Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 1.1 Activity: Tendering/ Publish Project Details on E-Tenders
WBS No:
Activity Description: This activity involves summiting project details online for relevant parties interested
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires basic computer skills for details on E-tenders.
Activity Predecessors:
Activity Successors: Expressions of Interest
Type of Effort: This activity is a fixed duration activity which will have duration of 30 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 1.2 Activity: Tendering/ Expressions of Interest
WBS No:
Activity Description: This activity involves detailing/document all parties interested in the project
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires basic computer skills.
Activity Predecessors: Publish Project Details on E-Tenders
Activity Successors: Review Tender Pack
Type of Effort: This activity is a fixed duration activity which will have duration of 23 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
2
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 1.3 Activity: Tendering/ Review Tender Pack
WBS No:
Activity Description: This activity involves reviewing all necessary components of tender pack
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires basic computer skills.
Activity Predecessors: Expressions of Interest
Activity Successors: Preparation of BoQ
Type of Effort: This activity is a fixed duration activity which will have duration of 7 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 1.4 Activity: Tendering/ Preparation of BoQ
WBS No:
Activity Description: This activity involves Preparing a bill of quantities for project
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires basic computer skills for Preparation of BoQ.
Activity Predecessors: Review Tender Pack
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 7 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
3
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.1 Activity: Feasibility/ WWTP Selection
WBS No:
Activity Description: This activity involves selecting an appropriate WWTP based on chosen P.E size and cost.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires computer skills for WWTP Selection.
Activity Predecessors:
Activity Successors: Site Layouts
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.2 Activity: Feasibility/ Site Layouts
WBS No:
Activity Description: This activity involves preparing site layout drawings for project.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires computer skills AutoCAD and software's for the decision on the Site layout.
Activity Predecessors: WWTP Selection
Activity Successors: Permits
Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
4
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.3 Activity: Feasibility/ Permits WBS No:
Activity Description: This activity involves contacting relevant authorities to obtain necessary permits i.e. discharge permits etc
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Site Layouts
Activity Successors: Contractor Submissions
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.4 Activity: Feasibility/ Contractor Submissions
WBS No:
Activity Description: This activity involves detailing all submissions received from the contractor.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Permits
Activity Successors: Material Submissions
Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
5
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.5 Activity: Feasibility/ Material Submissions
WBS No:
Activity Description: This activity involves detailing all relevant material submissions for the project.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Contractor Submissions
Activity Successors: Plant Submissions
Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.6 Activity: Feasibility/ Plant Submissions
WBS No:
Activity Description: This activity involves detailing all relevant plant submissions for the project.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Material Submissions
Activity Successors: Health & Safety Audits
Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
6
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.7 Activity: Feasibility/ Health & Safety (H & S) Audits
WBS No:
Activity Description: This activity involves preparing a health and safety audit for the continued development and implementation of H & S throughout the project
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Plant Submissions
Activity Successors: Human resources
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.8 Activity: Feasibility/ Human resources
WBS No:
Activity Description: Human resources is required to distinguish roles and responsibilities for the project and to organize organizational charts and a staffing Management Plan
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Health & Safety (H & S)Audits
Activity Successors: Procurement Completion
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
7
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.1.9 Activity: Feasibility/ Procurement Completion
WBS No:
Activity Description: This activity involves bringing the project procurement to a completion
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Human resources
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.2.1 Activity: Contact Suppliers/ WWTP Supplier
WBS No:
Activity Description: This activity involves ordering WWTP systems/materials
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Concrete Supplier
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
8
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.2.2 Activity: Contact Suppliers/ Concrete Supplier
WBS No:
Activity Description: This activity involves ordering concrete supplies.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: WWTP Supplier
Activity Successors: Building Materials Supplier
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.2.3 Activity: Contact Suppliers/ Building Materials Supplier
WBS No:
Activity Description: This activity involves ordering building materials supplies
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Concrete Supplier
Activity Successors: Plant Hire
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
9
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.2.4 Activity: Contact Suppliers/ Plant Hire
WBS No:
Activity Description: This activity involves hiring plant machinery for site
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Building Materials Supplier
Activity Successors: Submit Tender
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.2.5 Activity: Contact Suppliers/ Submit Tender
WBS No:
Activity Description: This activity involves submitting for tendering
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Plant Hire
Activity Successors: Tender Awarded
Type of Effort: This activity is a fixed duration activity which will have duration of 0 day.
Location of Activity: All work associated with this activity will occur at head office
Activity Assumptions:
Activity Constraints: :
10
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 2.2.6 Activity: Contact Suppliers/ Tender Awarded
WBS No:
Activity Description: This activity mean rewarding successful contractor with project
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Submit Tender
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 0 day.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 3.1 Activity: Preliminaries / Insurance
WBS No:
Activity Description: Insurance is the equitable transfer of the risk of a loss, from one entity to another in exchange for payment. It is a form of risk management primarily used to hedge against the risk of a contingent, uncertain loss.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Employers' Liability Insurance
Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
11
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 3.2 Activity: Preliminaries / Employers' Liability Insurance
WBS No:
Activity Description: Coverage against common law liability of an employer for accidents to employees, as distinguished from liability imposed by a workers' compensation law.
Activity Responsibility: Contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Insurance
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.
Location of Activity: All work associated with this activity will occur at head office.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.1.1 Activity: Commencing on Site / Site Office
WBS No:
Activity Description: This activity involves setting up site office on site for duration of the project
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Commencing on site
Activity Successors: Office Equipment
Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints: :
12
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.1.2 Activity: Commencing on Site / Office Equipment
WBS No:
Activity Description: This activity involves setting up all necessary office equipment for duration of project.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Site office
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.2.1 Activity: Mobilisation / Traffic Management
WBS No:
Activity Description: This activity involves setting up a traffic management plan to control and direct traffic in a safe manner during construction of the project.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Site Safety Induction
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints: :
13
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.2.2 Activity: Mobilisation / Site Safety Induction
WBS No:
Activity Description: Site induction communicates essential information regarding the site, the working methods and health and safety management.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Traffic Management
Activity Successors: Road Brushing
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.2.3 Activity: Mobilisation / Road Brushing
WBS No:
Activity Description: This activity involves removal of necessary brush from roadside ditches for the safety of the travelling public
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Site Safety Induction
Activity Successors: Site Clearing Plant & Equipment
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints: :
14
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.2.4 Activity: Mobilisation / Site Clearing Plant & Equipment
WBS No:
Activity Description: This activity involves hiring of necessary plant equipment for clearing of construction site
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires Site experience for Clearing Plant & Equipment.
Activity Predecessors: Road Brushing
Activity Successors: Excavation Equipment
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.2.5 Activity: Mobilisation / Excavation Equipment
WBS No:
Activity Description: This activity involves hiring of necessary excavation equipment for clearing of construction site
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires Site experience for Excavation Equipment.
Activity Predecessors: Site Clearing Plant & Equipment
Activity Successors: Paving Equipment
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
15
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.2.6 Activity: Mobilisation / Paving Equipment
WBS No:
Activity Description:
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: This activity requires Site experience for Paving Equipment.
Activity Predecessors: Excavation Equipment
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.3.1 Activity: Temporary Works / Site Security Fencing
WBS No:
Activity Description: This activity involves setting up of fencing around the site for public safety.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Car Parking
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
16
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.3.2 Activity: Temporary Works / Car Parking
WBS No:
Activity Description: This activity involves construction of temporary car park for onsite for duration of project.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Site Security Fencing
Activity Successors: Site Entrance / Access
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints: :
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.3.3 Activity: Temporary Works / Site Entrance and Access
WBS No:
Activity Description: This activity involves providing site entrance/access for to construction site.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Car Parking
Activity Successors: Temporary Site Services
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
17
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.3.4 Activity: Temporary Works / Temporary Site Services
WBS No:
Activity Description: This activity involves setting site up temporary site services for duration of project i.e. plumbing and electrics.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Site Entrance / Access
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.4.1 Activity: Ground Works/ Site Clearing
WBS No:
Activity Description: This activity involves clearing the site and getting it ready for construction.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Strip Top Soil
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
18
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.4.2 Activity: Ground Works/ Strip Top Soil
WBS No:
Activity Description: This activity involves the stripping back of top soil.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Site Clearing
Activity Successors: Top Soil Storage
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.4.3 Activity: Ground Works/ Top Soil Storage
WBS No:
Activity Description: This activity involves the storing of the top soil removed.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Strip Top Soil
Activity Successors: Trial Holes
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
19
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.4.4 Activity: Ground Works/ Trial Holes
WBS No:
Activity Description: This activity involves trial holes been dug to determine the geology and water table of the site.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Top Soil Storage
Activity Successors: Set Out Site
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.4.5 Activity: Ground Works/ Set Out Site
WBS No:
Activity Description: This activity involves setting out the site is to stake out reference points and markers that will guide the construction of new structures such as roads or buildings.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Trial Holes
Activity Successors: Place Access Road Sub-Base
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
20
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.4.6 Activity: Ground Works/ Place Access Road Sub-Base
WBS No:
Activity Description: This activity involves laying the sub base and providing and access road to the site.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Set Out Site
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.1 Activity: Control Room/ Setting Out
WBS No:
Activity Description: This activity involves setting out the site to stake out reference points and markers that will guide the construction of the Control room.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Excavate for Foundations and Services
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
21
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.2 Activity: Control Room/ Excavate for Foundations and Services
WBS No:
Activity Description: This activity involves excavating for foundations/ services for the control room.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Setting Out
Activity Successors: Pour Foundations
Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.3 Activity: Control Room/ Pour Foundations
WBS No:
Activity Description: The activity involves the pouring of concrete for the foundations.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate for Foundations / Services
Activity Successors: Block Work
Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
22
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.4 Activity: Control Room/ Block Work
WBS No:
Activity Description: This activity involves the laying of blocks by a competent builder.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Pour Foundations
Activity Successors: Roof
Type of Effort: This activity is a fixed duration activity which will have duration of 4 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.5 Activity: Control Room/ Roof WBS No:
Activity Description: This activity involves the building of the roof by a competent carpenter.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Block Work
Activity Successors: Finishing
Type of Effort: This activity is a fixed duration activity which will have duration of 4 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
23
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.6 Activity: Control Room/ Finishing
WBS No:
Activity Description: This activity involves the finishing of the control room.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Roof
Activity Successors: Wiring
Type of Effort:
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.7 Activity: Control Room/ Wiring
WBS No:
Activity Description: This activity involves the wiring of the control room by a competent electrician.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Finishing
Activity Successors: Control Panels (ICS)
Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
24
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.8 Activity: Control Room/ Control Panels (ICS)
WBS No:
Activity Description: This activity involves the installing of control panels for the WWTP.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Wiring
Activity Successors: Re-Furbish
Type of Effort: This activity is a fixed duration activity which will have duration of 7 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.9 Activity: Control Room/ Re-Furbish
WBS No:
Activity Description: This activity involves the refurbishing of the control room.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Control Panels (ICS)
Activity Successors: Windows
Type of Effort:
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
25
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.10 Activity: Control Room/ Windows
WBS No:
Activity Description: This activity involves the placing/fitting of the windows.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Re-Furbish
Activity Successors: Painting
Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Upgrade Works to WWTP at Keadue, Co. Roscommon
Date:
Activity ID: 4.5.11 Activity: Control Room/ Painting
WBS No:
Activity Description: This activity involves the painting of the control room.
Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.
Resources and Skill Sets Required: Contractor has relevant skills set to complete this task
Activity Predecessors: Windows
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.
Location of Activity: All work associated with this activity will occur at WWTP at Keadue.
Activity Assumptions:
Activity Constraints:
26
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.1 Activity: Excavate for Sub-base
WBS No:
Activity Description: This activity involves the excavating of the sub base
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Place Hardcore Sub-base
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.2 Activity: Place Hardcore Sub-base
WBS No:
Activity Description: This activity involves the placing of the hardcore base
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate for Sub-base
Activity Successors: Erect Formwork
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
27
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.3 Activity: Erect Formwork WBS No:
Activity Description: This activity involves the erecting of the formwork
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Place Hardcore Sub-base
Activity Successors: Place Reinforcement
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.4 Activity: Place Reinforcement
WBS No:
Activity Description: This activity involves the placing of the steel reinforcement
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Erect Formwork
Activity Successors: Pour Concrete Sub-Base
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
28
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.5 Activity: Pour Concrete Sub-Base
WBS No:
Activity Description: This activity involves the pouring of the concrete
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Place Reinforcement
Activity Successors: Strike Formwork
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.6 Activity: Strike Formwork WBS No:
Activity Description: His activity involves the striking of the formwork
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Pour Concrete Sub-Base
Activity Successors: Install BMS units
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day week.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
29
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.7 Activity: Install BMS units WBS No:
Activity Description: This activity involves the installing of the new package WWTP
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Strike Formwork
Activity Successors: Connect new infrastructure
Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.8 Activity: Connect new infrastructure
WBS No:
Activity Description: This activity involves the connecting of all pipes into the package WWTP
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Install BMS units
Activity Successors: Commission
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
30
Activity Attributes
Project: Keadue upgrade works/ Package system Date:
Activity ID: 4.6.6.9 Activity: Commission WBS No:
Activity Description: This activity involves the commissioning of the new package WWTP
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Connect new infrastructure
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of two day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Reinstatement Date:
Activity ID: 4.6.7.1 Activity: Placing Concrete Kerbs
WBS No:
Activity Description: This activity involves the placing of the concrete kerbs around the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors:
Pedestrian Paths
Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
31
Activity Attributes
Project: Keadue upgrade works/ Reinstatement Date:
Activity ID: 4.6.7.2 Activity: Pedestrian Paths WBS No:
Activity Description: This activity involves the placing /laying out of pedestrian foot paths
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Placing Concrete Kerbs
Activity Successors: Replacing Top Soil
Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Reinstatement Date:
Activity ID: 4.6.7.3 Activity: Replacing Top Soil
WBS No:
Activity Description: This activity involves the replacing of the top soil around the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Pedestrian Paths
Activity Successors: Seeding
Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
32
Activity Attributes
Project: Keadue upgrade works/ Reinstatement Date:
Activity ID: 4.6.7.4 Activity: Seeding WBS No:
Activity Description: This activity involves the reseeding of trees and plants around the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Replacing Top Soil
Activity Successors: Bitumen layer to Road
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Reinstatement Date:
Activity ID: 4.6.7.5 Activity: Bitumen layer to Road
WBS No:
Activity Description: This activity involves the laying of the bitumen layer for the road
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Seeding
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
33
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.1 Activity: Set Out Proposed Pipe Network
WBS No:
Activity Description: This activity involves the setting out of the proposed pipe network
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Excavate for, and Construct Manhole 1
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.2 Activity: Excavate for, and Construct Manhole 1
WBS No:
Activity Description: This activity involves the constructing for a new manhole (MH1)
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Set Out Proposed Pipe Network
Activity Successors: Excavate & Lay Sewer Pipe A - B
Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
34
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.3 Activity: Excavate & Lay Sewer Pipe A - B
WBS No:
Activity Description: This activity involves the excavating and the laying of pipe work from A - B
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate for, and Construct Manhole 1
Activity Successors: Excavate for, and Construct Manhole 2
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.4 Activity: Excavate for, and Construct Manhole 2
WBS No:
Activity Description: This activity involves the constructing for a new manhole (MH2)
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate & Lay Sewer Pipe A - B
Activity Successors: Excavate & Lay Sewer Pipe B - C
Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
35
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.5 Activity: Excavate & Lay Sewer Pipe B - C
WBS No:
Activity Description: This activity involves the excavating and the laying of pipe work from B - C
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate for, and Construct Manhole 2
Activity Successors: Excavate for, and Construct Manhole 3
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.6 Activity: Excavate for, and Construct Manhole 3
WBS No:
Activity Description: This activity involves the constructing for a new manhole (MH3)
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate & Lay Sewer Pipe B - C
Activity Successors: Excavate & Lay Sewer Pipe C - D
Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
36
Activity Attributes
Project: Keadue upgrade works/ Sewer Connection Date:
Activity ID: 4.7.7 Activity: Excavate & Lay Sewer Pipe C - D
WBS No:
Activity Description: This activity involves the excavating and the laying of pipe work from C - D
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate for, and Construct Manhole 3
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.1 Activity: Excavate for Sub-base
WBS No:
Activity Description: This activity involves the excavating of the sub base
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Place Hardcore Sub-base
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
37
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.2 Activity: Place Hardcore Sub-base
WBS No:
Activity Description: This activity involves the placing of the hard core sub base
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Excavate for Sub-base
Activity Successors: Erect Formwork
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.3 Activity: Erect Formwork WBS No:
Activity Description: This activity involves the erecting of the formwork
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Place Hardcore Sub-base
Activity Successors: Place Reinforcement
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
38
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.4 Activity: Place Reinforcement
WBS No:
Activity Description: This activity involves the placing of the steel reinforcement
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Erect Formwork
Activity Successors: Pour Concrete Sub-Base
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.5 Activity: Pour Concrete Sub-Base
WBS No:
Activity Description: This activity involves the pouring of the concrete sub base
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Place Reinforcement
Activity Successors: Strike Formwork
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
39
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.6 Activity: Strike Formwork WBS No:
Activity Description: This activity involves the striking of the formwork
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Pour Concrete Sub-Base
Activity Successors: Backfill Surrounds
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.7 Activity: Backfill Surrounds WBS No:
Activity Description: This activity involves the backfilling in the surrounds of the pump chamber
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Strike Formwork
Activity Successors: Install Pump
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
40
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.8 Activity: Install Pump WBS No:
Activity Description: This activity involves the installing of the pump
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Backfill Surrounds
Activity Successors: Commission
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Pump Chamber Date:
Activity ID: 4.8.9 Activity: Commission WBS No:
Activity Description: This activity involves the commissioning of the pump house
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Install Pump
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
41
Activity Attributes
Project: Keadue upgrade works/ Demolition Works Date:
Activity ID: 4.9.1 Activity: Demolish Existing WBS No:
Activity Description: This activity involves the demolishing of the existing WWTP
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Remove from Site
Type of Effort: This activity is a fixed duration activity which will occur over a period of five days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Demolition Works Date:
Activity ID: 4.9.2 Activity: Remove from Site WBS No:
Activity Description: This activity involves the removing of the old WWTP off site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Demolish Existing
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of five days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
42
Activity Attributes
Project: Keadue upgrade works/ Site Finishing Date:
Activity ID: 4.10.1 Activity: landscaping WBS No:
Activity Description: This activity involves the landscaping of the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Planting
Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Site Finishing Date:
Activity ID: 4.10.2 Activity: Planting WBS No:
Activity Description: This activity involves the planting of new plants on the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: landscaping
Activity Successors: Fencing
Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
43
Activity Attributes
Project: Keadue upgrade works/ Site Finishing Date:
Activity ID: 4.10.3 Activity: Fencing WBS No:
Activity Description: This activity involves the fencing around the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Planting
Activity Successors: Painting
Type of Effort: This activity is a fixed duration activity which will occur over a period of five days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Site Finishing Date:
Activity ID: 4.10.4 Activity: Painting WBS No:
Activity Description: This activity involves the painting of facilities around the site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Fencing
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
44
Activity Attributes
Project: Keadue upgrade works/ Testing Date:
Activity ID: 5.1 Activity: Air Testing Sewer Network
WBS No:
Activity Description: This activity involves the testing of the sewer network to ensure all connections pipes are working
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Testing BMS Unit
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Testing Date:
Activity ID: 5.2 Activity: Testing BMS Unit WBS No:
Activity Description: This activity involves the testing of the Package BMS system to insure its working
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Air Testing Sewer Network
Activity Successors: Testing Pump
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
45
Activity Attributes
Project: Keadue upgrade works/ Testing Date:
Activity ID: 5.3 Activity: Testing Pump WBS No:
Activity Description: This activity involves the testing of the pumps to insure there in working order
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Testing BMS Unit
Activity Successors:
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Completion Date:
Activity ID: 6.1 Activity: Final Inspection WBS No:
Activity Description: This activity involves the final inspection of all work carried out onsite
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors:
Activity Successors: Condition Survey of Roads and Paths
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
46
Activity Attributes
Project: Keadue upgrade works/ Completion Date:
Activity ID: 6.2 Activity: Condition Survey of Roads and Paths
WBS No:
Activity Description: This activity involves a survey of all roads and paths to insure there up to required standard
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Final Inspection
Activity Successors: CCTV Survey of Pipe work
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Completion Date:
Activity ID: 6.3 Activity: CCTV Survey of Pipe work
WBS No:
Activity Description: This activity involves the testing of the pipe work to insure there in working order
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Condition Survey of Roads and Paths
Activity Successors: Demobilisation of Site
Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
47
Activity Attributes
Project: Keadue upgrade works/ Completion Date:
Activity ID: 6.4 Activity: Demobilisation of Site
WBS No:
Activity Description: This activity involves the removing of site offices and plant machinery off site
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: CCTV Survey of Pipe work
Activity Successors: As Constructed Drawings
Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
Activity Attributes
Project: Keadue upgrade works/ Completion Date:
Activity ID: 6.5 Activity: As Constructed Drawings
WBS No:
Activity Description: This activity involves insuring site is of drawings specified
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: Demobilisation of Site
Activity Successors: Safety File Handover
Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints:
48
Activity Attributes
Project: Keadue upgrade works/ Completion Date:
Activity ID: 6.6 Activity: Safety File Handover
WBS No:
Activity Description: This activity involves the handing over of all files
Activity Responsibility: Sub - Contractor
Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task
Activity Predecessors: As Constructed Drawings
Activity Successors:
Type of Effort:
Location of Activity: Keadue Co Roscommon
Activity Assumptions:
Activity Constraints: