activity sequencing

Upload: abhiram-mudunuri

Post on 06-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Activity Sequencing

    1/15

    Project Scheduling: Lagging,

    Crashing and Activity Networks

    Chapter 10

  • 8/3/2019 Activity Sequencing

    2/15

    Lags in Precedence Relationships

    The logical relationship between the start

    and finish of one activity and the start and

    finish of another activity.

    Four logical relationships between tasks

    1. Finish to Start

    2. Finish to Finish3. Start to Start

    4. Start to Finish

  • 8/3/2019 Activity Sequencing

    3/15

    Finish to Start Lag

    Most common type of sequencing Shown on the line joining the modes

    Added during forward pass

    Subtracted during backward pass

    0 A 6Spec Design

    6

    6 B 11Design Check

    5

    15 C 22Blueprinting

    7

    Lag 4

  • 8/3/2019 Activity Sequencing

    4/15

    Finish to Finish Lag

    Two activities share a similar completion point

    The mechanical inspection cannot happen until

    wiring, plumbing, and HVAC installation are complete

    10 A 16

    Plumbing

    6

    16 B 21

    HVAC

    5

    21 C 22

    Inspection

    1

    15 D 21

    Wiring

    6

    Lag 3

  • 8/3/2019 Activity Sequencing

    5/15

    Start to Start Lag

    31 A 33

    Plumbing

    6

    33 B 36

    HVAC5

    36 C 37

    Inspection1

    30 D 36Wiring

    6

    Lag 3

  • 8/3/2019 Activity Sequencing

    6/15

    Start to Finish Lag

    Least common type of lagrelationship

    Successors finish dependent onpredecessors start

    22 A 28

    Plumbing

    6

    28 B 33

    HVAC

    5

    33 C 34

    Inspection

    1

    30 D 36

    Wiring

    6

    Lag 3

  • 8/3/2019 Activity Sequencing

    7/15

    Gantt Charts

    Establish a time-phased network

    Can be used as a tracking tool

    Benefits ofGantt charts

    1. Easy to create and comprehend

    2. Identify the schedule baseline network

    3. Allow forupdating and control

    4. Identify resource needs

  • 8/3/2019 Activity Sequencing

    8/15

    Create a Gantt chart based on the

    activities listed in the table.

    Task Time Pred Task Time Pred

    Z 8 -- U 3 W

    Y 5 Z T 6 V

    X 8 Z S 7 U,T

    W 4 Y,X R 9 S

    V 5 W

  • 8/3/2019 Activity Sequencing

    9/15

    Gantt Chart With Resources in MS Project

  • 8/3/2019 Activity Sequencing

    10/15

    Crashing Projects

    Accelerating a project by committing more

    resources than initially planned

    Principal methods for crashing

    Improving existing resources productivity

    Changing work methods

    Increasing the quantity of resources

  • 8/3/2019 Activity Sequencing

    11/15

    Managerial Considerations

    Determine activity fixed and variable costs

    The crash point is the fully expedited activity

    Optimize time-cost tradeoffs

    Shorten activities on the critical path

    Cease crashing when

    the target completion time is reached

    the crash cost exceeds the penalty cost

  • 8/3/2019 Activity Sequencing

    12/15

    What is the lowest cost to complete thisproject in 53 weeks? Times are in weeks

    and costs in dollars.Activity Pred NormalTime

    Min

    Time

    Normal

    Cost

    Crash

    Cost

    A -- 14 9 500 1500

    B A 5 2 1000 1600C A 10 8 2000 2900

    D B, C 8 5 1000 2500

    E D 6 5 1600 1900

    F D 9 6 1500 3000

    G E, F 7 4 600 1800

    H G 15 11 1600 3600

  • 8/3/2019 Activity Sequencing

    13/15

    Activity on Arrow Networks

    Activities represented by arrows

    Widely used in construction

    Event nodes easy to flag

    Forward and backward pass logic similar to AON

    Two activities may not begin and end at

    common nodes

    Dummy activities may be required

  • 8/3/2019 Activity Sequencing

    14/15

    1. Use AOA to sketch the network that represents the

    project as described in the table.

    2. Calculate early and late start and finish times for allactivities.

    Activity Time Pred Activity Time Pred

    A 4 -- F 4 D

    B 2 A G 15 D

    C 10 A H 7 E,F,G

    D 3 B,C K 11 G

    E 15 B

  • 8/3/2019 Activity Sequencing

    15/15

    Controversies in the Use of Networks

    Networks can be too complex

    Poornetwork construction creates problems

    Networks may be used inappropriately

    When employing subcontractors

    The master network must be available to them

    All sub-networks must use common methods

    Positive bias exists in PERT networks