a&e standardsmedia.flysfo.com.s3.amazonaws.com/sfoconstruction/_02...this section contains the...

118
A&E Standards Airfield Civil − Earthwork Division 31 − Earthwork Version 3.1 | SEP Subgroup 3.1 | March 2018

Upload: others

Post on 06-Apr-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

  • A&E Standards Airfield Civil − Earthwork

    Division 31 − Earthwork

    Version 3.1 | SEP Subgroup 3.1 | March 2018

  • PREFACE

    PURPOSE OF THIS DOCUMENT

    The intent of this document is to disseminate the San Francisco International Airport’s (SFO’s or Airport’s) expectations regarding the information presented to designers, engineers, general contractors and other industry specialists. The material provided in the following sections includes the minimal requirements, general information, design criteria, guide specifications and details for Airfield Civil - Earthwork installed at SFO. While this document addresses major areas of concern to SFO, it is not an all-inclusive document.

    HOW TO USE THIS DOCUMENT

    This document should be used as a resource for the development of project specific design documents including drawings, details and specifications. It is the responsibility of the design, engineering and construction professionals to adhere to all codes and regulations related to the content presented.

    SCOPE

    This section contains the Standards and Criteria for Airfield Civil - Earthwork. Any questions or concerns regarding the items or equals specified must be submitted to the Standards Committee in writing. All final decisions regarding products shall be made at the Airport’s discretion. If the Engineer of Record presents items that are not specified or named equals, they must be brought to the Standards Committee for evaluation of those products.

    GENERAL INFORMATION

    All work in this section must comply with Federal Aviation Administration’s (FAA) Advisory Circular AC 150/5370 -10 (current version) – Standards for Specifying Construction of Airports.

    DRAWING REQUIREMENTS

    A. All design disciplines including the architectural/engineering sub-consultants and the trade bid package subcontractors shall prepare documents using Revit in the current version utilized by the Airport in compliance with the Airport’s Building Information Modeling (BIM) Requirements as described in Document 00 73 87: BIM Requirements, unless waived by the Chief Development Officer.

    B. When Revit models may not be applicable, (for example, tasks with underground infrastructure beyond a building footprint), Civil 3D may be used to model utilities and applicable infrastructure if approved by the Chief Development Officer.

    C. Refer to technical specifications for As-Built requirements.

    D. Documents and plans submitted to SFO shall be searchable using PDFs with live text. This includes, but is not limited to, text and symbols. The document shall also provide the capability to turn layers on and off. Any project using legacy documents which may be composed image files shall be converted to live text via Optical Character Recognition (OCR).

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 1

  • Version Publish Date Revisions Reviewed By

    3.1 March 2018

    The March 2018 version was uploaded to SFOConstruction.com in November 2018.

    BIM language updated, content edits

    Standards Committee, BIM Integration Team, SFO Civil

    Engineering, N. King

    3.0 - - -

    2.0 December 2017 Content edits, formatting Jim Ogren, N. King

    1.0 June 2015 - SFO Civil Engineering

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 2

  • ......................................................................................................................................................................................................

    ...........................................................................................................................

    ......................................................................................................................

    ......................................................................................................

    Table of Contents

    PREFACE 1 SECTION 02 01 00 – GENERAL SITE WORK 4

    SECTION 02 21 13.16 – STAINLESS STEEL ROD SURVEY MONUMENT 12

    SECTION 02 22 26 – POTHOLING 16

    SECTION 02 41 19 – SURFACE PREPARATION (FAA ITEM P-101) 19

    FAA ITEM P-101 SURFACE PREPARATION 21 SECTION 02 41 26 – VINYL SEAWALL DEMOLITION 25

    SECTION 02 41 29 – JET BLAST DEFLECTOR DEMOLITION 27

    SECTION 02 61 00 – DISPOSAL OF CONTAMINATED SOIL, SLUDGE, AND WATER 29

    SECTION 02 61 13 – EXCAVATION AND REMOVAL OF CONTAMINATED SOIL, SLUDGE, AND WATER 36

    SECTION 06 10 10 – ROUGH CARPENTRY 49

    SECTION 31 11 00 – CLEARING AND GRUBBING (FAA Item P-151) 55

    FAA ITEM P-151 CLEARING AND GRUBBING 56 SECTION 31 23 00 – EXCAVATION AND EMBANKMENT (FAA ITEM P-152) 58

    FAA ITEM P– 152 EXCAVATION AND EMBANKMENT 60 SECTION 31 23 19 – DEWATERING 66

    SECTION 31 23 23 – BACKFILL AND GEOTEXTILES 71

    SECTION 31 25 00 – EROSION AND SEDIMENTATION CONTROL 82

    SECTION 31 32 16.16 – SOIL STABILIZATION AND DUST CONTROL 87

    SECTION 31 40 00 – SHORING AND BRACING 92

    SECTION 31 41 16.15 – VINYL SHEET PILING 95

    SECTION 31 50 00 – EXCAVATION SUPPORT SYSTEM FOR PITS 97

    SECTION 31 62 19 – TIMBER PILES 101

    SECTION 31 63 29 – DRILLED CONCRETE PIERS AND SHAFTS 107

    SECTION 33 05 23.13 – HORIZONTAL DIRECTIONAL DRILLING 110

    APPENDIX A – MASTER LIST OF MANUFACTURERS 116

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 3

  • SECTION 02 01 00 – GENERAL SITE WORK

    PART 1 – GENERAL

    1.1 SUMMARY

    A. The work to be performed under this section includes all labor, materials, and services to: furnish, install, test, and place in operation the complete systems as specified herein, and as shown on the drawings.

    1.2 RELATED SECTIONS

    A. Specification 02 25 00 – Underground Utilities Locating

    B. Specification 31 23 19 – Dewatering

    C. Specification 31 23 00 – Excavation and Embankment

    D. Specification 31 23 23 – Backfill and Geotextiles

    E. Specification 31 40 00 – Shoring and Bracing

    F. Specification 32 23 23.33 – Controlled Low-Strength Material (CLSM) (FAA Item P-153)

    1.3 REFERENCES

    A. The most current version published specifications, standards, tests and recommended methods of the following trade, industry or governmental organizations apply to the work in Section 02 01 00:

    1. AUUDM – Airport Underground Utility Design Manual

    2. NEMA – National Electric Manufacturer’s Association

    3. ANSI – American National Standards Institute

    4. ASME – American Society of Mechanical Engineers

    5. FAA – Federal Aviation Administration

    6. NFPA – National Fire Protection Agency

    7. ARI – Air-Conditioning and Refrigeration Institute

    8. UL – Underwriters Laboratories

    9. SMACNA – Sheet Metal and Air Conditioning Contractors’ National Association

    10. UPC – Uniform Plumbing Code

    11. UMC – Uniform Mechanical Code

    12. UBC – Uniform Building Code

    13. NEBB – National Environmental Balancing Bureau

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 4

  • Section 02 01 00 | General Site Work

    14. CBC – California Building Code

    15. ASTM – American Society for Testing and Materials

    16. AASHTO – American Association of State Highway and Transportation Officials

    17. San Francisco International Airport Rules and Regulations/Airport Building Regulations

    18. Geotechnical Report

    1.4 PERFORMANCE REQUIREMENTS

    A. The specifications and drawings are intended to provide the information for the purchase or fabrication, installation, and operational testing of the equipment and mechanical systems.

    B. Equipment and systems specified herein shall be suitable for installation within the overall dimensional limits shown on the applicable drawings. The equipment and systems shall be complete and operable in every respect with all components and accessories necessary for meeting the applicable performance, and environmental and safety requirements. Equipment, systems and components thereof, shall be new, of first quality, and the standard product of one manufacturer unless otherwise specified.

    1.5 EXAMINATION OF SITE

    A. Data in these specifications and on the drawings are as accurate as possible, but are not guaranteed. The contractor shall verify locations, levels, distances and features that may affect the work. No allowance will be made on his behalf for any extra expense resulting from failure or neglect in determining the conditions under which work is to be performed.

    1.6 MANUFACTURER'S INSTRUCTIONS

    A. Where it is required in the specifications that materials, products, processes, equipment or the like be installed or applied in accordance with manufacturer's instructions, directions, or specifications, it shall be construed to mean that said application or installation shall be in strict accordance with the current printed instructions furnished by the manufacturer of the material concerned for use under conditions similar to those at the job site.

    1.7 MATERIALS AND WORKMANSHIP

    A. Finished work shall be plumb, level, well-anchored, smooth, and uniform, with no unsightly or hazardous protrusions, burrs, or sharp edges and shall have provision for expansion and contraction.

    B. Finished surfaces shall be free from bubbles, streaks, peeling, pits, dents, cracks, stains, chips, or excess sealant. Operating hardware and other moving devices shall be secured and adjusted to operate freely and smoothly.

    C. Wherever cutting of existing surfaces is required, perform that work to minimize damage to surrounding surfaces. Restore all surfaces to match adjoining undisturbed areas.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 5

  • Section 02 01 00 | General Site Work

    D. Employ only experienced, competent, and properly trained workers.

    1.8 AS-BUILT DRAWINGS

    A. No progress payment will be processed prior to Project manager receiving all requested, acceptable updated as-built drawings from the contractor.

    B. No final payment will be made without the Engineer-approved as-built drawings and documentation.

    1.9 SUBMITTALS

    A. Individual Equipment Inventory Sheet shall be submitted for all equipment

    B. Underground Utility Report form shall be submitted for all utilities encountered that are not shown on the plans. The location and depth of any utilities that are shown on the drawing shall be updated on the contract As-Built drawings.

    PART 2 – MATERIALS AND EQUIPMENT

    2.1 UNDERGROUND UTILITY DETECTION TAPE

    A. Install colored warning tape above underground utility lines, which are shown on the drawings. The Colored tape shall be non-detectable, 6" wide, installed 6" above the utility, colored and labeled as noted:

    Utility Color of Tape Label Electrical Red Buried Electrical Duct

    Natural Gas Yellow Buried Gas Pipeline Jet Fuel/Oil Yellow Buried Jet Fuel/Oil Pipeline Telephone Orange Buried Telephone Duct

    Water Blue Buried Water Pipeline Sewer Green Buried Sewer Pipeline

    Industrial Waste Green Buried Industrial Waste Pipeline Drainage Green Buried Drainage Pipeline

    2.2 STAINLESS STEEL BOLTS

    A. The contractor shall use Stainless Steel 316 bolts for all underground applications. There are no exceptions.

    PART 3 – EXECUTION

    3.1 EXISTING UTILITIES

    A. The known existing utilities are shown on the drawings in their approximate location and the contractor shall exercise care in avoiding damage to these facilities, as the contractor will be held responsible for their repair if damaged. There is no guarantee that all utilities or obstructions are shown or that locations indicated are accurate.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 6

  • Section 02 01 00 | General Site Work

    B. The contractor shall exercise extreme caution in operating heavy equipment over all existing utilities. All leaks or breaks caused by the contractor's operations shall immediately be repaired at no extra cost to the City. The contractor shall control the banks of all excavated areas as is necessary to prevent movement of soil and in areas supporting existing foundations, slabs, pole lines, pipelines or other structures. If, as a result of the excavation or through fault or neglect of the contractor, the earth or ground under or around such foundations, slabs, pole lines, pipelines or other structure slips or is otherwise disturbed, corrective measures shall be taken as directed by the Engineer and at the expense of the contractor. The location of existing utilities on the drawings does not excuse the contractor from liability for damage to any existing utilities.

    C. If interference occurs at locations other than shown on the plans, the contractor shall notify the Engineer, and a method for correcting said interference shall be supplied by the Engineer.

    D. Written request for utility service shutdown shall be submitted to the Engineer for approval three (3) working days prior to actual work. All shutdown operations of existing utility systems and equipment, except that under exclusive control of a single tenant, shall be performed by or under supervision of Airport personnel.

    E. Planned utility service shutdowns shall be accomplished during periods of minimum use. In some cases, this may require weekend work, at no additional cost to the City. The contractor shall program his work so that service will be restored in the minimum possible time, and shall cooperate with City in reducing shutdowns of utility systems to a minimum.

    3.2 ASPHALT PAVEMENT REMOVAL

    A. The contractor may use any method of cutting the edges of trenches which will minimize damage to adjacent pavement. However, prior to repaving, the edges of all trenches shall be sawed on straight lines between angle points. Broken edges of pavement and pavement edges around manholes and other appurtenances shall be saw-trimmed in a neat rectangular shape and primed prior to final repaving.

    3.3 SHORING

    A. The sides of all excavations shall be supported in the manner set forth in the rules, orders and regulations prescribed by the Division of Industrial Safety of the State of California (Cal/OSHA). Submit shoring design to the Engineer for approval. See Specification 31 40 00 – Shoring and Bracing.

    3.4 WATER CONTROL

    A. See Specification 31 23 19 – Dewatering

    3.5 DISPOSITION OF EXCAVATED MATERIAL

    A. When approved by the Airport Engineer, the excavated material may be placed carefully alongside of the trench, or at a designated area, and kept trimmed up so as to cause as little inconvenience as possible to public travel and the normal use of adjacent properties. Free access shall be provided to all fire hydrants, valves, meters, and private drives and means shall be provided whereby storm and wastewater can flow uninterrupted.

    B. All material excavated and not required for backfilling, shall be immediately removed and disposed of off the site of the work and in a manner satisfactory to the Airport Engineer.

    C. The Engineer of Record shall determine whether or not, excavated material will be suitable for backfill. Unsuitable excavated material shall be disposed of off the Airport property by the contractor. New imported backfill sand or screened gravel shall be used to replace the unsuitable excavated material.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 7

  • Section 02 01 00 | General Site Work

    See Specification 31 23 23 Backfill and Geotextiles.

    3.6 EXCAVATION FOR PIPING AND RELATED APPURTENANCES

    A. All excavation for piping and related appurtenances shall be done to the OD of the pipe plus 12-inch width minimum on each side and 36-inch minimum cover. Excavation shall be made to such width outside the lines of piping and appurtenances to be constructed as may be required for proper working methods, the erection of forms and protection of the work.

    B. Excavation for pipe concrete thrust blocks shall be trimmed to undisturbed earth and to dimensions as required prior to placing concrete.

    3.7 STRIPPING

    A. All vegetable matter, such as grass, weeds, shrubs, etc., shall be stripped or otherwise removed from all areas prior to excavation and backfill work. See Section 31 11 00 Clearing and Grubbing (FAA Item P-151).

    3.8 LANDSCAPE REPLACEMENT

    A. Any landscape removed or damaged by the contractor's operations shall be replaced as required to match existing conditions.

    3.9 CURB/SIDEWALK REPLACEMENT

    A. Any curbs and/or sidewalks removed or damaged by the contractor's operations shall be replaced as required to match existing conditions.

    3.10 INSPECTION OF EXCAVATION

    A. The contractor shall notify the Airport when excavation for compacted fill or structure is complete and no forms, reinforcing steel, concrete, or pipe shall be placed until the excavation has been inspected by the Engineer.

    3.11 BACKFILL FOR PIPING AND APPURTENANCES

    A. Backfill material shall consist of suitable site excavated material, or imported material, free from vegetable matter, rubbish or other substances which will prevent compaction of the fill. As far as practicable, depending on the type of excavating equipment used, the excavated material suitable for backfilling shall be deposited in separate piles from that which is unsuitable for use as backfill. The fill shall be placed in 8-inch uniform layers around the pipe before compaction. Unless otherwise noted or shown in the plans, water shall be removed from or added to backfill as necessary to achieve optimum moisture content for 90% density of compaction as established by laboratory tests made in accordance with requirements of ASTM D 1557, Method C except that the upper 3 feet of the backfill below subgrade or ground surface shall be compacted to not less than 95% density, provided that if the Engineer determines that the nature of the ground in which the trench lies precludes compaction of the backfill to the specified density, the backfill shall be compacted to the maximum practical density. See Division 31 specification sections in the contract pertaining to Backfill and to the Geotechnical Report, if provided.

    3.12 ROADWAY REPAVING

    A. Where existing pavement is cut, removed or disturbed due to the contractor's operations it shall be repaired or replaced with a like type, but in no event less than the following:

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 8

  • Section 02 01 00 | General Site Work

    1. Replace roadway and shoulder bituminous pavement cut and removed during installation of piping system as specified in the contract drawings.

    Thickness of Bituminous Surface Course

    Maximum Thickness of One Lift

    Maximum Size of Aggregate

    Feathering – 3/8 or ½ inches 1½ inches 1 lift ¾ inches

    2 inches 1 lift 1 inch 3 inches 1 lift 1 inch 4 inches 2 inches 1 inch

    5 inches or more 3 inches 1 inch

    2. The final lift of bituminous surface shall be completed at the proper temperature except when otherwise directed by the Engineer.

    3. Width and finished grade elevations of pavement replacement shall match existing adjacent pavement.

    4. All painted striping and markings damaged or removed by the contractor's operations shall be replaced to match existing.

    3.13 UNDERGROND UTILITIES

    A. All underground utilities that are encountered and are not shown on the drawings shall be documented in the attached “Underground Utility Report” form. This report shall be submitted to the Airport as soon as possible after encountering the unknown utility.

    3.14 ABANDONED PIPES

    A. Any underground piping that is encountered and is determined to be abandoned by Airport Engineers shall be slurry sealed. See Specification 32 23 23.33 – Controlled Low-Strength Material (CLSM) for Abandoned Underground Pipes.

    PART 4 – TESTING AND START-UP

    4.1 INSPECTING AND TESTING

    A. The mechanical installation shall be inspected and tested to insure safety to building occupants, operating personnel, conformity to Code authorities and Contract Documents. The contractor shall follow recognized safety procedures and techniques during testing of all equipment to ensure employee safety.

    B. Special Inspector and BICE must be present during inspection and testing.

    4.2 PERFORMANCE

    A. After completion of testing and adjustment, operate the different systems and equipment under normal working conditions for 2 days of 8 hours and show specified performance. If, in the opinion of the Owner, performance of equipment or system is not in accordance with Specifications or submitted data, alter or replace equipment at no increase in Contract Price. Contractor at its option may order tests from an independent, approved laboratory to prove compliance. All such tests shall be at no increase in Contract Price.

    4.3 CERTIFICATION

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 9

  • Section 02 01 00 | General Site Work

    A. At completion of work, provide written certification that all systems are functioning properly without defects.

    4.4 FIELD TESTS

    A. As an exception to requirements that may be stated elsewhere in the contract the Engineer shall be given 5 working days’ notice prior to each test.

    4.5 TESTING EQUIPMENT

    A. The testing equipment and devices used in performing the required tests shall have a calibration sticker affixed to the device stating the date when calibrated, date due for re-calibration, and the signature of the individual who did the calibrations. In addition to the sticker, a certificate shall accompany the testing equipment stating to which standards the device was calibrated to, the name of the calibrating agency, the name and signature of the calibrating individual. The certificate shall also contain the brand name and the serial number of the devices.

    END OF SECTION 02 01 00

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 10

  • Section 02 01 00 | General Site Work

    SAN FRANCISCO INTERNATIONAL AIRPORT

    UNDERGROUND UTILITY REPORT

    Date: ____/____/____ Reported By: Company: Phone:

    Location (Sketch on Back):

    Type of Utility: Industrial Waste Electrical Duct Bank Water

    Telephone Drainage Gas Fuel Unknown

    Utility Asset: Forced Pipeline Anode Test Station Manhole

    Gravity Pipeline Valve Cleanout Other:

    Depth or Invert El.: Linear Feet of Utility Exposed:

    Coordinates (SFIA B or Other):

    Size: in. Wall Thickness: in. Material:

    Soil Type: Bay Mud Rock Sandy Clay Contamination

    Hard Clay Sand Other:

    Utility Condition:

    External - Rust: None Light Heavy N/A Photo: YES

    Pitting: None Light Heavy N/A NO

    Pit Depth (Max): Concrete Condition:

    Sewer

    Catch Basin

    Internal - Rust:

    Inspection:

    Condition:

    None

    Clean

    Light

    Dirty

    Heavy

    Oily N/A

    N/A Video:

    NO

    YES

    Coating: None (Bare) Double Wrap Concrete - Color:

    Single Wrap Poly Bag Other:

    Wrap Condition: Excellent Fair Poor:

    Cathodic Protection: NO YES (please explain):

    BREAK REPORT or COMMENTS: (Cause or probable cause)

    REPAIR REPORT or STATUS: (Who? When? How? Duration?) FOR INTERNAL USE ONL

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 11

  • SECTION 02 21 13.16 – STAINLESS STEEL ROD SURVEY MONUMENT

    PART 1 – GENERAL

    1.1 SUMMARY

    A. Description of Work: Stainless Steel Rod Survey Monument required for Secondary Control to be established in the project area as shown on the Drawings.

    1.2 RELATED SECTIONS:

    A. Section 03 30 00 – Structural Portland Cement Concrete FAA Item P-610.

    1.3 REFERENCE STANDARDS

    A. NOAA Manual NOS NGS 1

    1.4 QUALITY ASSURANCE

    A. FAA AC 150/5300-18 (current version) - General Guidance and Specification for Submission of Aeronautical Surveys to NFS: Field Data Collection and Geographic Information System (GIS), or most current version.

    1.5 SUBMITTALS

    A. Manufacture’s literature.

    B. Record of driving: depth of rod at refusal.

    1.6 COORDINATION

    A. Coordination will be performed as required.

    PART 2 – PRODUCTS

    2.1 MANUFACTURERS

    A. Berntsen [part numbers]

    1. Rod, stainless steel, 4-foot sections [MSS91604]

    2. Rod, stainless steel, one 4 inch [M1DPA]

    3. Studs (threads), stainless steel [M13 thread]

    4. Datum point, stainless steel [MSSDP1]

    5. Spiral (fluted) rod entry point, standard [MSS12]

    6. NGS logo caps, standard, aluminum [BMAC-6]

    7. Pipe, schedule 40 PVC, 6 inches inside diameter, 2-foot length [6PVC24]

    8. Pipe, schedule 40 PVC, 1 inch) inside diameter, 3- foot length [TSS3-Y]

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 12

  • Section 02 21 13.16 | Stainless Steel Rod Survey Monument

    9. Caps, schedule 50 PVC, (Slip-on caps centered and drilled to 0.567 inch ±0.002 [TSSEC-Y]

    10. Cement, PVC solvent [Eclectic® UV-6800]

    11. Loctite (2 oz. bottle)

    12. Grease-MIL SPEC G-10924D (B15395A, Grade 7) [Bel-Ray NO TOX AA-1-1]

    13. Fine-grained washed or play sand

    B. Surv-Kap [part numbers]

    1. Rod, stainless steel, 1-foot x 9/16 w/ lock screw installed [ER-916-1SS]

    2. Rod, stainless steel, 2-foot x 9/16 w/ lock screw installed [ER-916-2SS]

    3. Rod, stainless steel, 3-foot x 9/16 w/ lock screw installed [ER-916-3SS]

    4. Rod, stainless steel, 4-foot x 9/16 w/ lock screw installed [ER-916-4SS]

    5. Lock screw 3/8-16 1 3/8” long [LS-108]

    6. 9/16 x 4 1/2“ heat treated 4130 rod driving adapter [RDA-916]

    7. 3 ¼” flat plain cap w/ hole to fit 9/16“ stainless steel [SRBH-916-3 1/4FS]

    8. Cover [AC-WP]

    9. Pipe, schedule 40 PVC, 6 inches inside diameter, 2-foot length

    10. Pipe, schedule 40 PVC, 1 inch inside diameter, 3- foot length

    11. Caps, schedule 50 PVC, (Slip-on caps centered and drilled to 0.567 inch ±0.002

    12. Cement, PVC solvent [Eclectic® UV-6800]

    13. Loctite (2 oz. bottle)

    14. Grease-MIL SPEC G-10924D (B15395A, Grade 7) [Bel-Ray NO TOX AA-1-1]

    15. Fine-grained washed or play sand

    PART 3 – PRODUCTS

    3.1 INSTALLATION

    A. Using the solvent cement [Eclectic UV-6800] formulated specifically for PVC, glue the aluminum logo cap [BMAC] to a 2-foot section of PVC pipe [5PVC24]. This will allow the glue to set while continuing with the following setting procedures.

    B. Glue the PVC cap with a drill hole [TSSEC-Y] on one end of the 3-foot section of schedule 40 PVC pipe 1-inch (25mm) inside diameter [TSS3]. Pump the PVC pipe full of grease. Thoroughly clean the open end of the pipe with a solvent, which will remove grease. Then glue another cap with drill hole on the remaining open end. Set aside while continuing with the next step. (*NOTE: This step can also be done in advance, prior to going into the field.)

    C. Using a power auger or post hole digger, drill or dig a hole in the ground 12 - 14 inches in diameter

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 13

  • Section 02 21 13.16 | Stainless Steel Rod Survey Monument

    and 43 inches deep.

    D. Attach the standard spiral (fluted) rod entry point [SS-12 point] to one end of the 4-foot section of stainless steel rod [SS-916-04] with the standard 3/8-inch stud [M-13 thread] using thread adhesive. On the opposite end, screw on a short 4” piece of rod [M-1 DPA] which will be used as the impact point for driving the rod. Drive this section of rod with a reciprocating driver such as a Pionjar 120, Cobra 148, Wacker BHB 25 or another machine with an equivalent driving force.

    E. Remove the short piece of rod used for driving [M1DPA] and screw in a new stud [M13 thread]. Attach another 4-foot section of rod [SS-916-04] using thread adhesive. Tighten securely (*using vise grips or pipe wrenches). Reattach the short piece of rod [M-1DPA] and drive the new section into the ground.

    F. Repeat step 6 until the rod refuses to drive further or until a driving rate of 60 seconds per foot is achieved, but not more than 90 feet. The top of the rod should terminate about 5 inches below ground surface. Carefully remove the driver [M1DPA].

    G. Insert the grease filled 3-foot section of one inch (1”) PVC pipe sleeve [TSS3] over the rod with the unfilled portion at the top. The rod and datum point should protrude through the sleeve about 3”. The sleeve should be resting at or near the bottom of the hole.

    H. Using the existing threaded rod end, install the threaded stud [M13] using thread adhesive. Install the datum point [MSSDP1] using thread adhesive. Tighten ¼ turn past finger tight. The following alternative procedure may be used with the approval of the Engineer. Cut off the top removing the tapped and threaded portion of the rod leaving about 3 inches below ground surface. The top of the rod must be shaped to a smooth rounded (hemispherical) top, using a portable grinding machine to produce a datum point. The datum point must then be center punched to provide a plumbing (centering) point OR use a compression-fit bronze cap center punched.

    I. Backfill and pack with fine-grained washed or play sand around the sleeve [TSS3] to about 20 inches below surface. Place the 6” PVC [6PVC24] and logo cap [BMAC] over and around the 1” sleeve [TSS3] and rod. The datum point [SSDP-1] should be about 3 inches below the cover of the logo cap.

    J. Continue to backfill and pack with sand inside the 6” PVC [6PVC24] and around the outside of the 1-inch sleeve [TSS3] and rod to about 1 inch below the top of the sleeve.

    K. Place concrete around the outside of the 6-inch PVC [6PVC24] and logo cap [BMAC], up to the top of logo cover. Trowel the concrete until a smooth neat finish is produced.

    L. Remove all debris and excess dirt to leave area in original condition. Make sure all excess grease is removed and the datum point [SSDP-1] is clean.

    M. Install a Carsonite fiberglass witness post 2 to 3 feet adjacent to and behind the installed monument [CBM6004SM110] or approved equal.

    PART 4 – INCLUDED FAA SPECIFICATIONS

    Not applicable

    PART 5 – MEASUREMENT AND PAYMENT

    A. The installation of survey monuments and all Work associated therewith shall be measured per each complete contract unit and accepted by the Contract Manager.

    B. This price shall be full compensation for furnishing all materials and for all preparation, excavation, and for all labor, equipment, tools, and incidentals necessary to complete the installation of survey

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 14

  • Section 02 21 13.16 | Stainless Steel Rod Survey Monument

    monuments.

    C. Contractor shall furnish and install survey monuments at the locations as shown on the Survey Control and New Monument Plans.

    END OF SECTION 02 21 13.16

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 15

  • SECTION 02 22 26 – POTHOLING

    PART 1 – GENERAL

    1.1 SUMMARY

    A. Work Included:

    1. Exploratory excavations by potholing to verify or to discover the actual locations and the size of existing underground utilities and improvements.

    2. Potholing shall consist of excavations at the existing underground utilities within the construction area, or locations indicated on the drawings or as directed by the Contract Manager.

    1.2 REFERENCES

    A. Section 02 22 25 – Underground Utility Locating

    B. All applicable codes, rules and regulations.

    C. San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    D. CAL/OSHA Standards.

    1.3 SUBMITTALS

    A. The contractor’s proposed method of potholing and schedule for potholing shall be submitted to the Contract Manager for approval, a minimum of 5 working days prior to the commencement of operation.

    B. The survey records shall be submitted to the Contract Manager within 2 working days after the completion of potholing in each area. The records shall also include dates of the potholing operations and any additional discovered information or pertinent data.

    C. Submit the specifications and capability of the equipment proposed to be used to the Contract Manager for approval, a minimum of 10 working days prior to the start of work.

    1.4 QUALITY CONTROL

    A. The contractor shall perform work in accordance with all applicable codes, rules and regulations, and the San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    PART 2 – PRODUCTS

    Not Used

    PART 3 – EXECUTION

    3.1 EXAMINATION SUMMARY

    A. Verify the site conditions.

    3.2 SURVEY

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 16

  • Section 02 22 26 | Potholing

    A. The contractor shall use a licensed surveyor, at contractor’s expense to establish and record the coordinates, elevations, depths, and dimensions of all utilities and improvements verified or discovered by potholing.

    3.3 PREPARATION

    A. The contractor shall provide the final report, as prepared under Section 02 22 25 – Underground Utility Locating, to the Contract Manager to obtain authorization before any potholing work can begin.

    B. Protect utilities from damage.

    C. Obtain information and assistance from respective utility companies.

    D. Provide measures to protect workers, passengers, vehicles, and aircraft traffic in the vicinity of work site.

    E. Be familiar with the Airport's procedures for construction, safety, emergencies, and utility shutdowns.

    F. Submit work plan, schedule, and Job Safety Procedures to Airport Contract Manager for approval, a minimum of 5 working days before start of work.

    G. File request for utility shutdown, as required, to the Contract Manager a minimum of three (3) working days before shutdown date.

    H. Comply with CAL/OSHA Standards.

    3.4 EQUIPMENT AND METHODS

    A. The following alternative methods shall be utilized for potholing:

    B. Hand Digging - Hand digging is the method of excavating a pothole by manual means with hand-held, non- mechanical equipment such as a shovel.

    C. Vacuum Excavation - Vacuum excavation shall consist of air or water pressure to break up the soil and a vacuum device to collect the spoil. The contractor shall determine if air or water vacuum excavation shall be used dependent upon specific site and environmental characteristics. Soil type such as heavy clay may require water vacuum excavation. Air vacuum excavators shall be utilized if mud from water vacuum excavators cannot be disposed of properly. Air vacuum excavators shall be used if damage to utilities, such as cutting through cables, will occur with the use of water vacuum excavators.

    D. Air Vacuum - Air vacuum excavators shall utilize a high velocity air stream to penetrate, expand, and break-up the soil. The loosened particles of soil and rock shall be removed from the excavation through the use of a vacuum.

    E. Water - Water vacuum excavation systems shall excavate the pothole using high-pressure water to reduce and loosen the soil. The wet soil and mud slurry shall be removed to a spoil tank using a vacuum.

    3.5 POTHOLING

    A. Contractor shall prepare a schedule for potholing utility lines and shall provide this schedule to the Contract Manager a minimum of five (5) working days prior to beginning potholing. Contractor shall not pothole any fuel line without a fuel line owner/operator representative present, unless directed otherwise by the Contract Manager.

    B. After receiving approval from Contract Manager for potholing schedule, contractor shall commence

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 17

  • Section 02 22 26 | Potholing

    potholing to determine the actual location and elevation of all utility lines within the limits of excavations as shown on the Contract Drawings The utility lines shall be determined to be within the limits of the excavations based on the contract Drawings, on reference drawings included in the specifications, or drawings supplied by the utility owner/operators, as marked in the field by contractor and owner/operators or as indicated by surface signs. While performing the "potholing" operation, contractor shall exercise extreme care and caution so as not to damage any pipes, conduit, ductbank and directly buried cables and wires during excavation. Manual excavation may be required near the abandoned fuel lines as determined by the Contract Manager.

    C. Pothole excavations shall have surface dimensions of no more than 18 inches in diameter or 18” x 18 inch square, unless otherwise approved by the Contract Manager. Contractor shall backfill excavations after potholing is completed. In existing paved areas, backfill and restore to match existing pavement.

    3.6 REPORTING

    A. All the records shall be compiled, neatly organized, and presented to the Contract Manager. The records shall also include dates of the potholing operations and any additional discovered information or pertinent data in AutoCAD format (current version).

    B. The locations, elevations, depths, and alignments of the underground utilities and pipes potholes shall be presented with identification, coordinates, all dimensions and elevations in accordance with the Airport's horizontal and vertical control systems.

    3.7 BACKFILL AND RESTORATION

    A. Upon completion of potholing in each area, potholes shall be immediately backfilled and compacted in accordance with the specifications, or restored as directed by the Contract Manager.

    B. All the existing structures or utilities damaged during potholing shall be immediately reported to the Contract Manager and Inspector and repairs made immediately.

    C. Potholes shall be restored within 24 hours after the utility has been located. Potholes may only be left open if approved by the Contract Manager. Open potholes, where approved, shall be fenced with construction fencing 5 feet from the edge of the hole and delineated with approved barricades equipped with flashing lights.

    D. Clean up the site and remove all material and equipment immediately after the site work is completed.

    PART 4 – INCLUDED FAA SPECIFICATIONS

    Not applicable

    PART 5 – MEASUREMENT AND PAYMENT

    A. There will be no separate payment for work under this section. All work shall be considered incidental to contract bid items.

    END OF SECTION 02 22 26

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 18

  • SECTION 02 41 19 – SURFACE PREPARATION (FAA ITEM P-101)

    PART 1 – GENERAL

    1.1 SUMMARY

    A. The Work under this Section consists of providing surface preparation as shown on the Plans, as specified herein, or as directed by the Engineer.

    1.2 REFERENCES

    A. San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    B. FAA Specification Item P-101 – Surface Preparation, and as modified herein.

    C. Section 32 01 16.71 – Cold Milling Asphalt Pavement.

    1.3 SUBMITTALS

    A. The contractor shall submit the following surface preparation information:

    1. Concrete and asphaltic concrete repair materials.

    2. Joint and crack sealing materials.

    3. Paint and rubber removal method, material and equipment.

    4. Cold planning equipment.

    1.4 QUALITY ASSURANCE

    Not used.

    PART 2 – PRODUCTS

    2.1 MATERIALS

    A. Materials shall conform to FAA Specification Item P-101, and as modified herein.

    PART 3 – EXECUTION

    A. The contractor shall prepare existing pavement for overlay and remove existing pavement, and other miscellaneous items in accordance with FAA Specification Item P-101, and as modified herein.

    B. For removal of existing pavement by cold milling method refer to Section 32 01 16.71 – Cold Milling Asphalt Pavement.

    PART 4 – INCLUDED FAA SPECFICATIONS

    Item P-101 – Surface Preparation.

    PART 5 – MEASUREMENT AND PAYMENT

    A. The method of measurement and payment for the work under this section shall be in accordance with

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 19

  • Section 02 41 19 | Surface Preparation (FAA Item P-101)

    FAA Specification Item P-101, and as modified herein.

    B. If there is no quantity shown in the bidding schedule, the work covered by this section shall be considered as a subsidiary obligation of the contractor covered under the other contract items.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 20

  • FAA ITEM P-101 SURFACE PREPARATION

    PART 1 – DESCRIPTION

    101-1.1 – This item shall consist of preparation of existing pavement surfaces for overlay, surface treatments, removal of existing pavement, and other miscellaneous items. The work shall be accomplished in accordance with these specifications and the applicable drawings.

    PART 2 – EQUPIMENT

    101-2.1 – All equipment shall be specified here and in the following paragraphs or approved by the Engineer. The equipment shall not cause damage to the pavement to remain in place.

    PART 3 – CONSTRUCTION

    101-3.1 – REMOVAL OF EXISTING PAVEMENT

    A. Concrete Pavement. The existing concrete pavement to be removed shall be freed from the pavement to remain by sawing through the complete depth of the slab one foot (30 cm) inside the perimeter of the final removal limits or outside the dowels, whichever is greater when the limits of removal are located on the joints. The pavement between the perimeter of the pavement removal and the saw cut shall be carefully broken up and removed using hand-held jackhammers, weighing 30 pounds (14 kg) or less, or other light-duty equipment which will not cause distress in the pavement which is to remain in place. The contractor shall have the option of sawing through the dowels at the joint, removing the pavement and installing new dowels. Where the perimeter of the removal limits is not located on the joint and there are no dowels present, then the perimeter shall be saw cut the full depth of the pavement. The pavement inside the saw cut shall be removed by methods suitable to the Engineer which will not cause distress in the pavement which is to remain in place. If the material is to be wasted on the airport site, it shall be reduced to a maximum size designated by the Engineer. The contractor’s removal operation shall not cause damage to cables, utility ducts, pipelines, or drainage structures under the pavement. Concrete slabs that are damaged by under breaking shall be removed. Any damage shall be repaired at the contractor’s expense.

    B. Asphaltic Concrete Pavement. Asphalt concrete pavement to be removed shall be cut to the full depth of the bituminous material around the perimeter of the area to be removed. The pavement shall be removed so the joint for each layer of pavement replacement is offset 1 foot (30 cm) from the joint in the preceding layer. This does not apply if the removed pavement is to be replaced with concrete or soil. If the material is to be wasted on the airport site, it shall be broken to a maximum size of 1 inches.

    101-3.2 – PREPARATION OF JOINTS AND CRACKS. Remove all vegetation and debris from cracks to a minimum depth of 1 inch (25 mm). If extensive vegetation exists treat the specific area with a concentrated solution of a water-based herbicide approved by the Engineer. Fill all cracks, ignoring hairline cracks (< 1/4 inch (6 mm) wide) with a crack sealant per ASTM D6690. Wider cracks (over 1.5” wide (38 mm)), along with soft or sunken spots, indicate that the pavement or the pavement base should be repaired or replaced as stated below. Any excess joint or crack sealer on the surface of the pavement shall also be removed from the pavement surface.

    A. Cracks and joints may be filled with a mixture of emulsified asphalt and aggregate. The aggregate shall consist of limestone, volcanic ash, sand, or other material that will cure to form a hard substance. The combined gradation shall be as shown in the following table.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 21

  • FAA Item P-101 Surface Preparation (Section 02 41 19)

    Table 1

    Sieve Size Percent Passing No. 4 100 No. 8 90-100

    No. 16 65-90 No. 30 40-60 No. 50 25-42

    No. 100 15-30 No. 200 10-20

    B. Up to 3% cement can be added to accelerate the set time. The mixture shall not contain more than 20% natural sand without approval in writing from the Engineer.

    C. The proportions of asphalt emulsion and aggregate shall be determined in the field and may be varied to facilitate construction requirements. Normally, these proportions will be approximately one (1) part asphalt emulsion to five parts aggregate by volume. The material shall be poured or placed into the joints or cracks and compacted to form a voidless mass. The joint or crack shall be filled within 0 to 1/8 inches (0-3 mm) of the surface. Any material spilled outside the width of the joint shall be removed from the pavement surface prior to constructing the overlay. Where concrete overlays are to be constructed, only the excess joint material on the pavement surface and vegetation in the joints need to be removed.

    101-3.3 – REMOVAL OF PAINT AND RUBBER. All paint and rubber over 1 foot (30 cm) wide that will affect the bond of the new overlay shall be removed from the surface of the existing pavement. Chemicals, high-pressure water, heater scarifier (asphaltic concrete only), cold milling, or sandblasting may be used. Any methods used shall not cause major damage to the pavement. Major damage is defined as changing the properties of the pavement or removing pavement over 1/8 inch (3 mm) deep. If chemicals are used, they shall comply with the state’s environmental protection regulations. No material shall be deposited on the runway shoulders. All wastes shall be disposed of in areas indicated in this specification or shown on the plans. This shall not be used for removal of rubber deposits to improve skid resistance or obliterate traffic markings where a new overlay is not to be constructed.

    101-3.4 –CONCRETE SPALL OR FAILED ASPHALTIC CONCRETE PAVEMENT REPAIR.

    A. Repair of Concrete Spalls in Areas to be overlaid with Asphalt: The contractors shall repair all spalled concrete as shown on the plans or as directed by the Engineer. The perimeter of the repair shall be saw cut a minimum of 2 inches (50 mm) outside the affected area and 2 inches (50 mm) deep. The deteriorated material shall be removed to a depth where the existing material is firm or cannot be easily removed with a geologist pick. The removed area shall be filled with asphaltic concrete with a minimum Marshall stability of 1,200 lbs (544 kg) and maximum flow of 20 (units of 0.01 in). The material shall be compacted with equipment approved by the Engineer until the material is dense and no movement or marks are visible. The material shall not be placed in lifts over 4 inches (100 mm) in depth. This method of repair applies only to pavement to be overlaid.

    B. Asphaltic Concrete Pavement Repair – The failed areas shall be removed as specified in paragraph 101-3.1b. All failed material including surface, base course, subbase course, and subgrade shall be removed. The base course and subbase shall be replaced if it has been infiltrated with clay, silt, or other material affecting the load-bearing capacity. Materials and methods of construction shall comply with the other applicable sections of this specification.

    101-3.5 – COLD MILLING. Milling shall be performed with a power-operated milling machine or grinder,

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 22

    http:101-3.1b

  • FAA Item P-101 Surface Preparation (Section 02 41 19)

    capable of producing a finished surface that provides a good bond to the new overlay. The milling machine or grinder shall operate without tearing or gouging the under laying surface. The milling machine or grinder shall be equipped with automatic grade and slope controls. All millings shall be removed and disposed off of Airport property, unless otherwise specified. If the contractor mills or grinds deeper or wider than the plans specify, the contractor shall replace the material that was removed with new material at no additional cost to the Owner.

    A. Patching. The milling machine shall be capable of cutting a vertical edge without chipping or spalling the edges of the remaining pavement and it shall have a positive method of controlling the depth of cut. The Engineer shall layout the area to be milled with a straightedge in increments of 1 foot (30 cm) widths. The area to be milled shall cover only the failed area. Any excessive area that is milled because the contractor doesn’t have the appropriate milling machine, or areas that are damaged because of his negligence, shall not be included in the measurement for payment.

    B. Profiling, Grade Correction, or Surface Correction. The milling machine shall have a minimum width of 7 feet (2 m) and it shall be equipped with electronic grade control devices that will cut the surface to the grade and tolerances specified. The machine shall cut vertical edges. A positive method of dust control shall be provided. The machine shall have the ability to windrow the millings or cuttings or to remove the millings or cuttings from the pavement and load them into a truck.

    C. Clean-up. The contractor shall sweep the milled surface daily and immediately after the milling until all residual aggregate and fines are removed from the pavement surface. Prior to paving, the contractor shall wet down the milled pavement and thoroughly sweep and/or blow the surface to remove any remaining aggregate or fines.

    D. Cold Milling: For cold milling of existing pavement refer to Section 32 01 16.71 – Cold Milling Asphalt Pavement.

    101-3.6. – PREPARATION OF ASPHALT PAVEMENT SURFACES. Existing asphalt pavements indicated to be treated with a surface treatment shall be prepared as follows:

    A. Patch asphalt pavement surfaces that have been softened by petroleum derivatives or have failed due to any other cause. Remove damaged pavement to the full depth of the damage and replace with new asphalt concrete similar to that of the existing pavement in accordance with paragraph 101-3.4.

    B. Repair joints and cracks in accordance with paragraph 101-3.2.

    C. Remove oil or grease that has not penetrated the asphalt pavement by scraping or by scrubbing with a detergent, then wash thoroughly with clean water. After cleaning, treat these areas with an oil spot primer.

    D. Clean pavement surface immediately prior to placing the surface treatment by sweeping, flushing well with water leaving no standing water, or a combination of both, so that it is free of dust, dirt, grease, vegetation, oil or any type of objectionable surface film.

    101-3.7 – MAINTENANCE. The contractor shall perform all maintenance work necessary to keep the pavement in a satisfactory condition until the full section is complete and accepted by the Engineer. The surface shall be kept clean and free from foreign material. The pavement shall be properly drained at all times. If cleaning is necessary or if the pavement becomes disturbed, any work repairs necessary shall be performed at the contractor’s expense.

    101-3.8 – PREPARATION OF JOINTS IN RIGID PAVEMENT.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 23

  • FAA Item P-101 Surface Preparation (Section 02 41 19)

    101-3.8.1 – Removal of Existing Joint Sealant. All existing joint sealants will be removed by plowing or use of hand tools. Any remaining sealant and or debris will be removed by use of wire brushes or other tools as necessary. Resaw joints removing no more than 1/16 inch (2 mm) from each joint face. Immediately after sawing, flush out joint with water and other tools as necessary to completely remove the slurry. Allow sufficient time to dry out joints prior to sealing.

    101-3.8.2 – Cleaning prior to sealing. Immediately before sealing, joints shall be cleaned by removing any remaining laitance and other foreign material. Clean joints by sandblasting, or other method approved by the Engineer, on each joint face with nozzle held at an angle and not more than three inches (75 mm) from face. Following sandblasting, clean joints with air free of oil and water. Joint surfaces will be surface-dry prior to installation of sealant.

    101-3.9 – PREPARATION OF CRACKS IN FLEXIBLE PAVEMENT.

    101-3.9.1 Preparation of Crack. Widen crack with router or random crack saw by removing a minimum of 1/16 inch (2 mm) from each side of crack. Immediately before sealing, joints will be blown out with a hot air lance combined with oil and water-free compressed air.

    101-3.9.2 Removal of Existing Sealant. Existing sealants will be removed by routing or random crack saw. Following routing or sawing any remaining debris will be removed by use of a hot lance combined with oil and water-free compressed air.

    PART 4 – METHOD OF MEASUREMENT

    101-4.1 – Measurement.

    A. General: The work covered by this section shall be considered as a subsidiary obligation of the contractor covered under the other contract items.

    PART 5 – BASIS OF PAYMENT

    101-5.1 – Payment. There will be no separate payment for work under this section. All work shall be considered incidental to contract bid items.

    END OF SECTION 02 41 19

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 24

  • SECTION 02 41 26 – VINYL SEAWALL DEMOLITION

    PART 1 – GENERAL

    1.1 SUMMARY

    A. The Work under this Section shall consist of demolition and removal of existing vinyl seawall, including associated items of work, as shown on the Plans and as specified herein.

    1.2 REFERENCES

    A. Section 31 11 00 – Clearing and Grubbing (FAA Item P-151).

    B. Section 31 23 00 – Excavation and Embankment FAA Item (P-152).

    C. Section 31 23 19 – Dewatering.

    D. Section 31 40 00 – Shoring and Bracing.

    E. San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    1.3 SUBMITTALS

    A. Not used

    1.4 QUALITY ASSURANCE

    A. The contractor shall perform Work in accordance with all applicable codes, rules and regulations, and San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    PART 2 – PRODUCTS

    A. Not used

    PART 3 – EXECUTION

    3.1 DEMOLITION

    A. Demolish and remove the existing vinyl seawall as shown on plans, completely as indicated on the plans and as specified in these specifications. All excavated materials shall be removed and dispose of off Airport property. Vinyl seawall shall be salvaged or disposed of off Airport property as indicated on the plans or as directed by the Contract Manager.

    B. Refer to Section 31 11 00 – Clearing and Grubbing FAA Item P-151 for removal and disposal of material to off Airport property.

    3.2 BACKFILL

    A. Backfill is not included in this section and shall be performed, as required by the plans, under respective items of work.

    PART 4 – INCLUDED FAA SPECIFICATIONS

    A. Not applicable

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 25

  • Section 02 41 26 | Vinyl Seawall Demolition

    PART 5 – MEASUREMENT AND PAYMENT

    A. Demolition and removal of vinyl seawall as shown on the plans to be removed, and all Work associated therewith, shall be measured for payment by lump sum as a complete unit of Work, and accepted by the Contract Manager.

    B. Payment for demolition and removal of vinyl seawall completely, and all Work associated therewith, will be made at the contract unit price per lump sum.

    C. This price shall be full compensation for furnishing all materials, preparation, excavation, demolition, shoring, dewatering, reporting, and for all, labor, equipment, tools, hauling, removal of all materials from Airport property and disposal to off-site disposal area, except for salvaged seawall, and incidentals necessary to complete the item.

    END OF SECTION 02 41 26

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 26

  • SECTION 02 41 29 – JET BLAST DEFLECTOR DEMOLITION

    PART 1 – GENERAL

    1.1 SUMMARY

    A. The Work under this Section shall consist of demolition and removal of existing parabolic and vertical jet blast deflectors and foundations, including associated items of work as shown on the Plans and as specified herein.

    1.2 REFERENCES

    A. Section 31 11 00 – Clearing and Grubbing.

    B. Section 31 23 00 – Excavation and Embankment (FAA Item P-152).

    C. Section 31 23 19 – Dewatering.

    D. Section 31 40 00 – Shoring and Bracing.

    E. San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    1.3 SUBMITTALS

    A. Not used

    1.4 QUALITY ASSURANCE

    A. The contractor shall perform Work in accordance with all applicable codes, rules and regulations, and San Francisco International Airport Rules and Regulations/Airport Building Regulations.

    PART 2 – PRODUCTS

    A. Not used.

    PART 3 – EXECUTION

    3.1 DEMOLITION

    A. Demolish and remove the existing parabolic and vertical jet blast deflector and associated foundations completely when indicated on the plans and as specified herein. This includes the removal of the associated obstruction lighting and security infrastructure systems installed on the jet blast deflectors. All excavated and demolished materials shall be removed and disposed of off-Airport property.

    B. Vertical jet blast deflector panels and columns shall be salvaged and delivered on Airport property as directed by the Contract Manager.

    C. In areas where the existing jet blast deflector shall be replaced with a new proposed pavement section as indicated on the plans, the demolition and removal of the jet blast deflector shall include the removal of the associated foundation to a sufficient depth allow the installation of the proposed pavement section.

    D. In areas where the existing jet blast deflector shall to be demolished to top of grade only, the

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 27

  • Section 02 41 29 | Jet Blast Deflector Demolition

    demolition and removal of the existing jet blast deflector does not require the removal of the existing foundation. Contractor shall remove all above grade structures and protrusions and provide a flush surface free from hazards to traffic and to the satisfaction of the Contract Manager.

    E. The demolition of the blast fencing occurs within close proximity to active aircraft operations. Contractor work area shall be limited to boundaries shown on plans. Controlling debris and dust during demolition is of paramount importance and shall be considered incidental to this work.

    F. Refer to Section 31 11 00 – Clearing and Grubbing (FAA Item P-151), for removal and disposal of material to off Airport property.

    3.2 BACKFILL

    A. Backfill is not included in this section, and shall be performed as required by the plans under respective items of work.

    PART 4 – INCLUDED FAA SPECIFICATIONS

    A. Not applicable

    PART 5 – MEASUREMENT AND PAYMENT

    A. Demolition and removal of parabolic and vertical blast fencing and associated foundations as shown on the plans to be removed, and all Work associated therewith, shall be measured for payment by linear foot of fence, and accepted by the Contract Manager.

    B. Payment for demolition and removal of parabolic and vertical blast fencing and associated foundations to be removed, and all Work associated therewith, shall be measured for payment by the contract unit price of linear foot of fence removed, and accepted by the Contract Manager. No additional compensation will be provided due to limited work areas or access due to the proximity of active aircraft operations. Payment shall include all access and phasing considerations.

    C. This price shall be full compensation for furnishing all materials, preparation, excavation, demolition, shoring, dewatering, reporting, and for all labor, equipment, tools, hauling, removal of all materials from Airport property and disposal to off-site disposal areas except for salvaged vertical jet blast deflector panels and columns, and incidentals necessary to complete the item.

    END OF SECTION 02 41 29

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 28

  • SECTION 02 61 00 – DISPOSAL OF CONTAMINATED SOIL, SLUDGE, AND WATER

    PART 1 – GENERAL

    1.1 SUMMARY

    A. This Document specifies disposal of contaminated soil, sludge and water.

    B. Related Sections

    1. Document 02 61 13 – Excavation and Removal of Contaminated Soil, Sludge and Water

    1.2 DESCRIPTION OF WORK

    A. This Document sets forth the procedures to be followed in the handling, and disposal of contaminated soil, sludge, and water.

    1. Contractor shall provide storage containers, lifting, and hauling equipment for the handling and transportation of contaminated soils, sludge, and water encountered during the work activities.

    2. Contaminated groundwater shall be stored as described in Document 02 61 13 – Excavation and Removal of Contaminated Soil, Sludge, and Water.

    3. Contractor shall dispose of contaminated soil and sludge as described in Document 02 61 13 – Excavation and Removal of Contaminated Soil, Sludge, and Water.

    4. Airport may choose to allow its tenants to treat and dispose of contaminated soil, sludge, and water.

    1.3 CONTRACTOR'S RESPONSIBILITIES

    A. Contractor shall remove and dispose of all hazardous or contaminated materials/waste from the construction site. Contractor shall cooperate with the handling and disposal of contaminated materials by others if Airport chooses to allow tenants to perform handling, treatment, and disposal of contaminated materials.

    1.4 CODES AND REGULATIONS

    A. General Requirements:

    1. All work under this contract and any other trade work in conjunction with the handling, transportation and disposal of the materials shall be done in strict accordance with all applicable federal, state, and local laws, regulations, standards, and codes governing handling, transportation, and disposal of materials.

    2. The most recent edition of any relevant laws, regulations, standard, document or code shall be in effect. Where there is a conflict among the requirements or with these Specifications, the most stringent requirements shall be used.

    3. Contractor shall have copes of all standards, laws, regulations, codes, and other applicable documents (including this document) available at the work site.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 29

  • Section 02 61 00 | Disposal of Contaminated Soil, Sludge, And Water

    B. Federal Requirements:

    1. Occupational Safety and Health Administration (OSHA)

    a. Title 29 Code of Federal Regulations Part 1910

    b. Title 29 Code of Federal Regulations Section 1910.134, General Industry Standard for Respiratory Protection

    c. Title 29 Code of Federal Regulations Part 1926, Construction Industry

    d. Title 29 Code of Federal Regulations Section 1920.2, Access to Employee Exposure and Medical Records

    e. Title 29 Code of Federal Regulations Section 1910.1200, Hazard Communication

    f. Title 29 Code of Federal Regulations Section 1910.120, Hazardous Wastes Operations and Emergency Response

    g. Title 29 Code of Federal Regulations Section 1926.55, Gases, Fumes, Mists and Dusts

    2. Environmental Protection Agency (EPA):

    a. Title 40 Code of Federal Regulations Part 268 - Land Disposal Restrictions.

    b. Title 40 Code of Federal Regulations Part 261 - Identification and Listing of Hazardous Waste.

    c. Title 40 Code of Federal Regulations Section 172 - Department of Transportation Regulations for Use of Hazardous Materials Tables and for Communications.

    3. Department of Transportation (DOT)

    a. Title 49 Code of Federal Regulations Section 173.1090

    b. DOT 49 CFR 172

    c. DOT 40 CFR 173

    d. HM181 and HM126f

    C. State of California Requirements:

    1. California State Department of Health, Division of Toxic Substances Control, California Regulation 672-10-01 – California Hazardous Waste Management Regulations

    2. California Health and Safety Code, Sections 25100 et seq. – Hazardous Waste

    3. California Labor Code, Sections 6382, Subdivision B – Hazardous Materials

    4. Title 22 California Code of Regulations, Division 45, Environmental Health Standards for the Management of Hazardous Waste.

    5. Title 23 California Code of Regulations, Division 3, State Water Resources Control Board.

    6. Title 26 California Code of Regulations, Toxic Substances Control.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 30

  • Section 02 61 00 | Disposal of Contaminated Soil, Sludge, And Water

    1.5 WORKER PROTECTION:

    A. Contractor shall provide protective equipment to contractor's personnel who are handling, loading, and unloading containers. Protective equipment shall consist of disposable head, body, and foot protection and, at a minimum may include half/full face piece, air-purifying, dual cartridge respirators equipped with HEPA/organic vapor cartridges. If for any reason a contractor's employee at the disposal site suspects that his or her clothing has become contaminated during the disposal process, he or she shall remove the contaminated clothing at the disposal site and don clean disposable clothing.

    1.6 SUBMITTALS

    A. Notifications Prior to Commencement of Work: Contractor shall notify the appropriate disposal facility as selected and approved based on the type of material (characterized) to be disposed of prior to transportation of the material to the facility.

    B. Non-Airport Operated Disposal Facility Certification Submittal: Operator of the off-site disposal facility shall provide a signed certification to the Airport that contaminated materials received from the Airport will be tracked to allow identification of those materials at the disposal facility. Additionally, facility operator shall provide a signed certification that states that it, within 90 days of receiving the material for treatment, will provide the Airport a Certificate of Treatment for biologically treated or Certificate of Destruction for thermally treated soils.

    1.7 DISPOSAL OR TREATMENT OPTIONS

    A. Contaminated Soil and Sludge: After characterization, contractor shall dispose of contaminated soil at an approved off-site landfill. Contractor shall make all arrangements for disposal and shall comply with all regulatory requirements for documentation. Airport may require contractor to deliver contaminated materials to a thermal treatment system at the Airport, if available. Contractor will be required to dispose of the thermally treated waste or reuse the treated waste for fill as directed by the Airport.

    B. Contaminated Water:

    1. Contractor shall dispose of contaminated water at an off-site facility, or by treating and disposing to the Airport's industrial waste treatment facility provided that the effluent from contractor's treatment facility meets Airport's discharge requirements and there is capacity in the system, and the contractor obtains a permit from the Airport.

    2. For large scale operations involving significant volumes of contaminated water, contractor may with the written approval of Airport design and operate an on-site pretreatment or treatment system under a state-approved, contractor obtained NPDES permit. If there is an Airport-wide NPDES permit for discharge to the Airport storm drain system in existence during contractor's operations, contractor may discharge under that permit.

    3. Contractor may use an on-site treatment system for contaminated groundwater provided the treatment system meets Airport and regulatory requirements. For on-site treatment systems, contractor shall document the quality of the effluent and verify the system's effectiveness and compliance with any issued permit.

    4. Airport will monitor the system's effectiveness by sampling at periodic intervals for site-specific constituents. Costs for monitoring and sample analysis performed by contractor shall be borne by the contractor. Contractor shall obtain Airport approval prior to discharging into any collection system operated by the Airport. The capacity of the system may limit the availability

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 31

  • Section 02 61 00 | Disposal of Contaminated Soil, Sludge, And Water

    of the facility to contractor and may vary by season and the design flow rate of contractor's treatment facility.

    C. Free Phase Product: Contractor shall transport and dispose of all free phase product removed from the tanks or from the various excavations in accordance with applicable laws and regulations at a permitted recycling or treatment facility as approved by the Airport.

    1.8 HAULERS

    A. Only trucks meeting the minimum requirements below shall be loaded with material for transportation to the disposal facility.

    1. For transporting wet contaminated materials, trucks shall have bed liners or sealed polyethylene sheeting to prevent possible leakage from soils.

    2. The trucks shall be completely covered during transport.

    3. Vacuum trucks and drum hauler's trucks shall be placarded with appropriate signs.

    PART 2 – PRODUCTS

    2.1 GENERAL

    A. Contractor shall not use damaged, deteriorating, or previously used materials. Contractor shall remove these materials from the work site and dispose of them properly. Damaged or defective items, as determined by the Airport shall be replaced at no cost to the Airport.

    2.2 MATERIALS

    A. Spill Control: Contractor shall provide a spill control/spill response kit including but not limited to "mini" booms, absorbent pads, and absorbent pillows. The kit shall contain sufficient quantities of the above materials to quickly contain any spill, based on container sizes used for storage of materials waiting characterization and/or disposal, which might occur during the work activities.

    B. Polyethylene: Contractor shall use high density polyethylene sheeting with a minimum thickness of 12-mil to stockpile contaminated soil on, or to line bulk removal trucks, and a 6-mil HDPE to cover soil stockpiles.

    C. Fire Extinguisher:

    1. Contractor shall supply fire extinguishers with a minimum rating of 20 B:C for each piece of equipment operating in the work area.

    2. Contractor shall be required to supply additional fire extinguishers and/or fire suppressant equipment for each work area based on the fire hazards present and work activities to be performed.

    D. Drums: Contractor shall use standard steel drums, either open head or closed head. Drum size shall be standard 55-gallon. Contractor shall label drums with standard DOT markings in accordance with CFR Title 49. Drums used during the current activities shall be destroyed upon completion of the project.

    2.3 EQUIPMENT

    A. Contractor shall use, and have available at all times, equipment for the excavation and containment of contaminated materials.

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 32

  • Section 02 61 00 | Disposal of Contaminated Soil, Sludge, And Water

    PART 3 – EXECUTION

    3.1 BULK SOLID SHIPMENT

    A. For contaminated materials being handled, transported, and disposed, contractor shall meet to the following minimum requirements.

    1. Prior to materials being transported to the disposal facility, the laboratory results from the disposal characterization samples shall be obtained from contractor.

    2. Contractor shall keep bulk solids at least 6 inches below the top of the container. The load shall be secured to prevent shifting or release and shall be covered with a tarp.

    3. Contractor shall place a placard on all vehicles used for the material being handled.

    4. Contractor shall prepare and provide drivers with a manifest and or shipping papers meeting federal and state requirements for the waste material.

    5. The manifests shall be signed by the Airport prior to the vehicles leaving the project work site.

    6. Airport may request that contractor weigh his/her vehicles to ensure that vehicle and road weight limits are not exceeded. Contractor to provide state scale tickets where applicable.

    7. Contractor shall decontaminate haul vehicle tires prior to leaving the project work site.

    8. Contractor shall monitor vehicles periodically to ensure they not release dust or vapor off site.

    9. To assure quick response to vehicle breakdowns and accidents, contractor shall have procedures in place prior to vehicles leaving the site.

    3.2 MANIFESTS FOR NONHAZARDOUS WASTE

    A. Contractor shall provide completed (except for signatures and dates) manifest forms to the Airport. The manifest forms shall be sequentially numbered. The Generator listed on the manifests, unless otherwise directed by Airport, shall be:

    San Francisco International Airport Environmental Code Branch P.O. Box 8097 San Francisco, California 94128

    Point of Contact will be established at the pre-construction meeting.

    B. Waste Manifesting Requirements and Procedures:

    1. Contractor shall prepare standard waste manifest documents for the hauling of the hazardous and nonhazardous materials from the Airport property to the disposal facility. This manifest shall include, but is not limited to:

    a. Generator's U.S. EPA ID No., (hazardous wastes only)

    b. Manifest Document No.

    c. Generator's name, address, telephone number and point of contact, as noted above

    d. Transporter's name, telephone number

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 33

  • Section 02 61 00 | Disposal of Contaminated Soil, Sludge, And Water

    e. Transporter's EPA ID No. (registered hazardous waste hauler)

    f. Disposal facility's name, address, telephone number

    g. Disposal facility's EPA ID No.

    h. The type, shipping class of material (non-regulated, if applicable)

    i. The number of containers, the total quantity of material and/or weight/volume

    j. The physical properties of the waste material/handling code

    k. Emergency contact person and telephone number in the event of a spill and/or release

    2. Contractor and/or the Airport may add additional descriptive comments such as project name, job location, contract numbers, etc. within the Special Handling Instructions block to allow for better tracking of material.

    3. The Airport shall sign and date the waste manifest prior to the removal of the excavated, stockpiled, drummed or containerized waste material from the Airport property through written permission on behalf of the Generator/Airport.

    4. Contractor (Transporter) shall sign and date the manifest, accepting the material for transportation to the disposal facility. By this signature, the Transporter certifies that he/she is in compliance with all federal, state, and local regulations, including placarding, and weight limits for the transportation of the loaded, covered, and secured waste material.

    5. Contractor (Transporter) shall provide one original and two copies of the two signature (Generator, Transporter) copies to the Airport prior to the waste leaving the Airport property.

    6. Contractor (Transporter) shall be responsible for the safe handling of the material in transit to the disposal facility.

    7. Contractor (Transporter), upon initial delivery of the material to the disposal facility, shall receive a weight ticket or similar item indicating that the material has been received by the facility. This receipt does not necessarily constitute acceptance of the material, only receipt of the material. Contractor (Transporter) shall provide an initialed and dated copy of this receipt (weight ticket) to the Airport within 5 working days of the delivery.

    8. The Contractor shall be responsible for any additional costs associated with additional characterization of the material for disposal performed by the disposal facility. Once this is complete, the disposal facility shall return a signed and dated copy of the three signature manifest (Generator, Transporter, Disposal Facility Operator) accepting the material for disposal. This shall be submitted to Airport within 15 days after delivery of the material by the Waste Transporter.

    9. Contractor shall, in the event that the material is rejected by the disposal facility, supply all labor materials and equipment to retrieve the material from the disposal facility. Costs for this retrieval, re-stockpile, re-characterization, and transportation and disposal shall be the responsibility of contractor. Contractor shall be responsible for proper manifesting of this waste using the process specified herein. Contractor shall be responsible for proper disposal of this material within 30 days of the rejection by the original disposal facility.

    10. Contractor shall advise the disposal facility that, upon treatment or destruction of the material, the facility shall submit to the Airport a letter certifying that the specific manifested waste has

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 34

  • Section 02 61 00 | Disposal of Contaminated Soil, Sludge, And Water

    been treated in accordance with all federal, state, and local regulations. This shall be submitted to the Airport within 90 days of receipt of the material by the Disposal Facility Operator unless contractor obtains specific written permission from Airport to extend this deadline.

    PART 4 – MEASUREMENT AND PAYMENT

    4.1 PRICE AND PAYMENT PROCEDURES

    A. The contractor will be compensated for all work as described under this section, acceptably performed as determined by the Contract Manager, by the respective contract bid price unit for each respective bid item.

    B. If no separate items are provided in the bid schedule for work required or described, such work shall be considered as incidental work, and compensation for such work is included in compensation for the bid items provided under this contract.

    END OF SECTION 02 61 00

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 35

  • SECTION 02 61 13 – EXCAVATION AND REMOVAL OF CONTAMINATED SOIL, SLUDGE, AND WATER

    PART 1 – GENERAL

    1.1 SUMMARY

    A. Contractor shall follow the specifications in this Document when excavating and removing contaminated soil, sludge, and water. Known areas and quantities of contaminated material have been identified. When contractor encounters contaminated material which has not been previously identified, contractor shall suspend work in the contaminated area and redeploy forces as necessary to minimize delay or disruption, until the testing has been completed and the soil, sludge, and water to be removed has been identified. If contamination occurs in separate and distinct areas, contractor may continue the Work in other areas of the project site while characterization is carried in newly discovered contamination zones.

    B. If underground fuel lines are exposed, contractor shall arrange for Contract Manager to test the soil surrounding the pipe. Contaminated soil and water associated with the pipeline shall be remediated as part of the pipeline abandonment. Fuel lines shall be removed or abandoned as defined in in the contract.

    C. Airport may, at its option, use the Airport's "On-Call" contractor to remediate the hazardous materials/waste encountered at the site. Where utilized, the "On-Call" contractor shall mobilize within 48 hours of confirmation testing of the site. The remediation will be conducted in cooperation with contractor to avoid unnecessary interference with the Work. Contractor shall cooperate with the remediation effort and shall give access to the site to the "On-Call” remediation contractor.

    D. Related Sections

    1. Document 02 61 00 – Disposal of Contaminated Soil, Sludge and Water

    1.2 CODES AND REGULATIONS

    A. General Requirements

    1. Work under this contract and other trade work in conjunction with the handling, storage, treatment, transportation and disposal of the contaminated materials shall be done in accordance with current versions of all applicable federal, state, and local laws, regulations, standards, and codes governing handling, storage, treatment, transportation, and disposal of contaminated materials.

    2. Contractor shall comply with the version in-force at the time of Work of any relevant law regulation, standard, document or code. When there is a conflict among the state, federal, and local requirements or with these Specifications, the most stringent requirements shall be used.

    3. Contractor shall have copies of all laws, standards, regulations, codes, and other applicable documents (including this document) available at the work site.

    B. Federal Requirements

    1. Occupational Safety and Health Administration (OSHA)

    a. 29 CFR, 1910

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 36

  • Section 02 61 13 | Excavation and Removal of Contaminated Soil, Sludge, And Water

    b. 29 CFR, 1910.134, General Industry Standard for Respiratory Protection

    c. 29 CFR, 1926, Construction Industry

    d. 29 CFR, 1920.2, Access to Employee Exposure and Medical Records

    e. 29 CFR, 1910.1200, Hazard Communication

    f. 29 CFR, 1910.120, Hazardous Wastes Operations and Emergency Response

    g. 29 CFR, 1926.55, Gases, Fumes, Mists and Dusts

    2. Environmental Protection Agency (EPA)

    a. 40 CFR, 268 - Land Disposal Restrictions.

    b. 40 CFR, 261 - Identification and Listing of Hazardous Waste.

    c. 40 CFR, 172 - Department of Transportation Regulations for Use of Hazardous Materials Tables and for Communications.

    d. 40 CFR, 262 - Standards Applicable to Generators of Hazardous Waste.

    e. 40 CFR, 263 - Standards Applicable to Transportation of Hazardous Waste.

    f. 40 CFR, 266 - Standards for Management of Specific Hazardous Waste, and Types of Hazardous Waste Management Facilities.

    3. Department of Transportation (DOT)

    a. CFR, 173.1090

    b. DOT 49 CFR 172

    c. DOT 40 CFR 173

    d. HM181 and HM126f

    4. State of California Requirements

    a. California State Department of Health, Division of Toxic Substances Control, California Regulation 672-10-01 – California Hazardous Waste Management Regulations

    b. California Health and Safety Code, Sections 25100 et seq. - Hazardous Waste

    c. California Labor Code, Sections 6382, Subdivision B - Hazardous Materials

    d. 22 CCR, Division 45, Environmental Health Standards for the Management of Hazardous Waste.

    e. 23 CCR, Division 3, State Water Resources Control Board.

    f. 26 CCR, Toxic Substances Control.

    1.3 REFERENCES AND STANDARDS FOR CONTAMINATED SOIL/WATER REMOVAL

    A. Definitions: The following definitions relate to the removal and disposal of contaminated soil, sludge, and water.

    1. Aboveground Release: Release to the surface of the land or to surface water.

    2. Ancillary Equipment: Devices including, but not limited to, such devices as piping, fittings, flanges, valves, and pumps used to distribute, meter, or control the flow of regulated substances to and from fuel storage facilities.

    3. Below Ground Release: Release to the subsurface of the land and to water bodies (either ground

    Division 31 – Earthwork A&E Standards: Airfield Civil, Earthwork

    Version 3.1 | March 2018 Page 37

  • Section 02 61 13 | Excavation and Removal of Contaminated Soil, Sludge, And Water

    water or surface water). This includes, but is not limited to, releases from the below ground portions of an underground storage and delivery system and below ground releases associated with overfills and transfer operations as regulated substance moves to or from a storage facility.

    4. Beneath the Surface of the Ground: Beneath the ground surface or otherwise covered with earthen materials.

    5. CERCLA: Comprehensive Environmental Response Compensation and Liability Act, 42 U.S.C. § 9601 et seq.

    6. Connected Piping: Aboveground and underground piping, including valves, elbows, joints, flanges, and flexible connectors attached to a tank system through which regulated substances flow. For the purpose of determining how much piping is connected to any individual UST system, the piping that joins two UST systems should be allocated equally between them.

    7. Discarded material: Material defined in 40 CFR, 261, that is applied to or placed on the land in a manner that constitutes disposal.

    8. Disposal: The removal of any contaminated or hazardous materials/waste from the Airport property including temporary stockpiling and storage, treatment, loading, transportation, and depositing or transferring to an approved disposal site. On-site or off-site treatment, if approved, may constitute a means of disposal.

    9. Disposal Facility: A facility or part of a facility at which contaminated or hazardous m