addendum number two date: may 03, 2018 project: …

26
LAND PLANNERS LANDSCAPE ARCHITECTS CIVIL ENGINEERS MUNICIPAL PLANNING LAND SURVEYORS Page 1 of 4 4174 Silver Peak Parkway, Suwanee, GA 30024 OFFICE. 770-932-6550 FAX. 770-932-6551 www.GOMDA.net ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: Graves Park Amenities Gwinnett County Parks and Recreation BID NO: BL044-18 This addendum supersedes and supplements all portions of the bidding documents and becomes part of the Contract Documents for the above-referenced project. Where any item called for in the specifications or indicated on the drawings is not supplemented hereby, the original requirements shall remain in effect. Where any original item is amended, voided, or superseded hereby, the provision of such item not so specifically amended, voided, or superseded shall remain in effect. Failure to acknowledge this addendum in the Bid Schedule may result in Bid being deemed non- responsive. ITEM NO. 1 GENERAL STATEMENTS / CLARIFICATIONS: 1. THE DEADLINE FOR BIDS HAS BEEN EXTENDED TO WEDNESDAY, MAY 9, 2018 AT 2:50 P.M., LOCAL TIME. 2. CDBG requirements will need to be considered in the bid, including but not limited to Davis- Bacon Wage rates. See Division 00 of the specifications for additional information. 3. The splashpad is to have a sand blast finish with approval of finish required prior to installation. See Section 03-3001 for additional information. 4. Public access will need to be maintained to the restroom facilities during the course of the construction project. During the time that the restrooms are being switched from septic tank and drain field to sanitary sewer, portable facilities will need to be provided for public use by the contractor. See Sheet C201 for additional information. 5. The Unit Price quantities and Costs listed in the bid schedule are to be included in the base bid. 6. The two bridges are designed to withstand the loading of a Gator-type utility vehicle. The bridges are not designed for vehicles exceeding this weight. 7. The Field Office requirements, in Specification Section 01-5213 Field Offices and Sheds, have been updated. The Section is attached as part of this Addendum.

Upload: others

Post on 18-Dec-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

LAND PLANNERS │ LANDSCAPE ARCHITECTS │ CIVIL ENGINEERS

MUNICIPAL PLANNING │ LAND SURVEYORS Page 1 of 4

4174 Silver Peak Parkway, Suwanee, GA 30024

OFFICE. 770-932-6550 FAX. 770-932-6551 www.GOMDA.net

ADDENDUM NUMBER TWO

DATE: May 03, 2018

PROJECT: Graves Park Amenities

Gwinnett County Parks and Recreation

BID NO: BL044-18

This addendum supersedes and supplements all portions of the bidding documents and becomes part of

the Contract Documents for the above-referenced project.

Where any item called for in the specifications or indicated on the drawings is not supplemented

hereby, the original requirements shall remain in effect.

Where any original item is amended, voided, or superseded hereby, the provision of such item not so

specifically amended, voided, or superseded shall remain in effect.

Failure to acknowledge this addendum in the Bid Schedule may result in Bid being deemed non-

responsive.

ITEM NO. 1

GENERAL STATEMENTS / CLARIFICATIONS:

1. THE DEADLINE FOR BIDS HAS BEEN EXTENDED TO WEDNESDAY, MAY 9, 2018

AT 2:50 P.M., LOCAL TIME.

2. CDBG requirements will need to be considered in the bid, including but not limited to Davis-

Bacon Wage rates. See Division 00 of the specifications for additional information.

3. The splashpad is to have a sand blast finish with approval of finish required prior to installation.

See Section 03-3001 for additional information.

4. Public access will need to be maintained to the restroom facilities during the course of the

construction project. During the time that the restrooms are being switched from septic tank and

drain field to sanitary sewer, portable facilities will need to be provided for public use by the

contractor. See Sheet C201 for additional information.

5. The Unit Price quantities and Costs listed in the bid schedule are to be included in the base bid.

6. The two bridges are designed to withstand the loading of a Gator-type utility vehicle. The bridges

are not designed for vehicles exceeding this weight.

7. The Field Office requirements, in Specification Section 01-5213 Field Offices and Sheds, have

been updated. The Section is attached as part of this Addendum.

Page 2: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

Graves Park Amenities Gwinnett County

Addendum No. 2, 05/02/18 BL044-18

LAND PLANNERS │ LANDSCAPE ARCHITECTS │ CIVIL ENGINEERS

MUNICIPAL PLANNING │ LAND SURVEYORS Page 2 of 4

ITEM NO. 2

QUESTIONS:

The following questions have been received and are answered as follows:

1. What is the project budget?

Answer: There is approved funding for this project. Gwinnett County expects each contractor to bid

a competitive price. Award will be made to the lowest responsive and responsible bidder.

2. I see the bridges are wooden, can we offer a steel bridge with a wooden deck and railing as an

alternate?

Answer: Prepare your bid based on the wooden bridge as designed. Any Changes to the bridge

design after the contract is executed would require approval of the engineer, and be at no additional

cost to the owner.

3. Also, I only saw drawings for one bridge do you know what page the second is on, or are there two of

the same? The first one is on page 49(C303).

Answer: The details for both bridges are on sheet C805. The curb rail detail (1/C805) applies only

when the height of the bridge is less than 30 inches. Both bridges appear on Sheet C303 – Site Plan

(Trail).

4. Civil drawing details show 4” but structural drawing 12/S301 indicates 6” concrete pad. Please verify

the Splash pad concrete thickness.

Answer: The structural drawings are for the splashpad concrete and 6 inches is the correct

thickness. The Civil drawings only depict the site concrete adjacent to the splashpad. See Section

03-3001 for additional information on the concrete for the splashpad.

5. Please verify if the concrete strip at the bottom of chain link fence is required all around the soccer

field as indicated in 1/C803 & 3/C103.

Answer: Per Detail 1 on Sheet C803, the mowing strip is to be installed under all of the 10 foot

fencing. The mowing strip will also be under the 6 foot fences to the north and south of the field.

Sheets C302 and C803 are being re-issued with this Addendum to clarify this condition.

6. Does the stated mulch quantity in landscape drawings include the temporary trail surface mulch?

Answer: No, the quantity is not included in the Landscape Quantities. All quantities are the

responsibility of the contractor. Mulch trail must be 6 feet wide and 3 inches deep minimum.

Quantity should be included in the base bid. See Sheet C201.

7. On sheet C603, the detail for the compost filter sock seems to be missing.

Answer: This is a standard GSWCC Detail. It was missing the bid set; a copy of the detail is

included in this Addendum.

8. Will the Soccer Field installer need to be a sportsfield installer?

Answer: No, but the field will be laser graded. See Section 32-0513 of the Specifications for

additional information.

Page 3: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

Graves Park Amenities Gwinnett County

Addendum No. 2, 05/02/18 BL044-18

LAND PLANNERS │ LANDSCAPE ARCHITECTS │ CIVIL ENGINEERS

MUNICIPAL PLANNING │ LAND SURVEYORS Page 3 of 4

9. What is the bid depth for the helical piles at the bridges?

Answer: See detail on Sheet C805 – each pile to be installed to a minimum depth of 26 vertical feet.

A Unit Price has been added to Section 01-2200 and the Bid Schedule to provide for the adjustment

of depth of the helical piles. Paragraph 1.4B regarding Helical Piles has been added to Section 01-

2200. These revised sections are included as part of this Addendum.

10. Will the structural engineer be present for inspections during the construction of the splashpad

concrete?

Answer: Yes

11. What is the extent of the temporary fencing?

Answer: Tree protection fence is shown on sheet C101. Temporary chain link fence is shown on sheet

C201. Temporary chain link fence is required for the splashpad construction area, but may be needed

elsewhere. It is up to the contractor to protect active construction areas from the public. The park

will be open to the public during construction. See the notes on Sheet C201.

12. What fees is the contractor responsible for paying?

Answer: The County has paid the Land Disturbance Permit fees. The contractor will be responsible

for paying any other permit fees required during construction. See the Special Provisions of the

General Conditions for more information.

13. Will the Notes on Sheet C303 regarding the qualifications of the Trail Builder be enforced?

Answer: Yes. Note that the trail is to be constructed with minimal disturbance to the existing wooded

area.

14. What is the soil mix for the soccer field?

Answer: As noted on Sheet C302, this mix is described in Section 32-0513 of the Specifications.

15. Does the mulch used for the temporary trails need to be removed at the end of the project?

Answer: Yes, it will need to be removed and the area restored to a stable state per the Landscape

and Erosion Control plans.

Attachment(s):

• Pre-Bid Conference Sign-in Sheet

• Pre-Bid Handout

• Revised Bid Schedule

• Specification Section 01-2200 Unit Prices

• Specification Section 01-5213 Field Offices and Sheds

• Civil Drawings C302 and C803

• Sd1-B Composite Filter Sock Detail

Page 4: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

Graves Park Amenities Gwinnett County

Addendum No. 2, 05/02/18 BL044-18

LAND PLANNERS │ LANDSCAPE ARCHITECTS │ CIVIL ENGINEERS

MUNICIPAL PLANNING │ LAND SURVEYORS Page 4 of 4

Receipt of this addendum should be acknowledged on the bid schedule. It is the bidder’s responsibility to ensure

that they have all applicable addenda prior to bid submittal.

END OF ADDENDUM

Page 5: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …
Page 6: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …
Page 7: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …
Page 8: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA PAGE 13R

GRAVES PARK AMENITIES BL044-18

FAILURE TO RETURN THIS PAGE AS PART OF YOUR

BID DOCUMENT MAY RESULT IN REJECTION OF BID.

BID SCHEDULE

The Bidder has carefully examined and fully understands the Contract, Plans and Specifications and other

Documents hereto attached, and has made a personal examination of the Site of the proposed Work, and has

satisfied himself as to the actual conditions and requirements of the Work, and hereby proposes and agrees that

if his bid is accepted, he will contract with Gwinnett County according to bidding Documents entitled Graves

Park Amenities and Addenda, as well as the existing conditions of the project, and conditions affecting the

Work, the undersigned proposes to furnish all services, labor and materials required by them in accord with said

documents, personal observations of the site conditions, including the total sums for Unit Price Items A through

I below, for the sum as follows:

($_________________________), which sum is hereinafter called "Base Bid".

The Undersigned agrees to commence work within 10 days of the date of Notice to Proceed issued by Gwinnett

County Purchasing Office and to commit adequate forces on site to fully complete all Work, including punch list

items and clean-up, as determined by the County, within 300 calendar days. Gwinnett County will charge the

Contractor One Thousand Dollars and no cents ($1,000.00) per day for liquidated damages for every day beyond

300 calendar days that the Work is not complete.

REVISED UNIT PRICE SCHEDULE

Should rock or other unforeseen conditions be encountered, and for other indicated construction items, the

Base Bid shall include performing the work below. The stated unit prices are for items in excess of what is

indicated on the drawings and include only those items listed in Section 012200, Unit Prices.

The following Unit Price Schedule is FULLY INCLUDED IN THE BASE LUMP SUM BID PRICE. These Unit Prices are

to be used as directed by the Owner’s Representative. If actual cost is more than or less than the Unit Price

Totals, the Contract shall be adjusted accordingly by Change Order. Unit Price Items are in addition to quantities

that are illustrated, described or inferred as part of the Bid Drawings and Specifications.

Base Bid includes all work described in the project description and items A through O described below. The total

cost amounts for the estimated quantities below are included in the Base Bid.

Estimated Unit

No. Item Unit Quantity Price Total

A. Rock (Open Excavation) CY 250 ________ _________

B. Rock (Trench Excavation) CY 150 ________ _________

C. Excavation of unsatisfactory materials

and replacement w/suitable soil material CY 750 ________ _________

D. Excavation of unsatisfactory materials

and replacement w/ #57 crushed stone CY 200 ________ _________

Company _______________________________________________________________

Page 9: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA PAGE 14R

GRAVES PARK AMENITIES BL044-18

FAILURE TO RETURN THIS PAGE AS PART OF YOUR

BID DOCUMENT MAY RESULT IN REJECTION OF BID.

Estimated Unit

No. Item Unit Quantity Price Total

E. Excavation of unsatisfactory materials

and replace with surge stone CY 200 ________ _________

F. Construct and Remove Stone Check Dam,

per Cd/C603 EA 10 ________ _________

G. Decorative Bollards, per 5/C808 EA 6 ________ _________

H. Silt Fence – Type “C”, per Sd1-S/C602 LF 1,000 ________ _________

I. Add’l Erosion Control Fabric,

per Ss/C604 and Specifications SY 200 ________ _________

J. Add’l 419 Bermuda sod SF 10,000 ________ _________

K. Planting of Trees EA 25 ________ _________

L. Installation of Type B Benches, per 3/C807 EA 5 ________ _________

M. Installation of Trail Drains, per 7/C800 EA 5 ________ _________

N. Installation of 4’ Fence, per 4/C800 LF 250 ________ _________

O. Installation of Pasture Fence, per 2/C806 LF 100 ________ _________

P. Additional Installation Depth for Helical Piles VF 144 ________ _________

The undersigned represents that the unit prices listed above are complete as specified in Section 01 2200 Unit

Prices, acknowledges that the quantities are not guaranteed, and agrees that payment will be for actual in-place

quantities installed in addition to what is shown on the plans and as directed by the County. Prices must be

entered for all blanks in the schedule. If there is an error in the calculation for the total amount entered, the bid

unit price multiplied by the Estimated Quantity will be the bid amount that is considered included in the Base

Bid.

Removal of rock or providing items A through O in excess of the estimated amount will be paid at the unit price,

upon verification by the County's geotechnical firm and/or site representative.

The quantity of rock and/or unsatisfactory materials will be verified by the County's representative or

geotechnical firm. Should the amount included in the Base Bid for any of items A through O not be

encountered, a change order will be initiated to refund to the County the difference at the bid unit price.

SCHEDULE OF ALTERNATES

No Alternates are included in this Bid.

[Contractor Information next page]

Company _____________________________________________________________

Page 10: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-1 GRAVES PARK AMENITIES BL044-18

SECTION 01 2200

UNIT PRICES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes

1. Unit price work.

2. List of Unit Prices.

3. Procedures for unit price work.

B. Measurement and payment criteria applicable to Work performed under a Unit Price Payment

method. (See Bid Schedule Items)

C. Defect assessment and non-payment for rejected work.

1.2 COSTS INCLUDED

A. Unit Prices included on the Bid Schedule shall include full compensation for all required labor,

products, tools, equipment, plant, transportation, services and incidentals; erection,

application or installation of an item of the Work; overhead and profit.

1.3 RELATED SECTIONS

A. Application for payment: As outlined in General Conditions and Bid Schedule.

B. Procedures for modifications to the contract: As outlined in the General Conditions.

C. Section 01 4525 Structural Testing / Inspecting Agency Services – Procedure for utilization of

testing and inspection: As outlined in Specifications.

D. Section 01 7700 Contract Close-out: As outlined in Specifications.

1.4 UNIT QUANTITIES SPECIFIED

A. Quantities indicated in the Bid Schedule are for bidding and contract purposes only.

Quantities and measurements of actual Work in addition to what is indicated on the Drawings

will determine the payment amount. The quantities and costs associated with the quantities

in the Bid Schedule are in addition to the items indicated on the Drawings and in the

Specifications. These costs shall be included in the Base Bid amount, but will only be paid for

if quantities in excess of what are shown on the Drawings are ordered or approved by the

Owner. Reference 01-2200 1.4B for information regarding the Helical Piles.

B. Helical Piles: Include the cost of the minimum 26 vertical feet (V.F.) for each pile (12 total

piles) and the additional estimated vertical feet in the base bid. Provide a unit cost per V.F. of

pile. The Helical Piles are a design build portion of the project. If in situ conditions warrant an

adjustment of depth, per the recommendation of the geotechnical engineer, to obtain the

allowable bearing pressure then the vertical footage of the pile shall be adjusted accordingly.

Page 11: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-2 GRAVES PARK AMENITIES BL044-18

Install the piles in the presence of the geotechnical engineer to verify depths and bearing

pressures. Furnish any pile design revision, along with the geotechnical recommendations to

the Owner’s representative for approval. The unit price provided will be used to adjust the

quantities to match those installed and quantified by the geotechnical engineer.

1.5 MEASUREMENT OF QUANTITIES

A. Measurement methods delineated in the individual specification sections complement the

criteria of this section. In the event of conflict, the requirements of the individual specification

section govern.

B. Take all measurements and compute quantities. Measurements and quantities will be verified

by Owner’s Representative.

C. Assist by providing necessary equipment, workers, and survey personnel as required.

D. Perform surveys required to determine quantities, including control surveys to establish

measurement reference lines.

E. Reference 01-2200 1.4B for information regarding the Helical Piles.

1.6 PAYMENT

A. Payment for Work governed by unit prices will be made on the basis of actual measurements

and quantities of Work which is incorporated in or made necessary by the Work and accepted

by the Owner’s Representative, multiplied by the unit sum / price.

B. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from the transporting vehicle.

4. Products placed beyond the lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

7. Items described or illustrated in the drawings that are not considered additional.

8. Reference 01-2200 1.4B for information regarding the Helical Piles.

1.7 DEFECT ASSESSMENT

A. Replace Work, or portions of the Work, not conforming to specified requirements.

B. If, in the opinion of the Owner’s Representative, it is not practical to remove and replace the

Work, Owner’s Representative will direct on the following remedies:

1. The defective Work will be partially repaired to the instructions of the Owner’s

Representative.

2. The Unit sum / price will be adjusted to a new sum / price at the discretion of the Owner’s

Representative.

Page 12: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-3 GRAVES PARK AMENITIES BL044-18

1.8 UNIT PRICE LIST

A. Unit Price No. 1: Rock, Open Excavation

1. Removal of mass rock encountered and requiring excavation as defined in the

specifications.

2. Purpose: To adjust the contract sum when actual quantity is determined.

3. Quantity to be indicated in contract sum: 250 cubic yards

4. Unit of measurement: Cubic Yard

5. Include only the following in the unit price:

a. Excavation to plan subgrade

b. Hauling and disposal off site

c. Cost of providing sufficient quantity of suitable offsite fill material to replace the rock

removed from subgrade to original level of rock

d. Overhead and profit.

6. Include all other cost in the contract base bid.

7. Method of measurement: Measurement will be made and verified by the County for

actual quantities as outlined in the specifications.

B. Unit Price No. 2: Rock, Trench Excavation

1. Removal of trench rock encountered and requiring excavation as defined in the

specifications.

2. Purpose: To adjust the contract sum when actual quantity is determined.

3. Quantity to be indicated in contract sum: 150 cubic yards

4. Unit of measurement: Cubic Yard

5. Include only the following in the unit price:

a. Excavation to 6” below plan subgrade, or below as defined in the specifications

b. Hauling and disposal off site

c. Cost of providing sufficient quantity of suitable offsite fill material to replace rock

removed from 6” below subgrade to original level of rock

d. Overhead and profit.

6. Include all other cost in the contract base bid.

7. Method of measurement: Measurement will be made and verified by the County for

actual quantities as outlined in the specifications.

C. Unit Price No. 3: Excavation of Unsatisfactory Materials and replacement with suitable soil

material

1. Removal of unsatisfactory materials encountered and requiring excavation and

replacement with suitable soil material to subgrade shown on drawings

2. Purpose: To adjust the contract sum when actual quantity is determined.

3. Quantity to be indicated in contract sum: 750 cubic yards

4. Unit of measurement: Cubic Yard

5. Include only the following in the unit price:

a. Excavation as directed by the County

b. Hauling and disposal off site

c. Cost of providing from offsite sufficient and suitable fill material to subgrade, and for

replacement quantity of all unsuitable material removed

d. Overhead and profit

6. Include all other cost in the contract base bid.

7. Method of measurement: Measurement will be made as outlined in the specifications for

actual quantities and verified by the County.

Page 13: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-4 GRAVES PARK AMENITIES BL044-18

D. Unit Price No. 4: Excavation of Unsatisfactory Material and replacement with #57 crushed

stone

1. Removal of unsatisfactory materials encounter and requiring excavation and replacement

with #57 crushed stone to subgrade shown on drawings

2. Purpose: To adjust the contract sum when actual quantity is determined.

3. Quantity to be indicated in contract sum: 200 cubic yards

4. Unit of measurement: Cubic Yard

5. Include only the following in the unit price:

a. Excavation as directed by the County

b. Hauling and disposal off site

c. Cost of providing sufficient and suitable #57 crushed stone to subgrade, and for

suitable fill material from offsite for replacement of all unsuitable material removed

above subgrade

d. Overhead and profit.

6. Include all other cost in the contract base bid.

7. Method of measurement: Measurement will be made for actual quantities as outlined in

the specifications and verified by the County.

E. Unit Price No. 5: Excavation of Unsatisfactory Material and replacement with Surge Stone

1. Removal of unsatisfactory material encountered and replacement with surge stone to

subgrade shown on drawings.

2. Purpose: To adjust the contract sum when actual quantity is determined

3. Quantity to be indicated in contract sum: 200 cubic yards

4. Unit of measurement: Cubic Yard

5. Include only the following in the unit price:

a. Excavation as directed by the County

b. Hauling and disposal off site

c. Cost of providing sufficient and suitable Surge Stone to subgrade, and for suitable fill

material from offsite for replacement of all unsuitable material removed above

subgrade

d. Overhead and profit.

6. Include all other cost in the contract base bid.

7. Method of measurement: Measurement will be made for actual quantities as outlined in

the specifications and verified by the County.

F. Unit Price No. 6: Construct and Remove Stone Check Dam (per Cd/ C603)

1. Construction of Erosion Check dams in addition to those indicated on the drawings.

2. Purpose: To adjust the contract sum for actual quantity used.

3. Quantity to be included in contract sum: 10.

4. Unit of Measurement: Each.

5. Include only the following in the unit price:

a. Material and construction of dam.

b. Refer to detail Cd/ C603 – location(s) to be determined by owner

c. Maintenance, repair, and removal of dam.

d. Overhead and profit.

6. Include all other costs in the contract base bid.

7. Method of measurement: Actual quantity installed in addition to what is shown on the

drawings that is authorized prior to start of work by Owner’s Representative.

Page 14: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-5 GRAVES PARK AMENITIES BL044-18

G. Unit Price No. 7: Decorative Bollards (per 5 / C808)

1. Construction of Pipe Bollards in addition to those shown on the drawings, as directed by

the County.

2. Purpose: To adjust the contract sum for actual quantity used.

3. Quantity to be included in contract sum: 6.

4. Unit of Measurement: Each.

5. Include only the following in the unit price.

a. Material and installation of Steel Pipe Bollard

b. Refer to detail 5 / C808 - location(s) to be determined by owner

c. Overhead and profit.

6. Include all other costs in the contract base bid.

7. Method of measurement: Actual quantity installed in addition to what is shown on the

drawings that is authorized prior to start of work by Owner’s Representative.

H. Unit Price No. 8: Silt Fence Type “C,” (per Sd1-S / C602)

1. This item is for Silt Fence in excess of that shown or described on the Drawings only.

2. Construction of Silt Fence Type “C” in addition to that shown on the drawings and / or as

directed by the County’s representative.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Quantity to be included in contract sum: 1,000 linear feet.

5. Unit of Measurement: Linear feet.

6. Include only the following in the unit price:

a. Material and installation of Silt Fence Type “C.” Refer to detail Sd1-S / C602.

b. Maintenance, repair, replacement and removal of silt fence.

c. Overhead and profit.

7. Include all other costs in the contract base bid.

8. Seventy-five percent of the Contract Price bid per linear foot will be paid when fence is

complete in place. The remaining twenty-five percent will be paid after removal when

area is stabilized or upon acceptance by the County.

9. Method of measurement: Actual quantity installed in addition to what is shown on the

drawings that is authorized prior to start of work by Owner’s Representative.

I. Unit Price No. 9: Additional Erosion Control Fabric, (per Ss / C604 and Section 31 2500)

1. This item is for Fabric in excess of that shown or described on the Drawings only.

2. Placement of erosion control fabric in addition to areas shown in the drawings and

specifications as directed by the County’s representative.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 200 square yards

5. Unit of measurement: Square yards

6. Include only the following in the unit price:

a. Cost of providing and installing geotextile fabric, overhead and profit.

b. Refer to detail Ss / C604.

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for areas requiring permanent

stabilization (not temporary stabilization during construction at the contractor’s

discretion) and verified by the County. Payment will be made for actual ground coverage

area installed (not for quantity required to meet manufacturer’s recommendations, to

overcome overlap, waste, etc.) and authorized prior to start of work by County’s

representative.

Page 15: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-6 GRAVES PARK AMENITIES BL044-18

J. Unit Price No. 10: Additional 419 Bermuda Sod

1. This item is for Sod in excess of that shown on the Drawings only.

2. Preparation of fine graded topsoil surface and placement of additional sod from that

described and shown in the drawings and specifications as directed by the County’s

representative.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 10,000 square feet

5. Unit of measurement: Square Feet

6. Include only the following in the unit price:

a. Cost of ground preparation, providing, installing and maintaining sod until fully rooted

in.

b. Includes all ancillary materials and labor to complete the installation.

c. Overhead and profit

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for actual square feet of additional

sod installed by the Contractor and verified by the County.

K. Unit Price No. 11: Planting of Trees

1. This item is for planting in excess of that shown on the Drawings only.

2. Preparation of fine graded topsoil surface and planting of 1 ½” caliper native hardwood

shade trees as directed by the County’s representative. Examples of tree types include:

White Oak, Red Oak, Red Maple and Beech.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 25 trees.

5. Unit of measurement: Each

6. Include only the following in the unit price:

a. Cost of ground preparation, providing, installing and maintaining trees until substantial

completion, or a minimum of 60 days after installation, whichever is longer.

b. Includes all ancillary materials and labor to complete the installation.

c. Overhead and profit.

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for actual additional trees installed

by the Contractor and verified by the County.

L. Unit Price No. 12: Installation of Type B Benches (per 3 / C807)

1. This item is for benches in excess of those shown on the Drawings only.

2. Construction of concrete bench pad and installation of new Type B bench as directed by

the County’s representative.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 5 benches.

5. Unit of measurement: Each

6. Include only the following in the unit price:

a. Cost of ground preparation, construction of concrete bench pad, provide new bench

and install bench.

b. Includes all ancillary materials and labor to complete the installation.

c. Overhead and profit.

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for number of additional benches

installed by the Contractor and verified by the County.

Page 16: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-7 GRAVES PARK AMENITIES BL044-18

M. Unit Price No. 13: Installation of Trail Drain

1. This item is for Trail Drain as directed by the County’s representative.

2. Construction of 20’ long 12” HDPE corrugated dual wall drainage pipe with flared end

sections as directed by the County’s representative. Use Trail Drain Detail 7/C800 and

described in Section 32 1625 2.1E.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 5 trail drains.

5. Unit of measurement: Each

6. Include only the following in the unit price:

a. Cost of ground preparation, installation of pipe, flared end sections and medium river

rounds, provide new pipe and flared end sections.

b. Includes all ancillary materials and labor to complete the installation.

c. Overhead and profit.

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for number of additional trail drains

installed and verified by the County.

N. Unit Price No. 14: Installation of 4’ ht. Vinyl Coated Chain-Link Fence (per 4/C800)

1. This item is for 4’ fence in excess of that shown on the Drawings only.

2. Construction of 4’ Black Vinyl Coated Chain-Link Fence.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 250 lf of fence.

5. Unit of measurement: Linear Foot

6. Include only the following in the unit price:

a. Cost of ground preparation, installation of posts and fabric, provide new post, fabric

and hardware.

b. Includes all ancillary materials and labor to complete the installation.

c. Refer to detail 4/C800.

d. Overhead and profit.

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for additional linear feet of fence

installed by the Contractor and verified by the County.

O. Unit Price No. 15: Installation of Pasture Fence (per 2/C806)

1. This item is for Pasture Fence in excess of that shown on the Drawings only.

2. Construction of Pasture Fence.

3. Purpose: To adjust the contract sum when actual quantity is determined.

4. Estimated quantity to be added in contract sum: 100 lf of fence.

5. Unit of measurement: Linear Foot

6. Include only the following in the unit price:

a. Cost of ground preparation, installation of posts and fabric, provide new post, fabric

and hardware.

b. Includes all ancillary materials and labor to complete the installation.

c. Refer to detail 2/C806.

d. Overhead and profit.

7. Include all other cost in the contract base bid.

8. Method of measurement: Measurement will be made for additional linear feet of fence

installed by the Contractor and verified by the County.

Page 17: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-8 GRAVES PARK AMENITIES BL044-18

P. Unit Price No. 16: Additional Installation Depth for Helical Piles.

1. Reference 01-2200 1.4B for information regarding the Helical Piles.

2. Adjustment for installation of total Helical Pile depth differing from an average depth of 26

vertical feet per pile. A total of 12 helical piles are shown on the Drawings with a total

estimated vertical footage of 312 feet. An adjustment will be made for actual vertical

footage of piles installed.

3. Purpose: To adjust the contract sum for actual quantity used.

4. Quantity to be indicated in contract sum: 144 vertical feet.

5. Unit of Measurement: vertical feet.

6. Include only the following in the unit price.

a. Material and installation for installation of Helical Piles beyond the estimated total

depth.

b. Refer to details on Sheet C805 - location(s) as shown on the drawings.

c. Overhead and profit.

7. Include all other costs in the contract base bid.

8. Method of measurement: Actual quantity constructed and authorized prior to start of

work by Owner’s Representative and as quantified by the Geotechnical Engineer.

9. All helical pile construction shall take place in the presence of the Owner’s Representative

and the Geotechnical Engineer.

1.9 SUBMITTALS

A. Supporting Data: With applications for payment covering unit price work submit

substantiated measurement of quantity installed or executed.

1.10 CONTRACT CONSIDERATIONS

A. Unit Prices

1. Indicate unit price for each item on bid form.

2. Costs included in each unit price: Unless otherwise indicated, include in each unit price

the cost of materials, delivery at the site, unloading, handling, storage, labor, installation,

overhead and profit, and related expenses.

3. Quantities

a. Include in the Bid Schedule a unit price and an amount equal to the unit price times

the estimated quantities. If there is a discrepancy between the unit price and the

calculated total, the unit price takes precedence.

b. Actual quantities will be determined by measurement, and the contract sum will be

adjusted accordingly.

4. The total amount of the estimated quantities times the accepted unit prices will be

included in the total bid and contract amount.

B. Procedures for Modifications to the Contract: Procedures for submitting and handling

modifications due to changes are specified elsewhere.

PART 2 – PRODUCTS

N / A

Page 18: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-9 GRAVES PARK AMENITIES BL044-18

PART 3 – EXECUTION

N / A

END OF SECTION

Page 19: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 2200-10 GRAVES PARK AMENITIES BL044-18

Page intentionally left blank.

Page 20: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 5213-1 GRAVES PARK AMENITIES BL044-18

SECTION 01 5213

FIELD OFFICES AND SHEDS

PART 1 - GENERAL

1.1 SCOPE

A. Construction facilities required for this Work to be provided by Contractor, include, but are

not necessarily limited to:

1. Field office(s).

2. Sanitary Facilities.

3. Enclosures such as tarpaulins, barricades, and canopies.

4. Fencing of construction area for safety and security.

5. Parking of construction personnel vehicles.

6. Jobsite security as necessary to protect the Project and the property.

1.2 PROTECTION

A. Use all means necessary to maintain construction facilities in proper and safe conditions

throughout progress of Work.

1.3 REPLACEMENTS

A. In event of loss or damage, Contractor shall immediately make all repairs and replacements

necessary to construction facilities to Owner Representative’s satisfaction at no additional

cost to Owner.

1.4 UTILITY HOOKUP

A. All fees for temporary utility tie-ins will be Contractor's responsibility.

PART 2 - PRODUCTS

2.1 JOB TRAILER AND JOB ENTRANCE

A. The location of job construction trailers, work area and the materials storage area shall be

determined at the pre-construction conference, and shall be within a construction fence.

Contractor shall confine his storage therein and take necessary precautions to protect

materials from all forms of damage and theft as a part of this Work. Area within scope of

Contractor’s work shall be fenced and moved as necessary to accommodate Project phasing

on the site. Entrance drives to the site must be kept open and in good repair at all times.

B. Gravel construction entrance to job trailer and staging area shall be established at the

beginning of work and maintained throughout construction.

C. Furnish and maintain field office trailer(s) for Contractor’s use. The field office trailer(s) shall

be structurally sound, secure, and weather-tight, with floors raised above ground, and

conform to all applicable regulations for the occupancy classification.

Page 21: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 5213-2 GRAVES PARK AMENITIES BL044-18

D. The field office(s) shall include a conference table for monthly meetings with the Owner and

their Representatives. It shall be equipped with sufficient lighting, electrical outlets,

restrooms, and heating, cooling and ventilating equipment and vents. All systems shall comply

with applicable codes, laws and regulations.

E. Prepare and submit a layout plan of all proposed field offices, and related amenities and

utilities to be used for the duration of the Project. Do not proceed with furnishing and

installation of temporary field office(s) prior to Owner and Engineer approval of location(s).

F. Provide and maintain all required utilities for the temporary field office(s) and associated

facilities necessary to support work crews in compliance with applicable codes, laws and

regulations and as acceptable to Owner and Engineer from time of mobilization until

Substantial Completion of the Work.

G. Maintain the temporary field office(s) and related temporary utilities until Substantial

Completion of the Work, at which time the temporary facilities shall be removed.

2.2 PARKING OF VEHICLES

A. Contractor shall assume all responsibility for parking of his and his subcontractors vehicles.

"Job Site Parking" means an area or areas within the bounds of the property or other

authorized areas to be used for parking for vehicles associated with this project. Such areas

shall be designated at the preconstruction meeting.

2.3 COMPLIANCE WITH FEDERAL CLEAN WATER ACT

A. To maintain compliance with Federal Clean Water Act, the requirements of Georgia’s NPDES

GAR100000 General Permit (The Permit) for construction are to be met in the following

manner:

1. Prior to the commencement of the work, the Owner’s Representative will prepare the

Notice of Intent (NOI) form and submit it to Contractor first for execution. The NOI shall

then be sent to the Owner for final execution. Owner will then mail the executed NOI, by

Certified Mail, to EPD and keep the Receipt Certificate in their project files. A copy of the

NOI and letter to EPD will be mailed to the Owner’s Representative, the Geotechnical

Consultant, the NPDES Testing Agency, and Contractor for their records.

2. A certification statement will be signed by the General Contractor and the grading

subcontractor, stating that they agree to comply with the requirements of the Erosion,

Sedimentation and Pollution Control Plan.

3. INSPECTIONS - Each site is required to be inspected once every twenty-four (24) hours and

after the end of a storm that has 0.5 inches of rainfall or greater as mandated by the

NPDES Permit. The inspector must identify needed changes and revise the drawing

accordingly or certify that the site is in compliance. Once a site is stabilized, inspections

are required daily, weekly and monthly until a Notice of Termination (NOT) is filed with

EPD. EPD staff may have access to records at any time. Inspections are to be done by

“qualified personnel” (as defined in the GAR Permit) employed by and paid by the General

Contractor.

4. A log book will be furnished by Owner to the General Contractor for use in logging in each

inspection required in Item 3. The log book is to be available to the Owner’s

Representative for review at any time. This log book is to be turned over to the Owner at

Project close-out.

Page 22: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 5213-3 GRAVES PARK AMENITIES BL044-18

5. A copy of the Erosion, Sediment and Pollution Control plan (ESPC) is to be updated by the

General Contractor depicting any corrections or modifications to the ESPC plan as may

occur during the course of the Work. This drawing is to be turned over to the Owner at

Project close-out.

6. At the close-out of the Project and when all site-work has been signed-off on by the

Owner, the Owner will then issue a Notice of Termination to the Georgia EPD.

B. Failure of the General Contractor to properly maintain the prescribed erosion, sediment and

pollution control requirements and after a twenty-four (24-hour) hour written notice from the

Owner, may result in the Owner performing any necessary repairs or shutting down all work

on the Project except work associated with compliance with the ESPC Plan until the site is

considered in compliance with the Permit. A back charge to the Contract price will be done to

compensate the Owner for all expenses incurred through a change order.

PART 3 – EXECUTION

N/A

END OF SECTION

Page 23: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …

GWINNETT COUNTY, GEORGIA 01 5213-4 GRAVES PARK AMENITIES BL044-18

Page intentionally left blank.

Page 24: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …
Page 25: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …
Page 26: ADDENDUM NUMBER TWO DATE: May 03, 2018 PROJECT: …