aemip year 5 quarter 1 (july-sept 2017) progress report

25
Winrock International Agriculture Education and Market Improvement Program (AEMIP) AEMIP Year 5 Quarter 1 (July-Sept 2017) Progress Report Submitted by: AEMIP Winrock International ISAV/F Campus Faranah, Guinea October 30th, 2017 AEMIP is funded by USAID Cooperative Agreement No. AID-675-A-13-00003, as an Associate Award under the Farmer-to-Farmer LWA Cooperative Agreement No. EDH-00-0900003-00. Contact AEMIP Andrew Kovarik, Program Director ISAV/F Campus Faranah, Guinea

Upload: others

Post on 27-Oct-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Winrock International

Agriculture Education and Market Improvement Program

(AEMIP)

AEMIP Year 5 Quarter 1 (July-Sept 2017) Progress Report

Submitted by:

AEMIP

Winrock International

ISAV/F Campus

Faranah, Guinea

October 30th, 2017

AEMIP is funded by USAID Cooperative Agreement No. AID-675-A-13-00003, as an Associate Award under the

Farmer-to-Farmer LWA Cooperative Agreement No. EDH-00-0900003-00.

Contact AEMIP

Andrew Kovarik,

Program Director

ISAV/F Campus

Faranah, Guinea

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | ii

TABLE OF CONTENTS

ACRONYMS .................................................................................................................................. iii

1. EXECUTIVE SUMMARY – QUARTER OVERVIEW ............................................................. 4

Discussion of Planned Activities that are Delayed, Postponed or Cancelled, or Unplanned

Activities that Took Place ..................................................................................................... 5

III. ACCOMPLISHMENTS ......................................................................................................... 5

A. Activities Implemented in Quarter 1 .................................................................................. 5

B. Success Story ......................................................................................................................... 7

A. Deliverables & Reports Prepared ......................................................................................... 9

III. PROGRAM MANAGEMENT ................................................................................................ 9

C. Key Stakeholder Meetings Held ........................................................................................... 9

D. Program Communications and Public Relations ................................................................ 9

E. Requested Adjustments to Approved Work Plan and PMP ............................................. 9

IV. WORK PLAN FOR NEXT QUARTER .............................................................................. 10

A. Activities Planned ................................................................................................................ 10

B. Volunteer Assignments Planned ........................................................................................ 10

C. Staff and Consultant Technical Assistance Planned ......................................................... 11

V. APPENDICES ......................................................................................................................... 12

Appendix 1: WORK PLAN PROGRESS –STATUS OF PLANNED ACTIVITIES ................ 12

Appendix 2 ................................................................................................................................... 19

Quarter Outputs ......................................................................................................................... 19

Appendix 3 ................................................................................................................................... 22

Y5Q1 Outputs Indicator Update Table ..................................................................................... 22

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | iii

ACRONYMS

AAPR

AET

Association des Animateurs Pisci-rizicoles de Guinée

Agriculture Education and Training

DPD AEMIP Deputy Program Director

F2F USAID’s Farmer to Farmer for Agriculture Education and Training

F2FCD

FEPAF-BG

F2F Country Director

Fédération des Planteurs de la Filière Fruitières de la Baisse Guinée

GAIN

GAS

GPS/GID

Guinean Agriculture Institutions Network

Guinean Agriculture Services

Global Positioning System/Global Information System

ISAV/F Institut Supérieur Agronomique et Vétérinaire de Faranah

JDR

LTTA

John David Rockefeller Grants

Long-Term Technical Assistance

M&E Monitoring and Evaluation

PD AEMIP Program Director

PMP Performance Monitoring Plan

PPP

PUP

SPSS

Public-Private Partnership

Private Utility Platform

Statistical Package for the Social Sciences

STTA Short-Term Technical Assistance

TA Technical Assistance

ToT Training of Trainers

USAID U.S. Agency for International Development

USG United States Government

VTA Volunteer Technical Assistance

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 4

1. EXECUTIVE SUMMARY – QUARTER OVERVIEW

This report is a synthesis of the major activities planned and implemented, and the results achieved

during the period from July-September. Below is a list and short summary of key project activities during

the quarter organized by major program component. A more detailed description of these activities is

available in the accomplishments section of this report.

Activity 1 – Curriculum Strengthening

• In September, AEMIP supported monitoring visits by ISAV/F faculty for internships for 3rd year

students established in the previous quarter with potential employers. AEMIP supported senior

ISAV/F faculty and the Deputy Chief of Party to conduct visits with 21 employers that provided

90 internships to ISAV/F students. Two teams of faculty met with all of the employers to

evaluate the students’ internships, facilitate future partnerships and understand employers’

needs for improvement of coursework and curriculum. Drawing on information gathered

during the field visits, ISAV/F and AEMIP are currently developing a job and internship readiness

training module that will be taught to 4th year students and future interns. Once students

return to ISAV/F in the coming quarter, AEMIP will facilitate a day of presentations whereby

interns will share their work experiences with faculty and student peers. This experience will

broaden student and faculty understanding of activities and actors in the Guinea ag-sector while

preparing subsequent classes for the realities of an internship. The knowledge collected from

both hosts and participants will allow ISAV/F faculty to refine and improve the delivery of

career-readiness training content for future internship cohorts.

Activity 2 – Faculty Strengthening

• In July, Dr. Michael Miller provided a ToT to 12 ISAV/F faculty and students on the use of

GPS/GIS technology for soil and land management. Dr. Miller instructed participants on usage of

software called QGIS. The training focused on online data, navigation points and downloading of

data into QGIS system. Additional training topics included use of Google Earth with QGIS and

use of land mapping databases. ISAV/F faculty participants were selected based on ability to

incorporate trainings into coursework on GPS/GIS.

• In September, Dr. Gonzalo Rojos-Cifuentes conducted a ToT on effective strategies for plant

selection and breeding. The training provided ISAV/F faculty and graduate students with

information on plant breeding and selection for yield, disease resistance, flooding and taste. Dr.

Rojos-Cifuentes also provided information on emerging diseases and common pest issues in rice

and tomato production. He thenled site visits to the ISAV experimental station and rice fields to

diagnose issues in local rice and crop production. On the final day of the training, rice varieties

purchased from the local market were used to demonstrate a sensory panel exercise.

Activity 3 – AEMIP Innovation Grants

• Grant activities during the quarter included submission of two innovation grants to USAID for

approval in July 2017; preselection of three JDR grants; and, participation of grant beneficiary,

Mamadou Tanou, at the Conference for the European Association of Potato Producers where he

presented AEMIP funded research on potato production in Guinea and met with contacts

involved in potato production from around the world.

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 5

Project Management

AEMIP and SMARTE received visits from home office management staff in June and July to support

operations assessments; develop communications materials; and, inspect the new office in Faranah.

During the quarter numerous staff took 1-2 week vacations in August and September.

Discussion of Planned Activities that are Delayed, Postponed or Cancelled, or Unplanned

Activities that Took Place

Below is a list of delayed or cancelled activities during the quarter as per Work Plan assignments.

Activity 3 – AEMIP Innovation and Challenge Grants

3.2 Award and Implementation of Challenge Grants. AEMIP submitted two grants for USAID

approval in July 2017 and is currently waiting on approval.

3.3 Award and Implementation of JDR the 3rd Grant. Three pre-selected grants teams are

currently working to refine their proposals.

III. ACCOMPLISHMENTS

A. Activities Implemented in Quarter 1

(1) ISAV/F Faculty Conduct Monitoring and Partnership Visits with Interns and Employers

(Activity 2)

To follow up on the partnership meetings

conducted between ISAV/F and private sector

employers in the previous quarter, AEMIP worked

with ISAV/F to select and field 90 interns with 21

public and private sector enterprises. Interns were

placed with host institutions intervening in a

diverse set of commodities across value chains

including: fish farming, aviculture, beekeeping,

veterinary services, fruit production, rice

production, irrigation management, market

gardening, construction transport, transformation

and commercialization. The internships provide

professional opportunities related to both hands-

on experience working with clients and future recruitment and employment with firms and institutions.

Major recommendations from partners included the following:

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 6

• Offer more time for practical training for students

especially in the final years of study;

• Strengthen training in rural entrepreneurism,

communication, computer literacy and critical analysis and

creativity.

The majority of hosts reported satisfaction with the internship experience and would host interns again.

(2) ToT on GPS/GIS for Soil and Land Management (Activity 2)

A primary ISAV/F goal is for staff and graduates to lead

development in a modern ag-sector. GIS and GPS, especially

for the purpose of soil mapping, are modern tools that can

allow for more efficient and profitable agricultural management

systems. The assignment conducted by Dr. Mike Miller

supported staff and faculty to improve their ability to use and

train on GIS/GPS to benefit research and better equip students

with skills needed in the job market. Twelve faculty received a

3-week training on QGIS, an open-source software free to

install on any computer. All participants were trained to collect

point and line data, navigate to a point, download the data for

incorporation in QGIS, and use aerial photography in QGIS to

create digital data for relevant land and soil mapping projects.

Several participants displayed advanced ability to operate QGIS

and the trainer noted that they could provide training to others.

Dr. Miller identified the lack of quality aerial photography as an

issue and showed participants how to view Google Earth

imagery in QGIS as a partial solution since google earth data can

then be digitized directly from the image using QGIS’s digitizing

tools.

In order to support ISAV/F faculty and staff to provide client

based services, the trainer provided guidelines for estimating costs of mapping projects, including the

importance of a pilot project to help uncover unanticipated issues and estimate labor costs.

(3) ToT on Plant Selection and Breeding (Activity 2)

While ISAV/F does not currently have the necessary infrastructure for plant breeding, this training provided

10 trainees with resources to support farmers in Faranah to improve local plant varieties by adopting

management practices to select the best-adapted plants from their fields. Under this training, Dr. Rojas-

Cifuentes presented information regarding plant breeding and selection for yield, diseases, flood tolerance,

quality, and taste while providing hands on practical experience on techniques to select the best individuals,

and remove rogue off-type, volunteers, and diseased plants, susceptible to flood and lodging.

Trainees were taught to determine the best area of the field for seed to cover the grower needs perennially

and use of the “seed production field” (SPF). Dr. Rojas-Cifuentes taught maintenance and management

techniques for the SPF, allowing farmers to select plants, harvest seeds and replant superior seed from

The AEMIP Deputy Director Visiting

Interns at PBAP (Planteurs of

Banana, Pineapple and Papaya)

Mike Miller with participants during

the training.

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 7

selected plants each year. All participants from this training are now capable of training local farmers on

the practice. The trainees also conducted a sensory panel to evaluate 8 different varieties of rice based

upon color, smell and taste. Sensory panels are important for evaluating the end results of a plant selection

or breeding process.

(4) Grants Evaluation and Implementation (Activity 3)

Mr. Mamadou Tanou Diallo traveled to Paris in

July to present his research on the combined

effects of triple 17 fertilizer and compost for

potato production in Pita at the 20th Conference

for the European Association of Potato Research.

Although a significant producer of potato in west

Africa, this was the first time Guinea has sent a

representative to the conference. The research

theme was placed within climate smart

agriculture actions at the conference due to the

combination of organic and mineral fertilization.

The conference provided Mr. Diallo, who is a

dedicated specialist in potato production, with

numerous contacts in the sector from around

the world. The up to date information and

contacts provided Mr. Diallo with potential sources for solutions to problems such as phytophthora that

has menaced the Guinea potato sector over two consecutive years.

A second grantee, Professor Abdoulaye Barry prepared travel for his attendance and presentation grants

on interaction of manure and potash fertilizer on water stress in rice at the International Symposium for the

Water and Climate Society 2017: Antropogenic Impacts of Climate Change on Water Resources. The

symposium takes place in Hammamet, Tunisia in October 2017.

AEMIP also evaluated proposals under two rounds of innovation grants funding. Team proposals were

rigorously reviewed in terms of market demand, impact economic and viability. All teams wishing to

continue the application process were required to provide an impact analysis showing profitability across

various actors within the value chain. AEMIP selected two proposals on market facilitation of datura

senegalensis and production of livestock feed pellets and submitted finalized Fixed Amount Awards and

approval and concurrence memos to USAID in July.

B. Success Story

The 2015 Analysis of the Dynamics of the Formal Sector Employment Market in Guinean Agriculture

provided several recommendations to improve formal sector employment by meeting employer needs. In

terms of training one of the major remarks was the need for students to enhance their understanding

and mastery of the agricultural technical packages. The report stated that in many cases the private

sector was the best place for students to be exposed to modern agricultural technical packages.

Promotion of internships was presented as a solution to improve student’s practical and technical

Mr. Tanou Dialo with a conference organizer

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 8

knowledge, create contact with potential employers, and improve ISAV/F formal relationship with

employers through onsite faculty visits and consultations.

After developing relationships with employers by hosting a

career fair for 4th year students at ISAV/F in June 2016,

starting in February 2017, AEMIP and ISAV/F begin to

contact a list of over 50 employers concerning their

interests in taking on second and third year students as

interns during the break from school. AEMIP proposed

ISAV/F faculty as intern advisors and establishment of

formal partnerships with ISAV/F for interns and

collaboration. A total of 38 structures expressed interest

taking on interns and were invited to ISAV/F on May 19th

and 20th, 2017 to; discuss the opportunities for ISAV /

Faranah student internships; and, provide an opportunity

for the structures present to discuss collaboration and

formal partnership with ISAV/F. By July, 2017 a total of 21

institutions had agreed to provide internships for 90

students moving into their fourth year at ISAV/F. Internship

started directly after the end of the school year in late June.

In September AEMIP supported ISAV/F’s intern advisor’s visits to all 21 host institutions to support the

students intern reports, gain a better understanding of employer needs and realities and modify

curriculum and training based upon work force needs.

ISAV/F students as whole were very pleased with the

opportunity to participate in the internships and build their

professional experience. When called to discuss her initial experience working at AAPR-GF in

Nzerekore, Ivette KANHARA expressed satisfaction that she learned valuable skills including calculation

of feeding and correct fish density based upon pond size as well techniques to share this information with

farmer clients. She felt the experience could allow her to access several career paths including: self-

employed fish farming activities; providing extension and outreach to other interested in starting fish

farming; and, building upon her experience working with livestock within a broad skill set to work as a

quality control specialist of animal products.

The ISAV/G general direction was satisfied with the initiatives role in creating new partnerships,

strengthening their ability to provide advisory and employment services to students, and the possibility of

strengthening market based curriculum by intern advisors. The ISAV/F Director General Professor Sara,

Bailo DIALLO has also stated that given discussion with employers, he believes the internships will lead

to at least 40 new jobs.

Alhassane Diane, President of the Federation of Fruit Planters of Lower Guinea (FEPAF-BG) stated that

the Federation received students that showcased exemplary behavior. FEPAF appreciates the training

they have received from ISAV/F and welcomes students from ISAV/F with open arms for future

internships.

Three interns hosted by FEPAF-BG

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 9

AEMIP will work with SMARTE and IASV/F to prepare an open house presentation for students to share

their internship experience with other students and faculty in November while also pursuing possibilities

to introduce high performing interns directly into the SMARTE AVENIR program with corresponding

internship hosts upon graduation.

A. Deliverables & Reports Prepared

During the reporting period, the following deliverables and reports were submitted to USAID:

• Quarterly Report for the period of April-June, 2017 and Annual Report for the period of July

2016- June 2017.

III. PROGRAM MANAGEMENT

Volunteer Assignments Completed

Two volunteer assignments were completed during the quarter with the support oftwo volunteers.

A. Dr. Mike Miller provided on the use of GIS/GPS for modern land mapping; and,

B. Dr. Gonzalo Rojas-Cifuentes provided a ToT on Plant Selection and breeding.

International Travel

International travel during the quarter consisted of 2 trips. A list of trips by assignment and

volunteers/consultants involved can be found below:

• Two volunteer trips as described above;

C. Key Stakeholder Meetings Held

No key stakeholder meetings were engaged during the quarter.

D. Program Communications and Public Relations

During the quarter the AEMIP DCOP, COP and ISAV/F General Direction worked with a local

cinematographer to produce a 10-minute advertisement on ISAV/F for the upcoming school year. The

film was completed and aired on RTG and Espace Television. The film featured students and ISAV/F

facilities to encourage students graduating from the high school to enroll at ISAV/F

E. Requested Adjustments to Approved Work Plan and PMP

Several planned activities were delayed to the following quarter. See section on discussions of planned

activities that are delayed, postponed or cancelled, or unplanned activities that took place.

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 10

IV. WORK PLAN FOR NEXT QUARTER

A. Activities Planned

Activities Planned Dates

Foundational Activities

Support ISAV/F’s Self-Assessment of the Institutional Development Plan and prepare

plan for 2018-2022

September – November

2017

Prepare the programmatic Exit Plan with ISAV/F

September – November

2017

Activity 1 Curriculum Strengthening

Launch delivery of the four new courses developed with AEMIP support

September – October

2017

Development of Value Chain Analysis curricula

Engaging the ISAV/F Directorate and Rural Economics department in integrating the

curriculum and supporting selected faculty in integrating value chain analysis curriculum

in existing courses and new courses

November - December

2017

Pursue partnership with private sector computer training company November – December

2017

Activity 3 AEMIP Innovations Grants Program

Implementation of Conference Presentation Sponsorship (phase 3) Complete in October

2017

Implement Round 1 and 2 Fixed Obligation Grants

October – Dec 2017

Implement JDR the 3rd Grant

September – December

2017

Activity 4 Management Strengthening

Facilitate a system for information sharing between ISAV/F and the National

Meteorological Agency

November 2017

Facilitate GAIN meeting to catalyze the GAIN PMU to develop an internship database

of major agriculture sector employers, as well as to identify AET curricular

supplements to support employer needs.

Oct-Nov 2017

ToT for ISAV/F Gender Committee to Mainstream Gender in ISAV/F Policies Nov 2017

B. Volunteer Assignments Planned

Below is volunteer travel scheduled for the upcoming quarter:

Volunteer Anticipated Dates Assignment Description

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 11

Suzanne Ondrus November 2017 ToT Institutional gender mainstreaming

C. Staff and Consultant Technical Assistance Planned

Below is international travel scheduled for the upcoming quarter:

Technical Assistance

Provider

Anticipated Dates Trip Purpose

Mr. Peter Saling October 2017 Visit for Meetings with USAID,

Mr. Robert Foster Dec, 2017 Solar Pump Installation

TBD November-Dec, 2017 Integration of Value Chain Curriculum into

ISASV/F Curriculum

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 12

V. APPENDICES

Appendix 1: WORK PLAN PROGRESS –STATUS OF PLANNED ACTIVITIES

In general, the implementation of activities has followed the planning outlined in the approved Year 4 Work Plan, and the implementation schedule

is noted below with the status of programmed activities indicated.

Status of Planned Activities - AEMIP Year 5 Timeline

Table 4. AEMIP Year 5 Timeline

Acronyms

AA: AEMIP Admin Assistant

DG: ISAV/F Director General

DPD: Deputy Program Director

F2F: F2F Office in Conakry

FM: AEMIP Financial Manager

GTA: AEMIP Grants & TA Manager

HQPM: Headquarters Program Manager

IT: AEMIP IT Specialist

LC: Local Consultant

M&E: AEMIP M&E Specialist

PD: AEMIP Program Director

PMU: GAIN Project Management Unit

RMS: Recruitment & Mobilization Specialist

STTA: short-term technical assistance

STVTA: short-term volunteer

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Project Management, Monitoring and Evaluation, and Communications and Outreach

Complete staff annual

performance reviews

PD

Complete

d

Recruit ISAV/F student interns

for Cyber Café management and

Technical Assistance

PD, DPD, IT

Completed

Prepare quarterly progress

reports

PD, M&E, HQPM Completed

Support volunteers to post on

the Winrock Volunteer Facebook

page and Winrock Volunteer

Blog

RMS

Develop ISAV/F Promotional

Advertisement

PD, DPD, IT, LC, ISAV/F

DG Completed

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 13

Acronyms

AA: AEMIP Admin Assistant

DG: ISAV/F Director General

DPD: Deputy Program Director

F2F: F2F Office in Conakry

FM: AEMIP Financial Manager

GTA: AEMIP Grants & TA Manager

HQPM: Headquarters Program Manager

IT: AEMIP IT Specialist

LC: Local Consultant

M&E: AEMIP M&E Specialist

PD: AEMIP Program Director

PMU: GAIN Project Management Unit

RMS: Recruitment & Mobilization Specialist

STTA: short-term technical assistance

STVTA: short-term volunteer

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Support management and

updating of ISAV/F’s website and

Facebook page

PD, DPD, IT, ISAV/F DG

Ongoing

Hold an event with key

stakeholders to present the

results of the Internship

Program

PD, DPD, GTA, ISAV/F

DG

Update project inventory,

prepare Asset Dispensation

Plan, and submit to USAID

approval

PD, AA, IT

Prepare the Project Income

Spending Plan and submit to

USAID for approval

HQPM, PD, FM

Prepare the Operational Close-

Out Plan and submit to USAID

for approval

HQPM, PD

Foundational Activities

Support ISAV/F’s Self-

Assessment of the Institutional

Development Plan and prepare

plan for 2018-2022

PD, DPD, ISAV/F DG

Prepare the programmatic Exit

Plan with ISAV/F

PD, DPD, ISAV/F DG

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 14

Acronyms

AA: AEMIP Admin Assistant

DG: ISAV/F Director General

DPD: Deputy Program Director

F2F: F2F Office in Conakry

FM: AEMIP Financial Manager

GTA: AEMIP Grants & TA Manager

HQPM: Headquarters Program Manager

IT: AEMIP IT Specialist

LC: Local Consultant

M&E: AEMIP M&E Specialist

PD: AEMIP Program Director

PMU: GAIN Project Management Unit

RMS: Recruitment & Mobilization Specialist

STTA: short-term technical assistance

STVTA: short-term volunteer

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Conduct the AEMIP Endline

Evaluation

STVTA, M&E, PD, RMS

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Activity 1 – Curriculum Strengthening

1.1 Development and Expansion of New and Existing ISAV/F Infrastructure

Complete infrastructure

procurement support

PD, FM, ISAV/F DG

Ongoing support for the

development of ISAV/F’s library

collection

PD, IT, ISAV/F DG

Ongoing

1.2 Curriculum Development for Master’s Program

Launch delivery of the four new

courses developed with AEMIP

support

DPD, ISAV/F DG

Identify challenges and issues

and update the curricula

DPD, ISAV/F DG

1.3 Support Formal Partnerships in Internship Program

Implement 65-70 internships DPD, ISAV/F faculty

internship advisors

Complete

d

Work with employers and

ISAV/F faculty internship

advisors to evaluation individual

internships

DPD, ISAV/F faculty

internship advisors Completed

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 15

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Support ISAV/F faculty

internship advisors to develop

short-course on workforce

readiness

DPD, ISAV/F faculty

internship advisors

Ongoing – Outline

completed

1.4 Integration of Value Chain ISAV/F Curricula

Arrange exchanges between

ISAV/F and University of Thies

PD, DPD, ISAV/F DG Underway

Support faculty to integrate

value chain content into ISAV/F

curricula

PD, DPD, ISAV/F DG

1.5 Computer Literacy Training

Pursue partnership with private

sector computer training

company

IT, PD, DPD, ISAV/F DG

Underway

1.6 Weather Forecast and Analysis

Support incorporation of

meteorological data into ISAV/F

training

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Activity 2 – Faculty Strengthening

2.1 Design and delivery of TOTs

Deliver the TOT Water Quality

in Irrigation

STVTA, PD, DPD, GTA,

RMS, ISAV/F DG Completed

Deliver the TOT on Usage of

Modern Mapping Equipment

STVTA, PD, DPD, GTA,

RMS, ISAV/F DG Completed

Deliver TOT on Agriculture

Statistics: Experimental Research

STVTA, PD, DPD, GTA,

RMS, ISAV/F DG Completed

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 16

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Deliver the TOT course on Plant

Breeding and Selection

STVTA, PD, DPD, GTA,

RMS, ISAV/F DG Completed

Deliver TOT on Soil Testing and

Data Analysis Using HACH kits

STVTA, PD, DPD, GTA,

RMS, ISAV/F DG

Activity 3 – AEMIP Innovation and Challenge Grants

3.1 Award and Implementation of AEMIP Conference Grants

Implement grants HQPM, PD, DPD, GTA,

FM, M&E

One completed second

underway

3.2 Award and Implementation of Challenge Grants

Implement Challenge Grants HQPM, PD, DPD, GTA,

FM, M&E Awaiting USAID approval

3.3 Award and Implementation of JDR the 3rd Grant

Evaluate applications for grant,

prepare request for USAID

approval

HQPM, PD, DPD, GTA,

FM, M&E Grants Evaluated

Implement JDR the 3rd Grant HQPM, PD, DPD, GTA,

FM, M&E

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Activity 4 – ISAV/F Management Strengthening

4.1 Development of the GAIN

Facilitate GAIN meeting to

catalyze the GAIN PMU to

develop an internship database of

major agriculture sector

employers, as well as to identify

AET curricular supplements to

support employer needs.

PD, DPD, F2F, GAIN

PMU

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 17

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Host presentation of Endline

Evaluation for GAIN and other

key stakeholders

PD, DPD, F2F, GAIN

PMU, STVTA

Facilitate GAIN meeting on

planning to ensure the

sustainability of GAIN after

AEMIP support concludes

PD, DPD, F2F, GAIN

PMU

Provide budget support for GAIN

members to attend FTF training

on internship programs in Kobe

PD, FM, GAIN PMU

Deliver F2F training to GAIN

members on the Systematic

Process for Continuous

Assessment and Improvement of

Curricula.

PD, DPD, F2F, GAIN

PMU

Deliver AEMIP training to GAIN

members on working with

USAID

STVTA, PD, DPD, GTA,

RMS, GAIN PMU

4.2 Link Weather Station to National Meteorological Agency

Facilitate a system of information

sharing between ISAV/F and the

national meteorological agency

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

4.3 Strengthen ISAV/F management approaches for gender equity

Support the ISAV/F Gender

Committee to Mainstream

Gender in ISAV/F Policies

STVTA, DPD, GTA, RMS,

ISAV/F DG

4.4 Strengthening ISAV/F Resource Mobilization

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 18

Task & Activity Partner/Staff

Responsible

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Support ISAV/F to commercialize

services and products from of the

ISAV/F agriculture experimental

research station

PD, FM, ISAV/F DG

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 19

Appendix 2

Quarter Outputs

AEMIP Indicators

Results

Framework

Level

Indicator

#

Indicator Indicator

Type

Quarter Results

Results Level (baseline and final stage measurements)

Goal 1 Increase in the number of ISAV/F

graduates formally employed in

agriculture or in an agricultural-related

sector

Custom No data to report

2 Increase in ISAV/F faculty engaged in

formal collaborative partnerships with

“client” stakeholders

Custom No data to report

Goal

(GCC

Pilot Q1)

3 Stakeholders (AET faculty and students)

with increased capacity to adapt to the

impacts of climate variability and change

as a result of USG assistance

GCC

4.8.2-29

78 (35 female)

Adoption of improved rice

production techniques in the

communities odf

Heremakono, Belleya and

Kamara

Goal

(GCC

Pilot Q2)

4 ISAV/F developed and disseminated

“farming system strategies” for climate

smart agriculture established

Custom No data to report

IR 1 5 Increase in ISAV/F-led applied research

projects in market-driven, gender-

transformative or climate-smart

technologies

Custom No data to report

IR 2 6 AET institutional stakeholders involved in

formal outreach efforts

Custom No data to report

IR 3 7 Increase in women students entering

classes at ISAV/F

Custom 21%

Outcome Level (annual measurements)

Outcome

2

8 ISAV/F has structured and costed annual

research agendas

Custom Yes

Outcome

3

9 ISAV/F has an operational strategy on the

topics of gender equity and resource

mobilization

Custom Yes

An institutional gender

strategy and Action plan

have been developed

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 20

Outcome

3

10 Public-private partnerships explored

and/or formed as a result of USG (FTF)

assistance

FTF

4.5.2-12

1

MOU with Federation of

Farmer’s Organizations of

lower Guinea

Output Level (quarterly measurements)

Activity 1 11 New technical content modules or

experiential learning tools and methods in

the ISAV/F curriculum developed and

delivered

Custom No Data to Report

Activity 1 12 Faculty and students using new

infrastructure and material resources

secured with support of AEMIP

Custom 17 (4 women)

Use of GPS/GIS and Cyber

Café

Activity 2 13 Trainings delivered for ISAV/F faculty on

technical content or pedagogy that

directly leads to new faculty-developed

curricular elements

Custom No data to report

Activity 3 14 AEMIP Innovation Grants implemented Custom No data to report

Activity 3 15 Climate adaptation technologies and

techniques developed/adapted, tested

and/or adopted

Custom 1 technology improved rice

production practice

Activity 3 16 Stakeholders implementing risk-reducing

practices/actions to improve resilience to

climate change as a result of USG

assistance

FTF

4.5.2-34

78 (35 women)

Adopted improved rice

production techniques

Activity 3 17 Farmers and others who have applied new

technologies and management practices as

a result of USG assistance

FTF

4.5.2-5

78 (35 women)

Adopted improved rice

production techniques

Activity 4 18 AET faculty trained or coached in

institutional development

Custom 8 faculty (0 women)

Activity 4 19 Innovative mechanisms, approaches,

platforms and techniques established and

utilized for outreach activities to network

with external AET stakeholders, partners,

alumni and clients

Custom No data to report

Cross-

cutting

20 People receiving training in global climate

change as a result of USG assistance

GCC

4.8.2-6

No data to report

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 21

Cross-

cutting

21 Individuals who have received USG

supported short-term agricultural sector

productivity/food security

FTF

4.5.2-6

157 (31 women)

ToTs, summary presentation

of potato conferenceWere

trained under various

research grants

Cross-

cutting

22 Individuals who have received USG

supported long-term agricultural sector

productivity/food security training

FTF

4.5.2-7

No data to report

Outcome

3

23 Project Management Unit has been

created by ISAV/F to provide management

capacity for resource mobilization within

GAIN

Custom -

Outcome

Yes

Activity 2

24 AET Faculty trained on USAID financial

and administrative regulations as a result

of USG Assistance

Custom -

Output

No Data to Report

Cross

Cutting

25 Number of members of producer

organizations and community based

organizations receiving USG assistance(S)

FTF 4.5.2-

27

20 (10 female)

Improved rice production

techniques

Cross

Cutting

26 AET Faculty and students participating in

internships due to support from AEMIP

Custom -

Outcome

11 (1 Female)

10 Intern advisors and intern

(other interns will be added

in the next quarter once final

reports are received).

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 22

Appendix 3

Y5Q1 Outputs Indicator Update Table

Results Framew

ork

Level

Indicator #

Indicator

Indicator T

ype

Unit of M

easure

Disaggreg

ation

Baseline Year

Baseline Value

FY 2014 Target

FY 2014 Actual

FY 2015 Target

FY 2015 Actual

FY 2016 Target

FY 2016 Actual

FY 2017 Target

FY 2017 Actual

FY 2018 Target

FY 2018 Actual

LOP Target

LOP Actua

l

LOP Cum

ulative/Not

Com

ulative

Goal 1Increase in the number of ISAVF graduates formally employed in agriculture

or in an agricultural-related sector

Custom,

Result%

M/F; ISAVF

Department2013

34%

(25% F)n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a

25% (to

59% all,

50%F)

0 n/a

Goal 2Increase in ISAVF faculty engaged in formal collaborative partnerships with

"client" stakeholders

Custom,

Result% M/F; MD/GT/CS 2014 5.41% n/a n/a n/a n/a n/a 17.90% n/a n/a n/a n/a 40% 17.90% n/a

Goal (GCC

Pilot Q1)3

[AET faculty and students] stakeholders with increased capacity to adapt

to the impacts of climate variability and change as a result of USG

Assistance

GCC 4.8.2-

29# M/F 2014 0 n/a n/a n/a 47 n/a 0 n/a 469 n/a 0 588 516 n/a

Goal (GCC

Pilot Q2)4

ISAVF-developed and disseminated "farming system strategies" for climate

smart agriculture established

Custom,

Result# n/a 2014 0 n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a 5 0 n/a

IR1 5Increase in ISAVF-led applied research projects in market-driven, gender-

transformative or climate-smart technologies

Custom,

Result% M/F; MD/GT/CS 2014 35.14% n/a n/a n/a n/a n/a 19.20% n/a n/a n/a n/a 40% 0.192 n/a

IR2 6 AET institutional stakeholders involved in formal outreach effortsCustom,

Result#

Efforts targeting

women2014 0 n/a n/a n/a 3 n/a 5 n/a 0 n/a 0 12 8 n/a

IR2 7 Increase in women students entering classes at ISAVFCustom,

Result%

Academic

discipline2013 21% n/a n/a n/a n/a n/a n/a n/a n/a n/a n/a

15% (to

36%)0.21 n/a

Outcome 2 8 ISAVF has structured and costed annual research agendas. Custom,

Outcomey/n n/a 2013 n n n y n y n y n y n y n n/a

Outcome 3 9ISAVF has an operational strategy on the topics of gender equity and

resource mobilization

Custom,

Outcomey/n n/a 2013 n n n y n y n y n y n y n n/a

Outcome 3 10Public-private partnerships explored and/or formed as a result of USG (FTF)

assistance

FTF 4.5.2-

12# n/a 2013 0 2 0 5 4 5 17 5 23 5 0 22 44 C

Results level (baseline and final stage measurements)

Outcome level (annual measurements)

AEMIP Quarterly Progress Report (July – Sep 2017)

Winrock International P a g e | 23

Results Framew

ork

Level

Indicator #

Indicator

Indicator T

ype

Unit of M

easure

Disaggreg

ation

Baseline Year

Baseline Value

FY 2014 Target

FY 2014 Actual

FY 2015 Target

FY 2015 Actual

FY 2016 Target

FY 2016 Actual

FY 2017 Target

FY 2017 Actual

FY 2018Target

FY 2018 Actual

LOP Target

LOP Actua

l

LOP Cum

ulative/Not

Com

ulative

Activity 1 11New technical content modules or experiential learning tools and methods

in the ISAVF curriculum developed and delivered

Custom,

Output# MD/GT/CS/EL 2013 0 4 15 8 15 8 22 8 5 10 0 38 57 C

Activity 1 12Faculty and students using new infrastructure and material resources

secured with support of AEMIP

Custom,

Output#

M/F; Resource

used2013 0 400 747 750 475 1000 1038 1250 2132 500 0 3900 4392 NC

Activity 2 13Trainings delivered for ISAVF faculty on technical content or pedagogy that

directly leads to new faculty-developed curricular elements

Custom,

Output# MD/GT/CS/EL 2013 0 4 1 7 1 7 6 7 4 5 0 30 12 C

Activity 3 14 AEMIP Innovation Grants implementedCustom,

Output#

MD/GT/CS; Type

of Grant2013 0 0 0 25 9 25 27 3 8 15 0 68 44 C

Activity 3 15Climate adaption technologies and techniques developed/adapted, tested

and/or adopted

Custom,

Output# n/a 2013 0 0 1 15 17 15 13 10 15 10 0 50 46 C

Activity 3 16Stakeholders implementing risk-reducing practices/actions to improve

resilience to climate change as a result of USG assistance

FTF 4.5.2-

34# n/a 2013 0 0 0 30 0 475 510 475 455 150 0 1130 965 C

Activity 3 17Farmers and others who have applied new technologies and management

practices as a result of USG assistance

FTF 4.5.2-

5 # M/F 2013 0 0 0 32 10 150 290 150 271 150 0 482 571 C

Activity 4 18 AET faculty trained or coached in institutional development topics Custom,

Output#

M/F; AET

institution;

functional roles

2013 0 30 55 90 466 90 330 30 37 90 0 330 888 C

Activity 4 19

Innovative mechanisms, approaches, platforms and techniques established

and utilized for outreach activities to network with external AET

stakeholders, partners, alumni and clients

Custom,

Output# n/a 2013 0 2 2 20 21 20 9 10 1 15 0 67 33 C

Cross-cutting 20People receiving training in global climate change as a result of USG

assistance

GCC

4.8.2-6 # M/F 2013 0 60 39 950 6208 950 5602 0 274 0 0 1960 12123 C

Output level (quarterly measurements)

AEMIP Quarterly Progress Report (April - June 2015)

Winrock International P a g e | 24

Cross-cutting 21Individuals who have received USG supported short-term agricultural sector

productivity/food security training

FTF

4.5.2-7# M/F 2013 0 65 0 300 253 300 560 100 157 200 0 965 970 C

Cross-cutting 22Individuals who have received USG supported long-term agricultural sector

productivity/food security training

FTF

4.5.2-7# M/F 2013 0 5 0 300 170 1500 98 200 2670 200 0 2205 2938 C

Outcome 323

Project Management Unit has been created by ISAV/F to provide

management capacity for resource mobilization within GAIN (custom,

outcome-level)

Custom -

Outcomey/n n/a 2016 no n/a n/a n/a n/a No oui No 0 No 0 Yes Y NC

Activity 2

24AET Faculty trained on USAID financial and administrative regulations as a

result of USG Assistance (custom, output-level)

Custom -

Output#

Sex; AET

institution;

functional roles of

staff

2016 n/a n/a n/a n/a n/a n/a 0 15 0 45 0 60 0 C

Cross Cutting

25Number of members of producer organizations and community based

organizations receiving USG assistance(S)(Cross Cutting, Activities 2, 3

and 4)

FTF 4.5.2-

27

#

Sex. type of

producer

organization (i.e.

potato, cocoa, oil

palm, rice,

vegetables, etc)

2016 n/a n/a n/a n/a n/a n/a n/a 250 20 250 0 500 0 C

Cross Cutting

26

AET Faculty and students participating in internships due to support from

AEMIP

Custom -

Outcome#

Sex of Intern, Sex

of Advisor,

Department of

Intern and

Department of

Advisor

2016 n/a n/a n/a n/a n/a n/a 10 15 11 35 0 50 21 C

AEMIP Quarterly Progress Report (April - June 2015)

Winrock International P a g e | 25