ac/dc isolated boost converter for direct connection of ... · the high voltage direct current –...
TRANSCRIPT
1
AC/DC isolated boost converter for direct connection of wind
generators to HVDC cable
Bruno Miguel Dias Raposo,
Instituto Superior Técnico – UTL,
Lisboa, Portugal
Abstract – Wind generation seems to be one of the most
relevant sources of renewable energy, providing an
alternative to conventional energy sources. However, most of
the places onshore that assure an economic viability has been
taken or are restricted by environmental organizations.
Furthermore, for offshore wind farms there are no obstacles
to slow down the wind speeds, making the sea a suitable
place to install wind turbines. However, one of the big
challenges can be the long distance to the onshore power
substation, in order to take advantage of the strong wind
speeds far offshore. Therefore, an alternative to the AC
power transmitting technique is needed, because when the
cables transmit large amounts of AC energy they generate
significant amounts of reactive power which have to be
compensated with expensive equipment (STATCOMs or
capacitor banks for example). Dielectric losses or the need to
use several cables in parallel are also constraining factors.
The DC technology does not have these problems, becoming
an option to be taken in account when we want to link
offshore wind parks to the onshore grid. The work proposes
a power conversion to interface the offshore wind park
turbine to a DC cable using an innovative solution that
associates an isolated Boost Converter with a high frequency
tri-phase transformer (2 kHz), followed by a series
association of diode rectifiers. This association will be
studied, analyzed and reviewed in terms of electrical
viability for this application.
Key-words: Offshore wind parks, HVDC, Active-Clamp Full-
Bridge Boost Converter, PMSG, wind turbine clusters.
I. INTRODUCTION
Our social model is firmly dependent of the electricity
production which has raised several issues over time. The
emissions of CO2 to the atmosphere by burning fossil
fuels or the continued use of this raw material to
exhaustion are just some of them. In this context
renewable energies can matter. Wind energy has been
gaining ground in the electrical power generation. In
nominal operation, it is possible to produce large amounts
energy. On the other hand the high volatility and
irregularity of wind, makes wind an almost non
predictable energy source with low duty factor. So it is
always necessary to build thermal power plants to work as
a "backup". However, the winds are more stable and
predictable offshore, therefore offshore wind turbines can
be more successful. There are some challenges like
extreme environment, corrosion of the materials due to the
salinity, large distance to shore, among others. However
there are advantages as well. Europe alone has a large
wind potential to be explored, reduced visual pollution
and existent infrastructures to be used from the oil
platforms out of service [1][2]. In Europe, the United
Kingdom was the one that installed more offshore wind
turbine in 2011, followed by Denmark and Netherlands
[3]. Portugal installed a 2 MW wind turbine for testing,
the Wind Float project. Normally, these wind turbines
have a 50/60Hz transformer. However, in this article it
will be used a high frequency transformer (2 kHz) in order
to be smaller/lighter than a transformer of the same
power. This is ideal for applications that require
transformers inside the turbine itself. The system must
increase (using some steps) the voltage supplied by the
generator to transmission levels in order to minimize
losses in the HVDC cable. Generating high voltages
through the use of power converters has its drawbacks.
The semiconductors used will have to bear this same
voltage. The association in series of semiconductors is an
option, however risky because it may cause the failure of
switches due to poor synchronization or other issues.
Some solutions on the market circumvent these problems,
but require a substation at sea due to its size and weight.
What is proposed is a wind park arrangement and power
converters able to convert the 690 V ac from the generator
to a DC voltage (50 kV), without using series connection
of controlled power semiconductors.
Figure 1 - System in study
II. TRANSMITION SYSTEMS FOR OFFSHORE
WIND PARKS
A. Solutions Available
The High Voltage Alternating Current (HVAC) is the
most common way to transmit energy and the most used
around the globe. For this application, this technology is
2
limited by the distance of the park to shore.
Figure 2 – Electrical layout – HVAC [4]
The High Voltage Direct Current – Line Commutated
Converter (HVDC-LCC) is well known and is used to
transmit energy in DC. However, it is more expensive and
it is only economic viable for large amounts of energy and
long distances.
Figure 3 - Electrical layout - HVDC-LCC [4]
The High Voltage Direct Current – Voltage Source
Converter (HVDC-VSC) is the most recent of these
technologies, introduced to the market by ABB and
Siemens. It uses IGBTs and enables the control of active
and reactive power produced/consumed by the
installation.
Figure 4 - Electrical layout - HVDC-VSC
B. Proposed solution
The proposed structure is based on the association of
turbines in series or in parallel, forming clusters [5]. If we
choose to form clusters of turbines in parallel we must
have a transformer to raise the voltage levels of the
transmission or even to raise the voltage within the park.
The low voltage (high current) in the park and the
platform required by the fact of having a transformer will
increase the cost of the installation. The advantages are
that the transmission losses are further reduced since we
have high voltage, we have no reactive power and it is a
mature technique used over the years. An alternative to
the internal network of the park in AC and so the
transformer, consists in having the converters raising the
voltage to transmission levels. This assumption may not
be easy or even achievable due to limitations of the
semiconductors.
Figure 5 - Parallel clusters of turbines with AC internal network
and DC transmission [5]
If we choose to put turbines in series [5][6], we can
achieve higher voltage levels without an external
transformer. The losses are substantially reduced in the
park because the voltage is higher which result in a better
efficiency and less material needed. However losses in
converters remain significant, but this depends in the type
of converter used.
Figure 6 - Series clusters of turbines with DC internal network
and transmission
In this paper, for a typical wind farm of 100 turbines with
2MW each, it was chosen to place four close turbines in
series and it was assumed that each have in their terminals
50 kV DC, being 200 kV the transmission voltage. No
guarantee that they are optimal voltage levels, but these
values are proper to show the concept of system
operation.
3
Figure 7 - Proposed structure for the wind park
III. POWER CONVERTERS
A. Tri-phase association of DC-DC boost converters,
isolated with high frequency tri-phase transformer and
half-bridge rectifiers
This work studies a combination of three-phase DC-DC
boost converters with clamp circuits isolated by a high
frequency (2 kHz) three-phase transformer. In each block
the commands for the semiconductor are 120º advanced to
each other in order to obtain a balanced three-phase
system. The complete system is shown in Figure 9.
Connected to the transformer there are three half-bridge
rectifiers connected in series to obtain the 50kV DC
voltage. With this topology is intended to prevent the
placement of power semiconductor devices in series [7].
The input DC voltage is obtained by a three-phase
rectifier switching forced placed after the generator.
Figure 8 - Input voltage building
Figure 9 - Tri-phase association of DC-DC boost converters,
isolated with high frequency tri-phase transformer and double
half-bridge rectifiers
B. Active-Clamp Full-bridge boost converter
This Active-Clamp Full-bridge boost converter must raise
the AC voltage (690V) from the generator into DC
voltage (50kV) step-by-step. The rectified voltage (1.2
kV) of the permanent magnet synchronous generator
(PMSG) is obtained so the maximum possible power is
extracted using a unity power factor rectifier, described
later. Each block of Active-Clamp Full-bridge boost
converter, shown in Figure 10, is constituted by an
inductance L for an intermediate storage of energy which
then is delivered to the transmission cable. Below is a full
bridge to do the inversion from DC to AC.
Figure 10 - Active-Clamp Full-bridge boost converter,
transformer and double half-bridge rectifier
The semiconductors have the following behavior:
(1)
As the transformer is not ideal, the stray fluxes are
represented by a coil (primary), as shown in Figure
10, which cannot be neglected, since when all
semiconductors in the bridge are conducting, and
will be in series. Since the current will not be the same,
high voltages will be generated. For the circuit to operate
without these issues, we need a capacitor that will load
until the current in is equal to the one in . It
discharges when the voltage at its terminals is higher than
the primary of the transformer. However, in the situation
when all semiconductors are conducting, the capacitor
would be short-circuited. So it is necessary to place a
diode before Cc and a controlled semiconductor Sc
allowing the discharge of the capacitor. It will be ON
when S1, S2, S3 and S4 are not connected simultaneously.
As this is a boost converter, the equations in [8] are valid
to size the components. To control the current in the
inductance L, the control scheme in the Figure 11 is
presented.
Figure 11 - L current linear control
4
Table 1 - Parameters
Taking into account the losses in the system, we will have
an efficiency of 96%, which is acceptable. To command
the semiconductors we used the Pulse-width modulation
(PWM) technique because the times of conduction must
be equal in all the semiconductors so we don’t have any
DC component that can saturate the transformer.
Figure 12 - Current wave forms - boost converter
Figure 13 - Voltage wave forms - boost converter
As we can see in the Figure 13, the voltage is boosted
step-by-step along the components of the boost converter. The Figure 14 shows the controlled DC voltages at
several levels of the system. Compared with a standard
rectifier with diodes, this converter has several DC levels
of voltage, allowing a phased voltage boost.
Figure 14 - Controlled DC voltages of the boost converter
C. Three-phase rectifier switching forced
This converter will operate as an elevator three-phase
rectifier, in order to transform AC magnitudes generated
by the PMSG (690 V compounds) to DC magnitudes of
higher value (1200 V).
5
Figure 15 - Magnitudes generated by the PMSG rectification
The command chosen was the Nonlinear Vector Control
of Three-Phase Currents [8] which is based on comparing
currents in αβ coordinates with the reference currents and
using the sum of two hysteretic comparators, considering
the component as suggested in [9]. As we can see
in the Figure 16, the single phase voltage and the current
are in phase opposition, which means that the generator is
delivering energy to the system.
Figure 16 - Power, single-phase voltage and current – PMSG
Figure 17 - Output currents from the PMSG
To control the voltage 1,2 kV, the control scheme in the
Figure 18 is proposed.
Figure 18 - Input voltage 1,2 kV linear control
IV. WIND TURBINE CONTROL
A. Gear-Box
The link between the turbine and PMSG was made using
a gearbox, modeled by a gain. On one side we have about
20 rpm and the gearbox will have to increase this speed to
approximately 1500 rpm, the speed that most generators
require to produce electricity. The parameters used are
from [10].
(2)
( ) (3)
(4)
B. The Generator
The generator chosen for the wind turbines was the
Permanent Magnet Synchronous Generator (PMSG). This
choice is based on their viability and low maintenance.
The machine dynamics can be represented by a bi-phase
system, represented by two axes - the d axis aligned with
the rotor position and the q axis that lies ahead 90º from
the d axis [9].
Figure 19 – abc and dq coordinates in an electrical machine [9]
( )
( )
(5)
[ ( ) ] (6)
(7)
Table 2 - PMSG specifications
C. Wind Modulation
6
The kinetic energy available in the wind, combined with a
mass of air m that moves at constant and uniform speed u,
in a wind turbine is given by [11]:
(8)
Considering , the power available in
the wind is:
(9)
The Bezt limit, considering β the pitch angle, is given
by:
(10)
(
)
(11)
(12)
(13)
(14)
Based on [12], we can draw the turbine characteristics for
different wind speeds and a null pitch angle.
Figure 20 - β =0 turbine characteristics for different wind speeds
For the speed control of the wind turbine, the optimal
generator speed that grants the maximum power extracted
is:
(15)
The optimal value can be followed by the system using
the control scheme presented in the Figure 21.
Figure 21 - PMSG speed control
For the torque control of the wind turbine, the optimal
generator torque that grants the maximum power extracted
is:
(16)
The optimal value can be followed by the system using
the control scheme presented in the Figure 22.
Figure 22 - PMSG torque control
V. WIND PARK DC VOLTAGE CONTROL
A. HVDC Cable
The type of cable chosen for the connection between the
wind farm and the shore was the XLPE (Cross-linked
polyethylene). This is the type of cable used in most of the
applications at sea, having high elasticity, resistance to
abrasive elements and with extreme viability. In order to
calculate the losses in the HVDC cable, we must choose
the most appropriate for the situation. So it is necessary to
estimate the current that pass through it in nominal
conditions.
(17)
Consulting [13], we concluded that a 1400 mm2 cable is
suitable for this case because it has a rated current of
1600A, giving the system a good safety margin. Their
resistance per km in length is then:
(18)
Also from [13] we know that the cable have an
inductance . The distance that
the wind farm would be from the coast with this system
must be such that the HVDC had more advantages than
the HVAC. According to [14], when comparing HVDC
technology with the HVAC, the "break-even-point" will
be at around 100 km. From this distance it will be more
7
cost effective to install an HVDC system than a HVAC
one. This point varies from system to system because it
depends on the potency of the park, power electronics
used, types of cables, hand labor, required infrastructures,
among others.
Figure 23 - break-even-point [14]
(19)
The losses in the cable can be estimated by:
(20)
B. Cable voltage control 200kV
The architecture and inverter operation on land that will
connect the cable to the HVDC grid are not in the goals of
this article [15]. However, controlling the DC voltage for
200kV must be done, since this is essential to the wind
farm. To simulate the control of this magnitude we
decided to consider the control scheme in the Figure 24.
The wind farm generates a current which is divided
between a condenser and the inverter connected to the
grid.
Figure 24 - 200 kV voltage linear control
Figure 25 - Transmission voltage in HVDC cable
VI. RESULTS
The results are now presented.
Figure 26 - Wind speed profile [19]
Figure 27 - Reference and electromagnetic torque
Figure 28 - Reference and generator speed
8
Figure 29 - Power comparison between torque and speed control
VII. CONCLUSIONS
This paper investigated the possibility of using a three-
phase boost converter isolated with a high frequency
transformer and half-bridge double rectifiers associated in
series to transform 690VAC from the PMSG to the output
50kV DC of a wind turbine with a single converter and no
power semiconductors in series. The most important
advantage of this system is that no substation at sea is
required, reducing dramatically the installation cost.
Thanks to its electrical architecture, we can increase the
voltage to transmission levels, with equipment that fits
perfectly within the framework of the turbines. The
simulation results match the theoretical ones,
demonstrating that the system is properly designed and
with optimal conditions. Accounting system losses,
approximately 86.7 kW, we conclude that the efficiency is
about 96%, which is acceptable given the amount of
power electronics involved. Losses are well distributed
among the various elements of the system. The
simulations show a stable DC voltage in both the internal
network of the park as in the transmission cable, with no
significant ripples. The system responds very well to both
torque and speed controls, being able to follow the
optimal references, depending on the wind speed
occurring in a given instant. We also conclude that the
speed control takes over 7% more power at the startup
than the torque control. Within thirty seconds of
simulation the turbine can generate about 8.1 kWh of
energy.
VIII. REFERENCES
[1] Silva, Filipe, “Offshore wind Parks Electrical
Connection”, IST, Julho de 2008.
[2] Ackermann, Thomas, “Wind Power in Power
Systems”, Royal Institute of Technology, Sweden, 2005.
[3] J. Wilkes, J. Moccia, A. Arapogianni, M. Dragan, N.
Plytas, A. Genachte, J. Guillet, P. Wilczek, “The
European offshore wind industry key 2011 trends and
statistics”, The European Wind Energy Association
(EWEA), January 2012.
[4] Ulsund, Ragnar, “Offshore Power Transmission –
Submarine high voltage transmission alternatives”,
NTNU, 2009.
[5] A. Garcés, M. Molinas, “Coordinated control of
series-connected offshore wind park based on matrix
converters”, Wind Energy, 2011.
[6] Anish Prasai, Jung-Sik Yim, Deepak Divan, Ashish
Bendre, Seung-Ki Sul, Frank Kreikebaum, “A New
Architecture for Offshore Wind Farms”, Georgia Tech,
Atlanta, Seoul National University Korea, DRS
Technologies.
[7] Martins, H., “Interactive anti-islanding inverter”, IST,
Outubro de 2009.
[8] Alves da Silva, J. F., “Sistemas de Energia em
Telecomunicações: Textos de Apoio”, DEEC, Instituto
Superior Técnico.
[9] Domingos Marques, G., “Controlo de Motores
Elétricos”, Fevereiro 2007.
[10] Ming Yin, Gengyin Li, Ming Zhou, Chengyong
Zhao, “Modeling of the Wind Turbine with a Permanent
Magnet Synchronous Generator for Integration”, IEEE,
2007.
[11] Gameiro de Castro, R. M., “Uma Introdução às
Energias Renováveis: Eólica, Fotovoltaica e Mini-
hídrica”, Lisboa: IST Press, 1ª Edição.
[12] Catalogo V80-2MW VESTAS.
[13] XLPE Submarine Cable Systems – User’s Guide,
Rev 5, ABB
[14] Bresesti, Paola, “HVDC Connection of Offshore
Wind Farms to the Transmission System”, IEEE, Março
2007.
[15] Nunes, H., “Nova topologia de conversor multinível
para parques eólicos marinhos”, IST, Setembro de 2010.