ae303 intro to deep foundations
TRANSCRIPT
-
8/18/2019 AE303 Intro to Deep Foundations
1/6
5/17/
• When the soil directly below a building is not strongenough, or the footing size would be larger than practical,
a deep foundation can be used.• Deep foundations can be divided into two types.. A drilled
and poured in place “pier”, or a driven “pile”.
Piers and piles have two components to their load capacity:
End bearing and shaft friction.
Piles are made of:
Steel; H- piles, Steel pipe
Concrete; Site cast or Precast
Wood;.. Often used as temporarypiling today...but wood was used forpermanent piling in the past. Theseare 100+ year old piles under city hall.Wood piles will last “forever” as longas they stay wet.
Driven Piles:8” to 10” pipe piles driven 25’ to 35’ are very common In this area.
H piles are used for soil retaining systemsand to support buildings where the required
pile strength and depth is greater than can becarried by pipe. H piles under the US bank
building in Milwaukee go150’ deep.
-
8/18/2019 AE303 Intro to Deep Foundations
2/6
5/17/
Drilled Piers
Deep FoundationsBell Creator
Shaft Casing
Drilled Piers
Deep Foundations
Rebar Cage Insertion
Rebar Cage
Shaft Casing
-
8/18/2019 AE303 Intro to Deep Foundations
3/6
5/17/
Piles and Piers are always Load Tested
Sometimes the pile is loaded by
pressing against a static deadload.
Piles and Piers are always Load Tested
Sometimes they aretested by reacting
against other piles.
-
8/18/2019 AE303 Intro to Deep Foundations
4/6
5/17/
Deep Foundation Design
Deep Foundation Design
-
8/18/2019 AE303 Intro to Deep Foundations
5/6
5/17/
Pile caps are footings used to tie a group of piers orpiles together to support and transmit column loads
to them.
Pile caps: ACI Rules :
-
8/18/2019 AE303 Intro to Deep Foundations
6/6
5/17/
Deep Foundation Design
Group Efficiency.
Stresses coming from the piers or piles in the soil mass overlapwhen they are placed too close to each other. The load-bearing
capacity of the group is less than the sum of the individual
capacities .
There are a number
of methods forpredicting the
capacity of groups.
Deep Foundation DesignGroup Efficiency, here are three representative methods of calculation.
1) The Converse-LaBarré method. In this method, η represents the group’sefficiency expressed as a percentage of the theoretical total group load. The
theoretical group load is the ultimate load of each pile multiplied by the total
number of piles.
The ni represents the number of rows and columns, d is the pile diameter and s isthe spacing between piles (center-to-center).
2) The Feld rule reduces the calculated load capacity of each pile in a group by
0.0625 for each adjacent pile. The pile spacing s is not taken into account.
3) The Contractor’s rule reduces the calculated load capacity of each pile by a
factor I for each adjacent pile, where,