award and Implementation of Challenge Grants. AEMIP submitted two grants for USAID
approval in July 2017 and is currently waiting on approval.
3.3 Award and Implementation of JDR the 3rd Grant. Three pre-selected grants teams are
currently working to refine their proposals.
III. ACCOMPLISHMENTS
A. Activities Implemented in Quarter 1
(1) ISAV/F Faculty Conduct Monitoring and Partnership Visits with Interns and Employers
(Activity 2)
To follow up on the partnership meetings
conducted between ISAV/F and private sector
employers in the previous quarter, AEMIP worked
with ISAV/F to select and field 90 interns with 21
public and private sector enterprises. Interns were
placed with host institutions intervening in a
diverse set of commodities across value chains
including: fish farming, aviculture, beekeeping,
veterinary services, fruit production, rice
production, irrigation management, market
gardening, construction transport, transformation
and commercialization. The internships provide
professional opportunities related to both hands-
on experience working with clients and future recruitment and employment with firms and institutions.
Major recommendations from partners included the following:
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 6
• Offer more time for practical training for students
especially in the final years of study;
• Strengthen training in rural entrepreneurism,
communication, computer literacy and critical analysis and
creativity.
The majority of hosts reported satisfaction with the internship experience and would host interns again.
(2) ToT on GPS/GIS for Soil and Land Management (Activity 2)
A primary ISAV/F goal is for staff and graduates to lead
development in a modern ag-sector. GIS and GPS, especially
for the purpose of soil mapping, are modern tools that can
allow for more efficient and profitable agricultural management
systems. The assignment conducted by Dr. Mike Miller
supported staff and faculty to improve their ability to use and
train on GIS/GPS to benefit research and better equip students
with skills needed in the job market. Twelve faculty received a
3-week training on QGIS, an open-source software free to
install on any computer. All participants were trained to collect
point and line data, navigate to a point, download the data for
incorporation in QGIS, and use aerial photography in QGIS to
create digital data for relevant land and soil mapping projects.
Several participants displayed advanced ability to operate QGIS
and the trainer noted that they could provide training to others.
Dr. Miller identified the lack of quality aerial photography as an
issue and showed participants how to view Google Earth
imagery in QGIS as a partial solution since google earth data can
then be digitized directly from the image using QGIS’s digitizing
tools.
In order to support ISAV/F faculty and staff to provide client
based services, the trainer provided guidelines for estimating costs of mapping projects, including the
importance of a pilot project to help uncover unanticipated issues and estimate labor costs.
(3) ToT on Plant Selection and Breeding (Activity 2)
While ISAV/F does not currently have the necessary infrastructure for plant breeding, this training provided
10 trainees with resources to support farmers in Faranah to improve local plant varieties by adopting
management practices to select the best-adapted plants from their fields. Under this training, Dr. Rojas-
Cifuentes presented information regarding plant breeding and selection for yield, diseases, flood tolerance,
quality, and taste while providing hands on practical experience on techniques to select the best individuals,
and remove rogue off-type, volunteers, and diseased plants, susceptible to flood and lodging.
Trainees were taught to determine the best area of the field for seed to cover the grower needs perennially
and use of the “seed production field” (SPF). Dr. Rojas-Cifuentes taught maintenance and management
techniques for the SPF, allowing farmers to select plants, harvest seeds and replant superior seed from
The AEMIP Deputy Director Visiting
Interns at PBAP (Planteurs of
Banana, Pineapple and Papaya)
Mike Miller with participants during
the training.
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 7
selected plants each year. All participants from this training are now capable of training local farmers on
the practice. The trainees also conducted a sensory panel to evaluate 8 different varieties of rice based
upon color, smell and taste. Sensory panels are important for evaluating the end results of a plant selection
or breeding process.
(4) Grants Evaluation and Implementation (Activity 3)
Mr. Mamadou Tanou Diallo traveled to Paris in
July to present his research on the combined
effects of triple 17 fertilizer and compost for
potato production in Pita at the 20th Conference
for the European Association of Potato Research.
Although a significant producer of potato in west
Africa, this was the first time Guinea has sent a
representative to the conference. The research
theme was placed within climate smart
agriculture actions at the conference due to the
combination of organic and mineral fertilization.
The conference provided Mr. Diallo, who is a
dedicated specialist in potato production, with
numerous contacts in the sector from around
the world. The up to date information and
contacts provided Mr. Diallo with potential sources for solutions to problems such as phytophthora that
has menaced the Guinea potato sector over two consecutive years.
A second grantee, Professor Abdoulaye Barry prepared travel for his attendance and presentation grants
on interaction of manure and potash fertilizer on water stress in rice at the International Symposium for the
Water and Climate Society 2017: Antropogenic Impacts of Climate Change on Water Resources. The
symposium takes place in Hammamet, Tunisia in October 2017.
AEMIP also evaluated proposals under two rounds of innovation grants funding. Team proposals were
rigorously reviewed in terms of market demand, impact economic and viability. All teams wishing to
continue the application process were required to provide an impact analysis showing profitability across
various actors within the value chain. AEMIP selected two proposals on market facilitation of datura
senegalensis and production of livestock feed pellets and submitted finalized Fixed Amount Awards and
approval and concurrence memos to USAID in July.
B. Success Story
The 2015 Analysis of the Dynamics of the Formal Sector Employment Market in Guinean Agriculture
provided several recommendations to improve formal sector employment by meeting employer needs. In
terms of training one of the major remarks was the need for students to enhance their understanding
and mastery of the agricultural technical packages. The report stated that in many cases the private
sector was the best place for students to be exposed to modern agricultural technical packages.
Promotion of internships was presented as a solution to improve student’s practical and technical
Mr. Tanou Dialo with a conference organizer
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 8
knowledge, create contact with potential employers, and improve ISAV/F formal relationship with
employers through onsite faculty visits and consultations.
After developing relationships with employers by hosting a
career fair for 4th year students at ISAV/F in June 2016,
starting in February 2017, AEMIP and ISAV/F begin to
contact a list of over 50 employers concerning their
interests in taking on second and third year students as
interns during the break from school. AEMIP proposed
ISAV/F faculty as intern advisors and establishment of
formal partnerships with ISAV/F for interns and
collaboration. A total of 38 structures expressed interest
taking on interns and were invited to ISAV/F on May 19th
and 20th, 2017 to; discuss the opportunities for ISAV /
Faranah student internships; and, provide an opportunity
for the structures present to discuss collaboration and
formal partnership with ISAV/F. By July, 2017 a total of 21
institutions had agreed to provide internships for 90
students moving into their fourth year at ISAV/F. Internship
started directly after the end of the school year in late June.
In September AEMIP supported ISAV/F’s intern advisor’s visits to all 21 host institutions to support the
students intern reports, gain a better understanding of employer needs and realities and modify
curriculum and training based upon work force needs.
ISAV/F students as whole were very pleased with the
opportunity to participate in the internships and build their
professional experience. When called to discuss her initial experience working at AAPR-GF in
Nzerekore, Ivette KANHARA expressed satisfaction that she learned valuable skills including calculation
of feeding and correct fish density based upon pond size as well techniques to share this information with
farmer clients. She felt the experience could allow her to access several career paths including: self-
employed fish farming activities; providing extension and outreach to other interested in starting fish
farming; and, building upon her experience working with livestock within a broad skill set to work as a
quality control specialist of animal products.
The ISAV/G general direction was satisfied with the initiatives role in creating new partnerships,
strengthening their ability to provide advisory and employment services to students, and the possibility of
strengthening market based curriculum by intern advisors. The ISAV/F Director General Professor Sara,
Bailo DIALLO has also stated that given discussion with employers, he believes the internships will lead
to at least 40 new jobs.
Alhassane Diane, President of the Federation of Fruit Planters of Lower Guinea (FEPAF-BG) stated that
the Federation received students that showcased exemplary behavior. FEPAF appreciates the training
they have received from ISAV/F and welcomes students from ISAV/F with open arms for future
internships.
Three interns hosted by FEPAF-BG
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 9
AEMIP will work with SMARTE and IASV/F to prepare an open house presentation for students to share
their internship experience with other students and faculty in November while also pursuing possibilities
to introduce high performing interns directly into the SMARTE AVENIR program with corresponding
internship hosts upon graduation.
A. Deliverables & Reports Prepared
During the reporting period, the following deliverables and reports were submitted to USAID:
• Quarterly Report for the period of April-June, 2017 and Annual Report for the period of July
2016- June 2017.
III. PROGRAM MANAGEMENT
Volunteer Assignments Completed
Two volunteer assignments were completed during the quarter with the support oftwo volunteers.
A. Dr. Mike Miller provided on the use of GIS/GPS for modern land mapping; and,
B. Dr. Gonzalo Rojas-Cifuentes provided a ToT on Plant Selection and breeding.
International Travel
International travel during the quarter consisted of 2 trips. A list of trips by assignment and
volunteers/consultants involved can be found below:
• Two volunteer trips as described above;
C. Key Stakeholder Meetings Held
No key stakeholder meetings were engaged during the quarter.
D. Program Communications and Public Relations
During the quarter the AEMIP DCOP, COP and ISAV/F General Direction worked with a local
cinematographer to produce a 10-minute advertisement on ISAV/F for the upcoming school year. The
film was completed and aired on RTG and Espace Television. The film featured students and ISAV/F
facilities to encourage students graduating from the high school to enroll at ISAV/F
E. Requested Adjustments to Approved Work Plan and PMP
Several planned activities were delayed to the following quarter. See section on discussions of planned
activities that are delayed, postponed or cancelled, or unplanned activities that took place.
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 10
IV. WORK PLAN FOR NEXT QUARTER
A. Activities Planned
Activities Planned Dates
Foundational Activities
Support ISAV/F’s Self-Assessment of the Institutional Development Plan and prepare
plan for 2018-2022
September – November
2017
Prepare the programmatic Exit Plan with ISAV/F
September – November
2017
Activity 1 Curriculum Strengthening
Launch delivery of the four new courses developed with AEMIP support
September – October
2017
Development of Value Chain Analysis curricula
Engaging the ISAV/F Directorate and Rural Economics department in integrating the
curriculum and supporting selected faculty in integrating value chain analysis curriculum
in existing courses and new courses
November - December
2017
Pursue partnership with private sector computer training company November – December
2017
Activity 3 AEMIP Innovations Grants Program
Implementation of Conference Presentation Sponsorship (phase 3) Complete in October
2017
Implement Round 1 and 2 Fixed Obligation Grants
October – Dec 2017
Implement JDR the 3rd Grant
September – December
2017
Activity 4 Management Strengthening
Facilitate a system for information sharing between ISAV/F and the National
Meteorological Agency
November 2017
Facilitate GAIN meeting to catalyze the GAIN PMU to develop an internship database
of major agriculture sector employers, as well as to identify AET curricular
supplements to support employer needs.
Oct-Nov 2017
ToT for ISAV/F Gender Committee to Mainstream Gender in ISAV/F Policies Nov 2017
B. Volunteer Assignments Planned
Below is volunteer travel scheduled for the upcoming quarter:
Volunteer Anticipated Dates Assignment Description
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 11
Suzanne Ondrus November 2017 ToT Institutional gender mainstreaming
C. Staff and Consultant Technical Assistance Planned
Below is international travel scheduled for the upcoming quarter:
Technical Assistance
Provider
Anticipated Dates Trip Purpose
Mr. Peter Saling October 2017 Visit for Meetings with USAID,
Mr. Robert Foster Dec, 2017 Solar Pump Installation
TBD November-Dec, 2017 Integration of Value Chain Curriculum into
ISASV/F Curriculum
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 12
V. APPENDICES
Appendix 1: WORK PLAN PROGRESS –STATUS OF PLANNED ACTIVITIES
In general, the implementation of activities has followed the planning outlined in the approved Year 4 Work Plan, and the implementation schedule
is noted below with the status of programmed activities indicated.
Status of Planned Activities - AEMIP Year 5 Timeline
Table 4. AEMIP Year 5 Timeline
Acronyms
AA: AEMIP Admin Assistant
DG: ISAV/F Director General
DPD: Deputy Program Director
F2F: F2F Office in Conakry
FM: AEMIP Financial Manager
GTA: AEMIP Grants & TA Manager
HQPM: Headquarters Program Manager
IT: AEMIP IT Specialist
LC: Local Consultant
M&E: AEMIP M&E Specialist
PD: AEMIP Program Director
PMU: GAIN Project Management Unit
RMS: Recruitment & Mobilization Specialist
STTA: short-term technical assistance
STVTA: short-term volunteer
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Project Management, Monitoring and Evaluation, and Communications and Outreach
Complete staff annual
performance reviews
PD
Complete
d
Recruit ISAV/F student interns
for Cyber Café management and
Technical Assistance
PD, DPD, IT
Completed
Prepare quarterly progress
reports
PD, M&E, HQPM Completed
Support volunteers to post on
the Winrock Volunteer Facebook
page and Winrock Volunteer
Blog
RMS
Develop ISAV/F Promotional
Advertisement
PD, DPD, IT, LC, ISAV/F
DG Completed
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 13
Acronyms
AA: AEMIP Admin Assistant
DG: ISAV/F Director General
DPD: Deputy Program Director
F2F: F2F Office in Conakry
FM: AEMIP Financial Manager
GTA: AEMIP Grants & TA Manager
HQPM: Headquarters Program Manager
IT: AEMIP IT Specialist
LC: Local Consultant
M&E: AEMIP M&E Specialist
PD: AEMIP Program Director
PMU: GAIN Project Management Unit
RMS: Recruitment & Mobilization Specialist
STTA: short-term technical assistance
STVTA: short-term volunteer
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Support management and
updating of ISAV/F’s website and
Facebook page
PD, DPD, IT, ISAV/F DG
Ongoing
Hold an event with key
stakeholders to present the
results of the Internship
Program
PD, DPD, GTA, ISAV/F
DG
Update project inventory,
prepare Asset Dispensation
Plan, and submit to USAID
approval
PD, AA, IT
Prepare the Project Income
Spending Plan and submit to
USAID for approval
HQPM, PD, FM
Prepare the Operational Close-
Out Plan and submit to USAID
for approval
HQPM, PD
Foundational Activities
Support ISAV/F’s Self-
Assessment of the Institutional
Development Plan and prepare
plan for 2018-2022
PD, DPD, ISAV/F DG
Prepare the programmatic Exit
Plan with ISAV/F
PD, DPD, ISAV/F DG
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 14
Acronyms
AA: AEMIP Admin Assistant
DG: ISAV/F Director General
DPD: Deputy Program Director
F2F: F2F Office in Conakry
FM: AEMIP Financial Manager
GTA: AEMIP Grants & TA Manager
HQPM: Headquarters Program Manager
IT: AEMIP IT Specialist
LC: Local Consultant
M&E: AEMIP M&E Specialist
PD: AEMIP Program Director
PMU: GAIN Project Management Unit
RMS: Recruitment & Mobilization Specialist
STTA: short-term technical assistance
STVTA: short-term volunteer
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Conduct the AEMIP Endline
Evaluation
STVTA, M&E, PD, RMS
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Activity 1 – Curriculum Strengthening
1.1 Development and Expansion of New and Existing ISAV/F Infrastructure
Complete infrastructure
procurement support
PD, FM, ISAV/F DG
Ongoing support for the
development of ISAV/F’s library
collection
PD, IT, ISAV/F DG
Ongoing
1.2 Curriculum Development for Master’s Program
Launch delivery of the four new
courses developed with AEMIP
support
DPD, ISAV/F DG
Identify challenges and issues
and update the curricula
DPD, ISAV/F DG
1.3 Support Formal Partnerships in Internship Program
Implement 65-70 internships DPD, ISAV/F faculty
internship advisors
Complete
d
Work with employers and
ISAV/F faculty internship
advisors to evaluation individual
internships
DPD, ISAV/F faculty
internship advisors Completed
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 15
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Support ISAV/F faculty
internship advisors to develop
short-course on workforce
readiness
DPD, ISAV/F faculty
internship advisors
Ongoing – Outline
completed
1.4 Integration of Value Chain ISAV/F Curricula
Arrange exchanges between
ISAV/F and University of Thies
PD, DPD, ISAV/F DG Underway
Support faculty to integrate
value chain content into ISAV/F
curricula
PD, DPD, ISAV/F DG
1.5 Computer Literacy Training
Pursue partnership with private
sector computer training
company
IT, PD, DPD, ISAV/F DG
Underway
1.6 Weather Forecast and Analysis
Support incorporation of
meteorological data into ISAV/F
training
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Activity 2 – Faculty Strengthening
2.1 Design and delivery of TOTs
Deliver the TOT Water Quality
in Irrigation
STVTA, PD, DPD, GTA,
RMS, ISAV/F DG Completed
Deliver the TOT on Usage of
Modern Mapping Equipment
STVTA, PD, DPD, GTA,
RMS, ISAV/F DG Completed
Deliver TOT on Agriculture
Statistics: Experimental Research
STVTA, PD, DPD, GTA,
RMS, ISAV/F DG Completed
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 16
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Deliver the TOT course on Plant
Breeding and Selection
STVTA, PD, DPD, GTA,
RMS, ISAV/F DG Completed
Deliver TOT on Soil Testing and
Data Analysis Using HACH kits
STVTA, PD, DPD, GTA,
RMS, ISAV/F DG
Activity 3 – AEMIP Innovation and Challenge Grants
3.1 Award and Implementation of AEMIP Conference Grants
Implement grants HQPM, PD, DPD, GTA,
FM, M&E
One completed second
underway
3.2 Award and Implementation of Challenge Grants
Implement Challenge Grants HQPM, PD, DPD, GTA,
FM, M&E Awaiting USAID approval
3.3 Award and Implementation of JDR the 3rd Grant
Evaluate applications for grant,
prepare request for USAID
approval
HQPM, PD, DPD, GTA,
FM, M&E Grants Evaluated
Implement JDR the 3rd Grant HQPM, PD, DPD, GTA,
FM, M&E
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Activity 4 – ISAV/F Management Strengthening
4.1 Development of the GAIN
Facilitate GAIN meeting to
catalyze the GAIN PMU to
develop an internship database of
major agriculture sector
employers, as well as to identify
AET curricular supplements to
support employer needs.
PD, DPD, F2F, GAIN
PMU
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 17
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Host presentation of Endline
Evaluation for GAIN and other
key stakeholders
PD, DPD, F2F, GAIN
PMU, STVTA
Facilitate GAIN meeting on
planning to ensure the
sustainability of GAIN after
AEMIP support concludes
PD, DPD, F2F, GAIN
PMU
Provide budget support for GAIN
members to attend FTF training
on internship programs in Kobe
PD, FM, GAIN PMU
Deliver F2F training to GAIN
members on the Systematic
Process for Continuous
Assessment and Improvement of
Curricula.
PD, DPD, F2F, GAIN
PMU
Deliver AEMIP training to GAIN
members on working with
USAID
STVTA, PD, DPD, GTA,
RMS, GAIN PMU
4.2 Link Weather Station to National Meteorological Agency
Facilitate a system of information
sharing between ISAV/F and the
national meteorological agency
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
4.3 Strengthen ISAV/F management approaches for gender equity
Support the ISAV/F Gender
Committee to Mainstream
Gender in ISAV/F Policies
STVTA, DPD, GTA, RMS,
ISAV/F DG
4.4 Strengthening ISAV/F Resource Mobilization
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 18
Task & Activity Partner/Staff
Responsible
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Support ISAV/F to commercialize
services and products from of the
ISAV/F agriculture experimental
research station
PD, FM, ISAV/F DG
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 19
Appendix 2
Quarter Outputs
AEMIP Indicators
Results
Framework
Level
Indicator
#
Indicator Indicator
Type
Quarter Results
Results Level (baseline and final stage measurements)
Goal 1 Increase in the number of ISAV/F
graduates formally employed in
agriculture or in an agricultural-related
sector
Custom No data to report
2 Increase in ISAV/F faculty engaged in
formal collaborative partnerships with
“client” stakeholders
Custom No data to report
Goal
(GCC
Pilot Q1)
3 Stakeholders (AET faculty and students)
with increased capacity to adapt to the
impacts of climate variability and change
as a result of USG assistance
GCC
4.8.2-29
78 (35 female)
Adoption of improved rice
production techniques in the
communities odf
Heremakono, Belleya and
Kamara
Goal
(GCC
Pilot Q2)
4 ISAV/F developed and disseminated
“farming system strategies” for climate
smart agriculture established
Custom No data to report
IR 1 5 Increase in ISAV/F-led applied research
projects in market-driven, gender-
transformative or climate-smart
technologies
Custom No data to report
IR 2 6 AET institutional stakeholders involved in
formal outreach efforts
Custom No data to report
IR 3 7 Increase in women students entering
classes at ISAV/F
Custom 21%
Outcome Level (annual measurements)
Outcome
2
8 ISAV/F has structured and costed annual
research agendas
Custom Yes
Outcome
3
9 ISAV/F has an operational strategy on the
topics of gender equity and resource
mobilization
Custom Yes
An institutional gender
strategy and Action plan
have been developed
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 20
Outcome
3
10 Public-private partnerships explored
and/or formed as a result of USG (FTF)
assistance
FTF
4.5.2-12
1
MOU with Federation of
Farmer’s Organizations of
lower Guinea
Output Level (quarterly measurements)
Activity 1 11 New technical content modules or
experiential learning tools and methods in
the ISAV/F curriculum developed and
delivered
Custom No Data to Report
Activity 1 12 Faculty and students using new
infrastructure and material resources
secured with support of AEMIP
Custom 17 (4 women)
Use of GPS/GIS and Cyber
Café
Activity 2 13 Trainings delivered for ISAV/F faculty on
technical content or pedagogy that
directly leads to new faculty-developed
curricular elements
Custom No data to report
Activity 3 14 AEMIP Innovation Grants implemented Custom No data to report
Activity 3 15 Climate adaptation technologies and
techniques developed/adapted, tested
and/or adopted
Custom 1 technology improved rice
production practice
Activity 3 16 Stakeholders implementing risk-reducing
practices/actions to improve resilience to
climate change as a result of USG
assistance
FTF
4.5.2-34
78 (35 women)
Adopted improved rice
production techniques
Activity 3 17 Farmers and others who have applied new
technologies and management practices as
a result of USG assistance
FTF
4.5.2-5
78 (35 women)
Adopted improved rice
production techniques
Activity 4 18 AET faculty trained or coached in
institutional development
Custom 8 faculty (0 women)
Activity 4 19 Innovative mechanisms, approaches,
platforms and techniques established and
utilized for outreach activities to network
with external AET stakeholders, partners,
alumni and clients
Custom No data to report
Cross-
cutting
20 People receiving training in global climate
change as a result of USG assistance
GCC
4.8.2-6
No data to report
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 21
Cross-
cutting
21 Individuals who have received USG
supported short-term agricultural sector
productivity/food security
FTF
4.5.2-6
157 (31 women)
ToTs, summary presentation
of potato conferenceWere
trained under various
research grants
Cross-
cutting
22 Individuals who have received USG
supported long-term agricultural sector
productivity/food security training
FTF
4.5.2-7
No data to report
Outcome
3
23 Project Management Unit has been
created by ISAV/F to provide management
capacity for resource mobilization within
GAIN
Custom -
Outcome
Yes
Activity 2
24 AET Faculty trained on USAID financial
and administrative regulations as a result
of USG Assistance
Custom -
Output
No Data to Report
Cross
Cutting
25 Number of members of producer
organizations and community based
organizations receiving USG assistance(S)
FTF 4.5.2-
27
20 (10 female)
Improved rice production
techniques
Cross
Cutting
26 AET Faculty and students participating in
internships due to support from AEMIP
Custom -
Outcome
11 (1 Female)
10 Intern advisors and intern
(other interns will be added
in the next quarter once final
reports are received).
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 22
Appendix 3
Y5Q1 Outputs Indicator Update Table
Results Framew
ork
Level
Indicator #
Indicator
Indicator T
ype
Unit of M
easure
Disaggreg
ation
Baseline Year
Baseline Value
FY 2014 Target
FY 2014 Actual
FY 2015 Target
FY 2015 Actual
FY 2016 Target
FY 2016 Actual
FY 2017 Target
FY 2017 Actual
FY 2018 Target
FY 2018 Actual
LOP Target
LOP Actua
l
LOP Cum
ulative/Not
Com
ulative
Goal 1Increase in the number of ISAVF graduates formally employed in agriculture
or in an agricultural-related sector
Custom,
Result%
M/F; ISAVF
Department2013
34%
(25% F)n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a
25% (to
59% all,
50%F)
0 n/a
Goal 2Increase in ISAVF faculty engaged in formal collaborative partnerships with
"client" stakeholders
Custom,
Result% M/F; MD/GT/CS 2014 5.41% n/a n/a n/a n/a n/a 17.90% n/a n/a n/a n/a 40% 17.90% n/a
Goal (GCC
Pilot Q1)3
[AET faculty and students] stakeholders with increased capacity to adapt
to the impacts of climate variability and change as a result of USG
Assistance
GCC 4.8.2-
29# M/F 2014 0 n/a n/a n/a 47 n/a 0 n/a 469 n/a 0 588 516 n/a
Goal (GCC
Pilot Q2)4
ISAVF-developed and disseminated "farming system strategies" for climate
smart agriculture established
Custom,
Result# n/a 2014 0 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a 5 0 n/a
IR1 5Increase in ISAVF-led applied research projects in market-driven, gender-
transformative or climate-smart technologies
Custom,
Result% M/F; MD/GT/CS 2014 35.14% n/a n/a n/a n/a n/a 19.20% n/a n/a n/a n/a 40% 0.192 n/a
IR2 6 AET institutional stakeholders involved in formal outreach effortsCustom,
Result#
Efforts targeting
women2014 0 n/a n/a n/a 3 n/a 5 n/a 0 n/a 0 12 8 n/a
IR2 7 Increase in women students entering classes at ISAVFCustom,
Result%
Academic
discipline2013 21% n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a
15% (to
36%)0.21 n/a
Outcome 2 8 ISAVF has structured and costed annual research agendas. Custom,
Outcomey/n n/a 2013 n n n y n y n y n y n y n n/a
Outcome 3 9ISAVF has an operational strategy on the topics of gender equity and
resource mobilization
Custom,
Outcomey/n n/a 2013 n n n y n y n y n y n y n n/a
Outcome 3 10Public-private partnerships explored and/or formed as a result of USG (FTF)
assistance
FTF 4.5.2-
12# n/a 2013 0 2 0 5 4 5 17 5 23 5 0 22 44 C
Results level (baseline and final stage measurements)
Outcome level (annual measurements)
AEMIP Quarterly Progress Report (July – Sep 2017)
Winrock International P a g e | 23
Results Framew
ork
Level
Indicator #
Indicator
Indicator T
ype
Unit of M
easure
Disaggreg
ation
Baseline Year
Baseline Value
FY 2014 Target
FY 2014 Actual
FY 2015 Target
FY 2015 Actual
FY 2016 Target
FY 2016 Actual
FY 2017 Target
FY 2017 Actual
FY 2018Target
FY 2018 Actual
LOP Target
LOP Actua
l
LOP Cum
ulative/Not
Com
ulative
Activity 1 11New technical content modules or experiential learning tools and methods
in the ISAVF curriculum developed and delivered
Custom,
Output# MD/GT/CS/EL 2013 0 4 15 8 15 8 22 8 5 10 0 38 57 C
Activity 1 12Faculty and students using new infrastructure and material resources
secured with support of AEMIP
Custom,
Output#
M/F; Resource
used2013 0 400 747 750 475 1000 1038 1250 2132 500 0 3900 4392 NC
Activity 2 13Trainings delivered for ISAVF faculty on technical content or pedagogy that
directly leads to new faculty-developed curricular elements
Custom,
Output# MD/GT/CS/EL 2013 0 4 1 7 1 7 6 7 4 5 0 30 12 C
Activity 3 14 AEMIP Innovation Grants implementedCustom,
Output#
MD/GT/CS; Type
of Grant2013 0 0 0 25 9 25 27 3 8 15 0 68 44 C
Activity 3 15Climate adaption technologies and techniques developed/adapted, tested
and/or adopted
Custom,
Output# n/a 2013 0 0 1 15 17 15 13 10 15 10 0 50 46 C
Activity 3 16Stakeholders implementing risk-reducing practices/actions to improve
resilience to climate change as a result of USG assistance
FTF 4.5.2-
34# n/a 2013 0 0 0 30 0 475 510 475 455 150 0 1130 965 C
Activity 3 17Farmers and others who have applied new technologies and management
practices as a result of USG assistance
FTF 4.5.2-
5 # M/F 2013 0 0 0 32 10 150 290 150 271 150 0 482 571 C
Activity 4 18 AET faculty trained or coached in institutional development topics Custom,
Output#
M/F; AET
institution;
functional roles
2013 0 30 55 90 466 90 330 30 37 90 0 330 888 C
Activity 4 19
Innovative mechanisms, approaches, platforms and techniques established
and utilized for outreach activities to network with external AET
stakeholders, partners, alumni and clients
Custom,
Output# n/a 2013 0 2 2 20 21 20 9 10 1 15 0 67 33 C
Cross-cutting 20People receiving training in global climate change as a result of USG
assistance
GCC
4.8.2-6 # M/F 2013 0 60 39 950 6208 950 5602 0 274 0 0 1960 12123 C
Output level (quarterly measurements)
AEMIP Quarterly Progress Report (April - June 2015)
Winrock International P a g e | 24
Cross-cutting 21Individuals who have received USG supported short-term agricultural sector
productivity/food security training
FTF
4.5.2-7# M/F 2013 0 65 0 300 253 300 560 100 157 200 0 965 970 C
Cross-cutting 22Individuals who have received USG supported long-term agricultural sector
productivity/food security training
FTF
4.5.2-7# M/F 2013 0 5 0 300 170 1500 98 200 2670 200 0 2205 2938 C
Outcome 323
Project Management Unit has been created by ISAV/F to provide
management capacity for resource mobilization within GAIN (custom,
outcome-level)
Custom -
Outcomey/n n/a 2016 no n/a n/a n/a n/a No oui No 0 No 0 Yes Y NC
Activity 2
24AET Faculty trained on USAID financial and administrative regulations as a
result of USG Assistance (custom, output-level)
Custom -
Output#
Sex; AET
institution;
functional roles of
staff
2016 n/a n/a n/a n/a n/a n/a 0 15 0 45 0 60 0 C
Cross Cutting
25Number of members of producer organizations and community based
organizations receiving USG assistance(S)(Cross Cutting, Activities 2, 3
and 4)
FTF 4.5.2-
27
#
Sex. type of
producer
organization (i.e.
potato, cocoa, oil
palm, rice,
vegetables, etc)
2016 n/a n/a n/a n/a n/a n/a n/a 250 20 250 0 500 0 C
Cross Cutting
26
AET Faculty and students participating in internships due to support from
AEMIP
Custom -
Outcome#
Sex of Intern, Sex
of Advisor,
Department of
Intern and
Department of
Advisor
2016 n/a n/a n/a n/a n/a n/a 10 15 11 35 0 50 21 C