act ground water

Upload: jadavrima

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Act Ground Water

    1/41

    Dewatering/Ground Water Control

    1

  • 7/29/2019 Act Ground Water

    2/41

    DefinitionGround water can be defined as water which is heldtemporarily in the soil above the level of water table

    Dewatering is a process to lower down the water table togive reasonably dry working conditions especially for

    excavations activities.

    2

  • 7/29/2019 Act Ground Water

    3/41

    Control of Ground WaterCan be divided into two groups:

    Permanent exclusion of ground water (cut-off wall tothe flow of ground water)

    Temporary exclusion of ground water by lowering downthe water table

    3

  • 7/29/2019 Act Ground Water

    4/41

    Control of Ground Water

    4

  • 7/29/2019 Act Ground Water

    5/41

    5

  • 7/29/2019 Act Ground Water

    6/41

    SUMP PUMPING Pumping from sumps is the most widely used since it can

    be applied to all types of ground conditions and iseconomical to install and maintain.

    The only problem is the settlement: the ground is likely tomove as the water flows towards the sump area. There is also a risk of instability at the formation level in

    supported excavations, owing to the upward movement ofwater.

    These problems can be partially overcome by positioningthe sump at a corner of the excavation at a level below theformation level

    6

  • 7/29/2019 Act Ground Water

    7/41

    OPEN PUMPING / SUMP PUMPING

    pumping from sumps and ditches

    least expensive method: from the standpoint of direct dewatering cost

    if conditions are wrong, it can result in delays, cost

    overrun or catastrophic failures

    must identify those conditions that are not favorable toopen pumping before deciding to proceed with it:

    impairing the foundation of proposed structure or of

    existing structure nearby

    delaying the project or escalating cost of excavation

    endangering workers

    SUMP PUMPING

    7

  • 7/29/2019 Act Ground Water

    8/41

    SUMP PUMPING

    sump below formation level in corner of

    excavation

    8

  • 7/29/2019 Act Ground Water

    9/41

    SUMP PUMPING

    9

  • 7/29/2019 Act Ground Water

    10/41

    Jetted Sump Detail

    10

  • 7/29/2019 Act Ground Water

    11/41

    WELLPOINT SYSTEM

    has been used> 50 years, most versatile method and

    effective in all type of soil

    may not be the most economical method for a given

    job due to advances in other pre drainage tool

    most suitable for shallow aquifer (water level need

    to be lowered < 6 m)

    multi stages will be used for lowering > 6 m

    11

  • 7/29/2019 Act Ground Water

    12/4112

  • 7/29/2019 Act Ground Water

    13/41

    well points13

  • 7/29/2019 Act Ground Water

    14/41

    14

  • 7/29/2019 Act Ground Water

    15/41

    15

  • 7/29/2019 Act Ground Water

    16/41

    16

  • 7/29/2019 Act Ground Water

    17/41

    DEEP BORED WELLS

    Each with individual pump (involve a high unit cost) Advances in well design (aquifer analysis) and

    construction techniques, and pump technology have

    made it practical to utilize deep well

    Best suited to homogeneous aquifers that extendedwell below the excavation level

    Can be installed to greater depth (up to 12 m)

    Volume pumped by each well is high thus wider

    spacing is practical

    Careful exploration, including a pump test, must be

    carried out before undertaking this method

    17

  • 7/29/2019 Act Ground Water

    18/41

    DEEP BORED WELL

    18

  • 7/29/2019 Act Ground Water

    19/41

    Horizontal Ground Water Control

    19

  • 7/29/2019 Act Ground Water

    20/41

    Horizontal Ground Water Control Installing into the ground 100mm diameter PVC

    perforated suction pipe covered with a nylon filtersleeve to prevent the infiltration of fine particles

    Using special machine which excavate a narrowtrench, lays the pipe and backfill the excavation

    20

  • 7/29/2019 Act Ground Water

    21/41

    Horizontal Ground Water Control

    Procedure:

    To sink a lined shaft by boring methods into claylayers.

    Shaft is large enough to allow men to go down & installhorizontal wells, which are jacked into ground.

    Wells consist of outer and inner casing.

    Wells are provided with valves, where they pass

    through the wall of shaft. It the method of permanent drainage measure.

    21

  • 7/29/2019 Act Ground Water

    22/41

    Electro-osmosis

    22

  • 7/29/2019 Act Ground Water

    23/41

    Electro-osmosis Uncommon method

    Costly

    Cohesive soils- clay and silts On the principles that soils carry a negative charge.

    Insert two electrodes and passing electric chargebetween them, anode and cathode (well point)

    Electric current is passed between the anode andcathode causes the positively charged water moleculeto flow the well point.

    23

  • 7/29/2019 Act Ground Water

    24/41

    24

  • 7/29/2019 Act Ground Water

    25/41

    GROUTING METHOD CEMENT GROUT

    - form a curtain. Mixture of neat cement and water

    CLAY/CEMENTS GROUT

    - suitable for sand and gravels where soil particles are too small for cement grout.

    Bentonite with additive (Portland cement/soluble silicates) CHEMICAL GROUTING

    - for medium to coarse sands and gravels. The chemical form a permanent gel

    RESIN GROUTING

    - for silty fine sand, similar application of chemical grouts

    BITUMINOUS GROUT

    - For fine sand to decrease permeability not increase the strength thus unsuitable forunderpinning works

    GROUT INJECTION

    - Grouts of all kinds are usually injected into the subsoil by pumping in the mixture athigh pressure through tubes.

    25

  • 7/29/2019 Act Ground Water

    26/41

    GROUTING

    Grouting is a displacement process in which a fluid, overlying the voids inGroundmass (soil or rocks) is placed by another fluid which is more suitablefor improving the properties of the groundmass.

    This fluid will solidify overtime by physio-chemical action and interaction with

    pores. This grouting increasing the strength and/or reducing the permeability of

    groundmass. Thus improving the characteristics of ground mass.

    The success of grouting is dependent in selection and type of grout materialsand suitable grouting technique.

    There are mainly two types of grouts which commonly used, cement grout andchemical grout/Chemical consolidation.

    26

  • 7/29/2019 Act Ground Water

    27/41

    27

    TYPICAL SKETCH OF GROUTING EQUIPMENT

  • 7/29/2019 Act Ground Water

    28/41

    Characteristics of Grout

    Stability of grout

    Particle size

    Viscosity Strength

    Permanence

    28

  • 7/29/2019 Act Ground Water

    29/41

    Types of Grout use Cement-based:

    * OPC/SRC.

    * Cement/ Bentonite.

    * Cement/Sand.

    * Cement/ Fly ash

    * Micro fine Cement

    Chemical based:* Sodium Silicates.

    * Polyurethanes.

    * Resins.

    * Asphalt emulsion

    29

  • 7/29/2019 Act Ground Water

    30/41

    Procedure for cement grouting A small (100-200mm dia.) hole is drilled to the requireddepth.

    Injection pipes are installed into soil at design locations todesired depths.

    After placing pipe to the desired depth, the grout- a rock lessconcrete, is forced through the pipes.

    Injection continues until a pre-determined refusal pressureis reached or uplift occurs at the surface.

    The injection pipes are then raised to a shallower depth andthe process is repeated.

    30

  • 7/29/2019 Act Ground Water

    31/41

    Installation Process of Grid Pattern The installation of grouting for large area treatments follows the

    phase system as applied for Impact Compaction.

    The effective radius of the grout hole varies with the type of soilbeing treated.

    31

  • 7/29/2019 Act Ground Water

    32/41

    32

  • 7/29/2019 Act Ground Water

    33/41

    33

    The neat cement grout isinjected through a smallnozzle at high pressure andmixes with the in-situ soil.

    This method produces themost homogeneous soil-cement element with thehighest strength and the

    least amount of grout spoilreturn.

  • 7/29/2019 Act Ground Water

    34/41

    Clay Grouting Injection of bitumen emulsion or slurries of clay or

    bentonite.

    Grouting with chemically treated bentonite clay can

    be used for impermeable cut offs in alluvial strata. Method is applicable by using bentonite clay in

    combination with Portland cement , soluble silicateand other agent in different proportion.

    Larger voids are filled with clay cement grout followedby clay- chemical grout with finer material.

    34

  • 7/29/2019 Act Ground Water

    35/41

    Chemical Consolidation Chemical injection is applicable for sandy gravels and

    sand of finest grading.

    Chemical Used is sodium silicate in conjunction with

    other chemical which forms silica get. Pipes are driven into the ground about 0.5m apart &

    Calcium chloride is injected down followed by sodiumsilicate ,which is known as two shot method.

    Complete cut off of water can be obtained byrepetition of injection.

    35

  • 7/29/2019 Act Ground Water

    36/41

    Freezing Suitable method for all types of subsoils with a

    moisture content in excess of 8% of the voids

    Insert freezing tubes into ground and circulate afreezing solution around the tubes to form ice in thevoids

    Thus creating a wall of ice to act as impermeable

    barrier Circulating solution magnesium chloride/calcium

    chloride at -15 and -25 c

    Liquid Nitrogen is more suitable then chilled brine.

    36

  • 7/29/2019 Act Ground Water

    37/41

    Freezing

    highly effective cutoff and ground support 37

  • 7/29/2019 Act Ground Water

    38/41

    Vibro Floatation

    38

    Vibro flotation is a techniquefor in situ densification of thicklayers of loose granular soildeposits. It was developed inGermany in the 1930s. Vibrators are inserted intoloose granular soils & withdrawnby leaving a column ofcompacted soils.

    Vibro flotation Procedures

  • 7/29/2019 Act Ground Water

    39/41

    Vibro flotation-Procedures

    39

    .

    Stage1: The jet at the bottom of the Vibro float is turned on and lowered into theground.

    Stage2: The water jet creates a quick condition in the soil. It allows the vibratingunit to sink into the ground

    Stage 3: Granular material is poured from the top of the hole. The water from thelower jet is transferred to the jet at the top of the vibrating unit. This water carriesthe granular material down the hole

    Stage 4: The vibrating unit is gradually raised in about 0.3-m lifts and held vibratingfor about 30 seconds at each lift. This process compacts the soil to the desired unit

    weight.

  • 7/29/2019 Act Ground Water

    40/41

    VibroflotationGround Type Relative Effectiveness

    Sands Excellent

    Silty Sands Marginal to Good

    Silts Poor

    Clays Not applicable

    Mine Spoils Good (if granular)

    Dumped Fill Depends upon nature offill

    Garbage Not Applicable

  • 7/29/2019 Act Ground Water

    41/41

    Appropriate dewatering MethodsEffective Grain Size(D10)

    Example Dewatering Method

    Larger than 0.1mm

    0.1 004 mm

    0.004 0.0017 mm

    Gravel, rock, boulders

    Sand

    Silt, clay

    Sumps, ordinary wellpoints

    Vacuum wells or wellpoints

    Electro osmosis