accelerator systems management overview · pdf filekevin jones instrument ... lebt chopper...
TRANSCRIPT
ORNL is managed by UT-Battelle for the US Department of Energy
Accelerator Systems Management Overview
Presented to SNS Accelerator Advisory Committee Presented by Kevin Jones Research Accelerator Division Director March 24, 2015
3 Accelerator Systems Management Overview
There have been a number of management changes in NScD since the last meeting of the AAC
Associate Laboratory Director Paul Langan
Herb Mook, Senior Corporate Fellow Emeritus Jeanine Evans, Executive Secretary
Matrix Support Bonnie Hébert, HR Manager
Lorie Hickey, Business Manager
Directorate Operations Hans Vogel
Scientific and Program Services Office Crystal Schrof
Joint Institute for Neutron Sciences
Takeshi Egami
Deputy Associate Laboratory Director
Rob McQueeney
Chief Scientist
Alan Tennant
Research Reactors
Tim Powers
Research Accelerator Kevin Jones
Instrument and Source
Don Abercrombie (Acting)
Quantum Condensed Matter
Stephen Nagler
Chemical and Engineering Materials
Richard Ibberson
Neutron Data Analysis and Visualization Thomas Proffen
Biology and Soft Matter
Volker Urban (Acting)
4 Accelerator Systems Management Overview
Likewise, RAD has been reduced in size and scope to accommodate other organizational changes – mission remains focused on site, accelerator and target
Research Accelerator Division Kevin Jones, Director
Conventional Facility Operations
Sam McKenzie
Data Operations Karen White
Accelerator and Target Operations
George Dodson
Electrical and RF Systems
Mark Champion
Mechanical Systems and Operations
Michael Baumgartner
Superconducting Linac Systems
Sang-ho Kim
Maintenance Management &
Information Systems George Dodson
Accelerator Operations Glen Johns
Accelerator Physics, Beam Instrumentation
and Ion Source John Galambos
Control Systems Karen White
Instrument Data Acquisition and
Controls Steve Hartman
SNS ESH&Q Greg Rowland (Interim)
Facility Maintenance – Chestnut Ridge Sam McKenzie
Site Services Tom McLaughlin
NRPD Assignment – Radiological Control
George Stephens
Transferred to other organizations:
• Instrument Operations (ISD) • Scientific Information Systems (SPSO) • Deployed SNS IT (SPSO)
The RAD is responsible for the operation, maintenance and improvement of the SNS accelerator complex
The front end produces a 60 Hz, ~1 ms long chopped H- beam
Accumulator Ring: Compress ~1 msec pulse to 700 nsec
2.5 MeV
Superconducting LINAC Front-End
RTBT
HEBT
Injection Extraction
RF
Collimators
945 ns
1 ms macropulse
Cur
rent" mini-pulse
LEBT chopper system makes
gaps
Current"
1ms
Liquid Hg Target
~940 MeV
~1 ms macropulse 1 ms
~700 nsec
186 MeV
Warm Linac
• SNS is the highest power pulsed neutron source in the world
• The machine has over 100,000 control points and cycles ~5.2 million times a day
• Power (and base neutron flux) is the product of: – Beam Energy – Peak Current – Chopping Fraction
– Pulse Length – Repetition Rate
6 Accelerator Systems Management Overview
SNS design parameters Kinetic Energy 1.0 GeV Beam Power 1.4 MW Linac Beam Duty Factor 6% Modulator/RF Duty Factor Specification 8% Peak Linac Current 38 mA Average Linac Current 1.6 mA Linac pulse length 1.0 msec Repetition Rate 60 Hz SRF Cavities 81 Ring Accumulation Turns 1060 Peak Ring Current 25 A Ring Bunch Intensity 1.5x1014 Ring Space Charge Tune Spread 0.15
7 Accelerator Systems Management Overview
SNS performance relative to design Design Best
Ever Routine
Operation
Kinetic Energy [GeV] 1.0 1.07 0.939 Beam Power [MW] 1.4 1.427 0.8-1.35 Linac Beam Duty Factor [%] 6 6 5 Modulator/RF Duty Factor [%] 8 8 7 Peak Linac Current [mA] 38 42 35 Average Linac Current [mA] 1.6 1.6 1.1 Linac pulse length [msec] 1.0 0.98 0.8-0.9 Repetition Rate [Hz] 60 60 60 SRF Cavities 81 80 80 Ring Accumulation Turns 1060 1020 825 Peak Ring Current [A] 25 26 18 Ring Bunch Intensity 1.5x1014 1.55x1014 1.1x1014
Ring Space Charge Tune Spread 0.15 0.18 0.12
8 Accelerator Systems Management Overview
The SNS neutron source has achieved stable 1MW operation capability for 4500 hours at ≥90% reliability
Since FY09 the SNS neutron source has exceeded all DOE PMM operational commitments for hours delivered and availability
65#
70#
75#
80#
85#
90#
95#
0#
1000#
2000#
3000#
4000#
5000#
6000#
FY07# FY08# FY09# FY10# FY11# FY12# FY13# FY14# FY15#(02/15)#
Reliability#(%
)#
Hou
rs#or#MW/Hrs#
SNS#OperaEonal#Performance#FY07#/#FY15#
Neutron#ProducEon#Delivered#
Neutron#ProducEon#Commitment#
MW/Hr#
Down#Time#
Reliability#
Reliability#Commitment#
Incl
udes
101
8 ho
urs
from
targ
et fa
ilure
s
Incl
udes
415
hou
rs fr
om ta
rget
and
MEB
T fa
ilure
s
Incl
udes
894
hou
rs fr
om ta
rget
and
MEB
T fa
ilure
s
DOE PMM Hours and Availability are not the same as scheduled hours and availability: • Annual DOE BES
Facility Questionnaire submitted in October sets planned hours for that FY
• Neutron Production Commitment is 90% of planned hours
• Schedule has contingency and is published quarterly one month in advance
• Additional hours are provided
• Possible to meet DOE PMM of 90% while not meeting 90% against published schedule
9 Accelerator Systems Management Overview
SNS FY 2016 Q1-4 Planning Only (02-23-15)
1 1 1 1 1 1 1 1 1 1 1 12 2 2 2 2 2 2 2 2 2 2 23 3 3 3 3 3 3 3 3 3 3 34 4 4 4 4 4 4 4 4 4 4 45 5 5 5 5 5 5 5 5 5 5 56 6 6 6 6 6 6 6 6 6 6 67 7 7 7 7 7 7 7 7 7 7 78 8 8 8 8 8 8 8 8 8 8 89 9 9 9 9 9 9 9 9 9 9 910 10 10 10 10 10 10 10 10 10 10 1011 11 11 11 11 11 11 11 11 11 11 1112 12 12 12 12 12 12 12 12 12 12 1213 13 13 13 13 13 13 13 13 13 13 1314 14 14 14 14 14 14 14 14 14 14 1415 15 15 15 15 15 15 15 15 15 15 1516 16 16 16 16 16 16 16 16 16 16 1617 17 17 17 17 17 17 17 17 17 17 1718 18 18 18 18 18 18 18 18 18 18 1819 19 19 19 19 19 19 19 19 19 19 1920 20 20 20 20 20 20 20 20 20 20 2021 21 21 21 21 21 21 21 21 21 21 2122 22 22 22 22 22 22 22 22 22 22 2223 23 23 23 23 23 23 23 23 23 23 2324 24 24 24 24 24 24 24 24 24 24 2425 25 25 25 25 25 25 25 25 25 25 2526 26 26 26 26 26 26 26 26 26 26 2627 27 27 27 27 27 27 27 27 27 27 2728 28 28 28 28 28 28 28 28 28 28 2829 29 29 29 29 29 29 29 29 29 29 2930 30 30 30 30 30 30 30 30 30 30
31 31 31 31 31 31 31
Accelerator Physics Machine Downtime Major Periods(Maintenance/Upgrades)Accelerator Startup/Restore Scheduled Maintenance (starts at 06:30)Accelerator Physics/Maintenance Periods Neutron Production Major Unplanned Outages for Failures (background color is original plan) Transition to Neutron Production
Apr-2016 May-2016 Jun-2016 Jul-2016 Aug-2016 Sep-2016Oct-2015 Nov-2015 Dec-2015 Jan-2016 Feb-2016 Mar-2016
Apr-2016 May-2016 Jun-2016 Jul-2016 Aug-2016 Sep-2016Oct-2015 Nov-2015 Dec-2015 Jan-2016 Feb-2016 Mar-2016
SNS will have a significantly reduced operating schedule in FY2016 - ~3,500 scheduled hours for neutron production
• Current target may survive to end of FY2015 – will be at or near water shroud radiation damage limit • Inner Reflector Plug (IRP) is nearing end-of-life of ~32 GW-Hr (neutronic burn-up of moderator poisons) – could reach 32 GW-Hr in
December depending on operating conditions after April • New IRP scheduled for installation next summer – assumes delivery on schedule at end of CY2015 • Possible change-out of RFQ in parallel with IRP in Summer 2016
10 Accelerator Systems Management Overview
SNS experienced three major equipment failures in September – November 2014
SNS Target Module on Cart – Retracted Position
CV Seal Flange
Utility Jumpers
Shielded Cart
Replaceable Target Module
• At 10:30 pm on September 11, 2014 Target 10 indicated a mercury leak into the interstitial space that was confirmed using standard techniques
• While the target change was in progress, at 12:30 pm on September 15, 2014 the chopper target in the MEBT ruptured catastrophically, filling the MEBT vacuum envelope with water that vented through pressure relief valves
• At 11:45 pm on October 27, 2014 Target 11 indicated a mercury leak into the interstitial space that was again confirmed using standard techniques
• Again reduced to one spare target – entered target conservation mode with operation at 850 kW
MEBT Chopper Box – water visible in view ports
11 Accelerator Systems Management Overview
The MEBT water event was difficult to recover from
CV Seal Flange
Utility Jumpers
Shielded Cart
• DTL was also affected (isolation valve unseated under water pressure) requiring replacement of subset of ion pumps
• Electrically complex environment – needed comprehensive approach to hazardous energy control
• Required full disassembly of the MEBT (except for removing the 4 rebunching cavities) to properly dry and rehabilitate equipment
• Dewatering the rebunchers was tricky – final solution was to circulate heated glycol mix through the cooling passages at temperatures >100C but below O-ring limits of ~120C
• Excellent performance by a large team of people – no safety issues and only two minor equipment events during recovery
MEBT before disassembly
MEBT after disassembly
Dewatering rebunchers
12 Accelerator Systems Management Overview
SNS has also experienced a number of other operational events since March 2013
• The PPS event of August 2013 was very significant – ASE violation, and required DOE concurrence for restart, which was achieved in 9.5 days
Shielded Cart
FY 2014
Dec Jan FebMar Apr May Jun Jul Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep NovOctAug
FY 2013
LEGEND
- Radiological EventsTRCDART
- Injury Events
12
02
00
35
03
15
24
26
23
13
24
13
14
02
03
11
16
37
12
12
00
- Events to NTS Reportable
ORPS Events Non-ORPS Events
Failure to Wear PPE
Conduit Damaged During Excavation
Worker Suffers a Fracture of Right
Wrist
Worker Suffered a Metatarsal Bone Break
Employee Sustains Shoulder Injury
Resulting in Surgery
Mild Elec. Shock from Unplugged Lab. Equip.
Visiting Researcher Failed to Correctly
Apply LOTO
Hazardous Energy Control Procedural
Violation
Worker Suffers a fracture of Left Ankle
Unexpected Discharge of
Cryogenic Helium
Electrical Conduit Damaged during
Removal of Sidewalk
Facility Evacuation During Testing
Activity
Discovery of Non-Operable Safety System at SNS
Shoulder Injury Requiring Surgery
Worker Sustains Injury Requiring
Surgery
Employee Knee Injury Requiring
Surgery
Discovery of an Uncontrolled
Electrical Hazard
Injury to Arm Requiring Surgery
Electrical Program Weaknesses
Near Miss – Falling Hutch
Energized Electrical Cable
Severed
Elbow Injury Requiring Surgery
Fume Hood Fire with Explosion
Radioactive Sealed Source
Control
Subcontractor Injured Requiring
Surgery
Fire Engine Hose Bed Drive
Mechanism Fails
Employee Knee Injury Requiring
Surgery
13
Programming Error Results
in USQ
Knee Injury Requiring Surgery
Vacuum Tank Tips off Pallet
during Transport
13
01
Near Miss Installing a Glove
Box
Mild Electrical Shock (NNFD)
Contaminated Water in SNS
Off-Gas System
Vendor Receives Electrical Shock
Energized Electrical Cable
Severed
Energized Electrical Cable
Severed
Chronic Occupational
Illness
SNS Target Failure
SNS Target Failure
Mild Electrical Shock (ESD)
Discovery of Exposed Electrical
Contacts
Inconsistent Software Version
on IPPS (SNS)
Energized 120V Conduit Severed
Mild Electrical Shock (SNS)
Material Handling Programmatic
Unexpected Airborne
Radioactivity
Non-energized Electrical Cable
Removed during D&D
FY 2015
Worker Suffers Fractures to Both
Lower Legs
Worker Receives Shock from Jib Hoist
Fall Results in Fractured Wrist
SNS Linac Trap Key Assembly
Mechanical Failure
13 Accelerator Systems Management Overview
The outcome of the DOE Cost Review in November 2013 was generally positive for accelerator aspects
CV Seal Flange
Shielded Cart
• The advice received from this committee was helpful in our preparations
• “The reviewers noted the benefits and efficiencies of the new organization: – “The integration of the facility operations groups and crafts into the accelerator operations division.”
• “Other items of special mention from the reviewers: – “The high reliability of the accelerator and the continuing efforts to push toward the 1.4 MW design
power level. – “The effort to improve quality control and lifetime predictability of the SNS Hg target following the
disastrous sequential failure of two targets in October 2012.”
• “SNS Specific Recommendations: – “SNS must continue to make improvements that will facilitate sustained operation at the 1.4 MW
power level while maintaining better than 90% reliability. A timeline for 1.4 MW operation should be provided to BES.
– Target reliability and lifetime issues must be quantified so that a predictable run schedule can be maintained without major concern over unexpected target failures.”
• “The SNS and HFIR have demonstrated great progress over the past two plus years in reaching the goal of providing world leading scientific facilities for neutron scattering. … Optimization of …. must be the overarching priority for the facilities to meet or exceed their potential in producing high impact science. The management and staff are to be congratulated for embracing this goal and refocusing their efforts to achieve maximum scientific productivity.”
14 Accelerator Systems Management Overview
This committee is asked to assess our operations, our path to sustainable 1.4 MW operation, and the plans for the Second Target Station
CV Seal Flange
Shielded Cart
1. Assess the performance of the accelerator complex and neutron source since the last meeting.
2. Assess and provide advice on the plans for sustainable beam operation with availability at the ≥90% level at ~1.4MW beam power for 5000 operating hours per year in a constrained funding environment. Consider the lessons learned from the high power run in the first half of 2014 and current maintenance strategy.
3. Assess the adequacy of our approach to sustaining and developing critical systems, including High Voltage Converter Modulators, Superconducting Cavities (plasma processing), Injection Stripping (Foils, lasers), Personnel Protection System and Controls (including high level applications) and the Integrated Front End Test Stand facility.
4. Is the SNS response to the observed RFQ issues adequate?
5. Does the AIP investment strategy align with the 1.4MW reliable, sustainable operation and STS path?
6. Provide advice on the accelerator systems components of the draft technical design report for the Second Target Station and provide guidance on the reasonableness of the updated plan for the power upgrade in the SCL, with fewer new Cryo-modules than originally planned.
15 Accelerator Systems Management Overview
Summary • We can operate reproducibly with beam power ≥ 1 MW and availability ≥ 90%
• While we meet or exceed operating commitments many significant challenges remain
• Our immediate focus is on sustaining availability and continuing operation at the highest possible power subject to Target and RFQ limitations
• Our medium term effort will achieve reliable 1.4MW operation by 2017, lay the foundation for 3MW capability and maintain the potential to carry out the Second Target Station project
• Institutional commitment has been essential to our success
The hard work, dedication and talent of the SNS staff enable these achievements