advanced wind power technology wind power in energy systems teemu heiskanen juhani mäkelä
TRANSCRIPT
1. Wind power integration• Transmission system• Connection methods• Integration costs• Grid planning and wind power
2. Wind power operation • Wind turbine types• Requirements for the wind turbines• System stability and balance
3. Cases• Lapland• Meri-Lappi• Europe 2050
1. Wind power integration• Transmission system• Connection methods• Integration costs• Grid planning and wind power
2. Wind power operation • Wind turbine types• Requirements for the wind turbines• System stability and balance
3. Cases• Lapland• Meri-Lappi• Europe 2050
Transmission Grid Characteristics• Operated, maintained and
developed by Fingrid Oyj• Comprises 400/220/110 kV
power lines, substations, and cross-border connections
• Circular structure improves reliability
• Huge investment program 2010-2020 – nuclear and wind power
integration– Replacement of transmission
grid reaching the end of its life cycle
Source: Fingrid
Grid connection solutions
Substation connectionLine connection (<25MW)
Less expensive
Fingrid prefers substation connections
Hinders operational reliability
Takes transmission capacity
Connection point Connection point
Source: Fingrid
Grid connection solution Connection fee
Connection to a 110 kV transmission line
<25 MW connection: 0,5 m€
<25 MW connection: Not allowed
Connection to an existing substation
400kV: 2,0 m€
220 kV: 1,2 m€
110 kV: 0,6 m€
Connection to a new substation
For a single player: All construction costs
For multiple players: As for existing substations
Integration Costs
In addition, 150000 €/km for transmission lines
Source: Fingrid
Wind power projects: effect on grid planning
Wind projects have high uncertainty
• Especially the subsidy cutoff at 2500 MW
• Capacity allocation via letters of intent and connection contracts
Small wind parks are faster to build than a substation
• Need for temporary solutions
Wind projects in the same area can be in different phases
• Challenges for cooperation in connection costs
1. Wind power integration• Transmission system• Connection methods• Integration costs• Grid planning and wind power
2. Wind power operation • Wind turbine types• Requirements for the wind turbines• System stability and balance
3. Cases• Lapland• Meri-Lappi• Europe 2050
• Variable speed• Good voltage
and reactive power control
• Fixed speed• Draws reactive
power from the grid
• Slight voltage and reactive power control
Source: EWEA
Wind turbine on the grid
• Tolerance (U, f, Fault ride through)
• Reactive power control• Active power and
frequency response• Protective devices• Visibility
Source: Fingrid
Grid codes: Requirements for the wind turbines
Production variation
Wind power effects on the grid
Source: National Grid; WIREs Energy Environ 2012
Less inertia
1. Wind power integration• Transmission system• Connection methods• Integration costs• Grid planning and wind power
2. Wind power operation • Wind turbine types• Requirements for the wind turbines• System stability and balance
3. Cases• Lapland• Meri-Lappi• Europe 2050
In Lapland there is at the moment over 400 MW of over capacity
A failure in the blue marked 220 kV line: the wind power has to be transfered through Petäjäkoski.Transfer distance is now almost 400 km, which leads to very unstable situation.
Solution: Connect more capacity from the wind parks straight to Pirttikoski substation.
Case Keminmaa
Source: Fingrid
Case Meri-Lappi
Problem:
Grid has to be built to serve the future purpose but the grid projects takes years to construct and are expensive.
…Is the wind production going to boom or not?
Source: Fingrid
Case Meri-Lappi
Solution:
Improve the grid piece by piece:
1. Replace lines to more heat resistant ones
2. Reinforce the bottle necks
3. Build more 110 kV or 400 kV lines next to the old ones4. Temporary connections
Source: Fingrid