adjudication
TRANSCRIPT
Dr. Sherif EL-Haggan ([email protected])
Contract Administration & Arbitration Bureau (CAB) ١
١
FIDIC Middle East Contract Users’ Conference
Abu Dhabi 24 – 25 February 2010
Dispute Resolution - Latest Developments(Adjudication)
Dr. Sherif EL-HagganFCIArb, London / Ph.D., Sheffield University
Founder/Director, Contract Administration & Arbitration Bureau (CAB)Professor, The American University in Cairo
٢
Adjudication
ContractualStatutory
٣
Contractual Adjudication - Dispute Boards
٤
1996 � FIDIC adopted Dispute Adjudication Board
(DAB) � replaces the Engineer’s quasi arbitrator
role (ICE Clause 66 + FIDIC Red Book Clause 67).
The Dispute Board (DB) concept originated in the 1960’s
in the USA in the form of a Dispute Review Board (DRB).
Dr. Sherif EL-Haggan ([email protected])
Contract Administration & Arbitration Bureau (CAB) ٢
٥
Types of Dispute Boards
• Dispute Review Board � DRB
• Dispute Adjudication Board � DAB
• Combined Dispute Board � CDB
٦
Dispute Review Board (DRB)
The DRB issues ‘Recommendations’ with respect to any
dispute referred to it.
If no party expresses dissatisfaction with a
Recommendation within a stated time period, the parties
contractually agree to comply with the Recommendation.
If a party expresses dissatisfaction with the
Recommendation within such time period, that party may
refer the dispute to arbitration or the courts.
Pending a ruling by the arbitral tribunal or at the court, the
parties may voluntarily comply with the Recommendation
but are not bound to do so.
٧
Dispute Adjudication Board (DAB)
The DAB issues ‘Decisions’ with respect to disputes
referred to it.
The parties must comply with Decisions without delay.
If a party expresses dissatisfaction with a Decision within a
stated time period, it may refer the dispute to arbitration or
to the courts.
If no party expresses dissatisfaction with a Decision within
the stated time period, the parties contractually agree to
remain bound by it. ٨
The DAB has 4 main functions:
• Visit the site periodically & become familiar with
project.
• Keep up to date with progress & problems.
• Encourage the resolution of disputes.
• When a dispute is referred to it, prepare a
Decision in timely manner.
Dr. Sherif EL-Haggan ([email protected])
Contract Administration & Arbitration Bureau (CAB) ٣
٩
The existence of a readily available mutually acceptable
impartial board promotes agreement.
Participants do not want to lose their credibility with the
DAB by taking extreme positions.
Accumulation of claims is minimized.
١٠
The process encourages a win-win rather than a win-
lose philosophy.
Decisions not implemented may form the basis for
negotiated settlements.
DAB Decision is a condition precedent to the
commencement of arbitration proceedings.
The Decision is admissible in evidence in arbitration.
١١
Reasoning is an essential part of the decision.
May persuade the parties that the DAB studied all
relevant matters & reached a conclusion similar to that
which may be expected from an arbitrator.
The Reasoning
١٢
They also serve who only stand & wait
Members serve even when they wait & become an
instrument of dispute avoidance or at least minimising the
outbreak of disputes.
Quotation from one of John Milton’s sonnets (1673)
Dr. Sherif EL-Haggan ([email protected])
Contract Administration & Arbitration Bureau (CAB) ٤
١٣
FIDIC 1999 SuiteMulti-tier Dispute Resolution
١٤
1. Engineer endeavours to reach agreement
(mediator?)
2. Engineer’s Fair Determination
3. Adjudication
4. Amicable settlement � mediation?
then, if necessary,
5. Arbitration
١٥
Statutory Adjudication
١٦
Adjudication was given a boost following Sir Michael
Latham’s attention to two serious problems:
1. poor cash flow due to delays in payment by employers
2. arbitrary unsubstantiated withholding of monies
Constructing the Team (1994)(Sir Michael Latham)
Housing Grants Construction & Regeneration Act
(1996)
Dr. Sherif EL-Haggan ([email protected])
Contract Administration & Arbitration Bureau (CAB) ٥
١٧
The 1996 Act entitles a party to require that a dispute
be immediately referred to adjudication.
Courts decided that summary judgement could
be used to enforce an adjudicator’s decision.
١٨
Provided the adjudicator:
1.has jurisdiction &
2.has conducted the adjudication fairly
chances of a decision being set aside are remote
Adjudication succeeded in preventing the party which
is in the stronger position from abusing that position
١٩
Cases
٢٠
Macob Civil Engineering -v- Morrison Construction Ltd.
An adjudicator’s decision is enforceable by summary
judgement and shall not be stayed by a challenge that the
dispute is referable to arbitration.
Outwing Construction Ltd. -v- H. Randell & Son Ltd.
An adjudicator’s decision properly made should be complied
with fully and promptly,
Dr. Sherif EL-Haggan ([email protected])
Contract Administration & Arbitration Bureau (CAB) ٦
٢١
A & D Maintenance & Construction Ltd. -v- Pagehurst
Construction Services Ltd.
The courts can not open up an adjudicator’s decision if the
adjudicator is properly appointed and stays within his remit.
Grovedeck Ltd -v- Capitol Demolition
The court held that the adjudicator had no jurisdiction
because the contract did not fall within the definition of
construction contract as defined in the Act.
٢٢
Bloor Construction -v- Bowmer and Kirkland
If an arbitrator makes a clerical error, accidental slip or
omission when making his or her award, the arbitrator on
application of one of the parties is empowered under The
Arbitration Act 1996 to make a correction.
It was held by the court that an adjudicator would have a
similar power even though no such power was referred to
in the Act or the Scheme For Construction Contracts.
٢٣
Fastrack Contractors Ltd -v- Morrison Construction Ltd
The main contractor contested the adjudicator’s jurisdiction
on the basis that there was no dispute.
It was the court’s view that a dispute arose when a claim
had been notified and rejected. A dispute could be about
what sum was due rather than whether a particular amount
was due.
The court held that the adjudicator had jurisdiction as a
dispute existed between the parties.
٢٤
Homer and Burgess Ltd -v- Chirex (Annan) Ltd
The adjudicator’s award was not wholly unenforceable and
the court had to decide whether it should itself decide how
much of the adjudicator’s decision should be paid or refer it
back to the adjudicator.
On balance the court considered time would be saved in
referring the matter back to the adjudicator.