activity- based management - nely bachsin blog management. 4-2 unit cost is the total cost...
TRANSCRIPT
![Page 1: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/1.jpg)
4 -1
ActivityActivity--
Based Based
ManagementManagement
![Page 2: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/2.jpg)
4 -2
Unit cost is the total cost Unit cost is the total cost
associated with the units
produced divided by the
number of units produced.
Inventory valuation
Income determination
Providing input to a
variety of decisions
such as pricing, make or
buy, and accept or reject
special orders
Unit cost is used for--
![Page 3: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/3.jpg)
4 -3
sum of direct materials, direct labor,
Product cost is often defined as the
sum of direct materials, direct labor,
and manufacturing overhead. This
definition is required for external
financial reporting.
![Page 4: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/4.jpg)
4 -4
Cost measurement consists of
determining the dollar amounts of
direct materials, direct labor, and
overhead used in production.
![Page 5: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/5.jpg)
4 -5
The process of associating
the costs, once measured,
with the units produced is
called cost assignment.
![Page 6: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/6.jpg)
4 -6
Two possible measurement systems are
actual costing and normal costing.
Measurement SystemsMeasurement Systems Measurement SystemsMeasurement Systems
Actual costing assigns the actual costs
of direct materials, direct labor, and
overhead to products.
Normal costing assigns the actual
costs of direct materials and direct
labor to products; however, overhead
cots are assigned to products using
predetermined rates.
![Page 7: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/7.jpg)
4 -7
Measurement SystemsMeasurement Systems Measurement SystemsMeasurement Systems
A predetermined
overhead rate is a rate
based on estimated data.
Budgeted (estimated) cost
Estimated activity usage
![Page 8: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/8.jpg)
4 -8
Examples of UnitExamples of Unit--Level DriversLevel Drivers Examples of UnitExamples of Unit--Level DriversLevel Drivers
Units produced
Direct labor hours
Direct labor dollars
Machine-hours
Direct material dollars
![Page 9: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/9.jpg)
4 -9
Units
(of
driver)
Time
Theoretical
Practical
Normal
Expected actual
![Page 10: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/10.jpg)
4 -10
Functional-Based Costing: Plantwide Rate Functional-Based Costing: Plantwide Rate
Overhead CostsOverhead Costs
Assign CostsAssign Costs
Plantwide PoolPlantwide Pool
Assign CostsAssign Costs
ProductsProducts
Direct Tracing
Stage One: Pool Formation
Unit-Level Driver
Stage Two: Costs Assigned
![Page 11: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/11.jpg)
4 -11
Belring, Inc.
Belring, Inc. produces two telephones: a cordless and a regular model. The company has the following actual and budgeted data:
.
Budgeted overhead $360,000
Expected activity (DLH) 100,000
Actual activity (DLH) 100,000
Actual overhead $380,000
![Page 12: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/12.jpg)
4 -12
Predetermined Overhead Rate =
Belring, Inc.
Budgeted (estimated) cost
Estimated activity usage
Predetermined Overhead Rate =
$360,000
100,000 DLH
Predetermined Overhead Rate =
$3.60 per DLH
![Page 13: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/13.jpg)
4 -13
The total overhead assigned The total overhead assigned
to actual production is
called applied overhead.
Applied
overhead =
Overhead rate
x
Actual activity
output
![Page 14: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/14.jpg)
4 -14
Belring, Inc.
Applied
overhead = Overhead rate x Actual activity output
= $3.60 x 100,000 DLH
= $360,000
![Page 15: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/15.jpg)
4 -15
Cordless Regular
Prime costs $ 78,000 $ 738,000
Overhead costs:
$3.60 x 10,000 36,000 ---
$3.60 x 90,000 --- 324,000
Total manufacturing costs $114,000 $1,062,000
Units produced 10,000 100,000
Unit cost $ 11.40 $ 10.62
Belring, Inc.
PerPer--Unit CostUnit Cost
![Page 16: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/16.jpg)
4 -16
Overhead CostsOverhead Costs
Assign CostsAssign Costs
Assign CostsAssign Costs Assign CostsAssign Costs
ProductsProducts ProductsProducts
Stage One: Pool
Formation
Unit-Level Drivers
Stage Two: Costs
Assigned
Functional-Based Costing Department Rates Functional-Based Costing Department Rates
Department A PoolDepartment A Pool Department B PoolDepartment B Pool
Allocation
Direct Tracing Driver Tracing
![Page 17: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/17.jpg)
4 -17
Budgeted overhead $252,000 $108,000
Departmental DataDepartmental Data Departmental DataDepartmental Data
Belring, Inc.
FabricationFabrication Assembly Assembly
Expected and actual usage (dlh):
Cordless 7,000 3,000
Regular 13,000 77,000
20,000 80,000
Expected and actual usage (mh.):
Cordless 4,000 1,000
Regular 36,000 9,000
40,000 10,000
![Page 18: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/18.jpg)
4 -18
Belring, Inc.
Applied
overhead = ($6.30 x actual mh) + ($1.35 x actual dlh)
= ($6.30 x 40,000) + ($1.35 x 80,000)
= $360,000
= $252,000 + $108,000
![Page 19: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/19.jpg)
4 -19
Belring, Inc.
PerPer--Unit Cost: Departmental RatesUnit Cost: Departmental Rates PerPer--Unit Cost: Departmental RatesUnit Cost: Departmental Rates
Cordless Regular
Prime costs $ 78,000 $ 738,000
Overhead costs:
($6.30 x 4,000) + ($1.35 x 3,000) 29,250 ---
($6.30 x 36,000) + (1.35 x 77,000) --- 330,750
Total manufacturing costs $107,250 $1,068,750
Units produced 10,000 100,000
Unit cost $ 10.73 $ 10.69
![Page 20: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/20.jpg)
4 -20
Symptoms of an Outdated Symptoms of an Outdated Symptoms of an Outdated Symptoms of an Outdated
Functional Cost SystemFunctional Cost System
1. Hasil dari penawaran sulit dijelaskan.
2. Harga pesaing kelihatan rendah secara tidak
realistis.
3. Produk yang sulit dihasilkan menunjukkan
keuntungan yang tinggi.
4. Manajer operasional ingin menghapuskan produk
yang kelihatan menguntungkan.
5. Profit margin sulit untuk menjelaskan. ContinuedContinued ContinuedContinued
![Page 21: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/21.jpg)
4 -21
Symptoms of an Outdated Symptoms of an Outdated Symptoms of an Outdated Symptoms of an Outdated
Functional Cost SystemFunctional Cost System
6. Perusahaan memiliki celah yang sangat
menguntungkan semua secara sendirinya
7. Pelanggan tidak mengeluh tentang kenaikan harga.
8. Departemen akuntansi menghabiskan banyak
waktu untuk penyediaan data biaya untuk proyek-
proyek khusus.
9. Beberapa departemen menggunakan sistem
akuntansi mereka sendiri.
10. Biaya produk berubah karena perubahan peraturan
pelaporan keuangan.
![Page 22: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/22.jpg)
4 -22
Non unit activity drivers are
activities by products and other
Non-unit activity drivers are
factors that measure the
consumption of non-unit
activities by products and other
cost objects.
![Page 23: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/23.jpg)
4 -23
Product diversity (keragaman) means Product diversity (keragaman) means
that the products consume overhead
activities in systematically different
proportions.
![Page 24: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/24.jpg)
4 -24
Units produced per year 10,000 100,000 110,000
Prime costs $78,000 $738,000 $816,000
Direct labor hours 10,000 90,000 100,000
Machine hours 5,000 45,000 50,000
Production runs 20 10 30
Number of moves 60 30 90
Belring, Inc.
Activity Usage Activity Usage
Measures
Product-Costing Data Product-Costing Data
Cordless Regular Total
![Page 25: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/25.jpg)
4 -25
Activity Activity Cost
Belring, Inc.
Setups $120,000
Material handling 60,000
Machining 100,000
Testing 80,000
Total $360,000
Overhead Activities
Product-Costing Data Product-Costing Data
![Page 26: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/26.jpg)
4 -26
Belring, Inc.
Product Diversity: Consumption Ratios Product Diversity: Consumption Ratios
Setups 0.67 0.33 Production runs
Material
handling 0.67 0.33 Number of moves
Machining 0.10 0.90 Machine hours
Testing 0.10 0.90 Direct labor hours
Overhead Cordless Regular Activity
Activity Phone Phone Driver a a
b b
c c
d d
20/30 (cordless) and 10/30 (regular) a
![Page 27: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/27.jpg)
4 -27
Belring, Inc.
Product Diversity: Consumption Ratios Product Diversity: Consumption Ratios
Setups 0.67 0.33 Production runs
Material
handling 0.67 0.33 Number of moves
Machining 0.10 0.90 Machine hours
Testing 0.10 0.90 Direct labor hours
Overhead Cordless Regular Activity
Activity Phone Phone Driver a a
b b
c c
d d
60/90 (cordless) and 30/90 (regular) b
![Page 28: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/28.jpg)
4 -28
Belring, Inc.
Product Diversity: Consumption Ratios Product Diversity: Consumption Ratios
Setups 0.67 0.33 Production runs
Material
handling 0.67 0.33 Number of moves
Machining 0.10 0.90 Machine hours
Testing 0.10 0.90 Direct labor hours
Overhead Cordless Regular Activity
Activity Phone Phone Driver a a
b b
c c
d d
5,000/50,000 (cordless) and 45,000/50,000 (regular) c
![Page 29: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/29.jpg)
4 -29
Belring, Inc.
Product Diversity: Consumption Ratios Product Diversity: Consumption Ratios
Setups 0.67 0.33 Production runs
Material
handling 0.67 0.33 Number of moves
Machining 0.10 0.90 Machine hours
Testing 0.10 0.90 Direct labor hours
Overhead Cordless Regular Activity
Activity Phone Phone Driver a a
b b
c c
d d
10,000/100,000 (cordless) and 90,000/100,000 (regular) d
![Page 30: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/30.jpg)
4 -30
Setup rate: $120,000/30 =$4,000 per run
Material-handling
rate: $60,000/90 = $666.67 per move
Machining rate: $100,000/50,000 = $2 per MH
Testing rate: $80,000/100,000 = $0.80 per DLH
Belring, Inc.
Activity Rates Activity Rates
![Page 31: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/31.jpg)
4 -31
Cordless Regular
Prime costs $ 78,000 $ 738,000
Overhead costs:
Setups 80,000 40,000
Material handling 40,000 20,000
Machining 10,000 90,000
Testing 8,000 72,000
Total manufacturing costs $216,000 $ 960,000
Units produced 10,000 100,000
Unit cost (total costs/units) $ 21.60 $ 9.60
Belring, Inc.
Activity Rates Activity Rates
$4,000
x
20
$4,000
x
10 $667
x
60
$667
x
30 $2
x
5,000
$2
x
45,000 $0.80
x
10,000
$0.80
x
90,000
![Page 32: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/32.jpg)
4 -32
Plantwide rate $11.40 $10.62
Departmental rate 10.73 10.69
Activity rate 21.60 9.60
Comparison of Unit CostsComparison of Unit Costs Comparison of Unit CostsComparison of Unit Costs
Cordless Regular
Belring, Inc.
![Page 33: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/33.jpg)
4 -33
ABC: Two-Stage Assignment
Cost of ResourcesCost of Resources
Assign CostsAssign Costs
ActivitiesActivities
Assign CostsAssign Costs
ProductsProducts
Driver
Tracing
Driver
Tracing
Driver
Tracing
![Page 34: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/34.jpg)
4 -34
A is one A primary activity is one
that is consumed by a
product or customer.
A secondary activity is A secondary activity is
one that is consumed by
other primary and
secondary activities.
![Page 35: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/35.jpg)
4 -35
Resource drivers are
factors that measure the
consumption of
resources by activities.
![Page 36: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/36.jpg)
4 -36
Activity
Measure
Activity
Measure
An allocation base An allocation base
in an activity-based
costing system.
How Costs are Treated Under Activity–Based Costing
The term cost driver is
also used to refer to an
The term cost driver is
also used to refer to an
activity measure.
![Page 37: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/37.jpg)
4 -37
Simple count
of the number of
times an activity
occurs.
Transaction
driver
A measure
of the amount
of time needed
for an activity.
Duration
driver
Two common types of activity measures:
How Costs are Treated Under Activity–Based Costing
![Page 38: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/38.jpg)
4 -38
Unit-level activities are those that are performed each
time a unit is produced.
Examples: Power and machine hours are used
each time a unit is produced. Direct
materials and direct labor activities are
also unit-level activities, even though
they are not overhead costs.
Classification of ActivitiesClassification of Activities Classification of ActivitiesClassification of Activities
![Page 39: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/39.jpg)
4 -39
Batch-level activities are those that are performed
each time a batch of products is produced.
Examples: Setups, inspections, production
scheduling, and material handling.
Classification of ActivitiesClassification of Activities Classification of ActivitiesClassification of Activities
![Page 40: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/40.jpg)
4 -40
Product-level (sustaining) activities are those that are
performed as needed to support the various products
produced by a company. These activities consume inputs that
develop products or allow products to be produced and sold.
Examples: Engineering changes, process engineering, and
expediting.
Classification of ActivitiesClassification of Activities Classification of ActivitiesClassification of Activities
![Page 41: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/41.jpg)
4 -41
Facility-level activities are those that sustain a
factory's general manufacturing processes.
Examples: Plant management, landscaping,
maintenance, security, property
taxes, and plant depreciation.
Classification of ActivitiesClassification of Activities Classification of ActivitiesClassification of Activities
![Page 42: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/42.jpg)
4 -42
DriverDriver
FilterFilter
DriverDriver
FilterFilter
DriverDriver
FilterFilter
Unit Level Batch Level Product Level Facility Level
AA 11 AA AA AA AA 22 33 44 55
Set 1Set 1 Set 2Set 2 Set 3Set 3 Set 4Set 4 Set 5Set 5 Set 6Set 6 Set 7Set 7
Activit
y Level
Filter
![Page 43: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/43.jpg)
4 -43
Customer
Costing versus
Product Costing
![Page 44: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/44.jpg)
4 -44
Large Customer Ten Smaller Customers (50% of sales) (50% of sales)
Units purchased 500,000 500,000
Orders placed 2 200
Number of sales calls 10 210
Manufacturing cost $3,000,000 $3,000,000
Order-filling costs
allocated $202,000 $202,000
Sales-force costs
allocated $110,000 $110,000
ExampleExample ExampleExample
![Page 45: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/45.jpg)
4 -45
The purchasing manager uses two suppliers,
Murray Inc. and Plata Associates, as the source of
two machine parts: Part A1 and Part B2.
ExampleExample ExampleExample
Activity Costs
Repairing products $800,000
Expending products 200,000
![Page 46: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/46.jpg)
4 -46
ExampleExample ExampleExample
Murray Inc. Plata Associates
Part A 1 Part B2 Part A 1 Part B2
Unit purchase price $20 $52 $24 $56
Units purchased 80,000 40,000 10,000 10,000
Failed units 1,600 380 10 10
Late shipments 60 40 0 0
Repair rate = $800,000 ÷ 2,000 = $400 per failed part
Expediting rate = $200,000 ÷ 100 = $2,000 per late
delivery
60 + 40
(1,600 + 380 + 10 + 10)
![Page 47: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/47.jpg)
4 -47
ExampleExample ExampleExample
Murray Inc. Plata Associates
Part A 1 Part B2 Part A 1 Part B2
Purchase cost $1,600,000 $2,080,000 $240,000 $560,000
Repairing products 640,000 152,000 4,000 4,000
Expediting products 120,000 80,000
Total costs $2,360,000 $2,312,000 $244,000 $564,000
Units ÷ 80,000 ÷ 40,000 ÷ 10,000 ÷ 10,000
Total unit cost $ 29.50 $ 57.80 $ 24.40 $ 56.40
![Page 48: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/48.jpg)
4 -48 Characteristics of Successful ABC Implementations
Strong top Strong top
management support
Cross-functional Cross-functional
involvement
Link to evaluations Link to evaluations
and rewards
![Page 49: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/49.jpg)
4 -49
Designing an ABC System
Cost ObjectsCost Objects
(e.g., products(e.g., products
and customers)and customers)
ActivitiesActivities ActivitiesActivities
ConsumptionConsumption
of Resourcesof Resources
CostCost CostCost
![Page 50: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/50.jpg)
4 -50
Classic Brass – An ABC Example
Sales
Cost of goods sold 3,200,000$
Direct materials 975,000$
Direct labor 351,250
Manufacturing overhead 1,000,000 2,326,250
Gross margin 873,750
Selling and administrative expenses
Shipping expenses 65,000
Marketing expenses 300,000
General administrative expenses 510,000 875,000
Net operating incomeoperating loss (1,250)$
Classic Brass
Income Statement
Year Ended December 31, 2005
Manufacturing overhead is allocated to products using Manufacturing overhead is allocated to products using
a single plantwide overhead rate based on machine hours.
![Page 51: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/51.jpg)
4 -51 Define Activities, Activity Cost Pools, and Activity Measures
At Classic Brass, the ABC team, selected the following At Classic Brass, the ABC team, selected the following
activity cost pools and activity measures:
![Page 52: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/52.jpg)
4 -52
Customer Orders - assigned all costs of resources that are
Product Designs
Order Size assigned all costs of resources consumed as a
Customer Relations
Other assigned all overhead costs that are not associated
Customer Orders - assigned all costs of resources that are
consumed by taking and processing customer orders.
Product Designs - assigned all costs of resources
consumed by designing products.
Order Size - assigned all costs of resources consumed as a
consequence of the number of units produced.
Customer Relations – assigned all costs associated with
maintaining relations with customers.
Other – assigned all overhead costs that are not associated
with the other cost pools.
Define Activities, Activity Cost Pools, and Activity Measures
![Page 53: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/53.jpg)
4 -53
Learning Objective 2
Assign costs to cost pools Assign costs to cost pools
using a firstusing a first--stage allocation. stage allocation.
![Page 54: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/54.jpg)
4 -54 Assign Overhead Costs
to Activity Cost Pools
![Page 55: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/55.jpg)
4 -55 Assign Overhead Costs
to Activity Cost Pools
Direct materials, direct labor, and shipping are excludedDirect materials, direct labor, and shipping are excluded
because Classic Brass’ existing cost system can directlybecause Classic Brass’ existing cost system can directly
trace these costs to products or customer orders.trace these costs to products or customer orders.
![Page 56: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/56.jpg)
4 -56
At Classic Brass the following distribution of resource
consumption across activity cost pools is determined.
Assign Overhead Costs
to Activity Cost Pools
![Page 57: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/57.jpg)
4 -57
Indirect factory wages $500,000Indirect factory wages $500,000
Percent consumed by customer orders 25%Percent consumed by customer orders 25%
$125,000$125,000
Indirect factory wages $500,000Indirect factory wages $500,000
Percent consumed by customer orders 25%Percent consumed by customer orders 25%
$125,000$125,000
Assign Overhead Costs
to Activity Cost Pools
![Page 58: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/58.jpg)
4 -58
Factory equipment depreciation $300,000Factory equipment depreciation $300,000
Percent consumed by customer orders 20%Percent consumed by customer orders 20%
$ 60,000$ 60,000
Factory equipment depreciation $300,000Factory equipment depreciation $300,000
Percent consumed by customer orders 20%Percent consumed by customer orders 20%
$ 60,000$ 60,000
Assign Overhead Costs
to Activity Cost Pools
![Page 59: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/59.jpg)
4 -59 Assign Overhead Costs
to Activity Cost Pools
![Page 60: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/60.jpg)
4 -60
Calculate Activity Rates
The ABC team determines that Classic Brass will have
these total activities for each activity cost pool . . .
1,000 customer orders,1,000 customer orders,
400 new designs,400 new designs,
20,000 machine20,000 machine--hours,hours,
250 customer relations activities.250 customer relations activities.
Now the team can compute the individual activity
rates by dividing the total cost for each activity by
Now the team can compute the individual activity
rates by dividing the total cost for each activity by
the total activity levels.
![Page 61: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/61.jpg)
4 -61
Calculate Activity Rates
![Page 62: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/62.jpg)
4 -62
Traced Traced Traced Traced Traced Traced
Activity-Based Costing at Classic Brass
Direct
Direct
Materials
Direct Direct
Labor
Shipping Shipping
Costs Overhead Costs
Cost Objects:Cost Objects: Cost Objects:Cost Objects: Products, Customer Orders, CustomersProducts, Customer Orders, Customers
![Page 63: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/63.jpg)
4 -63
Activity-Based Costing at Classic Brass
Direct
Direct
Materials
Direct Direct
Labor
Shipping Shipping
Costs
Cost Objects:Cost Objects: Cost Objects:Cost Objects: Products, Customer Orders, CustomersProducts, Customer Orders, Customers
OrderOrder OrderOrder
SizeSize
CustomerCustomer CustomerCustomer
OrdersOrders
ProductProduct ProductProduct
DesignDesign
CustomerCustomer CustomerCustomer
RelationsRelations OtherOther
Overhead Costs
First-Stage Allocation
![Page 64: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/64.jpg)
4 -64
Activity-Based Costing at Classic Brass
Direct
Direct
Materials
Direct Direct
Labor
Shipping Shipping
Costs
Cost Objects:Cost Objects: Cost Objects:Cost Objects: Products, Customer Orders, CustomersProducts, Customer Orders, Customers
CustomerCustomer CustomerCustomer
OrdersOrders
OrderOrder OrderOrder
SizeSize
CustomerCustomer CustomerCustomer
RelationsRelations OtherOther
Overhead Costs
First-Stage Allocation
SecondSecond--Stage AllocationsStage Allocations SecondSecond--Stage AllocationsStage Allocations
$/Order $/Order $/Design $/Design $/MH $/MH $/Customer $/Customer
Unallocated Unallocated
ProductProduct ProductProduct
DesignDesign
![Page 65: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/65.jpg)
4 -65
Classic Brass Information
Standard Stanchions
1.1. Requires no new design resources.Requires no new design resources.
2.2. 30,000 units ordered with 600 separate orders.30,000 units ordered with 600 separate orders.
3.3. Each stanchion requires 35 minutes of machineEach stanchion requires 35 minutes of machine
time for a total of 17,500 machinetime for a total of 17,500 machine--hours.hours.
Custom Compass Housing
1. Requires new design resources.
2. 400 separate orders.
3. 400 custom designs prepared.
4. 1,250 compass housings produced, requiring 2
machine-hours each for a total of 2,500 machine-hours.
Assigning Overhead to Products
![Page 66: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/66.jpg)
4 -66
Assigning Overhead to Products
![Page 67: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/67.jpg)
4 -67
Let’s take a look at how Classic Brass system works for just one of the 250 customers – Windward Yachts who placed
a total of three orders.
Orders
1.1. Two orders for 150 standard stanchions per order.Two orders for 150 standard stanchions per order.
2.2. One order for a custom compass housing.One order for a custom compass housing.
Machine-hours
1.1. The 300 standard stanchions required 175 machineThe 300 standard stanchions required 175 machine--hours.hours.
2.2. The custom compass housing required 2 machine hours.The custom compass housing required 2 machine hours.
Assigning Overhead to Customers
![Page 68: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/68.jpg)
4 -68
Assigning Overhead to Customers
![Page 69: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/69.jpg)
4 -69
Prepare Management Reports
Custom
Standard Compass
Stanchions Housings Total
Sales 2,660,000$ 540,000$ 3,200,000$
Direct costs
Direct material 905,500 69,500 975,000
Direct labor 263,750 87,500 351,250
Shipping 60,000 5,000 65,000
Product Margin Calculations
The first step in computing product margins is to
gather each product’s sales and direct cost data.
![Page 70: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/70.jpg)
4 -70
Prepare Management Reports
Product Margin Calculations
The second step in computing product margins is to
incorporate the previously computed activity-based
cost assignments pertaining to each product.
Custom
Standard Compass
Stanchions Housings Total
Sales 2,660,000$ 540,000$ 3,200,000$
Direct costs
Direct material 905,500 69,500 975,000
Direct labor 263,750 87,500 351,250
Shipping 60,000 5,000 65,000
ABC cost assignments
Customer orders 192,000 128,000 320,000
Product design 252,000 252,000
Order size 332,500 47,500 380,000
![Page 71: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/71.jpg)
4 -71
Prepare Management Reports
Product Margin Calculations
The third step in computing product
margins is to deduct each product’s
direct and indirect costs from sales.
Sales 2,660,000$ 540,000$
Costs
Direct material 905,500$ 69,500$
Direct labor 263,750 87,500
Shipping 60,000 5,000
Customer orders 192,000 128,000
Product design 252,000
Order size 332,500 47,500
Total cost 1,753,750 589,500
Product margin 906,250$ (49,500)
Custom
Standard Stanchions Compass Housings
![Page 72: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/72.jpg)
4 -72
Custom
Standard Compass
Stanchions Housings Total
Sales 2,660,000$ 540,000$ 3,200,000$
Total costs 1,753,750 589,500 2,343,250
Product margins 906,250$ (49,500)$ 856,750$
Less costs not assigned to products:
Customer relations 367,500
Other 490,500
Total 858,000
Net operating incomet operating loss (1,250)$
Product Margin Calculations
The product margins can be reconciled with
the company’s net operating income as follows:
Prepare Management Reports
![Page 73: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/73.jpg)
4 -73
Prepare Management Reports
Customer Profitability Analysis
The first step in computing Windward Yachts’ customer
margin is to gather its sales and direct cost data.
Windward
Yachts
Sales 11,350$
Direct costs
Direct material 2,123
Direct labor 1,900
Shipping 205
![Page 74: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/74.jpg)
4 -74
Prepare Management Reports
Customer Profitability Analysis
The second step is to incorporate Windward Yachts’
previously computed activity-based cost assignments.
Windward
Yachts
Sales 11,350$
Direct costs
Direct material 2,123
Direct labor 1,900
Shipping 205
ABC cost assignments
Customer orders 960
Product design 630
Order size 3,363
Customer relations 1,470
![Page 75: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/75.jpg)
4 -75
Prepare Management Reports
Customer Profitability Analysis
The third step is to compute Windward Yachts’ customer margin ($699)
by deducting all its direct and indirect costs from its sales.
Sales 11,350$
Direct costs
Direct material 2,123$
Direct labor 1,900
Shipping 205
Customer orders 960
Product design 630
Order size 3,363
Customer relations 1,470 10,651
Customer margin 699$
Windward Yachts
![Page 76: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/76.jpg)
4 -76 Product Margins Computed Using
the Traditional Cost System
Custom
Standard Compass
Stanchions Housings Total
Sales 2,660,000$ 540,000$ 3,200,000$
Direct costs
Direct material 905,500 69,500 975,000
Direct labor 263,750 87,500 351,250
The first step in computing product margins is to
gather each product’s sales and direct cost data.
![Page 77: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/77.jpg)
4 -77 Product Margins Computed Using
the Traditional Cost System
Plantwide manufacturing
overhead rate
$1,000,000
20,000 MH = $50 per machine-hour =
The second step in computing product margins
is to compute the plantwide overhead rate.
Production Department
Indirect factory wages 500,000$
Factory equipment depreciation 300,000
Factory utilities 120,000
Factory building lease 80,000
Total manufacturing overhead 1,000,000$
Manufacturing Overhead Costs at Classic Brass
Machine-hours
Standard Stanchions 17,500
Custom compass Housings 2,500
Total machine-hours 20,000
![Page 78: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/78.jpg)
4 -78 Product Margins Computed Using
the Traditional Cost System
The third step in computing product margins is
allocate manufacturing overhead to each product.
Machine Overhead Overhead
Hours Rate Allocated
Standard Stanchions 17,500 50.00$ 875,000$
Custom Compass Housings 2,500 50.00 125,000
Total overhead allocated to products 1,000,000$
17,500 hours × $50 per hour = $875,000 17,500 hours × $50 per hour = $875,000
![Page 79: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/79.jpg)
4 -79 Product Margins Computed Using
the Traditional Cost System
The fourth step is to actually
compute the product margins.
Sales 2,660,000$ 540,000$ 3,200,000$
Cost of goods sold
Direct materials 905,500$ 69,500$ 975,000$
Direct labor 263,750 87,500 351,250
Manufacturing overhead 875,000 2,044,250 125,000 282,000 1,000,000 2,326,250
Product margin 615,750$ 258,000 873,750
Selling and administrative 875,000
Net operating incomet operating loss (1,250)$
Custom
Standard Stanchions Compass Housings Total
Shipping expenses 65,000$
Marketing expenses 300,000
General administrative expenses 510,000
875,000$
![Page 80: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/80.jpg)
4 -80
Standard Custom
Stanchions Compass Housings
Product margins – traditional 615,750$ 258,000$
Product margins – ABC 906,250 (49,500)
Change in reported margins 290,500$ (307,500)$
The Differences Between ABC and Traditional Product Costs
The traditional cost
system overcosts the
standard stanchions
and reports a lower
product margin
for this product.
The traditional cost
system undercosts the
custom compass
housings and reports
a higher product
margin for this product.
![Page 81: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/81.jpg)
4 -81 Differences Between ABC and Traditional Product Costs
There are three reasons why the
reported product margins for the two
costing systems differ from one another.
Traditional costing allocates all manufacturing
overhead to products. ABC costing only assigns
manufacturing overhead costs consumed by
products to those products.
![Page 82: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/82.jpg)
4 -82 Differences Between ABC and Traditional Product Costs
Traditional costing allocates all manufacturing
overhead costs using a volume-related allocation
base. ABC costing also uses non-volume related
allocation bases.
There are three reasons why the
reported product margins for the two
costing systems differ from one another.
![Page 83: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/83.jpg)
4 -83 Differences Between ABC and Traditional Product Costs
Traditional costing disregards selling and
administrative expenses because they are
assumed to be period expenses. ABC costing
directly traces shipping costs to products and
includes nonmanufacturing overhead costs caused
by products in the activity cost pools that are
assigned to products.
There are three reasons why the
reported product margins for the two
costing systems differ from one another.
![Page 84: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/84.jpg)
4 -84
Targeting Process Improvement
Activity-based management is used in
areas that would benefit from process
Activity-based management is used in
conjunction with ABC to identify
areas that would benefit from process
improvements.
While the theory of constraints approach
improvement efforts, activity rates can
also provide valuable clues on where to
While the theory of constraints approach
discussed in Chapter 1
is a powerful tool for targeting
improvement efforts, activity rates can
also provide valuable clues on where to
focus improvement efforts.
Benchmarking Benchmarking can be used to compare activity cost can be used to compare activity cost Benchmarking Benchmarking can be used to compare activity cost can be used to compare activity cost
information with worldinformation with world--class standards of performance class standards of performance
achieved by other organizations.achieved by other organizations.
![Page 85: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/85.jpg)
4 -85
Activity-Based Costing and External Reporting
Most companies do not use ABC
for external reporting because . . .
1. External reports are less detailed than internal reports. 1. External reports are less detailed than internal reports.
2. It may be difficult to make changes to the company’s
accounting system.
3. ABC does not conform to GAAP.
4. Auditors may be suspect of the subjective allocation
process based on interviews with employees.
![Page 86: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/86.jpg)
4 -86
ABC Limitations
Substantial resources
required to implement
and maintain.
Resistance to
unfamiliar numbers
and reports.
Desire to fully
allocate all costs
to products.
Potential
misinterpretation of
unfamiliar numbers.
Does not conform to
GAAP. Two costing
systems may be needed.
![Page 87: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/87.jpg)
4 -87
ABC Action Analysis
(Activity Based Management)
![Page 88: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/88.jpg)
4 -88
ABC Action Analysis
Analisis ABC konvensional tidak Analisis ABC konvensional tidak
mengidentifikasi biaya relevan secara
potensial. Laporan analisis tindakan
membantu karena:
•Menunjukkan biaya apa yang telah
dibebankan ke objek biaya?.
•Menunjukkan seberapa sulitnya
penyesuaian atas biaya-biaya tersebut
dihubungkan dengan perubahan tingkat
aktivitas?
![Page 89: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/89.jpg)
4 -89
Membuat laporan analisis tindakan dimulai dengan proses alokasi tahap pertama. Selain
menghitung keseluruhan tingkat aktivitas untuk setiap pul biaya aktivitas, tingkat aktivitas
dihitung untuk setiap jenis biaya overhead yang dikonsumsi mendukung kegiatan tertentu.
Mari kita tinjau kembali alokasi tahap-satu? Dari contoh Classic Brass yang kita bahas
sebelumnya.
ABC Action Analysis
![Page 90: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/90.jpg)
4 -90
ABC Action Analysis
$125,000 ÷ 1,000 orders = $125 per order
Other entries in the table are computed similarly.
![Page 91: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/91.jpg)
4 -91
$125 per order × 600 orders = $75,000
Other entries in the table are computed similarly.
ABC Action Analysis
![Page 92: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/92.jpg)
4 -92
$125 per order × 400 orders = $50,000
Other entries in the table are computed similarly.
ABC Action Analysis
![Page 93: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/93.jpg)
4 -93
Next, label each cost using an ease of adjustment code:
Biaya merah dapat disesuaikan dengan perubahan tingkat
Next, label each cost using an ease of adjustment code:
Biaya hijau menyesuaikan lebih atau kurang secara otomatis ke perubahan tingkat aktivitas tanpa tindakan
manajer. Biaya kuning dapat disesuaikan dengan perubahan tingkat aktivitas, tetapi akan memerlukan tindakan manajemen untuk mewujudkan perubahan biaya.
Biaya merah dapat disesuaikan dengan perubahan tingkat aktivitas hanya dengan perlakuan yang sulit /besar dan
dengan intervensi manajemen.
ABC Action Analysis
![Page 94: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/94.jpg)
4 -94
Sales 540,000$
Green costs
Direct materials 69,500$
Shipping costs 5,000 74,500
Green margin 465,500$
Yellow costs
Direct labor 87,500
Indirect factory wages 262,500
Factory utilities 19,500
Administrative wages and salaries 49,000
Office equipment depreciation 6,000
Marketing wages and salaries 42,000
Selling expenses 2,000 468,500
Yellow margin (3,000)$
Red costs
Factory equipment depreciation 46,500
Factory building lease -
Administrative building lease - 46,500
Red margin (49,500)$
Action Analysis of Custom Compass Housing
ABC Action Analysis
![Page 95: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/95.jpg)
4 -95
Using a Modified form of
Activity-Based Costing to
Determine Product costs for
External Reports
![Page 96: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/96.jpg)
4 -96
ABC product costs: • Include organization-sustaining costs
and unused capacity costs.
• Exclude nonmanufacturing costs even
if they are caused by the products.
A modified form of activity-based
costing can be used to develop product
costs for external financial reports.
![Page 97: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/97.jpg)
4 -97
Total estimated manufacturing overhead 1,520,000$
Total estimated direct labor hours 400,000
Premium Standard
Direct materials cost per unit 40.00$ 30.00$
Direct labor cost per unit 24.00$ 18.00$
Direct labor hours per unit 2.0 1.5
Units produced 50,000 200,000
Maxtar Industries provides the following information Maxtar Industries provides the following information
for the company as a whole and for its only two
products—premium and standard smoker/barbecue units.
![Page 98: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/98.jpg)
4 -98
Assuming that Maxtar’s traditional cost system relies on one Assuming that Maxtar’s traditional cost system relies on one Assuming that Maxtar’s traditional cost system relies on one Assuming that Maxtar’s traditional cost system relies on one
predetermined plantwide overhead rate with direct laborpredetermined plantwide overhead rate with direct labor--
hours (DLHs) as the allocation base, then its plantwide hours (DLHs) as the allocation base, then its plantwide
overhead rate is computed as follows:overhead rate is computed as follows:
Predetermined
overhead rate = $3.80 per DLH =
$1,520,000
400,000 DLHs
![Page 99: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/99.jpg)
4 -99
Premium Standard
Direct materials cost per unit 40.00$ 30.00$
Direct labor cost per unit 24.00 18.00
Manufacturing overhead per unit 7.60 5.70
Unit product cost 71.60$ 53.70$
Maxtar’s traditional cost system wouldMaxtar’s traditional cost system would Maxtar’s traditional cost system wouldMaxtar’s traditional cost system would
report unit product costs as follows:report unit product costs as follows:
2.0 DLH × $3.80 per DLH
1.5 DLH × $3.80 per DLH
![Page 100: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/100.jpg)
4 -100
The ABC project team at Maxtar has
developed the following basic information.
Activity and Activity Measures
Estimated
Overhead
Cost
Premium Standard Total
Direct labor support (DLHs) 800,000$ 100,000 300,000 400,000
Machine setups (setups) 480,000 600 200 800
Parts administration (part types) 240,000 140 60 200
Total manufacturing overhead 1,520,000$
Expected Activity
![Page 101: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/101.jpg)
4 -101
We can calculate the following activity rates:
Activity and Activity Measures
Estimated
Overhead
Cost
Total
Expected
Activity
Direct labor support (DLHs) 800,000$ ÷ 400,000 = 2$ per DLH
Machine setups (setups) 480,000 ÷ 800 = 600$ per setup
Parts administration (part types) 240,000 ÷ 200 = 1,200$ per part type
Total manufacturing overhead 1,520,000$
Activity Rate
Using the new activity rates, let’s assign overhead
to the two products based upon expected activity.
![Page 102: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/102.jpg)
4 -102
Activity and Activity Measures
Expected
Activity
Activity
Rate
Direct labor support (DLHs) 100,000 × 2$ = 200,000$
Machine setups (setups) 600 × 600$ = 360,000
Parts administration (part types) 140 × 1,200$ = 168,000
Total overhead cost assigned 728,000$
Amount
Premium Product
Activity and Activity Measures
Expected
Activity
Activity
Rate
Direct labor support (DLHs) 300,000 × 2$ = 600,000$
Machine setups (setups) 200 × 600$ = 120,000
Parts administration (part types) 60 × 1,200$ = 72,000
Total overhead cost assigned 792,000$
Amount
Standard Product
![Page 103: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/103.jpg)
4 -103
Premium Standard
Direct materials cost per unit 40.00$ 30.00$
Direct labor cost per unit 24.00 18.00
Manufacturing overhead per unit 14.56 3.96
Unit product cost 78.56$ 51.96$
Activity-based unit product costs for both product lines Activity-based unit product costs for both product lines
![Page 104: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/104.jpg)
4 -104
Activity-based unit product costs for both product lines Activity-based unit product costs for both product lines
Premium Standard
Direct materials cost per unit 40.00$ 30.00$
Direct labor cost per unit 24.00 18.00
Manufacturing overhead per unit 14.56 3.96
Unit product cost 78.56$ 51.96$
$728,000 ÷ 50,000 units
$792,000 ÷ 200,000 units
![Page 105: Activity- Based Management - NELY BACHSIN BLOG Management. 4-2 Unit cost is the total cost associated with the units ... in an activity-based costing system. How Costs are Treated](https://reader031.vdocuments.site/reader031/viewer/2022030416/5aa268427f8b9a1f6d8d2e9b/html5/thumbnails/105.jpg)
4 -105
Note that the unit product cost of a Standard unitNote that the unit product cost of a Standard unit Note that the unit product cost of a Standard unitNote that the unit product cost of a Standard unit
decreased from $53.70 to $51.96 . . . . .decreased from $53.70 to $51.96 . . . . .
. . . . . while the unit cost of a Premium unit increased from . . . . . while the unit cost of a Premium unit increased from . . . . . while the unit cost of a Premium unit increased from . . . . . while the unit cost of a Premium unit increased from
$71.60 to $78.56.$71.60 to $78.56.
Premium Standard Premium Standard
Direct material 40.00$ 30.00$ 40.00$ 30.00$
Direct labor 24.00 18.00 24.00 18.00
Manufacturing overhead 14.56 3.96 7.60 5.70
Unit product cost 78.56$ 51.96$ 71.60$ 53.70$
Activity-Based Costing Traditional Costing
Comparing the two approaches