Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 1.1 Activity: Tendering/ Publish Project Details on E-Tenders

WBS No:

Activity Description: This activity involves summiting project details online for relevant parties interested

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires basic computer skills for details on E-tenders.

Activity Predecessors:

Activity Successors: Expressions of Interest

Type of Effort: This activity is a fixed duration activity which will have duration of 30 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 1.2 Activity: Tendering/ Expressions of Interest

WBS No:

Activity Description: This activity involves detailing/document all parties interested in the project

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires basic computer skills.

Activity Predecessors: Publish Project Details on E-Tenders

Activity Successors: Review Tender Pack

Type of Effort: This activity is a fixed duration activity which will have duration of 23 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 3: Activity Attributes

2

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 1.3 Activity: Tendering/ Review Tender Pack

WBS No:

Activity Description: This activity involves reviewing all necessary components of tender pack

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires basic computer skills.

Activity Predecessors: Expressions of Interest

Activity Successors: Preparation of BoQ

Type of Effort: This activity is a fixed duration activity which will have duration of 7 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 1.4 Activity: Tendering/ Preparation of BoQ

WBS No:

Activity Description: This activity involves Preparing a bill of quantities for project

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires basic computer skills for Preparation of BoQ.

Activity Predecessors: Review Tender Pack

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 7 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 4: Activity Attributes

3

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.1 Activity: Feasibility/ WWTP Selection

WBS No:

Activity Description: This activity involves selecting an appropriate WWTP based on chosen P.E size and cost.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires computer skills for WWTP Selection.

Activity Predecessors:

Activity Successors: Site Layouts

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.2 Activity: Feasibility/ Site Layouts

WBS No:

Activity Description: This activity involves preparing site layout drawings for project.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires computer skills AutoCAD and software's for the decision on the Site layout.

Activity Predecessors: WWTP Selection

Activity Successors: Permits

Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 5: Activity Attributes

4

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.3 Activity: Feasibility/ Permits WBS No:

Activity Description: This activity involves contacting relevant authorities to obtain necessary permits i.e. discharge permits etc

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Site Layouts

Activity Successors: Contractor Submissions

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.4 Activity: Feasibility/ Contractor Submissions

WBS No:

Activity Description: This activity involves detailing all submissions received from the contractor.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Permits

Activity Successors: Material Submissions

Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 6: Activity Attributes

5

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.5 Activity: Feasibility/ Material Submissions

WBS No:

Activity Description: This activity involves detailing all relevant material submissions for the project.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Contractor Submissions

Activity Successors: Plant Submissions

Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.6 Activity: Feasibility/ Plant Submissions

WBS No:

Activity Description: This activity involves detailing all relevant plant submissions for the project.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Material Submissions

Activity Successors: Health & Safety Audits

Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 7: Activity Attributes

6

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.7 Activity: Feasibility/ Health & Safety (H & S) Audits

WBS No:

Activity Description: This activity involves preparing a health and safety audit for the continued development and implementation of H & S throughout the project

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Plant Submissions

Activity Successors: Human resources

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.8 Activity: Feasibility/ Human resources

WBS No:

Activity Description: Human resources is required to distinguish roles and responsibilities for the project and to organize organizational charts and a staffing Management Plan

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Health & Safety (H & S)Audits

Activity Successors: Procurement Completion

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 8: Activity Attributes

7

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.1.9 Activity: Feasibility/ Procurement Completion

WBS No:

Activity Description: This activity involves bringing the project procurement to a completion

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Human resources

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.2.1 Activity: Contact Suppliers/ WWTP Supplier

WBS No:

Activity Description: This activity involves ordering WWTP systems/materials

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Concrete Supplier

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 9: Activity Attributes

8

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.2.2 Activity: Contact Suppliers/ Concrete Supplier

WBS No:

Activity Description: This activity involves ordering concrete supplies.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: WWTP Supplier

Activity Successors: Building Materials Supplier

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.2.3 Activity: Contact Suppliers/ Building Materials Supplier

WBS No:

Activity Description: This activity involves ordering building materials supplies

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Concrete Supplier

Activity Successors: Plant Hire

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 10: Activity Attributes

9

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.2.4 Activity: Contact Suppliers/ Plant Hire

WBS No:

Activity Description: This activity involves hiring plant machinery for site

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Building Materials Supplier

Activity Successors: Submit Tender

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.2.5 Activity: Contact Suppliers/ Submit Tender

WBS No:

Activity Description: This activity involves submitting for tendering

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Plant Hire

Activity Successors: Tender Awarded

Type of Effort: This activity is a fixed duration activity which will have duration of 0 day.

Location of Activity: All work associated with this activity will occur at head office

Activity Assumptions:

Activity Constraints: :

Page 11: Activity Attributes

10

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 2.2.6 Activity: Contact Suppliers/ Tender Awarded

WBS No:

Activity Description: This activity mean rewarding successful contractor with project

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Submit Tender

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 0 day.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 3.1 Activity: Preliminaries / Insurance

WBS No:

Activity Description: Insurance is the equitable transfer of the risk of a loss, from one entity to another in exchange for payment. It is a form of risk management primarily used to hedge against the risk of a contingent, uncertain loss.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Employers' Liability Insurance

Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Page 12: Activity Attributes

11

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 3.2 Activity: Preliminaries / Employers' Liability Insurance

WBS No:

Activity Description: Coverage against common law liability of an employer for accidents to employees, as distinguished from liability imposed by a workers' compensation law.

Activity Responsibility: Contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Insurance

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.

Location of Activity: All work associated with this activity will occur at head office.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.1.1 Activity: Commencing on Site / Site Office

WBS No:

Activity Description: This activity involves setting up site office on site for duration of the project

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Commencing on site

Activity Successors: Office Equipment

Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints: :

Page 13: Activity Attributes

12

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.1.2 Activity: Commencing on Site / Office Equipment

WBS No:

Activity Description: This activity involves setting up all necessary office equipment for duration of project.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Site office

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.2.1 Activity: Mobilisation / Traffic Management

WBS No:

Activity Description: This activity involves setting up a traffic management plan to control and direct traffic in a safe manner during construction of the project.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Site Safety Induction

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints: :

Page 14: Activity Attributes

13

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.2.2 Activity: Mobilisation / Site Safety Induction

WBS No:

Activity Description: Site induction communicates essential information regarding the site, the working methods and health and safety management.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Traffic Management

Activity Successors: Road Brushing

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.2.3 Activity: Mobilisation / Road Brushing

WBS No:

Activity Description: This activity involves removal of necessary brush from roadside ditches for the safety of the travelling public

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Site Safety Induction

Activity Successors: Site Clearing Plant & Equipment

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints: :

Page 15: Activity Attributes

14

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.2.4 Activity: Mobilisation / Site Clearing Plant & Equipment

WBS No:

Activity Description: This activity involves hiring of necessary plant equipment for clearing of construction site

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires Site experience for Clearing Plant & Equipment.

Activity Predecessors: Road Brushing

Activity Successors: Excavation Equipment

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.2.5 Activity: Mobilisation / Excavation Equipment

WBS No:

Activity Description: This activity involves hiring of necessary excavation equipment for clearing of construction site

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires Site experience for Excavation Equipment.

Activity Predecessors: Site Clearing Plant & Equipment

Activity Successors: Paving Equipment

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 16: Activity Attributes

15

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.2.6 Activity: Mobilisation / Paving Equipment

WBS No:

Activity Description:

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: This activity requires Site experience for Paving Equipment.

Activity Predecessors: Excavation Equipment

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.3.1 Activity: Temporary Works / Site Security Fencing

WBS No:

Activity Description: This activity involves setting up of fencing around the site for public safety.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Car Parking

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 17: Activity Attributes

16

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.3.2 Activity: Temporary Works / Car Parking

WBS No:

Activity Description: This activity involves construction of temporary car park for onsite for duration of project.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Site Security Fencing

Activity Successors: Site Entrance / Access

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints: :

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.3.3 Activity: Temporary Works / Site Entrance and Access

WBS No:

Activity Description: This activity involves providing site entrance/access for to construction site.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Car Parking

Activity Successors: Temporary Site Services

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 18: Activity Attributes

17

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.3.4 Activity: Temporary Works / Temporary Site Services

WBS No:

Activity Description: This activity involves setting site up temporary site services for duration of project i.e. plumbing and electrics.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Site Entrance / Access

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.4.1 Activity: Ground Works/ Site Clearing

WBS No:

Activity Description: This activity involves clearing the site and getting it ready for construction.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Strip Top Soil

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 19: Activity Attributes

18

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.4.2 Activity: Ground Works/ Strip Top Soil

WBS No:

Activity Description: This activity involves the stripping back of top soil.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Site Clearing

Activity Successors: Top Soil Storage

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.4.3 Activity: Ground Works/ Top Soil Storage

WBS No:

Activity Description: This activity involves the storing of the top soil removed.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Strip Top Soil

Activity Successors: Trial Holes

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 20: Activity Attributes

19

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.4.4 Activity: Ground Works/ Trial Holes

WBS No:

Activity Description: This activity involves trial holes been dug to determine the geology and water table of the site.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Top Soil Storage

Activity Successors: Set Out Site

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.4.5 Activity: Ground Works/ Set Out Site

WBS No:

Activity Description: This activity involves setting out the site is to stake out reference points and markers that will guide the construction of new structures such as roads or buildings.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Trial Holes

Activity Successors: Place Access Road Sub-Base

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 21: Activity Attributes

20

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.4.6 Activity: Ground Works/ Place Access Road Sub-Base

WBS No:

Activity Description: This activity involves laying the sub base and providing and access road to the site.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Set Out Site

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.1 Activity: Control Room/ Setting Out

WBS No:

Activity Description: This activity involves setting out the site to stake out reference points and markers that will guide the construction of the Control room.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Excavate for Foundations and Services

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 22: Activity Attributes

21

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.2 Activity: Control Room/ Excavate for Foundations and Services

WBS No:

Activity Description: This activity involves excavating for foundations/ services for the control room.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Setting Out

Activity Successors: Pour Foundations

Type of Effort: This activity is a fixed duration activity which will have duration of 2 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.3 Activity: Control Room/ Pour Foundations

WBS No:

Activity Description: The activity involves the pouring of concrete for the foundations.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate for Foundations / Services

Activity Successors: Block Work

Type of Effort: This activity is a fixed duration activity which will have duration of 1 day.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 23: Activity Attributes

22

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.4 Activity: Control Room/ Block Work

WBS No:

Activity Description: This activity involves the laying of blocks by a competent builder.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Pour Foundations

Activity Successors: Roof

Type of Effort: This activity is a fixed duration activity which will have duration of 4 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.5 Activity: Control Room/ Roof WBS No:

Activity Description: This activity involves the building of the roof by a competent carpenter.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Block Work

Activity Successors: Finishing

Type of Effort: This activity is a fixed duration activity which will have duration of 4 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 24: Activity Attributes

23

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.6 Activity: Control Room/ Finishing

WBS No:

Activity Description: This activity involves the finishing of the control room.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Roof

Activity Successors: Wiring

Type of Effort:

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.7 Activity: Control Room/ Wiring

WBS No:

Activity Description: This activity involves the wiring of the control room by a competent electrician.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Finishing

Activity Successors: Control Panels (ICS)

Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 25: Activity Attributes

24

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.8 Activity: Control Room/ Control Panels (ICS)

WBS No:

Activity Description: This activity involves the installing of control panels for the WWTP.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Wiring

Activity Successors: Re-Furbish

Type of Effort: This activity is a fixed duration activity which will have duration of 7 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.9 Activity: Control Room/ Re-Furbish

WBS No:

Activity Description: This activity involves the refurbishing of the control room.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Control Panels (ICS)

Activity Successors: Windows

Type of Effort:

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 26: Activity Attributes

25

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.10 Activity: Control Room/ Windows

WBS No:

Activity Description: This activity involves the placing/fitting of the windows.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Re-Furbish

Activity Successors: Painting

Type of Effort: This activity is a fixed duration activity which will have duration of 0.5 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Upgrade Works to WWTP at Keadue, Co. Roscommon

Date:

Activity ID: 4.5.11 Activity: Control Room/ Painting

WBS No:

Activity Description: This activity involves the painting of the control room.

Activity Responsibility: Relevant sub-contractor will be responsible for performing the work for this activity.

Resources and Skill Sets Required: Contractor has relevant skills set to complete this task

Activity Predecessors: Windows

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will have duration of 3 days.

Location of Activity: All work associated with this activity will occur at WWTP at Keadue.

Activity Assumptions:

Activity Constraints:

Page 27: Activity Attributes

26

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.1 Activity: Excavate for Sub-base

WBS No:

Activity Description: This activity involves the excavating of the sub base

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Place Hardcore Sub-base

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.2 Activity: Place Hardcore Sub-base

WBS No:

Activity Description: This activity involves the placing of the hardcore base

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate for Sub-base

Activity Successors: Erect Formwork

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 28: Activity Attributes

27

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.3 Activity: Erect Formwork WBS No:

Activity Description: This activity involves the erecting of the formwork

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Place Hardcore Sub-base

Activity Successors: Place Reinforcement

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.4 Activity: Place Reinforcement

WBS No:

Activity Description: This activity involves the placing of the steel reinforcement

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Erect Formwork

Activity Successors: Pour Concrete Sub-Base

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 29: Activity Attributes

28

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.5 Activity: Pour Concrete Sub-Base

WBS No:

Activity Description: This activity involves the pouring of the concrete

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Place Reinforcement

Activity Successors: Strike Formwork

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.6 Activity: Strike Formwork WBS No:

Activity Description: His activity involves the striking of the formwork

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Pour Concrete Sub-Base

Activity Successors: Install BMS units

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day week.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 30: Activity Attributes

29

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.7 Activity: Install BMS units WBS No:

Activity Description: This activity involves the installing of the new package WWTP

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Strike Formwork

Activity Successors: Connect new infrastructure

Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.8 Activity: Connect new infrastructure

WBS No:

Activity Description: This activity involves the connecting of all pipes into the package WWTP

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Install BMS units

Activity Successors: Commission

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 31: Activity Attributes

30

Activity Attributes

Project: Keadue upgrade works/ Package system Date:

Activity ID: 4.6.6.9 Activity: Commission WBS No:

Activity Description: This activity involves the commissioning of the new package WWTP

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Connect new infrastructure

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of two day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Reinstatement Date:

Activity ID: 4.6.7.1 Activity: Placing Concrete Kerbs

WBS No:

Activity Description: This activity involves the placing of the concrete kerbs around the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors:

Pedestrian Paths

Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 32: Activity Attributes

31

Activity Attributes

Project: Keadue upgrade works/ Reinstatement Date:

Activity ID: 4.6.7.2 Activity: Pedestrian Paths WBS No:

Activity Description: This activity involves the placing /laying out of pedestrian foot paths

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Placing Concrete Kerbs

Activity Successors: Replacing Top Soil

Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Reinstatement Date:

Activity ID: 4.6.7.3 Activity: Replacing Top Soil

WBS No:

Activity Description: This activity involves the replacing of the top soil around the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Pedestrian Paths

Activity Successors: Seeding

Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 33: Activity Attributes

32

Activity Attributes

Project: Keadue upgrade works/ Reinstatement Date:

Activity ID: 4.6.7.4 Activity: Seeding WBS No:

Activity Description: This activity involves the reseeding of trees and plants around the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Replacing Top Soil

Activity Successors: Bitumen layer to Road

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Reinstatement Date:

Activity ID: 4.6.7.5 Activity: Bitumen layer to Road

WBS No:

Activity Description: This activity involves the laying of the bitumen layer for the road

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Seeding

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 34: Activity Attributes

33

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.1 Activity: Set Out Proposed Pipe Network

WBS No:

Activity Description: This activity involves the setting out of the proposed pipe network

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Excavate for, and Construct Manhole 1

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.2 Activity: Excavate for, and Construct Manhole 1

WBS No:

Activity Description: This activity involves the constructing for a new manhole (MH1)

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Set Out Proposed Pipe Network

Activity Successors: Excavate & Lay Sewer Pipe A - B

Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 35: Activity Attributes

34

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.3 Activity: Excavate & Lay Sewer Pipe A - B

WBS No:

Activity Description: This activity involves the excavating and the laying of pipe work from A - B

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate for, and Construct Manhole 1

Activity Successors: Excavate for, and Construct Manhole 2

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.4 Activity: Excavate for, and Construct Manhole 2

WBS No:

Activity Description: This activity involves the constructing for a new manhole (MH2)

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate & Lay Sewer Pipe A - B

Activity Successors: Excavate & Lay Sewer Pipe B - C

Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 36: Activity Attributes

35

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.5 Activity: Excavate & Lay Sewer Pipe B - C

WBS No:

Activity Description: This activity involves the excavating and the laying of pipe work from B - C

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate for, and Construct Manhole 2

Activity Successors: Excavate for, and Construct Manhole 3

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.6 Activity: Excavate for, and Construct Manhole 3

WBS No:

Activity Description: This activity involves the constructing for a new manhole (MH3)

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate & Lay Sewer Pipe B - C

Activity Successors: Excavate & Lay Sewer Pipe C - D

Type of Effort: This activity is a fixed duration activity which will occur over a period of two days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 37: Activity Attributes

36

Activity Attributes

Project: Keadue upgrade works/ Sewer Connection Date:

Activity ID: 4.7.7 Activity: Excavate & Lay Sewer Pipe C - D

WBS No:

Activity Description: This activity involves the excavating and the laying of pipe work from C - D

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate for, and Construct Manhole 3

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.1 Activity: Excavate for Sub-base

WBS No:

Activity Description: This activity involves the excavating of the sub base

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Place Hardcore Sub-base

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 38: Activity Attributes

37

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.2 Activity: Place Hardcore Sub-base

WBS No:

Activity Description: This activity involves the placing of the hard core sub base

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Excavate for Sub-base

Activity Successors: Erect Formwork

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.3 Activity: Erect Formwork WBS No:

Activity Description: This activity involves the erecting of the formwork

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Place Hardcore Sub-base

Activity Successors: Place Reinforcement

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 39: Activity Attributes

38

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.4 Activity: Place Reinforcement

WBS No:

Activity Description: This activity involves the placing of the steel reinforcement

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Erect Formwork

Activity Successors: Pour Concrete Sub-Base

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.5 Activity: Pour Concrete Sub-Base

WBS No:

Activity Description: This activity involves the pouring of the concrete sub base

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Place Reinforcement

Activity Successors: Strike Formwork

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 40: Activity Attributes

39

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.6 Activity: Strike Formwork WBS No:

Activity Description: This activity involves the striking of the formwork

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Pour Concrete Sub-Base

Activity Successors: Backfill Surrounds

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.7 Activity: Backfill Surrounds WBS No:

Activity Description: This activity involves the backfilling in the surrounds of the pump chamber

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Strike Formwork

Activity Successors: Install Pump

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 41: Activity Attributes

40

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.8 Activity: Install Pump WBS No:

Activity Description: This activity involves the installing of the pump

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Backfill Surrounds

Activity Successors: Commission

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Pump Chamber Date:

Activity ID: 4.8.9 Activity: Commission WBS No:

Activity Description: This activity involves the commissioning of the pump house

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Install Pump

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 42: Activity Attributes

41

Activity Attributes

Project: Keadue upgrade works/ Demolition Works Date:

Activity ID: 4.9.1 Activity: Demolish Existing WBS No:

Activity Description: This activity involves the demolishing of the existing WWTP

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Remove from Site

Type of Effort: This activity is a fixed duration activity which will occur over a period of five days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Demolition Works Date:

Activity ID: 4.9.2 Activity: Remove from Site WBS No:

Activity Description: This activity involves the removing of the old WWTP off site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Demolish Existing

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of five days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 43: Activity Attributes

42

Activity Attributes

Project: Keadue upgrade works/ Site Finishing Date:

Activity ID: 4.10.1 Activity: landscaping WBS No:

Activity Description: This activity involves the landscaping of the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Planting

Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Site Finishing Date:

Activity ID: 4.10.2 Activity: Planting WBS No:

Activity Description: This activity involves the planting of new plants on the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: landscaping

Activity Successors: Fencing

Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 44: Activity Attributes

43

Activity Attributes

Project: Keadue upgrade works/ Site Finishing Date:

Activity ID: 4.10.3 Activity: Fencing WBS No:

Activity Description: This activity involves the fencing around the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Planting

Activity Successors: Painting

Type of Effort: This activity is a fixed duration activity which will occur over a period of five days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Site Finishing Date:

Activity ID: 4.10.4 Activity: Painting WBS No:

Activity Description: This activity involves the painting of facilities around the site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Fencing

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 45: Activity Attributes

44

Activity Attributes

Project: Keadue upgrade works/ Testing Date:

Activity ID: 5.1 Activity: Air Testing Sewer Network

WBS No:

Activity Description: This activity involves the testing of the sewer network to ensure all connections pipes are working

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Testing BMS Unit

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Testing Date:

Activity ID: 5.2 Activity: Testing BMS Unit WBS No:

Activity Description: This activity involves the testing of the Package BMS system to insure its working

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Air Testing Sewer Network

Activity Successors: Testing Pump

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 46: Activity Attributes

45

Activity Attributes

Project: Keadue upgrade works/ Testing Date:

Activity ID: 5.3 Activity: Testing Pump WBS No:

Activity Description: This activity involves the testing of the pumps to insure there in working order

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Testing BMS Unit

Activity Successors:

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Completion Date:

Activity ID: 6.1 Activity: Final Inspection WBS No:

Activity Description: This activity involves the final inspection of all work carried out onsite

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors:

Activity Successors: Condition Survey of Roads and Paths

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 47: Activity Attributes

46

Activity Attributes

Project: Keadue upgrade works/ Completion Date:

Activity ID: 6.2 Activity: Condition Survey of Roads and Paths

WBS No:

Activity Description: This activity involves a survey of all roads and paths to insure there up to required standard

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Final Inspection

Activity Successors: CCTV Survey of Pipe work

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Completion Date:

Activity ID: 6.3 Activity: CCTV Survey of Pipe work

WBS No:

Activity Description: This activity involves the testing of the pipe work to insure there in working order

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Condition Survey of Roads and Paths

Activity Successors: Demobilisation of Site

Type of Effort: This activity is a fixed duration activity which will occur over a period of one day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 48: Activity Attributes

47

Activity Attributes

Project: Keadue upgrade works/ Completion Date:

Activity ID: 6.4 Activity: Demobilisation of Site

WBS No:

Activity Description: This activity involves the removing of site offices and plant machinery off site

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: CCTV Survey of Pipe work

Activity Successors: As Constructed Drawings

Type of Effort: This activity is a fixed duration activity which will occur over a period of half a day.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Activity Attributes

Project: Keadue upgrade works/ Completion Date:

Activity ID: 6.5 Activity: As Constructed Drawings

WBS No:

Activity Description: This activity involves insuring site is of drawings specified

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: Demobilisation of Site

Activity Successors: Safety File Handover

Type of Effort: This activity is a fixed duration activity which will occur over a period of three days.

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints:

Page 49: Activity Attributes

48

Activity Attributes

Project: Keadue upgrade works/ Completion Date:

Activity ID: 6.6 Activity: Safety File Handover

WBS No:

Activity Description: This activity involves the handing over of all files

Activity Responsibility: Sub - Contractor

Resources and Skill Sets Required:. Contractor has relevant skills set to complete this task

Activity Predecessors: As Constructed Drawings

Activity Successors:

Type of Effort:

Location of Activity: Keadue Co Roscommon

Activity Assumptions:

Activity Constraints: