repository.arizona.edu · abstract: this project involved designing a process that converts algae...
TRANSCRIPT
Gasification of Algae for the Production of CNG
Item Type text; Electronic Thesis
Authors Seamans, Kimberly Anne
Publisher The University of Arizona.
Rights Copyright © is held by the author. Digital access to this materialis made possible by the University Libraries, University of Arizona.Further transmission, reproduction or presentation (such aspublic display or performance) of protected items is prohibitedexcept with permission of the author.
Download date 31/01/2021 15:38:41
Link to Item http://hdl.handle.net/10150/146671
Abstract:
This project involved designing a process that converts algae into compressed natural gas
(CNG). The algae enter the process in a water slurry at 2.5% algae by mass. The algae are
then converted into methane and other gases at supercritical conditions in a reactor. The
gas mixture is then purified by removing the carbon dioxide and hydrogen gases. The
sellable products this process produces are CNG and hydrogen. In addition, the carbon
dioxide and salts are recycled back to the algae farms. This makes the process
environmentally responsible as the carbon dioxide created in the process is not released
to the atmosphere. Before the process is built, it is recommended that the reactor and salt
separator technologies are tested on a pilot scale to ensure their viability on an industrial
scale. A process hazard analysis was completed as a part of this project in order to
eliminate any safety issues with the process. Despite the process and equipment
optimizations that were performed, the economic analysis suggested that the process is
not economically viable. However, it may become viable in the future through the
development of the catalyst and equipment technologies.
Roles and Responsibilities of Group Members
My Honors Thesis is a part of a project completed with my senior design team.
My team members are Zachary Ronan, Kyle Kryger, and Amanda Rubio. Each team
member contributed to various sections and aspects of the project.
As the Project Manager, I was responsible for compiling the report and being the
main point of contact with our professor and our mentor. I also maintained continuous
communication between all members of the group and consistently issued group updates
with the most updated project information to ensure that everyone was aware of the
progress made, impeding internal and external deadlines, and individual assignments.
In the beginning of the semester, I took the initiative and did the majority of the
initial research for our project, finding the critical journal article on which our process
was primary based. I also created the original stream tables and equipment tables that
Kyle was later responsible for managing.
For the design aspect of the project, I assisted Zac Ronan by calculating the duties
of the heat exchangers, volume of the reactor, and mass of the catalyst. This involved
using fluid data tables to determine the heat capacities and researching the process and
catalyst. I also assisted Zac by typing up his calculations, which represents over fifty
pages of calculations given in Appendix A.
Another large part of my involvement in the project was writing several sections
of the report. I was responsible for writing the executive summary, introduction,
conclusions and recommendations, and the Process Hazard Analysis sheets (PHAs).
Writing the introduction section of the report required background research of the process
and of the related topic of the biodiesel industry. Writing the PHAs involved
understanding the safety hazards of the equipment and the contents of the equipment in
our process. This involved evaluating various failures or upsets, both direct and indirect,
that could affect our system, assess the consequences, and determine the corrective
actions to be taken to prevent safety hazards from occurring.
Writing the executive summary and conclusions and recommendations required that I
have knowledge of every aspect of the report and understanding of the decisions made
and analysis of the safety, environmental, and economic aspects of the project. This was
more easily accomplished because I had been the project manager and had been editing
and compiling each section of the report as the project developed.
Aside from writing my own sections of the report, I also edited all other sections
of the reports. This involved checking for spelling and grammatical errors, as well as
checking for consistency with numbers presented in the report and consistency amongst
various sections.
After all sections of the report were written, I was responsible for compiling the
report and formatting it to the specifications required. While doing this, I also wrote all of
the references by putting them in MLA format. This also involved going through the
entire paper and ensuring consistent numbering of the references to ensure that after
compiling the report all references were properly referred to and listed in the number in
which they appeared in the report. I also ensured correct numbering and formatting of all
of the figures and graphs.
Zac Ronan was mainly responsible for the design of the process. He completed the
majority of the equipment design and calculations. While designing the equipment, Zac
also determined what type of equipment to use and the cost of the equipment using cost
calculations and thus was responsible for determining the majority of the information on
the equipment tables. He was also responsible for determining the catalyst used and
conditions of the reactor in the process, which involved extensive research of the process
and evaluating various tradeoffs. Zac also wrote the equipment description, rationale, and
optimization section of the report, as well as the nomenclature section of the report. He
also was responsible for checking the overall mass and energy balances of the process
and compiled this into Appendix C. Zac also wrote Appendix E, which included the web
printouts he found for equipment that could be purchased from industrial suppliers. Zac
also helped edit sections of the report.
Kyle Kryger was responsible for maintaining the BFD and PFDs for the process. He
also managed the stream tables, equipment tables, and raw materials and utility tables. He
also designed the pieces of equipment that Zac did not design. Kyle was also responsible
for writing the process description and economics sections of the report. He also did all of
the calculations that required ChemCAD and compiled his work in Appendix B. He also
wrote Appendix B and helped in editing some parts of the report.
Amanda Rubio was responsible for the safety and environmental sections of the
report. She was also the team secretary and took notes at all of the team meetings, the
important of which she wrote and included in Appendix F of the report.
Gasification of Algae for the Production of CNG
Submitted by: CHEE 443 Team Kazaam
April 30, 2010
_______________________ _______________________
Kyle Kryger Zac Ronan
_______________________ _______________________
Amanda Rubio Kim Seamans
ii
Executive Summary This project examined the feasibility of compressed natural gas (CNG) production from
algae. Detailed process calculations, cost analysis, and optimization of the process and
equipment design were conducted to achieve the most economically viable solution.
The process is designed with 3000 kg/day of algae entering the process in a water slurry.
After being sent through a series of heaters, the algae slurry is sent through a salt
separator where the salts are removed from the stream into a brine solution and further
processed before being sent to the algae farm at a rate of 3080 kg/day. The algae slurry is
then sent to a reactor where it is gasified into methane and other gases. The methane
stream is sent through a CO2 scrubber where CO2 is removed and further processed
before being sent to the algae farm at a rate of 2929 kg/day. The methane stream is then
further compressed into CNG and a hydrogen membrane is used to remove the excess
hydrogen. The hydrogen is further processed and sold as a by-product at 4.63 kg/day for
$2.47 per kg. The CNG produced is comprised of 90.2 mol % methane, 3.6 mol %
ethane, 1.3 mol % propane, and 4.5 mol % of various inert gases.
It should be noted that some assumptions were made while designing this process. Most
importantly, there were several assumptions made concerning the reactor R-101. It was
assumed that the gases behaved ideally and that the density of the stream was the same as
the density of water because the stream was 97.8% water by mass. The required mass
ratio of catalyst and the residence time for R-101 were based limited data. Variation of
these numbers may cause an error in the resulting volumetric flow rate and therefore the
flow rate through the process may need to be altered in order to obtain the 63 minute
iii
residence time required for the reactor. Because this information is based off of one
design experiment, further testing should be done on a pilot scale to verify the values for
the design of the reactor.
It was determined that by selling the CNG and hydrogen from the facility, a total yearly
production of $72,600 could be achieved. However, the NPV of the process was
determined to be ($37,500,000), making the process very unprofitable. In order for the
process to become economically viable, it was determined that the price of natural gas
would have to be $1704.4 per 1000 scf, an increase over today’s prices by a factor of 156,
assuming that the ratio of the prices of natural gas and hydrogen remains constant and
that no operating costs change. Costs can also be mitigated by finding a cheaper catalyst.
The current catalyst used accounts for $4,500,000 a year, which represents over half of
the annual operating costs. Research should also be done to minimize the wall thickness
of the R-101 and S101 vessels thereby reducing equipment costs.
If the catalyst, R-101, and S-101 were all reduced in cost to $100,000 each, the NPV
would increase to ($7,400,000), an increase of $30.1MM. This would significantly
improve likelihood of this project becoming economically viable at a future time.
However, due to the current market of CNG and the high costs of production associated
with producing CNG from algae, it is the recommendation of this report that the proposed
design not be used at this time. However, if in the future CNG gains higher market
demands and the cost of algae and the catalyst decreases, this project can be reconsidered
as the process is both straightforward in design and has a minimal impact on the
environment.
Table of Contents
Executive Summary……………………………………………………………………….ii
Introduction………………………………………………………………………………..2
Overall goal
Current Market Information
Project Premises and Assumptions
Overall Process Description, Rationale and Optimization…………...…………………...6
Equipment Description, Rationale and Optimization………….………………………...19
Quantitative BFD………….………………………..............................................34
PFD………….………………………...................................................................35
Stream Table………….……………………….....................................................39
Major Equipment List………….………………………………………………...45
Raw Material and Utility Requirements………….………………………...........50
Safety/Environmental Factors……………….………………………..……………….....51
Safety Statement
Environmental Impact Statement
PHA documents
Economic Analysis……………………………………………………………………....71
Conclusion and Recommendations………..……………………………………………..78
Nomenclature.…….……...………………………………………………………………80
References………………………………………………………………………………..82
Appendices……………………………………………………………………..…….......87
Appendix A...………………………………………………………………………...87
Final Calculations
Appendix B…...…………………………………………………………………….136
Spread Sheets with Explanations
Appendix C…...…………………………………………………………………….141
Overall Mass and Energy Balances
Appendix D………...……………………………………………………………….143
ChemCad outputs
Appendix E…………………………………………………………………………151
WEB printouts
Appendix F………………………………………………………………………….154
Meeting Logs
2
Introduction As global warming awareness increases and the depletion of petroleum fuels rises, more
and more research is being devoted to alternative fuels such as compressed natural gas
(CNG) from algae. Biofuel from algae is a very sustainable alternative as it does not
interfere with food production like some other biofuel alternatives. Moreover, CNG is a
non-corrosive and non-toxic energy source that has significantly lower air emissions
compared to other fossil fuels and is piped directly to the fueling station, reducing the
cost of transportation (1). From Table 1, it is evident that algae have the greatest potential
in supplementing conventional fuels. Not only do algae have a high photosynthetic
activity, but they only require about two grams of CO2 per gram of biomass generated.
This results in approximately a 78% reduction in carbon dioxide emissions and a 50%
reduction in carbon monoxide emissions (2).
Table 1: Gallons of oil produced per year by various oil sources
Source Gallons of oil per acre per year
Algae 5000-20,000
Coconut 287
Jatropha 207
Canola 127
Peanut 113
Sunflower 102
Safflower 83
Soybeans 48
Hemp 39
Corn 18
Overall Goal
This project examined the feasibility of CNG production from algae through detailed
process calculations, cost analysis, and optimization. The production rate of CNG was
determined to be 364 kg/day, which was based on the assumption of an incoming algae
stream of 3000 kg/day. The composition of the final product is comprised of 90.2 mol %
3
methane, with the remaining gases being ethane, propane, and inert gases. The
specifications for the CNG composition were based on industry specifications which
require that the stream must contain at least 88 mol % of methane (3).
In order to create the most cost-effective scenario, it was determined that the outlet
streams containing the brine and carbon dioxide should be recycled and sold to the algae
farm. This would utilize the flue gas emitted from the process and reduce carbon dioxide
emissions into the atmosphere. There are 3075.6 kg/day of brine solution produced. The
carbon dioxide is retrieved from both the carbon dioxide scrubber and flue gas scrubber
at a total of 2929.10 kg/day. The hydrogen is removed from the process stream using a
hydrogen membrane at 4.63 kg/day can also be sold at $2.47 per kg (4).
Current Market Information
Currently the production of algae as a source for biofuels is still in the pre-commercial
stages of development. Some testing has been done on a lab-scale, but in order for algae
to be produced economically, some financial and technical barriers need to be conquered.
CNG is currently being sold at $2.40 per gasoline gallon equivalent (gge) (5). At this
competitive price, the proposed process needs to compete against CNG acquired through
more cost-effective methods than through the gasification of algae. CNG can be produced
from fossilized natural gas or biogas (6).
Due to the current market of CNG and the high costs of production associated with
producing CNG from algae, it is the recommendation of this report that the proposed
design not be used at this time. However, if in the future CNG gains higher market
4
demands and the cost of algae decreases, this project can be reconsidered as the process is
both straightforward in design and has a minimal impact on the environment.
Project Premises and Assumptions
The original premise of the project was to design a process that produced fuel from algae
with a by-product. CNG from algae was chosen because of the novelty of the process.
Other products, such as biodiesel, already have significant research and studies as to the
economic feasibility of production whereas CNG from algae is in its early stages of
research and development. The decision to use brine and carbon dioxide as the by-
products was made in order to reduce emissions and increase profitability with a minimal
increase in equipment cost.
In the design phase of the project, some assumptions were made in order to define
unknown parameters or factors in the process. An algae source of 3000 kg/day was
chosen in order to produce CNG on a significant scale. In addition, the algae were
assumed to be available for purchase as a slurry with 2.5% algae by mass per a
conversation with Dr. Wayne Seames (see Appendix F). Furthermore, the required mass
ratio of catalyst and the residence time for R-101 was based on only one literature value
(7), which may be slightly different for the designed process. Assumptions were also
made regarding some of the heat exchangers and pumps that may affect the accuracy of
the calculations conducted in Appendix A. Other assumptions include the viability of
processes such as the gravitational salt separator, hydrogen membrane, and availability of
the catalyst, which will all be discussed further in the following sections.
In order to determine if the process was economically viable, equipment choice, cost
analysis, and feedstock and utility requirements needed to be determined. Detailed
5
process calculations were completed for the process equipment in order to determine
equipment sizes and specifications. The final calculations can be found in Appendix A.
Calculations that were done using spreadsheets can be found in Appendix B. Mass and
energy balances were performed throughout the process to evaluate the feedstock
requirements and flow rates. Detailed calculations of the mass and energy balances can
be found in Appendix C. Because of the limited availability of data on the designed
process, CHEMCAD was used for some of the calculations for the pumps, valves, and
heat exchanger duties to check against hand calculations to ensure accuracy. The outputs
from CHEMCAD can be found in Appendix D. Any WEB printouts, such as price
quotes, can be found in Appendix E. Meeting logs were kept in order to track progress
and decisions made throughout the project. A copy of the meeting logs can be found in
Appendix F.
6
Overall Process Description, Rationale, and Optimization The big picture of the process is displayed in the block flow diagram (BFD) in Figure 2;
this diagram represents the general layout of the process as well as showing where mass
enters and leaves the process. Summing the input streams, a total of 156,000 kg/hr enter
the process. Summing the output streams, a total of 156,000 kg/hr leave the process. A
more thorough description of the overall mass balance is provided in Appendix C.
A detailed schematic of the process is presented in the process flow diagrams (PFDs) in
Figures 3-6 below. These diagrams depict the process streams, their temperature and
pressure and their relation to pieces of equipment. The compositions of the streams are
further detailed in the stream tables (see Tables 4-9).
Methane Production Line
The algae source of the process in stream 1 enters the plant at 25 °C and a pressure of
101.3 kPa. The algae slurry then enters P-101 A/B where it exits in stream 2 at a
temperature of 35 °C and a pressure of 31000 kPa as seen in Appendix D-2. This stream
is then fed to E-101 where it absorbs heat from the effluent leaving R-101. The algae
slurry emerges from E-101 in stream 3. At this point in the process, the slurry is
considered a compressible liquid; it has not yet reached its critical temperature of 374 °C
(8). Stream 3 then enters F-101 where it absorbs heat from natural gas fired heater. The
algae slurry exits the furnace in stream 4 at a temperature of 400 °C and a pressure of
30990 kPa. At this point, the fluid is supercritical as it has passed the critical point of
water, 374 °C and 22060 kPa (8).
7
In stream 4, two changes occur; firstly, the dissolved nutrient salts required for algae
production precipitate out. Secondly, the suspended algae begins to degrade into a syngas
precursor, ammonium salts and sulfide salts through mechanisms that are not presently
fully understood (7). Ammonium and sulfide salts exist as solid precipitate suspended in
the water flow; a total of 13.8 hg/hr of salts from algae are formed as shown in Appendix
A-7. Stream 4 then enters S-101.
Salts are removed from the vessel through openings in the bottom, where they are pushed
out by a small flow of supercritical water in stream 15. This stream is a two phase flow,
consisting of both solid and liquid components. The desalted algae slurry exits S-102 in
stream 5 where it is fed to R-101.
The algae slurry has a residence time of 63 minutes in R-101; here it interacts with a
Ru/C catalyst in an 8:1 catalyst:algae mass ratio. The reaction converts the incoming
algae material to a mixture of gasses as described in the stream tables below (see Tables
4-9). No water is consumed in this reaction. This reaction is slightly exothermic,
nominally causing the temperature of the reactor effluent to rise to 401 °C as shown in
Appendix A-6. However, this small increase is assumed to be lost to the surroundings of
the reactor, causing the reactor effluent in stream 6 to have a temperature of 400 °C.
Stream 6 is then fed into the tube side of E-101, where it discharges heat to the incoming
algae slurry. This heat loss drops the temperature of the reactor effluent’s temperature to
117 °C in stream 7. This stream is then fed through the letdown valve V-101; the effluent
adiabatically drops to a pressure of 300 kPa and rises to a temperature of 122 °C in
stream 8 as demonstrated in Appendix A-8.
8
The temperature of the effluent is further dropped in E-102. Next, stream 8 is fed into the
exchanger where it discharges heat to cooling water. The cooled effluent exits the
exchanger as a two phase vapor/liquid flow in stream 9. This stream is then fed to the
knockout drum D-201; in this drum, the vapor and the liquid phases are separated. The
majority of the liquid water exits the bottom of the drum in stream 30. This stream is
released from the process without any further treatment as this water meets EPA
specifications for a petroleum refinery (9). The vapor reactor effluent containing the
remaining vapor exits D-201 in stream 10.
Stream 10 is then fed into S-201, a CO2 scrubber. Also fed into this vessel is process
water. This water enters the process in stream 26. This stream is then passed through P-
201 A/B where it emerges in stream 27. This stream is then fed into S-201. In this vessel,
the two streams intimately mix in a packed bed, coming to thermal equilibrium at 25 °C.
The vapor exits the top of the scrubber in stream 11; 96.7% of the CO2 is removed from
the vapor stream. Justification for this removal rate is shown in Appendix A-14. Stream
28 exits the bottom of the scrubber containing water and dissolved carbon dioxide. This
water is then directed back to the algae farm where it is utilized as a carbon source.
Stream 11 is split into two streams, stream 12 and stream 15. Stream 12 has a mass flow
rate of 18 kg/hr and is sent to F-201 where it is used as an energy source. Stream 15 is
sent for further processing to the 400 unit. Here, stream 15 enters P-401 A/B where it is
compressed to 22000 kPa and 500 °C in stream 45 as shown in Appendix D-2. This
stream is then passed to S-401 where the hydrogen is completely separated from the
methane mixture. Stream 46 exits the membrane free from hydrogen and is then fed to E-
401 where it discharges heat to cooling water; the methane mix exits the exchanger in
9
stream 47 and is cooled further in E-402, where it again discharges heat to cooling water.
The resulting stream exits the exchanger and exits the process in stream 48 at pressure of
21980 kPa. A total of 14.3 kg/hr of CNG are produced by this process.
A secondary product is also produced. Hydrogen gas diffuses across the membrane in S-
401; this mass exits the membrane chamber in stream 49 at a pressure of 50 kPa. The
pressure is maintained at this low level by the vacuum pump P-401 A/B; stream 49 then
passes through the pump. The hydrogen exits the pump in stream 50 at a pressure of 115
kPa. This stream is then fed to E-403 where it discharges heat to a cooling water stream.
The hydrogen then exits the exchanger in stream 51; this stream is then fed to the final
hydrogen cooler E-404 where it again discharges heat to a cooling water stream. The
hydrogen exits the exchanger and the process in steam 52.
Cooling water used to cool the reactor effluent enters the process in stream 23. This water
is fed to P-102 A/B where it is pushed in stream 24 to E-102. Here it absorbs heat before
being discharged from the process in stream 25. Cooling water enters the 400 unit in
stream 44, coming off of the discharge of P-301 A/B. This stream is split into four
streams which are fed to all 400 unit exchangers. Here they absorb heat from product
streams before combining to form stream 61. Stream 61 is exits the process and is
discharged.
Air Inlet/Furnace/Superheater Loop
As described in Appendix A-10, ambient air enters the process in stream 17. This stream
is then drawn into the blower P-202 A/B where it is pressured up to 140 kPa in stream 18.
This stream is then fed to E-201 where the air absorbs heat from flue gas as; the heated
air exits E-201 in stream 19. This stream is then fed to F-101.
10
The energy source for F-101 is derived from the methane stream exiting S-201. Methane
at is taken from S-201 effluent in stream 12. In order to facilitate proper mixing in F-101,
this stream is fed to the letdown valve V-201; stream 13 exits the valve at a temperature
of 24 °C and a pressure of 140 kPa as shown in Appendix D-3. This stream is then fed to
E-202 where it absorbs heat from flue gas. The resulting stream 14 exits E-202 and is
then fed to F-101.
Streams 14 and 19 mix in F-101 where a combustion reaction occurs. The flue gas
transfers heat to the algae slurry before exiting the furnace in stream 20. This stream
passes through E-201 where it discharges heat to the incoming ambient air. This in cooler
flue gas emerges in stream 21, which is then fed to E-202. In this exchanger the flue gas
discharges heat to the methane mixture entering the furnace. The flue gas exits this
exchanger in stream 22. This stream is then sent to the 300 unit for treatment.
Stream 22 is fed to the carbon dioxide scrubber S-301. Also fed into this vessel is process
water. This water enters the process in stream 26. This stream is then passed through P-
201 A/B where it emerges in stream 29. This stream is then fed into S-301. In this vessel,
the two streams intimately mix in a packed bed, coming to thermal equilibrium at 25 °C.
The vapor exits the top of the scrubber in stream 32; this stream has had 90% of its CO2
removed. Justification for this removal rate is shown in Appendix A-19. Stream 31 exits
the bottom of the scrubber and is then directed back to the algae farm where it is utilized
as a carbon source.
11
Brine Treatment
As described above, salts are removed from S-101 through openings in the bottom, where
they are pushed out by a small flow of supercritical water in stream 15. This stream water
and salts in a two phase flow. This stream is then passed through E-301 where it
discharges heat to a cooling water stream. The brine stream 33 leaving the exchanger has
a pressure of 30975 kPa. This stream is then fed through a letdown valve V-301; the
exiting stream 34 has a temperature of 86 °C and a pressure of 110 kPa as shown in
Appendix A-20. This stream is then charged to E-302 where it discharges heat to a stream
of cooling water; stream 35 exits the exchanger and is then routed back to the algae farm
to be used as a nutrient source.
Cooling water enters the process in stream 36 and is fed into P-301 A/B. Streams 38 and
41 branch off from the pump discharge and pass through E-301 and E-302, respectively,
where they absorb heat from the brine stream. The effluent from E-301 and E-302
combine to produce stream 43 which exits the process. The remainder of the P-301 A/B
discharge is routed to the exchangers in the 400 unit in stream 44, as described above.
Process Rational and Optimization
After an analysis of many available process options, the final process presented in this
report represents an optimal blend of practicality and energy efficiency. Some
innovations were made as described below.
Reactor Conditions
Perhaps the biggest innovation incorporated into the process is the implementation of a
large scale reactor to convert algae into CNG. Supercritical conditions are required in the
12
reactor; the high temperatures and pressures initiate the breakdown of algae and provide
conditions that favor the production of methane over other products such as carbon
dioxide. Reactor conditions for the supercritical gasification of S. platensis were defined
by Stucki, et. al (7). In their experiments, they varied catalyst, algae concentration in the
feed, the weight ratio of catalyst to algae, and the residence time in the reactor. They
published the results of their research, which totaled 13 different combinations of the
aforementioned factors (7).
In selecting the reactor conditions most desirable for the process, the first factor
considered was catalyst choice. Two options were presented: Ru/C and Ru/ZrO2. Ru/C is
a commercially available catalyst (10). Ru/ZrO2 is not commercially available; this
catalyst was manufactured by the researchers in the laboratory (11). Because of the
impracticality of manufacturing large quantities of Ru/ZrO2 in house, Ru/C was selected
to be the catalyst used in our process.
All of the experiments using Ru/C were then compared to see which one produced the
most methane. The reactor was designed based on the best results as follows:
Catalyst: Ru/C
Feed concentration: 2.5 mass % algae
8:1 catalyst:algae mass ratio
63 minute residence time
The reactor effluent from this experiment had the following composition
42.7 vol % methane
1.7 vol % ethane
0.6 vol % propane
49 vol % carbon dioxide
0.1 vol % carbon monoxide
5.8 vol % hydrogen
13
Salt Separator
Another major innovation incorporated into the process is the inclusion of a supercritical
salt separator. Salts must be separated from the algae stream or else they would function
as a catalyst poison (7); a supercritical salt separator is the best alternative when
compared to traditional salt separation techniques such as utilizing an RO membrane.
Algae contains both nitrogen and sulfur; these elements form salts in a supercritical fluid
(7). Therefore, after the algae is taken supercritical, certain ammonium and sulfide salts
will form. These salts are insoluble in supercritical water (7); therefore, both the nutrient
salts and the salts formed from algae will exist as a solid in supercritical conditions. This
also implies that salt separation must occur after the solution is taken to a supercritical
state. Otherwise, the catalyst would be poisoned by the ammonium and sulfide salts.
Thus, salt separation should occur once the solution is in a supercritical state.
S-101 is a gravitational salt separator. With a residence time of 1 hour, the fluid velocities
through this vessel are low as seen in Appendix A-7. This allows the solid material to
sink to the bottom of the vessel, effectively separating the salts from the algae slurry
stream. This approach introduces the operational risk that the solid material could
accumulate and block exchanger tubes or process pipes. Furthermore, this approach
carries the risk that precipitate could foul the exchanger tubes, leading to a loss of heat
exchange. From a process safety standpoint, pipes and exchangers should be sized so that
fluid velocities are high enough to minimize the risk of precipitate blockage and scaling.
A gravitational salt separator was chosen as the best of three options, the other two
choices being a reverse flow gravity separator (RFGS) and a supercritical membrane
separator. In a RFGS, the algae solution would enter the vessel as a compressible liquid.
14
The slurry would be heated to a supercritical state inside the vessel, allowing the salts to
precipitate out as described above (12). From a process safety perspective, utilizing a
RFGS would be advantageous because it minimizes the risk or precipitate blocking pipes
or exchanger tubes; this is accomplished by having the salts precipitate and
gravitationally settle out of the fluid in the same vessel. Utilizing a RFGS would also
minimize the risk of precipitate scaling in E-102, thus preventing loss of effective heat
transfer. For reasons described in the Equipment Description section, a traditional heat
exchanger and a gravitational salt separator were selected over a RFGS. However, from a
process safety standpoint, if pipes and exchangers are sized so that fluid velocities are
high enough as described above, the process safety advantage a RFGS has over the
system selected is greatly reduced.
A supercritical membrane separator was not utilized for a number of reasons. First and
foremost, a membrane in supercritical application is typically used to separate solute
dissolved in a solvent in the product purification phase in order to eliminate the
depressurization and cooling steps usually required (13). Seeing as our process already
has the salts that are precipitated, there is no solute needed to be separated. A membrane
in the context of the process presented here would act as a physical barrier, forcing
suspended solids to separate from the fluid. The team believes that because of the low
fluid velocities in S-101 as described above, no membrane is needed in order to assist
with the separation.
However it should be noted that the gravitational salt separator presented here is an
untested piece of equipment. Thus, it is recommended that a pilot scale salt separator be
constructed and tested to ensure reliable equipment operation.
15
Algae Source
When selecting an algae variety to use as a feedstock, the typical biofuel process is
concerned with the lipid content of species. In a biodiesel plant, these lipids are then
extracted and converted into biodiesel (14). The process presented here is unique in that
the lipid content of the algae is irrelevant; because the entire cell is gasified, lipids were
not a factor in deciding the algae species to be used.
As such, the two biggest factors in considering algae source were availability of
information and growth rate of the algae. The algae selected must be able to reproduce
quickly in order to minimize the size of the algae farm associated with the process. After
consideration, the microalgae Spirulina platensis was selected. This algae is thought to
have a molecular formula proportional to C1.0H1.71O0.48N0.19S0.005 (7). The primary reason
that this algae was selected was that it is the only one with sufficient information
available describing the products formed by supercritical gasification and methanation.
(7). S. platensis was found to have a growth rate of 0.04 g/(L day) in open ponds, a
relatively high growth rate (15).
A total of 3 tons/day of algae enter the process, as was determined from a meeting with
Dr. Wayne Seames (see Appendix F). This algae is piped in directly from the algae farm
in the form of a slurry with 2.5 mass % algae (7). This solution also contains 22.8 g/L
nutrient salts; this number assumes that half of the nutrient salts needed to encourage
growth in solution are consumed (16).
16
Product Quality
A total of 14.3 kg/hr of CNG is produced by this process. At 21980 kPa, the product is
well within the acceptable pressure range for CNG of 200-250 bar (17). The product is
also well within composition specifications, as detailed by Table 2. Calculations
justifying these numbers are shown in Appendix A-14.
Table 2: Composition Specifications and Product Specifications of CNG
Compound Specification(3)
Product
Methane 88 mol % minimum 90.2 mol %
Ethane 6 mol % maximum 3.6 mol %
Propane 3 mol % maximum 1.3 mol %
Inert Gasses 4.5 mol % maximum 4.5 mol %
The hydrocarbon content of the stream is defined by the reactor R-101 and is relatively
difficult to change through traditional methods such as gas absorption. The hydrocarbons
are produced in the correct proportions and do not required blending or further reaction
before sale of the product. The inert gasses, however, are initially present in too great of
an amount to meet product quality specifications. These inert gasses include water,
carbon dioxide and carbon monoxide.
Carbon dioxide is the biggest contaminant in the reactor effluent. As such, the vapor
effluent is sent to S-201, a carbon dioxide scrubber. Here, 96.7% of the carbon dioxide is
removed from the effluent stream as shown in Appendix A-14. This brings the final mole
percent of CO2 in the CNG product to 3.1%. Water is introduced to the stream in S-201;
the water comes to equilibrium with the gas. As such, the final water mole percent in the
CNG product is 1.2%. The final CO mole percent in the product is 0.2. Summing these
together, the final mole percent of inert gasses in the product is 4.5%. By running the
product at the maximum allowable specification, money is saved by reducing the amount
17
of water needed in S-201. This minimizes the size of P-201 A/B and S-201, thereby
minimizing their costs as well. In the end, an on-spec product is delivered for minimal
cost.
No H2 gas is allowed to be in the final CNG product; however, 0.19 kg/hr of the gas are
in the stream sent to the 400 unit. This gas must be removed from the final product in
order to make the gas suitable for use in motor vehicles. This is accomplished by passing
the gas past S-401, a membrane engineered to remove hydrogen gas from a process
stream. The amount of hydrogen in the CNG stream leaving S-401 is negligible, thus
establishing a pure, on spec CNG product. The hydrogen exits S-401 in its own stream;
this secondary stream can also be sold as a fuel source.
Heat Exchanger Network
In order to maximize the amount of CNG produced by the process, the amount of energy
wasted must be minimized. This was accomplished through the construction of a
thorough heat exchanger network. The following incoming process streams are the only
places where opportunity exists to recover heat from outgoing process streams:
1. Algae stream from inlet to E-101
2. Air stream from inlet to F-201
3. Methane inlet to F-201
The first of these streams absorbs 2300 kW of heat from the outgoing reactor effluent. It
reaches a temperature of 372 °C; of all the process streams available to further heat this
while maintaining appropriate temperature approaches (18), none have a high enough
temperature. Thus, this stream has absorbed all the heat it can.
18
In order to minimize the amount of methane required for combustion in the furnace, both
the incoming methane and air streams must be preheated. The inlet air stream is heated in
E-201 to a temperature of 465 °C. There are no other streams available with a high
enough temperature to heat this stream any further. The incoming methane stream is
heated in E-202 to a temperature of 131 °C; while the brine stream could be used to
transfer a small amount of additional heat to this stream, this exchanger was not
implemented because the amount of heat recovered would not justify the cost of the
exchanger. Because this brine stream is the only steam available to heat up the methane
going into the furnace, the methane stream is as hot as it can get. Because all streams
cannot accept anymore heat from process effluent, the heat exchanger network is deemed
to have maximum efficiency. All exchanger calculations can be found in Appendix A.
Furnace
The primary heat source for the process is the methane combusted in F-101. In an ideal
world, no methane would be combusted and high pressure steam would be used to
superheat the algae slurry. However, because the algae slurry is required to be at 400°C,
steam cannot be used (18). The only other option for heating the stream is with a fired
furnace (18). Rather than purchase outside fuel sources, methane from the process was
chosen to be burned in the furnace. For a given volume of natural gas, it is cheaper to use
natural gas from the process than natural gas purchased from external sources.
19
Equipment Description, Rationale, and Optimization
E-101 and E-201
E-101 and E-201 are carbon steel floating head countercurrent shell-and-tube heat
exchangers. The duties and areas of the heat exchangers are 2038 kW and 436 ft2 for E-
101 and 80 kW and 240 ft2 for E-201 as shown in Appendix A-1 and A-2, respectively.
The reactor effluent is on the tube-side and the algae slurry is on the shell-side of E-101
in order to minimize heat loss to the surroundings. The rationale for this is that having the
higher temperature stream on the tube-side of the heat exchanger decreases the
temperature gradient between the shell-side of the exchanger and the surroundings,
thereby decreasing the heat lost to the surroundings (19). The flue gas is on the tube-side
and the air is on the shell-side of E-201 for the same reason.
The two streams flow in a countercurrent fashion for both of the heat exchangers in order
to allow for more heat to be transferred between the streams than would be obtained from
concurrent flow (20). For E-101, the countercurrent design allows the algae slurry stream
to exit the heat exchanger 28 oC less than the incoming reactor effluent stream, which
enters at a temperature of 400 oC. Similarly for E-201, the exiting temperature of the air
stream is set to be 28 oC less than the temperature of the entering flue gas, which enters at
a temperature of 493 oC. The exiting temperatures of the shell-side streams are set to be
28 oC less than the temperature of the entering tube-side streams because of the minimum
recommended temperature approach for temperatures above 150 oC (18). Having a
temperature approach less than 28 oC would cause the area of the heat exchanger to
increase dramatically per unit decrease in temperature. This would then cause the price of
the heat exchanger to increase at an exponential rate (18).
20
E-101 and E-201 are a shell-and-tube heat exchanger because of their relatively large
areas required for heat exchange. Areas of 436 ft2 and 240 ft
2 are outside the
recommended size for a double-pipe heat exchanger (18). E-101 and E-201 are floating
head shell-and-tube heat exchangers because of the ability of the floating head design to
handle large temperature differences between the tube and shell-side fluids (21). Floating
head designs are more expensive than other designs, however the 2038 kW and 80 kW of
energy conserved by E-101 and E-201 respectively more than justify their expense.
E-102, E-202, E-301, E-302, E-401, E-402, E-403, and E-404
E-102, E-202, E-301, E-302, E-401, E-402, E-403, and E-404 are all carbon steel double-
pipe heat exchangers. The duties and areas of these exchangers are 518 kW and 156 ft2
for E-102, 1.4 kW and 5.4 ft2 for E-202, 28 kW and 1.8 ft
2 for E-301, 3.8 kW and 1.7 ft
2
for E-302, 4.9 kW and 6.1 ft2 for E-401, 0.14 kW and 2.4 ft
2 for E-402, 0.34 kW and 0.5
ft2 for E-403, and 0.031 kW and 0.3 ft
2 for E-404 as shown in Appendix A.
The reactor effluent flows in the inner tube and the cooling water flows through the outer
tube of E-102. The cooling water flows through the outer tube of the heat exchanger in
order to prevent the safety issues involved with having the hot reactor effluent in the
outer tube. The outer temperature of the heat exchanger can be as hot as the fluid flowing
in the outer tube. Having the outside temperature of E-102 at 122 oC, the temperature of
the reactor effluent, would be hazardous to those working around the exchanger. The
cooling water flows through the outer tubes of E-301, E-302, E-401, E-402, E-403, and
E-404 for the same reason. The colder stream for E-202, the methane gas, flows through
the outer tube of the heat exchanger for the same reason. Also, this configuration for E-
202 reduces energy lost to the surroundings.
21
The two streams flow in a countercurrent fashion in all of the exchangers in order to
allow for more heat to be transferred between the streams than would be obtained from
concurrent flow (20).
For E-102, E-301, E-302, E-401, E-402, E-403, and E-404 the exiting temperature of the
cooling water is set to 49 oC by an environmental limit (18). Setting the exiting
temperature of the water to its maximum allows for the minimum amount of cooling
water to be used.
For E-102, E-302, E-402, and E-404 the exiting temperatures of the inner tube streams
are set at 43 oC, which is 11
oC above the temperature of the incoming cooling water.
This is because of the 11 oC minimum recommended temperature approach for streams
above ambient temperature but below 150 oC (18). For the same reason the exiting
temperature of the methane stream from E-202 is set to be 11 oC less than the temperature
of the entering flue gas. For E-401 and E-403, the exiting temperatures of the gas streams
were set to be 28 oC more than the temperature of the entering cooling water. This is
because of the minimum recommended temperature approach for temperatures above 150
oC (18). Similarly to E-101, the minimum approach temperatures are set in order to
maintain a reasonable heat exchanger area and cost.
The exiting temperature of the brine solution stream in E-301 is set to be 80 oC in order to
have a large approach temperature while keeping the water below its boiling point at a
pressure of 110 kPa. Increasing the temperature approach above the minimum
recommended approach, which is 28 oC for E-301 because temperature of the entering
brine is above 150 oC, decreases the area required for the heat exchanger thereby
22
decreasing its cost (18). At the same time, cooling the brine solution stream down to 80
oC keeps the water in the stream in the liquid phase after passing through V-301, as
shown in Appendix A-20. This prevents the salts from being left behind as the water
cannot change into the vapor phase.
E-102, E-202, E-301, E-302, E-401, E-403, E-403, and E-404 are double pipe heat
exchangers because of their relatively small areas. Double pipe heat exchangers are
recommended for areas up to 200 ft2 and are cheaper than shell-and-tube exchangers (18).
F-101
F-101 is a carbon steel methane fueled furnace. The duty of the furnace is 277 kW as
shown in Appendix A-3. A methane fueled furnace is used in this application because of
the abundant supply of methane that the process produces. A furnace is preferred over
other methods of heating because of the ability to integrate the furnace inputs and outputs
in other areas of the process in order to conserve energy. As shown in the 200 unit PFD,
the methane is sent through the methane preheater E-202 where 1.4 kW of energy are
conserved from the furnace flue gas. In addition, 80.1 kW are conserved from the furnace
flue gas through E-201 where the air is preheated. The combined energy conservation
allows the furnace to heat the algae slurry while using only 18 𝑘𝑔
𝑟 of methane, as shown in
Appendix A-3. Without this energy conservation, the furnace would not have been as
economical as a tubular heater, which would have required an estimated power source of
350 kW (22).
P-101A/B
P-101A/B are carbon steel reciprocating pumps with a required head of 10600 ft of water
and a required flow rate of 240 𝑔𝑎𝑙
𝑚𝑖𝑛 as shown in Appendix A-4. Reciprocating pumps are
23
used in this application because of the large head required by the pump. Reciprocating
pumps are recommended for applications requiring a head between 3200 and 20000 ft of
water (18). Reciprocating pumps are more expensive than centrifugal pumps, but a
centrifugal pump cannot be used in this application because of the large head required in
the process.
The electric motors that drive the pumps require a break horsepower of 82 hp and a
power consumption of 220 hp, as shown in Appendix A-4. The motors are enclosed in an
open, drip-proof enclosure. Open, drip-proof enclosures are designed to prevent the
entrance of liquid and dirt particles, but not airborne moisture or corrosive fumes, into the
internal working parts of the motor. This type of enclosure works in this particular
application because there are not any corrosive fumes being sent through the pump, as
shown Tables 4-9. Open, drip-proof enclosures are cheaper than other types of
enclosures, such as totally enclosed and explosion-proof enclosures, which protect the
inner working parts of the motor from fumes (18).
P-101A/B consists of two pumps because one of them serves as a backup for the other.
Since it costs $59,000 for one pump and one motor, as shown in Appendix A-4, which is
relatively cheap compared to the approximate $6,000,000 cost of all of the equipment, the
low cost justifies having a backup. The main goal of having a backup is so that the entire
process does not need to shut down in the event of the pump breaking.
P-102A/B, P-201A/B, and P-301A/B
P-102A/B, P-201A/B, and P-301A/B are cast iron centrifugal pumps. Centrifugal pumps
are used in these applications because of the small heads and flow rates required.
Centrifugal pumps are recommended for applications requiring a head less than 3200 ft
24
of water (18). Centrifugal pumps are used rather than reciprocating pumps because of
their lower cost and lower power consumption (18).
P-102 A/B has a required head of 4.0 ft of water and a required flow rate of 110 𝑔𝑎𝑙
𝑚𝑖𝑛 as
shown in Appendix A-5. The exact pumps used can be obtained from an industrial
supplier. The pumps are Dayton 2 hp centrifugal pumps. The pumps meet the head and
flow rate requirements of the process, with a maximum head of 63 ft of water and a
maximum flow rate of 170 𝑔𝑎𝑙
𝑚𝑖𝑛 (9). The exact pumps can be seen in Appendix E.
P-201A/B has a required head of 65 ft of water and a required flow rate of 560 𝑔𝑎𝑙
𝑚𝑖𝑛 as
shown in Appendix A-5. The electric motors that drive the pumps require a break
horsepower of 12 hp and a power consumption of 15 hp, as shown in Appendix A-5. The
motors are enclosed in an open, drip-proof enclosure for the same reasons as P-101A/B.
P-301A/B has a required head of 4.0 ft of water and a required flow rate of 8.6 𝑔𝑎𝑙
𝑚𝑖𝑛 as
shown in Appendix A-18. The exact pumps used in this application can be obtained from
an industrial supplier. The pumps are Dayton 1
3 hp self priming centrifugal pumps. The
pumps meet the head and flow rate requirements of the process, with a maximum head of
41 ft of water and a maximum flow rate of 43 𝑔𝑎𝑙
𝑚𝑖𝑛 (23). The exact pumps can be seen in
Appendix E.
P-102A/B, P-201A/B, and P-301A/B consist of two pumps for the same reason as P-
101A/B.
25
R-101
R-101 is a carbon steel packed bed reactor. Physically speaking, it is a high pressure
vertical vessel that is 3 m in height, has a 2.4 m inside diameter, and a volume of 13.7 m3.
It weighs 500,000 lbs and has a wall thickness of 24 inches. These sizes were chosen in
order to give the process fluid a residence time of 63 min as shown in Appendix A-6. A
residence time of 63 min is required in order to achieve the maximum conversion of the
algae into methane (7).
Assuming the same flow rate, a residence time smaller than 63 min would be a cheaper
option because the reactor would be smaller and therefore cost less. Also, less catalyst
would be required and the catalyst is one of the most expensive parts of the process at
$151 per 25 g of catalyst (24). However, the decreased residence time would cause
decreased methane production and an increased amount of undesirable products, such as
larger alkanes. The increased amount of the larger alkanes could result in the inability to
sell the product of this process, as the methane is required to be at a purity of 88% in
order to sell it (3), and separating the methane from the other alkanes would be difficult,
particularly for the ethane and propane. Assuming the same flow rate, a residence time
larger than 63 min would needlessly increase the weight and therefore the cost of the
reactor. In addition, the reactor would require more catalyst if the reactor size is
increased. Therefore, the volume of the reactor is set to be 13.7 m3 in order to have a
residence time of exactly 63 min so that the optimum combination of cost and product
purity is achieved.
Ru/C catalyst is used in this reactor in order to facilitate the gasification of the algae (7).
Ru/C is used over other ruthenium catalysts because of its availability. Although it is
26
expensive, it can be purchased from chemical suppliers (24). Other ruthenium catalysts,
such as Ru/ZrO2, selectively produce more methane than the Ru/C. In fact, the methane
conversion could be increased by as much as 20% with the use of Ru/ZrO2 (7). However,
Ru/ZrO2 is not available for commercial purchase and therefore would have to be made
on-site, thereby requiring a chemical plant to be added to the site. In addition, the
Ru/ZrO2 catalyst requires a residence time of 360 min, which would require six times as
much catalyst as the Ru/C catalyst (7). Therefore, Ru/C catalyst is used because of its
availability from commercial sources and for the lower volume of catalyst it requires.
S-101
S-101 is a gravitational salt separator. Physically speaking, it is a high pressure vertical
vessel that is 3 m in height, has a 2.4 m inside diameter, and a volume of 13.3 m3. It
weighs 371,000 lbs and has a wall thickness of 19 in. These sizes were chosen to give the
fluid inside the vessel a residence time of 1 hour as shown in Appendix A-7. Thus, the
fluid inside the vessel has a low fluid velocity as described in the process description in
order to facilitate effective phase separation. This size configuration minimizes the
amount of material used in construction, thus minimizing the cost of the unit as well.
This gravitational salt separator was chosen over
a reverse flow gravity separator (RFGS) (10). A
cross section of a RFGS can be seen in Figure 1.
If an RFGS were used, the algae slurry would not
be heated in F-101; instead, stream 3 would feed
directly into the interior chamber of the vessel (shown in figure as textured). Flue gas at a
temperature of 1708 °C as shown in Appendix A-3 would be piped into the outer
Interior
Chamber
Exterior
Chamber
Heat Transfer
Wall
Figure 1: Cross section of RFGS
27
chamber. The vessel would function as a large heat exchanger, passing heat from the flue
gas to the algae slurry in the inner chamber through the heat transfer wall. Thus, the algae
slurry would reach a supercritical state once inside the chamber. This would cause the
salts to precipitate out inside the vessel and fall to the bottom. The fluid, however, would
drop suddenly in density and rise up and out of the chamber, effectively separating the
two phases.
A gravitational salt separator and furnace combination was chosen over a RFGS for one
main reason. The flue gas at 1708 °C exceeds the safe operating limit of steel (18). To
operate the vessel with flue gas at that temperature could be dangerous. Lowering the
temperature of the flue gas is not an option; lowering the temperature would invariably
increase the amount of methane required to be combusted in the furnace due to the
increase in air flow required. A gravitational salt separator minimizes the amount of
methane consumed in the furnace; thus, the gravitational salt separator was deemed the
best choice.
V-101
V-101 is a letdown valve that adiabatically decreases the pressure of the reactor effluent
by 30670 kPa. The valve is used in the process in order to decrease the pressure of the
process stream without vaporizing the water. At the conditions of the process stream as it
exits the valve, 300 kPa and 122 oC, the liquid water does not vaporize as shown in Table
4. Vaporizing the water would greatly increase the volumetric flow rate of the process
stream and therefore would require the cooler, E-102, to have a much larger area. This
increased area is associated with an increased cost of the cooler. Therefore, to reduce the
28
cost of E-102 the exiting pressure of the valve is selected to keep the water in the liquid
phase.
D-201
D-201 is a carbon steel gravitational knockout drum. It is a low pressure vessel with a
height of 3 m, an inside diameter of 2.4 m, and a volume of 13.3 m3. It weighs 6,100 lbs
and has a wall thickness of 0.375 inches as shown in Appendix A-9. The volume of the
vessel is selected in order to allow for proper separation between the liquid and vapor
phases of the incoming process stream as shown in Table 4. Gravity pulls the denser
liquid water phase out of the bottom of the vessel while allowing the gases produced in
the reactor to flow freely out of the top.
P-202A/B
P-202A/B are aluminum centrifugal blowers with a required flow rate of 310 𝑓𝑡 3
𝑚𝑖𝑛 of air a
discharge pressure of 140 kPa as shown in Appendix A-13. A blower is used in this
application because of the required pressure increase of 40 kPa. Fans would be cheaper
alternatives, however fans are recommended for pressure increases of 10.6 kPa or less.
Compressors are not used because of their higher cost, and because they are
recommended for pressure increases of more than 206 kPa. A centrifugal blower is
chosen over a straight-lobe blower because of their lower purchase cost and higher
mechanical efficiencies. Centrifugal blowers have mechanical efficiencies of 70-80%, in
contrast to 50-70% efficiencies for straight-lobe blowers (18). Therefore, the centrifugal
blowers have a lower initial cost and a lower power consumption. The blowers require a
break horsepower of 9.7 hp and have a power consumption of 13 hp as shown in
Appendix A-13. P-202A/B consists of two blowers for the same reason as P-101A/B.
29
S-201
S-201 is a carbon dioxide scrubber; its task is to remove CO2 from natural gas. It removes
96.7% of the carbon dioxide from the incoming methane mixture, ensuring that the final
CNG product meets specifications as shown in Appendix A-14. The vessel itself has a
height of 2.5 m, an inside diameter of 1.9 m, and a volume of 7.2 m3. Made of carbon
steel, the vessel has a weight of 4,000 lbs and a wall thickness of 0.375 inches as shown
in Appendix A-14. The inside of the vessel is filled with 7 m3 of 1.5 inch ceramic
Raschig rings. Raschig rings of this size were chosen because of their low initial purchase
cost (18) and because they provide adequate area for the gas and liquid to interact. The
rest of the volume is taken up by distribution and redistribution apparatuses.
This vessel was sized to minimize the volume and amount of packing required while still
meeting the operational specification. See Appendix A-14 for calculations justifying
vessel sizing. In the end, S-201 was optimized by minimizing initial and operating costs
while still keeping the CNG product within specification.
V-201
V-201 is a letdown valve that adiabatically decreases the pressure of the methane by 145
kPa. The valve is used in the process in order to decrease the pressure of the methane so
that it has the same pressure as the air stream when it reaches the furnace F-101 as shown
in Table 5. The methane and air streams are required to be at the same pressure in the
furnace in order to prevent the backflow of one of the streams. If one stream is at a higher
pressure than the other, then the higher pressure stream may flow down the tube of the
lower pressure stream because of the pressure gradient between the streams. The
alternative to decreasing the pressure of the methane is to increase the pressure of the air.
30
However, to increase the pressure of the air to the pre-valve pressure of the methane
would require a compressor rather than the blowers P-202A/B. Compressors are
significantly more expensive than blowers and therefore are not preferable (18).
Therefore, the process lets the pressure of the methane down through the valve in order to
prevent the extra cost of adding a compressor.
S-301
S-301 is a flue gas scrubber; its task is to remove CO2 from flue gas before it is emitted to
the atmosphere. It removes 90% of the carbon dioxide from the incoming flue gas as
shown in Appendix A-19; this is an arbitrary number that lessens the carbon footprint of
the process without being too expensive of a unit. The vessel itself has a height of 2 m, an
ID of 1.5 m, and a volume of 3.5 m3. Made of carbon steel, the vessel has a weight of
2,070 lbs and a wall thickness of 0.3125 inches as shown in Appendix A-19. The inside
of the vessel is filled with 3.3 m3 of 1.5 inch ceramic Raschig rings. Raschig rings of this
size were chosen because of their low initial purchase cost (18) and because they provide
adequate area for the gas and liquid to interact. The rest of the volume is taken up by
distribution and redistribution apparatuses.
This vessel was sized to minimize the volume and amount of packing required while still
removing 90% of the carbon dioxide. See Appendix A-19 for calculations justifying
vessel sizing. In the end, S-301 was optimized by minimizing initial and operating costs
while reducing carbon emissions.
V-301
V-301 is a letdown valve that adiabatically decreases the pressure of the brine solution by
30865 kPa as shown in Table 7. The pressure of the brine solution needs to be let down to
31
near atmospheric pressure so that the brine solution can be safely sent back to the algae
farms. If the brine were sent back at too high of a pressure it could not be added to the
algae farm because of the large pressure gradient that would exist between the brine and
the algae slurry.
P-401A/B
P-401A/B are carbon steel screw compressors with a required flow rate of 4.6 𝑓𝑡 3
𝑚𝑖𝑛 and a
discharge pressure of 500 kPa as shown in Appendix A-25. A screw compressor is used
in this application because of their low purchase cost. Screw compressors are cheaper
than other types of compressors such as centrifugal and reciprocating compressors.
Centrifugal and reciprocating compressors are more flexible in their operation, and
therefore cost more (18). However, no flexibility is required by the compressor in the
process, and therefore screw compressors are chosen for their lower cost.
The motor driving the compressors are electric motors with a break horsepower of 8.4 hp
and a power consumption of 11 hp as shown in Appendix A-25. Electric motors are used
because of their higher efficiency. Electric motors have an efficiency of up to 95% at
1000 hp, in contrast to 65% and 35% for steam turbines and gas turbines respectively
(18).
Typically four compression stages with intercoolers would be used when compressing a
gas to a pressure that is 77 times its initial pressure (18). However, only one compression
stage is used in the process in order to increase the temperature of the gas to 500 oC, as
shown in Appendix D-1. The reason for this is because of the temperature requirements
of the hydrogen membrane S-401. Four compression stages with intercoolers would not
32
increase the temperature and therefore a heater would need to be added to heat the gas
stream. Adding a heater would increase the electricity use of the process as well as the
total cost of the process equipment. To eliminate this needless cost, only one compressor
without a cooler is used. P-401A/B consists of two compressors for the same reason as
P-101A/B.
P-402A/B
P-402A/B are carbon steel single stage rotary vane air-cooled vacuum pumps. The exact
pump used in this application can be obtained from an industrial supplier. The pumps are
TorrVac B series Rotary Vane Vacuum pumps. They are capable of displacing 21 𝑓𝑡 3
𝑚𝑖𝑛 of
gas and have a 1.5 hp motor (25), which meets the required flow rate of 0.43 𝑓𝑡 3
𝑚𝑖𝑛 as
shown in Appendix A-26. The exact pump can be seen in Appendix E. P-402A/B consists
of two pumps for the same reason as P-101A/B.
S-401
S-401 is a palladium hydrogen membrane cast on a ceramic support structure. The
purpose of this membrane is to separate hydrogen from the CNG stream; a dense metallic
membrane was chosen because of its superior properties. Table 3 summarizes
characteristics of the five main types of hydrogen membranes available today as
compiled by S.C.A. Kluiters (26).
Table 3: Characteristics of Various Hydrogen Membranes
Dense
Polymer
Microporous
Ceramic
Dense
Metallic
Porous
Carbon
Dense
Ceramic
Temperature Range (°C) <100 200-600 300-600 500-900 600-900
H2 Selectivity Low 5-139 >1000 4-20 >1000
H2 flux
(10-3
mol/m2s at dP=1 bar)
Low 60-300 60-300 10-200 6-80
33
The membrane must operate at a temperature of 500 °C as seen in Table 8. This clearly
eliminates the dense polymer and dense ceramic membranes from consideration. The
porous carbon membrane is eliminated as well because process upsets could drop the
temperature temporarily below 500, thus ruining the membrane.
Hydrogen selectivity was the next item considered in the choice of a membrane. The
selectivity shown in Table 3 is a unitless number defining the relative ease at which
hydrogen diffuses through a membrane compared to other compounds. (26) Palladium
membranes only let hydrogen diffuse through them; no other compound is physically
capable of moving through. (27) For this reason, a palladium membrane was chosen. By
utilizing a palladium membrane with a substantial pressure drop across the membrane, all
of the hydrogen is removed from the CNG stream as shown in Appendix A-27. As a
result, pure hydrogen and a maximum amount of CNG are produced by utilizing a
palladium membrane cast onto a ceramic support structure.
34
Figure 2. BFD for CNG Production from Algae
35
Figure 3. PFD for CNG Production from Algae
36
Figure 4. PFD for CNG Production from Algae (Continued)
37
Figure 5. PFD for CNG Production from Algae (Continued)
38
Figure 6. PFD for CNG Production from Algae (Continued)
39
Table 4. Steam Table Summary for CNG Production Process shown in Figures 3-6
Stream Number 1 2 3 4 5 6 7 8 9 10
Temperature (oC) 25 35 372 400 400 400 117 122 43 43 Presure (kPa) 101 31000 30995 30990 30980 30975 30970 300 295 290
Solid Fraction 0.025 0.025 0.025 0.025 0 0 0 0 0 0
Liquid Fraction 0.975 0.975 0.975 0.975 0.978 0.978 0.978 0.978 0.978 0 Vapor Fraction 0 0 0 0 0.022 0.022 0.022 0.022 0.022 1
Mass Flow (kg/hr) 5239 5239 5239 5239 5071 5071.28 5071.28 5071.28 5071.28 107.38
Component Mass Flow (kg/hr)
Algae 125 125 125 125 111 0 0 0 0 0 Air 0 0 0 0 0 0 0 0 0 0
Water 5000 5000 5000 5000 4960 4960 4960 4960 4960 1.40 Salts 114 114 114 114 0 0 0 0 0 0 Carbon Dioxide 0 0 0 0 0 81.7 81.7 81.7 81.7 76.4 Carbon Monoxide 0 0 0 0 0 0.21 0.21 0.21 0.21 0.21 Methane 0 0 0 0 0 26.0 26.0 26.0 26.0 26.0 Ethane 0 0 0 0 0 1.94 1.94 1.94 1.94 1.94 Propane 0 0 0 0 0 1.00 1.00 1.00 1.00 1.00 Hydrogen 0 0 0 0 0 0.43 0.43 0.43 0.43 0.43
40
Table 5. Steam Table Summary for CNG Production Process shown in Figures 3-6 (Continued)
Stream Number 11 12 13 14 15 16 17 18 19 20
Temperature (oC) 25 25 24 131 25 400 16 16 465 493 Presure (kPa) 285 285 140 135 285 30980 101.3 140 135 130
Solid Fraction 0 0 0 0 0 0.755 0 0 0 0
Liquid Fraction 0 0 0 0 0 0.245 0 0 0 0 Vapor Fraction 1 1 1 1 1 0 1 1 1 1
Mass Flow (kg/hr) 32.52 18.03 18.03 18.03 14.4 169.7 629.1 629.1 629.1 647.58
Component Mass Flow (kg/hr)
Algae 0 0 0 0 0 0 0 0 0 0 Air 0 0 0 0 0 0 621 621 621 548
Water 0.40 0.22 0.22 0.22 0.18 41.7 8.1 8.1 8.1 45.8 Salts 0 0 0 0 0 128 0 0 0 0 Carbon Dioxide 2.54 1.41 1.41 1.41 1.13 0 0 0 0 53.6 Carbon Monoxide 0.21 0.12 0.12 0.12 0.09 0 0 0 0 0.18 Methane 26.0 14.4 14.4 14.4 11.5 0 0 0 0 0 Ethane 1.94 1.08 1.08 1.08 0.86 0 0 0 0 0 Propane 1.00 0.56 0.56 0.56 0.45 0 0 0 0 0 Hydrogen 0.43 0.24 0.24 0.24 0.19 0 0 0 0 0
41
Table 6. Steam Table Summary for CNG Production Process shown in Figures 3-6 (Continued)
Stream Number 21 22 23 24 25 26 27 28 29 30
Temperature (oC) 142 136 32 32 49 25 25 25 25 43 Presure (kPa) 125 120 101.3 110 105 101.3 290 285 290 290
Solid Fraction 0 0 0 0 0 0 0 0 0 0
Liquid Fraction 0 0 1 1 1 1 1 1 1 1 Vapor Fraction 1 1 0 0 0 0 0 0 0 0
Mass Flow (kg/hr) 647.52 647.52 23300 23300 23300 125000 75300 75373.8 49200 4965.35
Component Mass Flow (kg/hr)
Algae 0 0 0 0 0 0 0 0 0 0 Air 548 548 0 0 0 0 0 0 0 0
Water 45.8 45.8 23300 23300 23300 125000 75300 75300 49200 4960 Salts 0 0 0 0 0 0 0 0 0 0 Carbon Dioxide 53.6 53.6 0 0 0 0 0 73.8 0 5.35 Carbon Monoxide 0.12 0.12 0 0 0 0 0 0 0 0 Methane 0 0 0 0 0 0 0 0 0 0 Ethane 0 0 0 0 0 0 0 0 0 0 Propane 0 0 0 0 0 0 0 0 0 0 Hydrogen 0 0 0 0 0 0 0 0 0 0
42
Table 7. Steam Table Summary for CNG Production Process shown in Figures 3-6 (Continued)
Stream Number 31 32 33 34 35 36 37 38 39 40
Temperature (oC) 25 25 80 86 43 32 32 32 49 32 Presure (kPa) 115 115 30975 110 105 101.3 110 110 105 110
Solid Fraction 0 0 0.485 0.485 0.485 0 0 0 0 0
Liquid Fraction 1 0 0.515 0.515 0.515 1 1 1 1 1 Vapor Fraction 0 1 0 0 0 0 0 0 0 0
Mass Flow (kg/hr) 49248.2 560.33 169.7 169.7 169.7 1900 1900 1440 1440 463
Component Mass Flow (kg/hr)
Algae 0 0 0 0 0 0 0 0 0 0 Air 0 548 0 0 0 0 0 0 0 0
Water 49200 6.85 41.7 41.7 41.7 1900 1900 1440 1440 463 Salts 0 0 128 128 128 0 0 0 0 0 Carbon Dioxide 48.2 5.36 0 0 0 0 0 0 0 0 Carbon Monoxide 0 0.12 0 0 0 0 0 0 0 0 Methane 0 0 0 0 0 0 0 0 0 0 Ethane 0 0 0 0 0 0 0 0 0 0 Propane 0 0 0 0 0 0 0 0 0 0 Hydrogen 0 0 0 0 0 0 0 0 0 0
43
Table 8. Steam Table Summary for CNG Production Process shown in Figures 3-6 (Continued)
Stream Number 41 42 43 44 45 46 47 48 49 50
Temperature (oC) 32 49 49 32 500 500 60 43 500 500 Presure (kPa) 110 105 105 110 22000 21990 21985 21980 50 115
Solid Fraction 0 0 0 0 0 0 0 0 0 0
Liquid Fraction 1 1 1 1 0 0 0 0 0 0 Vapor Fraction 0 0 0 0 1 1 1 1 1 1
Mass Flow (kg/hr) 191 191 1630 272 14.4 14.21 14.21 14.21 0.19 0.19
Component Mass Flow (kg/hr)
Algae 0 0 0 0 0 0 0 0 0 0 Air 0 0 0 0 0 0 0 0 0 0
Water 191 191 1630 272 0.18 0.18 0.18 0.18 0 0 Salts 0 0 0 0 0 0 0 0 0 0 Carbon Dioxide 0 0 0 0 1.13 1.13 1.13 1.13 0 0 Carbon Monoxide 0 0 0 0 0.09 0.09 0.09 0.09 0 0 Methane 0 0 0 0 11.5 11.5 11.5 11.5 0 0 Ethane 0 0 0 0 0.86 0.86 0.86 0.86 0 0 Propane 0 0 0 0 0.45 0.45 0.45 0.45 0 0 Hydrogen 0 0 0 0 0.19 0 0 0 0.19 0.19
44
Table 9. Steam Table Summary for CNG Production Process shown in Figures 3-6 (Continued)
Stream Number 51 52 53 54 55 56 57 58 59 60 61
Temperature (oC) 60 43 32 49 32 49 32 49 32 49 49 Presure (kPa) 110 105 110 105 110 105 110 105 110 105 105
Solid Fraction 0 0 0 0 0 0 0 0 0 0 0
Liquid Fraction 0 0 1 1 1 1 1 1 1 1 1 Vapor Fraction 1 1 0 0 0 0 0 0 0 0 0
Mass Flow (kg/hr) 0.19 0.19 247.3 247.3 17.3 17.3 7.09 7.09 0.66 0.66 272
Component Mass Flow (kg/hr)
Algae 0 0 0 0 0 0 0 0 0 0 0 Air 0 0 0 0 0 0 0 0 0 0 0
Water 0 0 247.3 247.3 17.3 17.3 7.09 7.09 0.66 0.66 272 Salts 0 0 0 0 0 0 0 0 0 0 0 Carbon Dioxide 0 0 0 0 0 0 0 0 0 0 0 Carbon Monoxide 0 0 0 0 0 0 0 0 0 0 0 Methane 0 0 0 0 0 0 0 0 0 0 0 Ethane 0 0 0 0 0 0 0 0 0 0 0 Propane 0 0 0 0 0 0 0 0 0 0 0 Hydrogen 0.19 0.19 0 0 0 0 0 0 0 0 0
45
Major Equipment List
Table 10: Equipment Table - Pump
Pump P-101 A/B P-102 A/B(28)
P-201 A/B
Type Reciprocating Centrifugal Centrifugal
Motor Open drip-proof CSTR
Open-drip-
proof
Component Algae/water Water Water
Flow [kg/hr] 5239.4 23321.9 124470.04
Fluid Density [kg/m3] 977 977 977
Efficiency 0.75 0.75 0.75
Power consumption (hp) 221 2 14.6
Break power (hp) 82.3 --- 11.94
MOC Carbon steel Cast Iron Carbon steel
Vendor --- Grainger ---
Pump P-301 A/B(29)
P-402 A/B(30)
Type Centrifugal Vacuum
Motor CSCR Rotary vane
Component Water Hydrogen
Flow [kg/hr] 1903.16 0.193
Fluid Density [kg/m3] 977 0.0899
Efficiency 0.75 0.75
Power (hp) 0.333 1.5
MOC Cast iron Carbon steel
Vendor Grainger US Vacuum
46
Table 11: Equipment Table - Heat Exchanger
Heat Exchanger E-101 E-102 E-201
Type Shell and tube Double pipe Shell and tube
Direction of Flow Counter-current
Counter-
current
Counter-
current
Duty (kW) 2308.381 518.265 32.601
Area (ft2) 435.71 156.07 233.8
MOC Carbon steel Carbon steel Carbon steel
Tube (Hot)
Component Reactor effluent
Reactor
effluent Flue gas
Inlet Temperature (oC) 400 122 493
Outlet Temperature (oC) 117 43 142
Pressure (kPa) 30975 295 125
Phase Liquid/vapor Liquid/vapor Vapor
Shell (Cold)
Component Algae slurry Cooling water Air
Inlet Temperature (oC) 35 32 16
Outlet Temperature (oC) 372 49 465
Pressure (kPa) 30995 105 135
Phase Liquid Liquid Vapor
Heat Exchanger E-202 E-301 E-302
Type Double pipe Double pipe Double pipe
Direction of Flow Counter-current
Counter-
current
Counter-
current
Duty (kW) 1.24 28.3 3.8
Area (ft2) 5.4 1.8 1.7
MOC Carbon steel Carbon steel Carbon steel
Tube (Hot)
Component Flue gas Brine Brine
Inlet Temperature (oC) 142 400 86
Outlet Temperature (oC) 136 80 43
Pressure (kPa) 120 30975 105
Phase Vapor Liquid/solid Liquid/Solid
Shell (Cold)
Component Methane mix Cooling water Cooling Water
Inlet Temperature (oC) 24 32 32
Outlet Temperature (oC) 131 49 49
Pressure (kPa) 135 105 105
Phase Vapor Liquid Vapor
47
Heat Exchanger E-401 E-402 E-403
Type Double pipe Double pipe Double pipe
Direction of Flow Counter-current
Counter-
current
Counter-
current
Duty (kW) 4.88 0.14 0.34
Area (ft2) 6.1 2.4 0.5
MOC Carbon steel Carbon steel Carbon steel
Tube (Hot)
Component CNG CNG Hydrogen
Inlet Temperature (oC) 500 60 500
Outlet Temperature (oC) 60 43 60
Pressure (kPa) 21985 21980 110
Phase Vapor Vapor Vapor
Shell (Cold)
Component Cooling water Cooling water Cooling water
Inlet Temperature (oC) 32 32 32
Outlet Temperature (oC) 49 49 49
Pressure (kPa) 105 105 105
Phase Liquid Liquid Liquid
Heat Exchanger E-404
Type Double pipe
Direction of Flow Counter-current
Duty (kW) 0.013
Area (ft2) 0.3
MOC Carbon steel
Tube (Hot)
Component Hydrogen
Inlet Temperature (oC) 60
Outlet Temperature (oC) 43
Pressure (kPa) 105
Phase Vapor
Shell (Cold)
Component Cooling water
Inlet Temperature (oC) 32
Outlet Temperature (oC) 49
Pressure (kPa) 105
Phase Liquid
48
Table 12: Equipment Table – Heater
Heater F-101
Type Furnace
Component Air/Methane
Temperature (oC) 493
Pressure (kPa) 135
Power (kW) 277.2
Phase Vapor
MOC Carbon Steel
Table 13: Equipment Table - Blower
Blower P-202 A/B
Type Centrifugal
Component Air
Efficiency 0.75
Power consumption (hp) 12.9
Break power (hp) 9.86
MOC Aluminum
Table 14: Equipment Table – Reactor
Reactor R-101 A/B
Type Vertical Vessel
Catalyst Ru/C
Volume (m3) 13.67
Temperature (oC) 400
Pressure (kPa) 30980
Phase Liquid
MOC Carbon Steel
Table 15: Equipment Table - Salt Separator
Salt Separator S-101
Type Gravitational
Volume (m3) 13.29
Temperature (oC) 400
Pressure (kPa) 30990
Phase Liquid/Solid
MOC Carbon Steel
49
Table 16: Equipment Table - Scrubber
Scrubber S-201 S-301
Type Gas Absorber Gas Absorber
Volume (m3) 7.2 3.5
Temperature (oC) 25 25
Pressure (kPa) 285 115
Phase
Mixed
Liquid/Vapor
Mixed
Liquid/Vapor
Packing
1.5 in. Raschig
Rings
1.5 in. Raschig
Rings
MOC Carbon Steel Carbon Steel
Table 17: Equipment Table - Valve
Valve V-101 V-201 V-301
Type Letdown Letdown Letdown
Pressure Drop (kPa) 30670 145 30865
Phase Liquid Vapor Liquid/Solid
Table 18: Equipment Table -Drum
Drum D-201
Type
Vertical
Vessel
Volume (m3) 3.29
Temperature (oC) 43
Pressure (kPa) 295
MOC Carbon Steel
Table 19: Membrane
Membrane S-401
Type Dense Metallic
Hydrogen Flux [kg/hr] 0.193
Temperature (oC) 500
Pressure drop (kPa) 21950
MOC Palladium/Ceramic
Table 20: Equipment Table - Compressor
Compressor P-401 A/B
Type Screw
Component CNG
Efficiency 0.75
Power (hp) 11.2
MOC Carbon Steel
50
Raw Material and Utility Requirements
Table 21 summarizes the annual utility requirements of the process. Calculations showing
yearly consumption are shown in Appendix C.
Table 21: Raw Material and Utility Requirements
Component Yearly Consumption Unit Cost Total Yearly Cost
Algae 1,095 tons $1.00/ton $1,095
Electricity 1,722,177.6 kWh $0.06/kWh(18)
$103,330.66
Cooling Water 220,971.53 m3 $0.02/m
3(18) $4419.43
Process Water 1,090,357.55 m3
$0.20/m3(18)
$218,071.51
Total Yearly Utility Cost $325,821.60
Total Yearly Raw
Material Cost
$1,095
51
Safety/Environmental Factors
Safety Statement
The safety of the plant is a key component to consider when constructing a prosperous
plant design, and safety requirements were reviewed to ensure there were no violations.
An examination of the chemicals, using several sources such as Material Safety Data
Sheets (MSDS) and the Environmental Protection Agency, was completed to evaluate the
potential health effects, PPE requirements, first aid measures, and handling and storage.
Accessible eye washes and body emergency baths will be located in each area of the
plant to ensure immediate access. When using the eye wash bath, it is important that the
individual lifts the upper and lower eyelids and removes contacts to improve rinsing. In
the event of a chemical spill on the body, an individual should remove any exposed
clothing to minimize the level of contamination and thoroughly rinse in the body bath.
The entire plant will be ventilated but a system will be integrated that will monitor the air
quality for contaminant levels. Safety meetings will be held to address any concerns that
may arise and to keep all personnel in compliance with all safety requirements. They
should only eat in designated areas after hands have been meticulously washed.
Table 22 lists all the chemicals that are used in the process and the possible symptoms of
exposure and the corrective actions. Hydrogen, salt, algae, ethane and methane do not
pose a threat to the safety of the personnel and the listed symptoms occur in rare cases. If
there is any exposure to these chemicals, including ingestion, the corrective actions
should be taken and medical attention is required, even if symptoms desist. Although
there are no fatal side effects to chronic exposure to these chemicals it is best to minimize
52
any exposure. Extra precautions should be taken when handling these chemicals and
employees should inform others when they are going to handle the chemicals in case of
an accident and to prevent leaks. It was determined that carbon dioxide carbon monoxide,
and propane were the most dangerous chemicals in the plant process. Gaseous methane
and ethane are simple asphyxiates but carbon dioxide, carbon monoxide, and propane can
cause suffocation at high exposure levels. Carbon monoxide has Permissible Exposure
Limit (PEL) set by the Occupational Safety and Health Administration (OSHA) of 50
ppm for an eight hour period (31). Carbon dioxide and propane has a PEL level of 5000
ppm and 1000ppm, respectively. These levels are not present in our process therefore
there is not a high concern (32, 33).
53
Table 22: Exposure Hazards and Appropriate Action
Inhalation Eyes Skin Ingestion
Compound Symptoms Action Symptoms Action Symptoms Action Symptoms Action
CO (31) Nausea, Vomiting,
Headache
Fresh Air,
Medical Attention Irritation
Flush with
water (15 min.) Irritation
Flush with cool
water (15 min.) Irritation
Medical
Attention
CO2 (32) Nausea, Vomiting,
Headache
Fresh Air,
Medical Attention Irritation
Flush with
water (15 min.) Irritation
Flush with cool
water (15 min.) Irritation
Do Not
Induce
Vomiting
H2 (34) Nausea, Vomiting,
Headache
Fresh Air,
Medical Attention
Irritation,
Redness
Water, Medical
Attention Irritation
Flush with
water (15 min.) Irritation
Medical
Attention
C2H6 (33) Shortness of Breath Fresh Air,
Medical Attention Irritation
Flush with
water (15 min.) Irritation
Flush with
water (15 min.) Irritation
Medical
Attention
CH4 (35) Rapid Breathing Fresh Air,
Medical Attention Irritation
Flush with
water (15 min.) Irritation
Flush with
water (15 min.) Irritation
Medical
Attention
C3H8 (36) Suffocation Relocate to Fresh
Air
Irritation,
Burning
Flush with
water (15 min.) Irritation
Flush with
water (15 min.) Irritation
Medical
Attention
Salt (37) Irritation Relocate to Fresh
Air Irritation
Flush with
water (15 min.) Irritation
Flush with
water (15 min.) Irritation
Drink
Plenty of
Water
Algae (38) None Relocate to Fresh
Air Irritation
Flush with
water (15 min.) Irritation
Flush with
water (15 min.) Irritation
Drink
Plenty of
Water
H2O (39) None N/A None N/A None N/A None N/A
Air (40) None N/A None N/A None N/A None N/A
54
The most hazardous chemicals were further evaluated for their flammability, reactivity,
incompatibly and any other special hazard and organized in Table 23. The storage of all
the chemicals will be in a cool, dry, well-ventilated location away from its incompatible
compounds. For the chemicals in our process the most incompatible compounds are
oxidizers which could react with the gases to cause a fire. Since there are no oxidizers
present in the plant the relative threat is minimal, but all precautions should remain. If a
gas base fire was to occur, it must be extinguished with foam, dry chemical or carbon
dioxide, but not water.
Table 23: General Hazards for Process Chemicals
Compound Flammability Reactivity Incompatibilities Special Hazards
CO (31) High Medium Oxidizers, Barium
Peroxide
Use dry chemical, foam, or
carbon dioxide to quench fire
CO2 (32) None Low Reactive Metals,
Hydrides N/A
H2 (34) Extremely Medium Oxidizers,
Chlorine, Lithium
Use dry chemical, foam, or
carbon dioxide to quench fire
C2H6 (33) Extremely Low Oxidizers Use dry chemical, foam, or
carbon dioxide to quench fire
CH4 (35) Extremely Low Heat, Sparks,
Flames, Oxidizers
Use dry chemical, foam, or
carbon dioxide to quench fire
C3H8 (36) Extremely Low Heat, Sparks,
Flames
Use dry chemical, foam, or
carbon dioxide to quench fire
Another safety consideration is the hazard that the equipment presents. A Process
Hazards Analysis (PHA) was conducted for most pieces of equipment and can be
reviewed below. The biggest hazard identified are upsets such as unit overpressures or
ruptures that release natural gas or hydrogen to the atmosphere, potentially causing a fire
or explosion. To minimize the number of ignition sources available, all electronics in
hazardous locations will have Specific Class I, Division 1 Groups B and D electrical
classification. Another risk is vessel failure when the vessel contents are supercritical; the
equipment is functioning at very high pressures and should be well maintained to prevent
55
any malfunction, rupture and resulting steam explosion in the equipment. Pressure
sensors will be installed on all necessary equipment and they will be hardwired to
appropriate alarms and automated. Many of the pieces of the equipment have a spare that
can be automatically utilized during maintenance or malfunction. Pump, compressor or
blower malfunctions could cause an upset down the line as in many of the cases for the
equipment, leading to fire or explosion. Safeguards against this possibility include
incorporating minimum flow lows and low flow alarms wired to the control house.
Steps were also taken to reduce temperature exposure safety concerns with individual
pieces of equipment. All of the shell-and-tube heat exchangers were designed to have the
higher temperature fluids on the tube-side. This design allows the outside of the heat
exchanger to be cooler than if the higher temperature streams were on the shell-side. All
of the double-pipe heat exchangers were designed to have the higher temperature stream
in the inner tube for the same reason. However, the outside temperatures of several pieces
of equipment are still at high temperatures, and therefore precautions need to be made in
order to prevent accidental exposure to the hot surfaces. Barriers will be set in place to
ensure these surfaces cannot be accidentally touched and heat-resistant clothing, such as
Nomex, will be required when working around these hot pieces of equipment.
Environmental Impact Statement
The effect that a chemical may have on the environment is an important aspect to
research when implementing a new process design. Throughout the process design, the
chemicals that were proposed were reconsidered if there was a negative impact on the
environment, such as a high toxicity level.
56
For all chemicals when an accidental spill or leak occurs it needs to be attended to
immediately to avoid further contamination, for the safety of the personnel and
environment. All piping will have a non-corrosive coating, nickel chrome alloy, targeted
to protect against gas corrosion (41). Chemical waste is either taken to a Resource
Conservation and Recovery Act (RCRA) approved disposal facility or incinerator. When
cleaning a chemical spill, all personnel will be required to wear the personal protective
equipment (PPE) appropriate to the situation and the supply source of the chemical
should be immediately shut off. If large amounts of any chemical are released into the
environment the Environmental Protection Agency should be informed. Providing a fire
was to start, the proper equipment needed to extinguish it would be available to minimize
byproduct discharge. Table 24 lists all the chemicals with their appropriate measures in
an accidental release, appropriate disposal method, and harmful degradation by-products.
Water and Air were not included in the table because they do not have any environmental
hazards.
Table 24: Appropriate Chemical Measures
Compound Accidental Spill Measures Disposal Method Degradation
Byproducts
Carbon
Dioxide (32)
Contained ventilated area,
collect in appropriate container
Observe State and
Local Regulations
Carbonic acid,
Carbon monoxide
Carbon
Monoxide
(31)
Contained ventilated area,
collect in appropriate container
Observe State and
Local Regulations Carbon Dioxide
Methane (35) Contained ventilated area,
collect in appropriate container
Send to a RCRA
approved incinerator
or facility
None
Ethane (36) Contained ventilated area,
collect in appropriate container
Observe State and
Local Regulations None
Propane (33) Contained ventilated area,
collect in appropriate container
Sealed Container to
BOC Gas Location None
Hydrogen (34) Contained ventilated area,
collect in appropriate container
Sealed Container to
BOC Gas Location None
57
Further research was conducted to evaluate the environmental effect were there to be a
release of the chemical from the plant. Carbon dioxide is a gas that is abundantly found in
the atmosphere, occurring naturally and man produced. Although the majority of plant
and animal life rely on carbon dioxide, the amount that is released into the air has exceed
the amount can be naturally sequestered (42). With excess carbon dioxide in the air more
heat is captured and remains in the atmosphere known as the greenhouse effect. The
estimated amount of the mass of the greenhouse gas that can contribute to capturing heat
is known as Global Warming Potential (GWP), and carbon dioxide has a GWP of 1.
Another chemical gas that is dealt with in the process design in methane and it has a
GWP of 21(43). This is more elevated potential than carbon dioxide and all safety
measures to prevent a leak should be taken. Carbon dioxide also is released from the
plant due to the use of electricity for several pieces of our unit operation. The estimated
amount of carbon dioxide emissions from the use of electricity for one year was
determined to be 1,720,000 kg (44).
The discharge of a flammable chemical or material into the environment is a hazard that
should be avoided. Ethane, propane and the catalyst, ruthenium on carbon, are all highly
flammable materials that need to have a properly functioning shut off valve in case of
fire. When any of these chemicals burn it produces carbon dioxide and the possible
incomplete combustion can produce carbon monoxide. If a fire is to occur, remove the
source of the ignition and contain the ventilated gases.
58
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit:100 System:
Method: What-if Type: Continuous Reactor Design Intent: To remove various salt components
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 1 Description: S-101 Salt Separator
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
1.1 What if the vessel over-pressurizes?
Valve failure P-101 A/B disturbance Unchecked salt accumulation in process pipes What if the vessel has excessive salt accumulation?
Vessel rupture Steam explosion Loss of effective salt separation R-101 catalyst poisoning and product loss
Pressure relief valves Pressure sensors hardwired to quench system Emergency shut-off system
1.2 What if the vessel overheats?
F-101 upset Unintended runaway chemical reaction Fire nearby caused by failure of other pieces of equipment
Increase in temperature in downstream units, leading to product quality loss or fire Over-pressuring of vessel Overheating of brine sent to algae farm, killing process feedstock
Temperature sensor hardwired to quench system Emergency shut-off system
1.3 What if there is excessive salt accumulation in the vessel?
Valve blockage E-301 upset Corrosion What if the vessel over-pressurizes?
Loss of effective salt separation R-101 catalyst poisoning and product loss
Emergency shut-off/Isolation Low-flow alarms wired to control house Regular maintenance
1.4 What if the temperature drops too low?
E-101 tube leak F-101 upset Vessel insulation failure Accidental quench system triggering
Loss of effective salt separation Loss of conversion of algae to syngas Product loss Poisoning of R-101 catalyst
Temperature sensor hardwired to emergency high pressure steam heater Use of slop tank to pass cold slurry to in order to spare R-101 Vessel isolation system
59
Company
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit:100 System:
Method: What-if Type: Continuous Reactor Design Intent: To gasify algae biomass & create methane
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 2 Description: R-101 Gasification & Methanation Reactor
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
2.1 What if the reactor ruptures? V-101 failure causes overpressure Upstream upset Runaway chemical reaction causes overpressure External impact Corrosion by supercritical conditions What if the reactor leaks?
Loss of containment Steam explosion Methane fire/explosion
Pressure relief valve Pressure sensors hardwired to quench system Regular inspections of reactor to look for corrosion or leaks Corrosion allowance Stress relief
2.2 What if the reactor overheats? Runaway chemical reaction S-101 overheating What if the reactor ruptures?
Destruction of carbon catalyst support, leading to catalyst loss Overheating of downstream units, leading to off-spec CNG
Temperature sensor hardwired to quench system
2.3 What if the reactor leaks? Corrosion by supercritical conditions Weakened or melted by high temperatures External Impact Metal fatigue
Loss of containment Fire/explosion caused by methane leak
Regular inspections to look for potential trouble spots Periodic nondestructive testing Deluge system Protective barriers
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
2.4 What if there is catalyst poisoning/loss?
S-101 upset Overheating of reactor Corrosion Retaining mechanism failure
Product Loss Unintended chemical reactions Loss of feed to F-101 Loss of effective salt separation in S-101
Proper catalyst containment Temperature sensor hardwired to quench system Corrosion allowance Knockout drum to absorb S-101 upsets
60
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 100 System:
Method: What-if Type: Heat Exchanger Design Intent: To increase the temperature of the algae slurry to be able to reach supercritical values before entering the salt separator
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 3 Description: E-101 Preheater & E-202 Superheater
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
3.1 What if there is a tube leak or rupture?
Corrosion Stress cracking Weakened/melted by exposure to high temperature Tube cracks because of differential thermal expansion
Loss of containment Methane fire/explosion Corrosion downstream S-101 has influx of new unwanted compounds, potentially causing upsets
Corrosion allowance Periodic nondestructive testing Deluge system
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
3.2 What if the tubes are subjected to excessive pressure?
R-101 upset Tubes blocked during startup Heat applied with tubes blocked in What if the shell is over-pressurized?
Tube leak or rupture Loss of containment Methane fire/explosion
Pressure relief valves on each pass Low flow alarms wired into control room Deluge system Exchanger bypass system
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
3.3 What if the exchanger shell is over-pressurized?
P-101 A/B deadheaded Blocked exit valve F-101 upset induces high pressure in outlet line
Loss of containment Methane fire/explosion Tube leak or rupture
Pressure relief valves Pressure alarms wired to control room P-101 A/B over-speed trip
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
3.4 What if the exchanger loses cooling stream feed?
P-101 A/B trip Algae farm loses feed Valve closure What if there is a tube leak or rupture?
High temperature induced failures, fires or explosions in downstream units Loss of reactor feed Loss of product Supercritical unit depressurization
A/B redundant pumps Temperature alarms wired to control room Low flow alarms wired to control room Emergency cooling water source available
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
61
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 100 System:
Method: What-if Type: Heater Design Intent: To heat air entering the E-102 heat exchanger
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 4 Description: F-101 Furnace
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
4.1 What if firebox leaks or ruptures?
Corrosion by flue gasses Localized damage by flame impingement External impact Stress corrosion cracking
Release of hot flue gases Loss of heat transfer to algae Poisoning of catalyst in R-101 by loss of salt removal in S-101 Product loss
Automatic burner shutdown Vacuum relief system Double block valves, caps, or plugs in all sample and drain connections
4.2 What if the firebox over-pressurizes?
Closed stack damper on forced draft furnace Liquid carryover in fuel gas What if the firebox leaks or ruptures?
Loss of containment Fire/explosion Tube failure
Pressure relief valve Furnace trip signals Firebox air intake separated from likely sources of flammable gas leaks
4.3 What if the air stream cannot reach the furnace?
P-202 A/B failure Valve closure Air inlet blockage (debris, etc.) What if the air supply starts up again and there is accumulation of uncombusted fuel in the firebox?
Loss of heat transfer to slurry Poisoning of catalyst in R-101 by loss of salt removal in S-101 Explosion
Automated shutoff of fuel gas source Spare blower Low flow alarms wired to control house Furnace isolation
4.4 What if the flame is extinguished?
Low fuel pressure What if there are still explosive vapors inside the furnace? What if the air stream cannot reach the furnace?
Explosion caused by sudden reignition in firebox Release of natural gas into atmosphere Fire downstream of S-301
Temperature sensors hardwired to automatic valve shutoff system Deluge system Automatic reignition system
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
62
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 400 System:
Method: What-if Type: Condenser Design Intent: To remove water from the process stream
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 5 Description: E-401, E-402, E-403, E-404 Coolers
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
5.1 What if there is a tube leak or rupture?
Corrosion Stress cracking Weakened/melted by exposure to high temperature Tube cracks because of differential thermal expansion
Loss of containment Product leak to environment Methane or hydrogen fire/explosion
Corrosion allowance Periodic nondestructive testing Deluge system
5.2 What if the tubes are subjected to excessive pressure?
P-401 A/B upset Tubes blocked during startup Heat applied with tubes blocked in What if there is a tube leak or rupture?
Tube leak or rupture Loss of containment Methane or hydrogen fire/explosion
Pressure relief valves Low flow alarms integrated into control room Deluge system Exchanger bypass system Incorporation of semi-automated back-flushing system
5.3 What if the exchanger shell is over-pressured?
P-301 A/B deadheaded Blocked exit valve What if the tubes are subjected to excessive pressure?
Loss of containment Methane or hydrogen fire/explosion Tube leak or rupture
Pressure relief valves Pressure alarms wired to control room P-301 A/B over-speed trip
5.4 What if the exchanger lost cooling stream feed?
P-301 A/B trip Cooling water source disrupted Valve closure
Product produced at too high a temperature Loss of product Fire/explosion
Spare pump Temperature alarms wired to control room Low flow alarms wired to control room Emergency cooling water source available
63
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 200 System:
Method: What-if Type: Scrubber Design Intent: To remove CO2 and excess water from the process stream
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 6 Description: S-201 Scrubber
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
6.1 What if the scrubber leaks or ruptures?
External impact V-101 failure Blockage of tower packing Stress fractures causes by temperature swings
Release of methane to atmosphere Fire/Explosion CO2 release to atmosphere CO2 feed to algae farm partially disrupted
Pressure relief valve Shielding from external impacts Annual tower scans to detect packing abnormalities Inspection of scrubber shell to find potential leak points/corrosion
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
6.2 What if the scrubber reaches too high a temperature?
Upstream heat exchanger failure Furnace upset Fouling in upstream exchangers Upstream exchangers bypassed What if the scrubber loses water feed?
Possible damage to tower packing Inadvertent reactions between vapor and water Loss of product quality
Temperature sensors hardwired to quench system Heat resistant packing Regular cleaning of exchangers
6.3 What if the scrubber loses water feed?
P-201 A/B failure Process water intake obstruction Inadvertent valve closure Leak in P-201 A/B discharge line
Loss of CO2 feed to algae farm Loss of product quality
Spare pump Regular line inspections to look for leaks/corrosion Low flow alarms wired to control house
6.4 What if the scrubber loses packing material?
Improper securing of packing Mechanical impact Packing degradation by high temperatures What if the scrubber loses water feed?
Loss of CO2 feed to algae farm Loss of product quality
Shielding from external impacts Heat resistant packing Maintenance of packing retention systems as needed
64
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 300 System:
Method: What-if Type: Scrubber Design Intent: Removes CO2 from flue gas
Number: S-201
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 7 Description: S-301 Flue Gas Scrubber
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
7.1 What if the scrubber leaks or ruptured?
External impact Blockage of tower packing Stress fractures causes by temperature swings Corrosion
CO2 release to atmosphere CO2 feed to algae farm disrupted
Pressure relief valve Shielding from external impacts Annual tower scans to detect packing abnormalities Inspection of scrubber shell to find potential leak points/corrosion
7.2 What if the scrubber reaches too high a temperature?
Upstream heat exchanger failure Furnace upset Fouling in upstream exchangers Upstream exchangers bypassed What if the scrubber loses water feed?
Possible damage to tower packing Inadvertent reactions between vapor and water Loss of product quality
Temperature sensors hardwired to quench system Heat resistant packing Regular cleaning of exchangers
7.3 What if the scrubber loses water feed?
P-201 A/B failure Process water intake obstruction Inadvertent valve closure
Loss of CO2 feed to algae farm CO2 release to atmosphere
Spare pump Regular line inspections to look for leaks/corrosion Low flow alarms wired to control house
7.4 What if the scrubber loses packing material?
Improper securing of packing Mechanical impact Packing degradation by high temperatures What if the scrubber loses water feed?
Loss of CO2 feed to algae farm CO2 release to atmosphere
Shielding from external impacts Heat resistant packing Maintenance of packing retention systems as needed
65
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 400 System:
Method: What-if Type: Compressor Design Intent: To compress methane to CNG
Number: P-202
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 8 Description: P-402 A/B Methane Compressors
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
8.1 What if liquid enters the compressor?
Entrainment from S-201 Condensation of water vapor in suction lines What if the compressor trips offline?
Compressor trip Loss of discharge temperature leads to hydrogen in CNG product and poisoning of S-401 Loss of containment Fire/explosion
Knockout drum on suction line Heat tracing on suction line High level alarm on knockout drum hardwired to trip
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
8.2 What if compressor discharge pressure increases?
Blocked discharge valve Compressor over-speed Ignition in compressor caused by air leak into compressor
Downstream overpressure leads to S-401 failure and product quality loss Line rupture/leakage Loss of containment Fire/explosion
Suction to discharge relief valve Minimum flow loop Compressor casing design pressure exceeds the maximum suction pressure plus the compressor shutoff pressure Compressor design such that air cannot enter product stream
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
8.3 What if compressor overheats?
Upstream upset causing compressor to run dry Excessive upstream temperature Coolers are bypassed or lose flow What if compressor discharge pressure increases?
Mechanical failure of compressor High discharge temperature yields off-sped product
Temperature sensor wired to high pressure trip Synthetic nonflammable lubricants Low flow alarms
8.4 What if compressor trips offline?
Electrical loss Mechanical failure of some part of the compressor
Reverse flow and rotation Backup power source Utilization of spare compressor Check valve in compressor discharge
66
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 400 System:
Method: What-if Type: Membrane Design Intent: Removal of H2 from final product
Number: S-202
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 9 Description: S-401 Hydrogen Membrane
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
9.1 What if the membrane ruptures?
P-401 A/B overpressure Corrosion Fatigue caused by temperature swings P-402 A/B over-speed induced greater vacuum What if the membrane chamber leaks or ruptures?
Loss of hydrogen separation Product quality loss Methane/hydrogen release through hydrogen product line Fire/Explosion
Pressure sensors hardwired to isolation system Pressure relief valves Bypass system to equalize pressure
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
9.2 What if the membrane is exposed to too low a temperature?
P-401 A/B failure
Hydrogen poisoning of membrane Loss of hydrogen separation Loss of product quality
Low temperature alarms wired to control room Emergency high pressure steam heating system
9.3 What if the membrane chamber leaks or ruptures?
P-402 A/B failure P-401 A/B overpressure Exit valve blocked What if the membrane ruptures?
Loss of containment Fire/Explosion Loss of ability to remove hydrogen Product loss
Nondestructive testing Deluge system Pressure relief valve High pressure alarm wired to control house Isolation system
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
67
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 300 System:
Method: What-if Type: Heat Exchanger Design Intent: Remove heat from brine solution
Number: E-201
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 10 Description: E-301, E-302 Brine Coolers
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
10.1 What if there is a tube leak or rupture?
Corrosion by exposure to brine Stress cracking Weakened/melted by exposure to high temperature Tube cracks because of differential thermal expansion What if the tubes are subjected to excessive pressure?
Loss of containment Release of hot, high pressure product to environment Further corrosion downstream
Corrosion allowance Periodic nondestructive testing
10.2 What if the tubes are subjected to excessive pressure?
S-101 upset Tubes blocked during startup Heat applied with tubes blocked in V-301 blockage
Tube leak or rupture Loss of containment Release of hot, high pressure product to environment
Pressure relief valves Low flow alarms integrated into control room Exchanger bypass system Incorporation of semi-automated back-flushing system
10.3 What if the exchanger shell were over-pressured?
P-301 A/B deadheaded Blocked exit valve What if the tubes are subjected to excessive pressure?
Loss of containment Release of hot, high pressure product to environment
Pressure relief valves High pressure alarms wired to control room P-301 A/B over-speed trip
10.4 What if the exchanger loses cooling stream feed?
P-301 A/B trip Cooling water source disrupted Valve closure
Brine produced at too high a temperature, killing algae feedstock in the algae farm Overpressure of E-302 tubes
A/B redundant pumps Temperature alarms wired to control room Low flow alarms wired to control room Emergency cooling water source
68
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: 200 System:
Method: What-if Type: Pump Design Intent: Provide water for heat and CO2 removal
Number: P-201, P-203
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 11 Description: P-201 A/B Water Pumps
Item What if...? Root Causes/Related Questions Consequences Safeguards Action Items
11.1 What if the pump trips offline?
Loss of electricity Mechanical failure
Loss of process water flow to scrubbers Overheating of CNG product Loss of CO2 scrubbing capacity, inducing product quality loss Release of hot flue gas to atmosphere Packing damage in S-301
Backup power source Spare pump Low flow alarm Pump run light
11.2 What if the pump is subjected to high temperature?
Lube oil coolers are bypassed or lose flow Pump run dry What if the pump overpressures?
High temperature in discharge stream Loss of CO2 scrubbing Product quality loss
Low flow alarms wired to control house Temperature sensors hardwired to lube oil coolers Spare pump
11.3 What if the pump overpressures?
Pump over-speed Leakage through the check valve of the parallel standby pump Blocked discharge valve
Over-pressurization of CO2 scrubbers Loss of containment in S-201 Methane discharge to atmosphere Fire/explosion
Suction to discharge relief valve Minimum flow loop
Specific Class I, Division 1 Group B and D electrical classification for Hazardous Locations
11.4 What if the pump leaks or ruptures?
Corrosion caused by contaminants Stress corrosion cracking Gasket leak Drain valve open What if the pump trips offline?
Water release to environment Loss of feed to scrubbers Loss of CO2 scrubbing capacity, inducing product quality loss Release of hot flue gas to atmosphere Packing damage in S-301
Corrosion allowance Periodic non-destructive testing Stress relief Provision for flushing out all pumps during startup and shutdown
69
Company:
Kazaam, LLC.
Plant: University of Arizona- Spring 2010 Chemical Engineering Department
Site: TBD Unit: System:
Method: What-if Type: Utilities and plant services Design Intent: Provide electric power, control system, plant air/steam/refrigeration. vacuum, fuel oil, natural gas, HVAC service, fire and cooling water, etc. to the facility
Number:
Team Members: Kyle Kryger, Kimberly Seamans, Zachary Ronan, Amanda Rubio
No.: 12 Description: Utilities and plant services
Item What if...? Root Causes/Related Questions
Consequences Safeguards Action Items
12.1 What if electric power were lost momentarily or longer?
What if high pressure steam were lost? Severed Cable Lightning strike Offsite utility power loss Overload Transformer fire Turbogenerator trip What if cooling water was lost?
Process stream backflow Loss of nighttime lighting Loss of control system Potential furnace upset
Alternate power source Breakers and protective logic Emergency shutdown procedures Backup power generators Status panel in the motor control center
12.2 What if the control system (DCS, PLC, etc.) were lost?
What if electric power were lost momentarily or longer?
Loss of controls inside the control room Process must by operated directly
All DCS-operated valves stay in their last valid position to keep the unit stable Backup control modules Backup power supply
12.3 What if cooling water was lost? Cooling water pump shuts off Fouling in the cooling water system Header rupture Low level in the cooling tower reservoir What if electric power were lost momentarily or longer?
Potential compressor damage Leaks on pumps with water cooled seals Overheating of process stream
Pressure indication and low pressure alarm Flow indication and low flow alarm Temperature indication and high temperature alarm Parallel backup pumps
12.4 What if fire suppression (water, carbon dioxide, Halon, etc.) were lost?
What if high pressure steam were lost? Pump tripping off Debris plugging intake
Loss of firefighting capability Possible explosion due to unresolved fire
Intake screens Parallel backup pumps Pressure indication and low pressure alarm
70
No.: 12 Description: Utilities and plant services
Item What if...? Root Causes/Related Questions
Consequences Safeguards Action Items
Fouling in the water system Header rupture Low level in the reservoir
12.5 What if there was inadequate drainage? Improper grade/slope Inadequate drain pipe diameter Sand/gravel/shell accumulation Sludge accumulation Collapsed or plugged piping
Drainage backup Flooding Slip hazards
Periodic cleaning
12.6 What if the flare or thermal oxidizer were lost?
Burner control system malfunction High level in knockout pot High wind Loss of assist gas What if fuel gas were lost?
Potential release of unburned methane and carbon dioxide
Independent pilot system Infrared heat sensors Natural gas backup to purge gas Video monitoring of flare Opacity monitoring of stack exhaust
12.7 What if nighttime lighting were lost? What if electric power were lost momentarily or longer? Lightning strike Offsite utility power loss Overload
Potential personnel injuries (falls, etc.) Inability to see equipment clearly
Battery power for selected lights Emergency lighting circuit Flashlights
12.8 Plant people and contractors are not adequately trained?
Inadequate training Lack of organized records maintenance Updates to computer software for process monitoring
Potential personnel injuries Potential equipment failures
Initial safety training with required refresher courses as needed Required work permits
71
Economic Analysis
Statewide Energy Markets
In addition to completing a full technical review, a thorough economic analysis of the
project was performed. To fully understand the economic impact of this process, the
Arizona natural gas market must first be analyzed. In the year 2009, a total of 32.4 billion
scf of natural gas were purchased by commercial consumers (45). As described in
Appendix A-14, 5,865,000 scf per year of CNG will be produced by this process,
representing 0.018% of the Arizona commercial market. This plant will have a very small
impact in this market; therefore, this plant is not expected to have any measurable impact
on the market price of natural gas.
Hydrogen is also produced by this process. The hydrogen market in the US is estimated
to be $1,600,000,000 (46) every year. As shown below, the 1690.68 gge of hydrogen
produced annually by this process has a value of $8500. This amount of hydrogen
amounts to 0.0005% of the American hydrogen market. This plant will have a very small
impact in this market; therefore, this plant is not expected to have any measurable impact
on the market price of hydrogen.
Sales Revenue
After defining the energy markets in Arizona, the next logical step is to find the annual
revenue this process can generate selling fuel in this market. Yearly production, market
prices and anticipated revenue are all summarized in Table 25.
72
Table 25: Yearly Production and Sales Revenue
Product Yearly Production Market Price Sales Revenue
Natural gas 5,865,000 scf $10.93 / 1000 scf(47)
$64,100
Hydrogen 1700 gge $5 / gge(48)
$8,500
Total: $72,600
Total Capital Investment and Operating Costs
After defining projected sales revenue, defining the costs involved in production of the
product was the next step. The total installed costs for all major pieces of equipment were
found and are summarized in Table 26. Calculations justifying all equipment costs are
found throughout Appendix A and in Appendix B-1. All dollar amounts are in 2010
dollars.
Table 26: Total installation Costs for Major Equipment
Name Cost Name Cost Name Cost
D-101 171900 E-402 4100
P-301
A/B 900
E-101 352000 E-403 2100
P-401
A/B 87000
E-102 5400 E-404 2000
P-402
A/B 5500.00
E-201 34700 F-101 101900 R-101 2802200
E-202 3100 P-101 A/B 410000 S-101 2236000
E-301 7600 P-102 A/B 1800 S-201 134400
E-302 2600 P-201 A/B 9400 S-301 94000
E-401 4800 P-202 A/B 14800 S-401 52400
Summing these numbers up, the cost of the equipment is $6,540,000. The other major
item to be purchased upfront is the initial catalyst charge. This has a price of $4,500,000.
As demonstrated in Appendix B-2, these purchase costs were used to find the total capital
investment required to build the plant, CTCI. The CTCI was found to be $18,200,000. As
shown in Appendix B-3, the value for CTCI was used to approximate the annual cost of
manufacturing (COM). The annual COM was found to be $7,230,000.
73
These numbers were used to find the net present value (NPV) of the plant. Table 27
summarizes the factors involved in computing NPV as well as the cumulative NPV. To
arrive at these numbers, a one year construction time was assumed. Depreciation was
modeled assuming no salvage effort will be made; the depreciation was modeled
according to the MACRS model on a seven year basis (18). The depreciation scheme
here is not identical to the depreciation scheme used in calculating COM, as justified in
Appendix B-4. Income taxes were not taken out of the net earnings because no profit is
turned. As explained in Appendix F, an interest rate of 30% was used to calculate the
discounted cash flow because the process is untested and thus inherently risky. Detailed
calculations for all values can be found in Appendix B-4.
74
Table 27: Net Present Value of the Plant
Year Investment Ctdc Investment Cwc D COM-D S Net Earnings Discounted Cash Flow Cash Flow (PV) Cum PV
2010 (14,458,476.54) (602,150.47) (15,060,627.01) (15,060,627.01) (15,060,627.01)
2011 2,066,116.30 6,794,942.86 72,560.67 (8,788,498.49) (6,722,382.19) (5,171,063.23) (20,231,690.24)
2012 3,540,880.90 6,794,942.86 72,560.67 (10,263,263.10) (6,722,382.19) (3,977,740.94) (24,209,431.18)
2013 2,528,787.55 6,794,942.86 72,560.67 (9,251,169.74) (6,722,382.19) (3,059,800.73) (27,269,231.91)
2014 1,805,863.72 6,794,942.86 72,560.67 (8,528,245.91) (6,722,382.19) (2,353,692.87) (29,622,924.77)
2015 1,291,141.95 6,794,942.86 72,560.67 (8,013,524.15) (6,722,382.19) (1,810,532.97) (31,433,457.75)
2016 1,289,696.11 6,794,942.86 72,560.67 (8,012,078.30) (6,722,382.19) (1,392,717.67) (32,826,175.42)
2017 1,291,141.95 6,794,942.86 72,560.67 (8,013,524.15) (6,722,382.19) (1,071,321.29) (33,897,496.71)
2018 644,848.05 6,794,942.86 72,560.67 (7,367,230.25) (6,722,382.19) (824,093.30) (34,721,590.00)
2019 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (633,917.92) (35,355,507.92)
2020 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (487,629.17) (35,843,137.09)
2021 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (375,099.36) (36,218,236.46)
2022 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (288,537.97) (36,506,774.43)
2023 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (221,952.28) (36,728,726.71)
2024 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (170,732.53) (36,899,459.24)
2025 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (131,332.71) (37,030,791.95)
2026 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (101,025.16) (37,131,817.11)
2027 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (77,711.66) (37,209,528.78)
2028 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (59,778.20) (37,269,306.98)
2029 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (45,983.23) (37,315,290.22)
2030 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (35,371.72) (37,350,661.93)
2031 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (27,209.01) (37,377,870.95)
2032 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (20,930.01) (37,398,800.96)
2033 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (16,100.01) (37,414,900.97)
2034 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (12,384.62) (37,427,285.59)
2035 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (9,526.63) (37,436,812.22)
2036 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (7,328.18) (37,444,140.40)
2037 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (5,637.06) (37,449,777.46)
2038 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (4,336.20) (37,454,113.66)
2039 6,794,942.86 72,560.67 (6,722,382.19) (6,722,382.19) (3,335.54) (37,457,449.20)
2040 602,150.47 6,794,942.86 72,560.67 (6,722,382.19) (6,120,231.72) (2,335.97) (37,459,785.17)
75
As can be seen in Table 27, above, the NPV of the process is ($37,500,000), making this
process very unprofitable.
Sensitivity Analysis
The spreadsheets described in Appendices B-3 and B-4 were used to analyze the impact
of fluctuations in the prices of utilities and feedstocks on the overall economics of the
process. Prices for these items were manually changed in the COM calculations in
Appendix B-3; the change in NPV using the spreadsheet in Appendix B-4 was noted in
order to determine how sensitive the process is to changes in input costs.
The price of the algae feedstock was first increased; for comparison’s sake, the price of
the algae was increased to $20 per ton, an increase by a factor of 20. This resulted in the
NPV decreasing to ($37,600,000), a decrease of 0.2%. Because of the small magnitude of
this change, the process economics are not considered to be sensitive to changes in
feedstock cost.
The price of the utilities (process and cooling water, electricity) was then analyzed. As a
basis of analysis, the price of utilities was increased by a factor of 2 to $600,000 per year.
This resulted in the NPV decreasing to ($38,000,000), a decrease of 1%. Because of the
small magnitude of this change, the process economics are not considered to be sensitive
to changes in utility costs. Analysis of the impacts of catalyst cost changes are discussed
later in this section.
Road to Profitability, Market Changes
In order for a project to be considered feasible, the NPV must be greater than or equal to
zero (18). An analysis was performed to see what the selling price of natural gas would
76
have to be in order to reach a NPV of zero, assuming that ratio of the prices of natural gas
and hydrogen remains constant and that no operating costs change. To reach a NPV of
zero, the price of natural gas would have to be $1700 per 1000 scf, an increase over
today’s prices by a factor of 156, an event that will likely never happen in the foreseeable
future. This factor was calculated using the spreadsheet described in Appendix B-4.
Road to Profitability, Catalyst Changes
Looking at the process, there are a few areas where attention should be focused in order
to reduce the high cost associated with production. The biggest opportunity to reduce cost
comes with the catalyst. Because the carbon support structure of the catalyst degrades
over time in the supercritical environment (7), the catalyst will have to be replaced every
year. This catalyst degradation is unavoidable because the reaction must occur in
supercritical conditions. Replacing the catalyst increases the annual operating cost of the
process by $4,500,000, well over half the annual operating budget. If the catalyst could
be reduced in cost to $100,000 per load, the CTCI would decrease to $11,200,000 and the
NPV would increase to ($15,300,000), as calculated using the spreadsheets shown in
Appendix B-4. The $22.2MM savings in NPV is significant, showing that finding an
inexpensive catalyst solution should be a top priority. This could include finding a new,
cheaper catalyst or finding a way to reduce the cost of the Ru/C catalyst.
There are only two metals that are capable of catalyzing the methanation reaction:
ruthenium and rhodium (49). Considering rhodium has a cost of $80,000 per kg (50), it is
not considered a viable option for a large quantity of catalyst. Therefore, an alternative
ruthenium catalyst must be found. Considering that the Ru/C catalyst included in the
process is 5% ruthenium by mass, the total mass of ruthenium in the reactor is 38 kg.
This has a market value of $250,000 (51). Assuming that this amount of ruthenium could
77
be affixed to a non-degradable support structure with negligible cost, the CTCI would
decrease to $11,400,000 and the NPV would increase to ($15,200,000), as calculated
using the spreadsheets shown in Appendix B-4. The $22.3MM savings in NPV is
significant, showing that finding an inexpensive, non-degradable catalyst solution should
be a top priority. One support structure that shows promise is zirconia; zirconia does not
show signs of degradation in supercritical environments (49). This catalyst would not
have to be purchased every year. Therefore, effort should be directed towards developing
a Ru/zirconia catalyst on a commercial scale with minimal cost.
Road to Profitability, Equipment Changes
Another opportunity to reduce costs comes with R-101 and S-101. These vessels, priced
at $2.8MM and $2.2MM, respectively, are more than four times more expensive than the
next most expensive piece of equipment, P-101 A/B. These vessels must operate at
supercritical conditions because the reaction requires the algae slurry to be supercritical.
If the cost of each of these vessels could be decreased to $100,000, the CTCI would
decrease to $10,800,000 and the NPV would increase to ($29,600,000). The $9MM in
savings shows that special attention should be focused on these vessels to find ways to
reduce their wall thicknesses; reducing the amount of material required to make these
vessels could significantly reduce their costs.
If R-101 and S-101 were reduced in cost to $100,000 each and a Ru/zirconia catalyst
were implemented with only a $250,000 initial purchase cost, the NPV would increase to
($7,300,000), an increase of $30.2 MM. This would significantly improve likelihood of
this project becoming economically viable.
78
Conclusions and Recommendations
The design presented in this report is expected to have minimal impact on the Arizona
energy market. With an annual output of 5,865,000 scf of CNG, this process captures
only 0.018% of the state’s commercial natural gas sales. Seeing as the design has a NPV
of ($37,500,000), it is recommended that this design is shelved until technological
improvements are made and economic conditions improve.
Several innovations were included in the design of the process; while the assumptions
relating to these innovations appear reasonable, there are several opportunities for future
work to test the accuracy of the design. The design centers around R-101, the
supercritical gasification and methanation reactor. Until now this technology has only
been tested on a lab scale. It is recommended that a pilot scale reactor be built in order to
confirm the feasibility of this reactor on the scale required for this process. A related
innovation was included in S-101, the supercritical gravitational salt separator. This
technology has also never been tested on an industrial scale. To ensure functionality, the
design team recommends that a pilot scale salt separator be built and tested as well.
Advancements in steel metallurgy should also be tracked to see if a RFGS becomes a
feasible alternative. A final major technological innovation was included in S-401, the
hydrogen separation membrane. The palladium/ceramic membranes included in the
design have only been tested on a lab scale; it is recommended that this technology be
tested on a pilot scale to ensure functionality in the final process.
Other opportunities exist to bring down the cost of the plant. Accounting for a $4.5MM
yearly expenditure, catalyst costs severely depress the NPV. Work should be directed at
creating a low cost Ru/zirconia catalyst that retains the functionality of ruthenium but
79
does not degrade like a carbon support structure. Pursuing this path has the potential to
increase the NPV by $22.3MM. Further costs could be cut by reducing the significant
costs of R-101 and S-101. Both vessels currently have large wall thicknesses due to the
supercritical state their contents are required to be at; future work should be directed at
reengineering the structure, shape and supports of the vessels to reduce their wall
thicknesses. If the vessels could be engineered such that the cost of each was $100,000, it
would increase the NPV by $9MM. If solutions to the high costs of the catalysts and the
high pressure vessels can be found, the NPV of the process would increase to ($7.3MM),
an increase of $32.2MM.
Economically speaking, the financial relationship this plant would have with the
associated algae farm must be more clearly defined. Currently, nutrient salts and carbon
dioxide are recycled to the algae farm in order to reduce the purchase price of the algae
feedstock. This decision should be reevaluated in later phases of engineering to
investigate whether selling the salts on the open market would be more profitable.
Included in this analysis should be the investigation of a brine purifying unit that could
separate the different salts so that a pure product can be sold.
Due to the current market of CNG and the high costs of production associated with
producing CNG from algae, it is the recommendation of this report that the proposed
design not be used at this time. However, if in the future the described technological
advances can be made in and the market cost of natural gas increases, this project can be
reconsidered as the process is both straightforward in design and has a minimal impact on
the environment.
80
Nomenclature
Symbol Description Units
a Material Construction Factor none
A Area length2
b Material Construction Factor none
CAlloc Allocated Costs dollars
CB Base Cost dollars
CDPI Direct Permanent Investment dollars
Cp Specific Heat
CP f.o.b. Purchase Cost dollars
CPL
Cost of Vessel Platforms and
Ladders dollars
CV Cost of Vessel dollars
CTBM Total Bare Module Cost dollars
CTCI Total Capital Investment dollars
CTDC Total Depreciable Capital dollars
Di Inner Diameter of Vessel length
E Fractional Weld Efficiency none
F Molar Flux ondsarea
moles
sec
FL Tube Length Correction Factor none
FM Material Factor none
FP Pressure Factor None
FTBM Total Bare Module Factor none
g Gravitational Constant
h Specific Enthalpy
Standard Enthalpy of Formation H Enthalpy energy
head Head of Water I Plant Cost Index none
k Specific Heat Ratio none
L Height length
m Mass mass
Mass Flow Rate
81
n Moles Mol
Molar Flow Rate
P Pressure
Pc Power Consumption energy (hp)
PB Break Horsepower energy (hp)
Pd Internal Design Gauge Pressure
Po Operating Pressure
Q Energy Flow Rate s Pump Size Factor None
S
Maximum Allowable Vessel
Stress None
SC Flow rate of cooling water Gpm
SP Flow rate of process water Gpm
tp Vessel Wall Thickness Inches
T Temperature oC,
oF, K
Log Mean Temperature Difference oC,
oF, K
Average Temperature Difference oC,
oF, K
U Overall Heat Transfer Coefficient
V Volume length3
Volumetric Flow Rate
Average Fluid Velocity W Weight Lbs
Wp Pump Work Z Height Above Datum Plane Length
Symbol Units
Density
η
Mechanical Efficiency of the
Pump None
ηP Pump Motor Fractional Efficiency None
ηM Pump Fractional Efficiency None
τ Residence Time Time
82
References
1. CNG/LNG." TransEco Energy Corporation Home Page. 26 Apr. 2010.
http://www.transecoenergy.com/pages/About_CNG.htm.
2. Production of biodiesel from macroalgae by supercritical CO2 extraction and
thermochemical liquefaction. Aresta, Michele, Angela Dibenedetto, Maria
Carone, Teresa Colonna, and Carlo Fragale. 2005, Vol 3.3.
3. California Environmental Protection Agengy Air Resources Board. Compressed
Natural Gas Specifications for Motor Vehicles. Rep. 3 Aug. 2005. 26 Apr. 2010.
http://www.arb.ca.gov/fuels/altfuels/080305arbprstn.pdf.
4. "Global Hydrogen Inc. Lowers Price of Hydrogen to $2.47 per Gallon | Hydrogen
Fuel Cars and Vehicles." Hydrogen Fuel Cell Cars H2ICE Vehicles and
Infrastructure. 25 July 2008. 26 Apr. 2010.
http://www.hydrogencarsnow.com/blog2/index.php/hydrogen-fuel-
production/global-hydrogen-inc-lowers-price-of-hydrogen-to-247-per-gallon/.
5. CNG Stations and Prices for the US, Canada and Europe. 26 Apr. 2010.
http://www.cngprices.com/.
6. "What Is Natural Gas?" NaturalGas.org. 26 Apr. 2010.
http://www.naturalgas.org/overview/background.asp.
7. Stucki, Samuel, Frederic Vogel, Christian Ludwig, Anca G. Haiduc, and Martin
Brandenberger. "Catalytic Gasification of Algae in Supercritical Water for
Biofuel Production and Carbon Capture." ENERGY & ENVIRONMENTAL
SCIENCE 2.5 (2009): 535-41.
8. "Critical Temperature and Pressure." Purdue University - Department of
Chemistry. 26 Apr. 2010.
http://www.chem.purdue.edu/gchelp/liquids/critical.html.
9. Effluent Guidelines and Standards. Rep. Vol. 39. Environmental Protection
Agency, 1974. Ser. 91. 26 Apr. 2010.
http://www.epa.gov/guide/petroleum/files/39fr16559.pdf
10. A. A. Peterson, P. Vontobel, F. Vogel and J. W. Tester, J. Supercrit. Fluids, 2008,
43(3), pg. 490–499.
11. "Supercritical Fluids at PNNL." Pacific Northwest National Laboratory. 26 Apr.
2010. http://www.pnl.gov/supercriticalfluid/tech_membrane.stm.
83
12. "Algal Oil Yields – Yield Data for Oil from Algae Strains." Biodiesel from Algae
Oil - Oilgae - Information, News, Links for Algal Fuel, Alga Bio-diesel, Biofuels,
Algae Biofuel, Energy - Oilgae.com. 26 Apr. 2010.
http://www.oilgae.com/algae/oil/yield/yield.html.
13. Costa, Jorge Alberto V., Luciane M. Colla, and Paulo D. Filho. "Spirulina
Platensis Growth in Open Raceway Ponds Using Fresh Water Supplemented with
Carbon, Nitrogen and Metal Ions." July-Aug. 2002. 26 Apr. 2010.
http://www.znaturforsch.com/ac/v58c/s58c0076.pdf.
14. "Media Detail." 26 Apr. 2010.
http://www.sbs.utexas.edu/utex/mediaDetail.aspx?mediaID=150.
15. http://www.coleparmer.com/catalog/product_view.asp?sku=8820818&pfx=
16. Stucki, Samuel, Frédéric Vogel, Christian Ludwig, and Anca G. Haiduc.
"Catalytic Gasification of Algae in Supercritical Water for Biofuel Production and
Carbon Capture: Electronic Supplementary Information." 26 Apr. 2010.
http://www.rsc.org/suppdata/EE/b8/b819874h/b819874h.pdf.
17. Hübner, Dirk, and Harald Ortwig. "Linear Modeling, Simulation and
Experimental Verification of a Pressure Regulator for CNG Injection Systems."
26 Apr. 2010. http://www.iiisci.org/journal/CV$/sci/pdfs/I135BV.pdf.
18. Product and Process Design Principles Synthesis, Analysis and Design. John
Wiley & Sons Inc, 2008.
19. Bird, R. Byron, Warren E. Stewart, and Edwin N. Lightfoot. Transport
Phenomena. New York: J. Wiley, 2007.
20. McCabe, Warren L., Julian C. Smith, and Peter Harriott. Unit Operations of
Chemical Engineering. Boston: McGraw-Hill, 2005.
21. Mukherjee, Rajiv. "Effectively Design Shell-and-tube Heat Exchangers |
Chemical Engineering Progress | Find Articles at BNET." Find Articles at BNET |
News Articles, Magazine Back Issues & Reference Articles on All Topics. Feb.
1998. 26 Apr. 2010.
http://findarticles.com/p/articles/mi_qa5350/is_199802/ai_n21418317/.
22. "WATER HEATING IN AN INSULATED TANK." Chart. 26 Apr. 2010.
http://www.nphheaters.com/quote/industrial_process_heaters/wattage_insulated.p
df.
84
23. Grainger Industrial Supply. 30 Apr. 2010. http://www.Grainger.com.
24. Waldner, Maurice Henri. "Catalytic Hydrothermal Gasification of Biomass for the
Production of Synthetic Natural Gas." 29 Apr. 2010. http://e-
collection.ethbib.ethz.ch/eserv/eth:29520/eth-29520-02.pdf.
25. "US VACUUM PUMPS: 2009/2010 VACUUM PRODUCTS CATALOG." U.S.
VACUUM. 26 Apr. 2010.
http://www.usvacuumpumps.com/2007USVPCatalog.pdf.
26. Status Review on Membrane Systems for Hydrogen Separation. Rep. S.C.A.
Kluiters, 2001. 26 Apr. 2010.
http://www.ecn.nl/docs/library/report/2004/c04102.pdf.
27. "Palladium Membrane Purification." Johnson Matthey Gas Purification
Technology - Gas Purifiers, Palladium Hydrogen Purifiers, Catalytic Nitrogen
Purifiers, Getter Argon Purifiers. 26 Apr. 2010.
http://pureguard.net/cm/Library/Palladium_Membrane_Purification.html.
28. "Centrifugal Pump, 2 HP - Straight Center Discharge Pumps." Grainger
Industrial Supply. 11 Apr. 2010.
http://www.grainger.com/Grainger/items/4ZA35?Pid=search.
29. "Pump, Centrifugal, 1/3hp - Self-Priming Pumps." Grainger Industrial Supply. 11
Apr. 2010. http://www.grainger.com/Grainger/items/4UA63?Pid=search.
30. "2009/2010 Vacuum Products Catalog." US Vacuum Pumps. 11 Apr. 2010.
http://www.usvacuumpumps.com/2007USVPCatalog.pdf.
31. “Carbon Monoxide MSDS.” Five Star Gas. 16 Feb. 2010.
http://www.fivestargas.com/pdfs/msds_CARBON_MONOXIDE.pdf .
32. “Carbon Dioxide MSDS.” Five Star Gas. 16 Feb. 2010.
http://www.fivestargas.com/pdfs/msds_CARBON_DIOXIDE.pdf .
33. “Propane MSDS.” Five Star Gas. 16 Feb. 2010.
http://www.fivestargas.com/pdfs/msds_PROPANE.pdf .
34. “Hydrogen MSDS.” Five Star Gas. 16 Feb. 2010.
http://www.fivestargas.com/pdfs/msds_HYDROGEN.pdf .
35. “Methane MSDS.” Five Star Gas. 16 Feb. 2010.
http://www.fivestargas.com/pdfs/msds_METHANE.pdf .
85
36. “Ethane MSDS.” Five Star Gas. 16 Feb. 2010.
http://www.fivestargas.com/pdfs/msds_ETHANE.pdf .
37. “Hydrogen Sulfide MSDS.” Valley National Gases LLC. 16 Feb. 2010.
http://www.vngas.com/pdf/g94.pdf.
38. Vonshak, A. (ed.). Spirulina platensis (Arthrospira): Physiology, Cell-biology and
Biotechnology. London: Taylor & Francis, 1997.
39. “Materials Safety Data Sheet – Water MSDS.” Sciencelab.com, 06 Mar. 2010.
http://www.sciencelab.com/msds.php?msdsId=9927321.
40. “Air.” Air Liquide, 26 Feb. 2010.
http://www.generalmonitors.com/downloads/msds/10003.pdf.
41. “Engineered Coatings.” Stork. 23 Apr. 2010.
http://www.storkcellramic.com/Stork/8924/Our_Products-
Engineered_Coatings.html.
42. "Environmental Impact CO2 Emissions". Eco Smart, 02 Mar. 2010.
http://www.ecosmartconcrete.com/enviro_co2.cfm.
43. "Greenhouse Gas Emissions". Environmental Protection Agency, 29 Feb. 2010.
http://www.epa.gov/climatechange/emissions/.
44. "Controlling Fossil Power Plant CO2 Emissions". Alstom. 28 Sep. 2008. 6 Apr
2010.
http://www.netl.doe.gov/publications/proceedings/03/carbonseq/PDFs/139.pdf.
45. "Natural Gas and Petroleum." 16 Apr. 2010.
http://tonto.eia.doe.gov/dnav/ng/hist/n3020az2m.ht.
46. "Hydrogen Market, Hydrogen R&D and Commercial Implication in The U.S. and
E.U.." MRG Multimedia Research Group Inc. 26 Apr. 2010.
http://www.mrgco.com/TOC_HydrogenMarket_May05.html.
47. "Arizona Natural Gas Summary." 16 Apr. 2010.
http://tonto.eia.doe.gov/dnav/ng/ng_sum_lsum_dcu_SAZ_m.htm.
48. "Hydrogen Filling Station in Irvine, California." Hydrogen Fuel Cell Cars H2ICE
Vehicles and Infrastructure. 16 Apr. 2010.
http://www.hydrogencarsnow.com/hydrogen-filling-station-irvine-ca.htm.
86
49. Ind. Eng. Chem. Res. 1993,32, 1542-1548 Chemical Processing in High-pressure
Aqueous Environments. 2. Development of Catalysts for Gasification Douglas C.
Elliott,' L. John Sealock, Jr., and Eddie G. Baker
50. http://www.kitco.com/charts/rhodium.html
51. http://www.ebullionguide.com/price-chart-ruthenium-last-30-days.aspx
52. "NIST Chemistry WebBook." Welcome to the NIST WebBook. 30 Apr. 2010.
http://webbook.nist.gov/chemistry/.
53. "IB Chemistry Higher Level Revision Notes: Energetics." IB Chemistry Revision
Notes and Syllabus. 30 Apr. 2010. http://ibchem.com/IB/ibnotes/brief/ene-hl.htm.
54. Felder, Richard M., and Ronald W. Rousseau. Elementary Principles of Chemical
Processes. Hoboken, NJ: Wiley, 2005.
55. "Enthalpy of Moist and Humid Air." The Engineering ToolBox. 29 Apr. 2010.
http://www.engineeringtoolbox.com/enthalpy-moist-air-d_683.html.
56. "Gases - Specific Heat Capacities and Individual Gas Constants." The
Engineering ToolBox. 29 Apr. 2010.
http://www.engineeringtoolbox.com/spesific-heat-capacity-gases-d_159.html.
57. "Solubility of Gases in Water." The Engineering ToolBox. 29 Apr. 2010.
http://www.engineeringtoolbox.com/gases-solubility-water-d_1148.html.
58. "Carbon Dioxide Absorption in Water." Wolfram Demonstrations Project.
http://demonstrations.wolfram.com/CarbonDioxideAbsorptionInWater/.
59. "Solvay Sodium Bicarbonate." Solvay Sodium Bicarbonate. 30 Apr. 2010.
http://www.solvaybicar.com/product/properties/0,0,-_EN-1000102,00.html.
60. "The Heat Capacity of Ammonium Nitrate from 15 to 315°K. - Journal of the
American Chemical Society (ACS Publications)." ACS Publications. 30 Apr.
2010. http://pubs.acs.org/doi/abs/10.1021/ja01613a035.
61. Criscuoli, A., A. Basile, E. Drioli, and O. Loiacono. "An Economic Feasibility
Study for Water Gas Shift Membrane Reactor." Journal of Membrane Science 1st
ser. 181.1 (2001): 21-27.
62. Chemical Engineering 117.3 (2010): 64.
87
Appendices
Appendix A: Final Calculations
A-1: E-101 Preheater Calculations
The minimum temperature approach was set to be 28 oC, the recommended minimum
approach for temperatures up to 150 oC (18).
CCCTTT ooo
approach 37228400min_24
Note: Assume almost all of the energy transfer is between the water in the streams
(because it is approximately 97.8% H2O by mass) and that the stream is entirely water
Note: Literature values used for the specific enthalpies, h (49). Q is the energy flow rate
and 𝑚 is the mass flow rate of the stream.
hr
Btu
hr
kJQ
kg
kJ
kg
kJ
hr
kgQ
hhmhmQ
32.788291816.8310055
23.1743.17604.5239
)( 14
kg
kJh
hkg
kJ
hr
kg
hr
kg
hhmhmQ
43.511
50.20974.523916.8310055
)(
3
3
32
2 MPa
CT o
975.30
4002
MPa
CT o
0.31
351 MPa
CT o
995.30
372?4 4 1
MPa
CT o
970.30
117?3 3
At P = 30.975 MPa, T3 = 117 oC (52)
88
E-101 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
200
46.90
956.242
6.701752ln
)956.242()6.701752(
ln
Note: U was determined based on a conservative estimate for water-water systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
2
2
71.435
46.90200
32.7882918
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a floating head counter current shell and tube heat exchanger
worked best for this application (18).
71.16296$
2)ln(09005.0)ln(8709.0667.11 AA
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BLMPP CFFFC
Where FP is the pressure factor, FM is the material factor, FL is the tube length correction
factor.
For carbon steel: 1100
0100
0
AAaF
b
M
Note: A conservative estimate of 8 ft was assumed for the tube length.
25.1LF
2.5
49.4481696.14325.101
696.1431000
1000017.0
100018.09803.0
2
P
P
F
psigpsikPa
psikPaP
PPF
61.105929$ BCMPP CFFFC
Where:
P = shell side pressure in psig
89
A-2: E-102 Cooler Calculations
Note: T1 determined from a conservative estimate for cooling water and T4 determined
from an environmental limit (18).
Component m (kg/hr) n (mol/hr) 2h
(kJ/mol) 3h
(kJ/mol)
)ˆˆ( 32 hhmQ
(kJ/hr)
CO2 81.702 1856.44 26.040 22.873 5879.35
CO 0.211 7.53 15.221 12.904 17.45
CH4 25.966 1618.63 18.26 15.221 4919.02
C2H6 1.936 64.39 25.697 20.925 307.27
C3H8 1.001 22.70 35.793 20.951 336.91
H2 0.434 215.29 10.747 8.448 494.95
H2O 4958.333 309896 9.231 3.249 1853797.87
1865752.82
Note: The energy balance above verifies previous assumption that the majority of the
heat transfer occurs in the water as it accounts for 99.3% of the energy.
The amount of cooling water required was determined through an energy balance where
the enthalpies were determined from literature values (49).
hr
m
kg
m
hr
kgv
hr
kg
g
kg
mol
g
hr
molm
hr
moln
mol
kJn
hr
kJ
hhnQ
OH
OH
OH
OH
OH
33
14
59.230010116.09.23321
9.233211000
1639.1457619
39.1457619
)420.2700.3(82.1865752
)ˆˆ(
2
2
2
2
2
MPa
CT o
11.0
321
MPa
CT o
3.0
1222
MPa
CT o
295.0
433
MPa
CT o
105.0
494 1
2
3
4
90
E-102 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
200
7.56
90110
120252ln
)90110()120252(
ln
Note: U was determined based on a conservative estimate for water-water systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
hr
Btu
J
Btu
kJ
J
hr
kgQ 13.1769853
10486.9100082.1865752
4
2
2
07.156
7.56200
13.1769853
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
94.2846$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures less than 600 psig, FP = 1
94.2846$ BMPP CFFC
91
A-3: F-101 Superheater Calculations
The temperature of the algae slurry exiting the superheater must be 400 °C. Note:
Assume almost all of the energy transfer is between the water in the streams (because it is
approximately 97.8% H2O by mass) and that the stream is entirely water. The amount of
heat Q required to be absorbed by the slurry is given by
TCmQ P.
)3600
1)(372400)(5000)(13.7(
s
hrCC
hr
kg
kgK
kJQ
kWQ 2.277
Where the average heat capacity of water at this pressure and range of temperatures is
7.13 (24)
This heat is provided by the combustion of natural gas in the furnace. The preheated air
and methane mix and come to an equilibrium temperature given by the following energy
balance.
)131)(05.18)(34.2()465)(5.629)(84.1)(013.0()5.629)(465)(01.1( CThr
kg
kgK
kJTC
hr
kg
kgK
kJ
kgair
kgwater
hr
kgTC
kgK
kJ
CT 445
The heat released by the combustion of methane is 55687.5 kJ/kg combusted (53).
Therefore, the total heat released is
HmQ
)3600
1)(5.55687)(05.18(
s
hr
kg
kJ
hr
kgQ
s
kJQ 2.279
The heat capacity of the combusted material is assumed to have the same heat capacity as
air. It has a moisture content of 0.149 kg water/kg air. The temperature of the recently
combusted air is shown to be
)445)(5.647)(84.1)(149.0()5.647)(445)(01.1(375.1005159 CThr
kg
kgK
kJ
kgair
kgwater
hr
kgCT
kgK
kJ
hr
kJ
CT 1702
Heat is then transferred to the algae mix. An approach temperature of 93 °C is used (18).
)4931702)(5.647)(84.1)(149.0()5.647)(4931702)(01.1( CChr
kg
kgK
kJ
kgair
kgwater
hr
kgCC
kgK
kJQ
kWQ 2.277
F-101 Cost Calculations
Note: F-101 was priced as a fired heater (18)
))ln(766.032325.0( Q
B eC
92
Where Q is in units of hr
Btu
BMPP
B
CFFC
C
hr
Btu
s
JkWQ
10.53063$
9466272772002.277
FM = 1 because of carbon steel
FP = 1 because P < 500 psig
CP = $53063.10
93
A-4: P-101 A/B Algae Pump Calculations
2
2VgZ
Phead
Note: Assume the difference between the heights of the suction and discharge
connections is negligible (i.e. 0Z )
Assume: m constant (same into pump as out of pump)
AVm
Therefore: A
mV
Note: Assume A and are the same at the inlet and outlet of the pump. Therefore, V
constant
kg
J
m
kg
PaPaPPhead 1.31626
977
)10013.1()101.3(
3
57
12
Note: was determined by assuming it to be water at 25oC and 101.3kPa (49)
kg
Jkg
J
headWp 1.42168
75.0
1.31626
where:
Wp = pump work
mechanical efficiency of the pump
A conservative estimate of 0.75 was made for (18)
hpWs
J
s
hr
hr
kg
kg
JmWP pB 3.826137161371
3600
14.52391.42168
where: PB = break horsepower
P-101 A/B Cost Calculations
ftftm
ft
s
m
kg
J
g
head32001.1058528.3
8.9
1.31626
2
Where: g is the gravitational constant.
where:
head = total head
V = average fluid velocity
Z = height above datum plane
P = pressure
= density of fluid
A = area of pipe
94
min5000
min85.23
17.264977
min60
14.5293
3
3
galgal
gal
m
m
kg
hr
hr
kg
mV
Where: V is the volumetric flow rate
Note: P-101A/B was determined to be a reciprocating pump due the large head (10585 ft)
it is required to generate (18)
Note: Cost determined from empirical correlations for reciprocating pumps (18)
20.29948$2)ln(06718.0)ln(26986.08103.7(
BB PP
B eC
CP = FMCB
For carbon steel, FM = 1.50
CP = $44922.40
Motor Cost Calculations:
mP
C
g
headV
P
33000
Where
g
head, is in feet.
9.0)ln(00182.0)ln(0319.08.0
32.0)ln(01199.0)ln(24015.0316.0
2
2
BBm
P
PP
VV
Where: ηP is the pump fractional efficiency and ηM is the pump motor fractional
efficiency
40.14328$)40.14238)($0.1(
40.14328$
00.221)9.0)(32.0(33000
32.81.10585min
85.23
432 )ln(0035549.0)ln(02828.0)ln(053255.0)ln(13141.08259.5
BTP
PPPP
B
C
CFC
eC
hpgal
lbft
gal
P
CCCC
Note: The motor was chosen to be a drip-proof enclosure, therefore, FT = 1 (18).
Thus,
The total cost for 1 pump and motor: $59250.80
Where:
PC = motor power consumption
= 8.32 lb/gal
𝑉 is in units of gal/min
95
The total cost for 2 pumps and motors: $118501.60
A-5: P-102A/B Cooling Water Pump Calculations
hpWs
J
s
hr
hr
kg
kg
JmWP
kg
Jkg
J
headW
kg
J
m
kg
PaPaPPH
PB
P
073.09.769.763600
9.233219.11
9.1175.0
9.8
9.8
977
)10013.1()101.1(
3
55
12
P-102A/B Cost Calculations
ftftm
ft
s
m
kg
J
g
head320098.328.3
8.9
9.11
2
min5000
min1.105
17.264977
min60
19.23321
3
3
galgal
gal
m
m
kg
hr
hr
kg
mV
Note: P-102A/B was determined to be a centrifugal pump due its small head (3.98 ft) and
flow rate
min1.105
gal (18)
Note: Cost determined from empirical correlations for a centrifugal pump (18)
5.0
g
headVs
Where: s is the pump sizing factor
5.05.075.20998.3
min1.105 ftgpmft
gals
Note: The size factor for this pump was too small to use empirical relationships to cost
the pump. Therefore, a pump was located that could meet the technical requirements of
the process was found.
96
A 2 hp straight center discharge pump with an optimum flow rate of 101 min
gal was
located with a cost of $900.00, including an assumed shipping and handling rate (23).
A-6: R-101 Gasification and Methanation Reactor Calculations
Note: The volume ratios of the gases produced in the reactor were determined from a
literature source (7).
Note: The gases were assumed to behave ideally
Component Vol % Mol % MW (g/mol) Mass
(100 mol sample) Mass %
CH4 42.7 42.7 16.042 684.993 23.34
C2H6 1.7 1.7 30.068 51.116 1.74
C3H8 0.6 0.6 44.094 26.456 0.90
CO2 49.0 49.0 44.010 2156.490 73.44
CO 0.2 0.2 28.010 5.602 0.19
H2 5.8 5.8 2.016 11.693 0.39
TOTAL: 100 100 2936.350 100
Volume of Reactor:
Note: The required residence time for the reactor was determined to be one hour (7).
Note: The density of the stream was assumed to have the same density as water at the
same conditions (because the stream is 97.8% water by mass) (49).
Q
V QV
min217.001.13
61.389
583.5069 33
3
m
hr
m
m
kghr
kg
mQ
367.13)217.0min)(63( mV
Mass of catalyst:
Note: The ratio of the mass of catalyst in the reactor to the mass of dry matter was known
to be eight from a literature source (7).
OHCatalystDMreactor VVVV2
Where mcat is the mass of the Ru/C catalyst, mDM is the mass of the algae, and mH2O is the
mass of water in the reactor.
97
OH
OH
catalyst
DM
DM
DM
OH
OH
catalyst
catalyst
DM
DMmmmmmm
m
2
2
2
28
67.13 3
Note: totalm is the total mass of DM and H2O in the reactor
Note: It was assumed that nonadecaneDM at 30.85MPa and 400oC (49)
DMcat mm 8
totaltotaltotal
total
DMDM mm
kg
kgm
m
mm 022.0
583.5069
25.111
totalOH mm 978.02
382.518
m
kgDM (52)
3260
m
kgcatalyst (Note: from the paper that Kyle sent)
361.389
2 m
kgOH (Note: at 30.85MPa and 400
oC (18))
totaltotaltotaltotal m
m
kg
m
m
kg
m
m
kg
mm 00323.0
61.389
978.0
260
022.810
82.518
022.067.13
333
3
kgmtotal 2.4232
Therefore,
kgmmm totalDMcat 87.744)022.0(88
98
T Across the Reactor
The temperature change across the reactor was determined with the aid of the
thermodynamic cycle illustrated below. A basis of one mole was used. Only one of the
methane producing reactions, the conversion of formaldehyde to methane and carbon
dioxide, was evaluated (7). The gases were assumed to behave ideally, and therefore
experienced no enthalpy change with a change in pressure.
Note: The enthalpy changes the formaldehyde, methane, and carbon dioxide experienced
during the temperature changes were determined using the specific heats of the
compounds (54).
kJH
dTTmolH
dTCnH
deformaldehy
C
C
deformaldehy
C
C
pdeformaldehydeformaldehy
o
o
o
o
26.16
)10268.41028.34(1
25
400
53
25
400
kJH
dTTTmolH
dTCnH
methane
C
C
methane
C
C
pmethanemethane
o
o
o
o
65.8
)103361.010469.51031.34(5.0
400
25
2853
400
25
CH2O(g) (400 oC, 30.85 MPa) 0.5 CH4(g) (400
oC, 30.85 MPa) 0.5 CO2(g)
0.5 CH4(g) (400 oC, 1 atm) 0.5 CO2(g)
0.5 CH4(g) (25 oC, 1 atm) 0.5CO2(g)
CH2O(g) (400 oC, 1 atm)
CH2O(g) (25 oC, 1 atm)
C(s,graphite) +H2(g)+0.5O2(g) C(s,graphite) +H2(g)+0.5O2(g)
0H
0H
0H 0H
kJH 26.16
kJH 9.115 kJH 44.37 kJH 76.196
kJH 65.8 kJH 15.8
99
kJH
dTTTmolH
dTCnH
dioxidecarbon
C
C
dioxidecarbon
C
C
pdioxidecarbondioxidecarbon
o
o
o
o
15.8
)10887.210233.41011.36(5.0
400
25
2853
400
25
Note: The enthalpy changes the formaldehyde, methane, and carbon dioxide experienced
during the formation of the compounds were determined using the standard enthalpy of
formation of the compounds (49).
mol
kJH
mol
kJmolH
hnH
deformaldehy
deformaldehy
o
fdeformaldehydeformaldehy deformaldehy
9.115
9.1151
mol
kJH
mol
kJmolH
hnH
methane
methane
o
fmethanemethane methane
44.37
88.775.0
mol
kJH
mol
kJmolH
hnH
dioxidecarbon
dioxidecarbon
o
fdioxidecarbondioxidecarbon methane
76.196
52.3935.0
100
Summing all of the enthalpy changes listed above yielded the net enthalpy change in the
reaction of one mole of formaldehyde to form one half of a mole of methane and one half
of a mole of carbon dioxide.
kJH
kJkJkJkJkJkJH
rxn
rxn
76.117
15.865.876.19644.379.11526.16
Therefore, the production one mole of methane would produce twice the enthalpy value
given above, and multiplying by the mass flow of methane provided the total energy flow
rate generated by the reaction.
442 37.3670
52.23276.117
CHkg
kJ
CHmol
kJ
OCHmol
kJH rxn
hr
kJ
kg
kJ
hr
kgQ 5.9531937.367097.25
This change in enthalpy could then be converted into a temperature change in the reactor
by assuming the water in the reactor absorbed all of the energy.
mol
kJh
hr
kghr
kJ
h
m
Qh
water
water
water
water
48.08467.26
33.4958
133115
mol
kJh
mol
kJ
mol
kJh
hhh
final
final
MPaCofinal
water
water
waterwaterwater
375.38
48.0895.37
85.30,400
Using a literature source, it was determined that the water would rise in temperature by
1.2 oC, exiting the reactor at a temperature of 401.2
oC (49). This small change in
101
temperature was assumed to be negligible as energy losses from the reactor to the
surroundings would likely compensate for the increase in energy due to the reaction.
Other methane and non-methane producing reactions occur in the reactor that are
exothermic, however it was assumed that they do not produce enough heat to drastically
influence the temperature of the stream exiting the reactor.
P Across the Reactor
The pressure of the stream would drop due to friction losses as it passed through the
catalyst in the reactor. However the pressure would increase due to the formation of the
gas molecules. Therefore, the pressure change across the reactor was assumed to be
negligible. In addition, the reaction rates are not affected greatly by small changes in
pressure (7).
Reactor Cost Calculations
Note: Reactor height, L, set to be 3m = 118.08 in
inmD
mD
m
hD
hrV
i
i
ii
86.9441.2
)3(2
67.13
2
2
3
2
2
Note: Empirical correlations used to determine the reactor wall thickness, tp (18).
d
idp
PSE
DPt
2.12
E =1 for carbon steel thicker than 1.25 in (18)
S = 15000 at T = 400oC (18)
Pd = 1.1Po (for Po > 1000 psig)
int
P
psigpsikPa
psikPaP
p
d
o
16.24
67.4927
7.4479696.143.101
696.1430980
where:
Di = inner diameter of the vessel (in)
tp = wall thinkness to withstand the internal pressure (in)
Pd = internal design gauge pressure (psig)
S = maximum allowable stress of the shell material at the
design temperature (psi)
E = fractional weld efficiency
where:
Po = operating pressure (psig)
102
Note: Empirical correlations used to determine the weight of the reactor
lbsin
lbinininininW
tDhtDW pipi
497640284.0)16.24))(86.94(8.008.118)(16.2486.94(
)8.0)((
3
Where 3
284.0in
lb for carbon steel (18)
PLvMP CCFC
Note: The reactor was designed as a vertical vessel
28.8399$)()(8.361
00.634124$
70684.07396.0
))ln(02297.0)ln(18255.00132.7( 2
LDC
eC
iPL
WW
v
For carbon steel, therefore FM = 1
CP = $642523.28
Where: Di and L are in feet
103
A-7: S-101 Salt Separator Calculations
Note: the molecular formula of algae is approximated to be C1.0H1.7O0.48N0.19S0.005 (7)
Note: All nitrogen and sulfur are removed from the algae.
Element Molecular Weight
Mass in 1 mole algae
Percent of total mass
C 12 12 49.6
H 1 1.71 7.1
O 16 7.68 31.7
N 14 2.66 10.9
S 32 0.16 0.5
11 % of the 125 kg algae/hr is removed. This corresponds to 13.75 kg salts precipitated
per hour.
hr
m
m
kghr
kg
mQ
QV
Q
V
3
3
29.13
20.394
4.5239
Therefore,
33
29.1329.13)1( mhr
mhrV
Fluid velocity 222 45.4)19.1( mmrA
s
m
m
s
hr
hr
m
A
QU 0008.0
45.4
)3600
1)(29.13(
3
3
S-101 Cost Calculations
Note: Separator height set to 3 m = 118.08 in
inmD
mD
m
LD
LrV
i
i
ii
48.9338.2
)3(2
29.13
2
2
3
2
2
d
idp
PSE
DPt
2.12
104
E =1 for carbon steel thicker than 1.25 in (18)
S = 15000 at T = 400oC (18)
Pd = 1.1Po (for Po > 1000 psig)
04.4928
04.4480696.143.101
696.1430990
d
o
P
psigpsikPa
psikPaP
int p 13.19
lbstDLtDW pipi 370690)8.0)((
Where 3
284.0in
lb for carbon steel
PLvMP CCFC
Note: S-101 was designed as a vertical vessel
63.8312$)()(8.361
504374$
70684.07396.0
))ln(02297.0)ln(18255.00132.7( 2
LDC
eC
iPL
WW
v
For carbon steel FM = 1
CP = $512686.63
105
A-8: V-101 Calculations
Note: Assume adiabatic expansion
Note: Assume that the expanding (cooling) gas does not affect the temperature of the
system much (because it is only about 2% gas by mass)
Note: Assume that the enthalpy of the system comes from the water only
kg
kJ
kg
kJ
hh OfHOiH
18.51318.513
22
Therefore, Tf = 122oC
Ti=117oC
Pi=36.97MPa
Tf = ?
Pf=0.3MPa
Q=0
@ P = 0.3 MPa, T = 122oC (52)
106
A-9: D-201 Knockout Drum Calculations
Note: A volume of 13.19 m3 was assumed (the same volume as S-101) in order to
achieve proper stream separation
D-201 Cost Calculations
Note: Separator height set to 3 m = 118.08 in
inmD
mD
m
LD
LrV
i
i
ii
48.9338.2
)3(2
29.13
2
2
3
2
2
Note: int p 375.0
for low pressure vessels with diameters between 6 and 8 ft (18).
lbstDLtDW pipi 31.6056)8.0)((
Where 3
284.0in
lb for carbon steel
PLvMP CCFC
Note: S-101 was designed as a vertical vessel
63.8312$)()(8.361
60.31105$
70684.07396.0
))ln(02297.0)ln(18255.00132.7( 2
LDC
eC
iPL
WW
v
For carbon steel FM = 1
CP = $39418.23
107
A-10: E-201 Air Preheater Calculations
Air quantity, based on 18.05 kg of natural gas combusted in furnace and double the
required oxygen
kgairkmolair
kg
kmolO
kmolair
kmolNG
kmolO
kg
kmolkgNGQ 5.629)
29)(
21.0)(
4)(
16)(05.18(
2
2
Note: Incoming air was assumed to be saturated and have a temperature of 16 °C and a
pressure of 101.3 kPa. The moisture content of air is 0.013 kg water per kg of air (20).
Note: The heat capacity of water in air is taken to be 1.84 (55)
Note: The approach is set at 28 °C (18)
Air:
)16465)(5.629)(84.1)(013.0()5.629)(16465)(01.1( CChr
kg
kgK
kJ
kgair
kgwater
hr
kgCC
kgK
kJQ
kWQ 1.80
Flue gas:
)493)(55.647)(84.1)(149.0()55.647)(493)(01.1(1.80 TChr
kg
kgK
kJ
kgair
kgwater
hr
kgTC
kgK
kJkWQ
CT 142
E-201 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
10
0.117
61288
869919ln
)61288()869919(
ln
Note: U was determined based on a conservative estimate for water-air systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
MPa
CT o
13.0
4931
MPa
CT o
14.0
162
MPa
CT o
135.0
4653
MPa
CT o
125.0
1424 1
2
3
4
108
2
2
8.233
0.11710
273538
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a floating head counter current shell and tube heat exchanger
worked best for this application (18).
90.14702$
2)ln(09005.0)ln(8709.0667.11 AA
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BLMPP CFFFC
Where FP is the pressure factor, FM is the material factor, FL is the tube length correction
factor.
For carbon steel: 1100
0100
0
AAaF
b
M
Note: A conservative estimate of 8 ft was assumed for the tube length.
25.1LF
FP = 1 for low pressure shell and tube heat exchangers
60.18378$ BCMPP CFFFC
109
A-11: E-202 Methane Preheater Calculations
Note: The approach for the exchanger was set at 11 °C (18)
Note: The heat capacity of natural gas is 2.34 kJ/kgK (56)
Methane:
)24131)(05.18)(34.2( CChr
kg
kgK
kJQ
kWQ 24.1
Flue gas:
)142)(55.647)(84.1)(149.0()142)(55.647)(01.1(24.1 TChr
kg
kgK
kJ
kgair
kgwaterTC
hr
kg
kgK
kJkWQ
CT 136
E-202 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
10
7.78
75277
268288ln
)75277()268288(
ln
Note: U was determined based on a conservative estimate for water-air systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
2
2
4.5
7.7810
6.4234
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
MPa
CT o
125.0
1421
MPa
CT o
14.0
242
MPa
CT o
135.0
1313
MPa
CT o
12.0
1364 1
2
3
4
110
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
08.1662$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures less than 600 psig, FP = 1
08.1662$PC
111
A-12: P-201A/B Cooling Water Pump Calculations
hps
J
s
hr
hr
kg
kg
JmWP
kg
Jkg
J
headW
kg
J
m
kg
PaPaPPH
PB
P
94.1176.89033600
04.12447052.257
52.25775.0
14.193
14.193
977
)10013.1()109.2(
3
55
12
P-201A/B Cost Calculations
ftftm
ft
s
m
kg
J
g
head320064.6428.3
8.9
14.193
2
min5000
min9.560
17.264977
min60
104.124470
3
3
galgal
gal
m
m
kg
hr
hr
kg
mV
Note: P-102A/B was determined to be a centrifugal pump due its small head (64.64 ft)
and flow rate
min9.560
gal (18)
Note: Cost determined from empirical correlations for a centrifugal pump (18)
5.0
g
headVs
Where: s is the pump sizing factor
5.05.058.450964.64
min9.560 ftgpmft
gals
BMTP
ss
B
CFFC
eC
93.4133$2)ln(0519.0)ln(6019.07171.9
For FT, it was determined a 1 stage, 3600 shaft rpm, horizontal split case (HSC), 50-900
gpm, 75 max motor hp best fits the application, leading to FT = 1. For FM cast iron was
assumed.
112
FT = 1
FM = 1
Therefore,
CP = $4133.93
Motor Cost Calculations:
mP
C
g
headV
P
33000
87.0)ln(00182.0)ln(0319.08.0
72.0)ln(01199.0)ln(24015.0316.0
2
2
BBm
P
PP
VV
50.1021$)50.1021)($0.1(
50.1021$
6.14)72.0)(54.0(33000
32.898.3min
9.560
432 )ln(0035549.0)ln(02828.0)ln(053255.0)ln(13141.08259.5
BTP
PPPP
B
C
CFC
eC
hpgal
lbft
gal
P
CCCC
Note: The motor was chosen to be a drip-proof enclosure, therefore, FT = 1 (18).
The total cost for 1 pump and motor: $5155.43
The total cost for 2 pumps and motors: $10310.86
113
A-13: P-202A/B Air Blower Calculations
min4.312
min85.8
101325
)289(314.8min
78.361
min78.361
29min10490
min10490
min49.10
min605.629
33
3
ftm
Pa
KKmol
Pammol
P
RTnV
mol
g
molgn
gkghr
hr
kgm
Note: Assume ideal gas
kPakPakPaP 675.38325.101140
Note: A blower was required to gain the necessary pressure increase (18)
11
00436.01k
k
I
O
B
IB
p
ppV
k
kP
Note: Selected a centrifugal blower because they are more efficient at a lower V
Therefore B = 0.7 (18)
Po = 140 kPa = 20.3 psi
PI = 101.325 kPa = 14.696 psi
4.1
029.21
389.29
Kmol
JKmol
J
C
CK
v
P
Note: Literature values used for CP and vC (49)
BMP
P
B
BC
B
CFC
eC
hphpP
P
hpP
C
73.7426$
9.1275.0
68.9
68.9
))ln(79.08929.6(
Note: Aluminum blades used, therefore FM = 0.6
CP = 4457.24
Thus,
The total cost for 1 blower: $4457.24
where:
K = specific heat ratio
PI = inlet pressure
Po = outlet pressure
V = inlet volumetric flow rate
B = mechanical efficiency
114
The total cost for 2 blowers: $8914.48
A-14: S-201 CO2 Scrubber Calculations
Note: Inert gasses must total no more than 4.5% of the final CNG product.
Note: All gasses except carbon dioxide in methane mix are assumed to have negligible
solubility in water (57)
Note: Due to the fact that the water stream has a mass flow rate three orders of magnitude
higher than the gas stream, the scrubber was assumed to operate at a temperature of 25
°C.
Carbon dioxide must be removed such that the final CNG product is no more than 4.5%
inert gasses. The amount of CO2 there dictates how much of the gas must be removed in
S-201.
Component Stream 10 (kg/hr) Stream 11 (kg/hr)
Methane 25.9 25.9
Ethane 1.9 1.9
Propane 1 1
Water 1.4 0.4
Carbon Monoxide 0.2 0.2
Carbon Dioxide 76.4 X
The value X must be found such that the combination of X and water content is 4.5% of
the molar volume of the gas. Assuming the gasses are ideal,
Component Mass flow
(kg/hr)
Molecular Weight Molar flow
(kmol/hr)
Methane 25.9 16 1.6
Ethane 1.9 30 0.06
Propane 1 44 0.02
Water 0.4 18 0.02
Carbon Monoxide 0.2 28 Negligible
Carbon Dioxide X 44 X/44
Using algebra and solving for X, the mass flow rate of 2.5 kg/hr was found. Thus, 73.8
kg/hr of carbon dioxide must be removed in the scrubber.
Note: Carbon dioxide has a solubility of 1.08 g/kg water (57). Thus the minimum flow
rate was found to be:
hr
kgwater
hr
kg
kg
g
g
kgwaterQ 68435)
8.73)(
1
1000)(
08.1(
This value was increased by 10%, making the final flow rate of water 75278.5 kg/hr y*=87x (58)
115
xa=0; y*a=0
03.0;0004.0
)18
(75278
)44
(8.73* bb y
kg
kmolkg
kg
kmolkg
x
yb-yb*=0.44
ya=0.029
ΔyLM=0.15
Noy= Δy/ΔyLM=0..47/0.15=3.1 transfer units
3.1*0.84 m=2.59 m tower height
S-201 Cost Calculations
Note: Separator height set to 2.5 m = 98.4 in
inmD
mD
m
LD
LrV
i
i
ii
2.7591.1
)5.2(2
2.7
2
2
3
2
2
Note: int p 375.0
for low pressure vessels with diameters between 6 and 8 ft (18).
lbstDLtDW pipi 33.4009)8.0)((
Where 3
284.0in
lb for carbon steel
PLvMP CCFC
Note: S-101 was designed as a vertical vessel
70.6245$)()(8.361
00.24343$
70684.07396.0
))ln(02297.0)ln(18255.00132.7( 2
LDC
eC
iPL
WW
v
For carbon steel FM = 1
CP = $30588.70
116
A-15: V-201 Calculations
Note: The temperature of the stream exiting the valve was calculated using ChemCAD,
as described in Appendix D-3.
Note: The cost of the valve was assumed to be negligible.
117
A-16: E-301 Brine Heat Exchanger Calculations
Note: All nutrient salts were assumed to have heat capacities similar to sodium
bicarbonate.
Note: All salts generated by the decomposition of algae were assumed to have heat
capacities similar to ammonium chloride.
Compone
nt m
(kg/hr
)
CP (kJ/kgK) ΔT Q
(kJ/hr)
Water 41.67 4.184 320 55791.13
NaHCO3 114.4 1.046 (59) 320 38158.08
NH4Cl 13.75 1.8 (60) 320 7930.79
101880
𝑄 = 28.3𝑘𝑊 = 𝑚𝐻2𝑂 3 − 2
28.3𝑘𝐽
𝑠= 𝑚𝐻2𝑂 205.24
𝑘𝐽
𝑘𝑔− 134.19
𝑘𝐽
𝑘𝑔
𝑚𝐻2𝑂 = 0.4𝑘𝑔
𝑠= 1440
𝑘𝑔
𝑟
Note: specific enthalpies obtained from literature (49)
Note: T2 determined from a conservative estimate for cooling water and T3 determined
from an environmental limit (18).
E-301 Cost Calculations
MPa
CT o
98.30
4001
MPa
CT o
11.0
322
MPa
CT o
105.0
493
MPa
CT o
975.30
804 1
2
3
4
118
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
200
7.273
90176
120752ln
)90176()120752(
ln
Note: U was determined based on a conservative estimate for water-water systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20
2
2
8.1
7.273200
4.96643
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
16.1394$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures greater than 600 psig:
9.2600
0198.0600
1292.08510.0
2
PPFP
06.4043$PC
119
A-17: E-302 Brine Heat Exchanger Calculations
Component m
(kg/hr
)
CP (kJ/kgK) ΔT Q
(kJ/hr)
Water 41.67 4.184 43 7496.93
NaHCO3 114.4 1.046 (59) 43 5145.48
NH4Cl 13.75 1.8 (60) 43 1064.25
13706.66
𝑄 = 3.8𝑘𝑊 = 𝑚𝐻2𝑂 3 − 2
3.8𝑘𝐽
𝑠= 𝑚𝐻2𝑂 205.24
𝑘𝐽
𝑘𝑔− 134.19
𝑘𝐽
𝑘𝑔
𝑚𝐻2𝑂 = 0.053𝑘𝑔
𝑠= 190.8
𝑘𝑔
𝑟
Note: specific enthalpies obtained from literature (49)
Note: T2 determined from a conservative estimate for cooling water and T3 determined
from an environmental limit (18).
E-302 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
200
8.38
90140
120187ln
)90140()120187(
ln
Note: U was determined based on a conservative estimate for water-water systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
MPa
CT o
11.0
861
MPa
CT o
11.0
322
MPa
CT o
105.0
493
MPa
CT o
105.0
434 1
2
3
4
120
2
2
7.1
8.38200
8.12976
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
47.1381$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures less than 600 psig, FP = 1
47.1381$PC
121
A-18: P-301A/B Cooling Water Pump Calculations
hps
J
s
hr
hr
kg
kg
JmWP
kg
Jkg
J
headW
kg
J
m
kg
PaPaPPH
PB
P
073.029.63600
16.19039.11
9.1175.0
9.8
9.8
977
)10013.1()101.1(
3
55
12
P-301A/B Cost Calculations
ftftm
ft
s
m
kg
J
g
head320098.328.3
8.9
9.11
2
min5000
min58.8
17.264977
min60
116.1903
3
3
galgal
gal
m
m
kg
hr
hr
kg
mV
Note: P-102A/B was determined to be a centrifugal pump due its small head (3.98 ft) and
flow rate
min1.105
gal (18)
Note: Cost determined from empirical correlations for a centrifugal pump (18)
5.0
g
headVs
Where: s is the pump sizing factor
5.05.075.20998.3
min1.105 ftgpmft
gals
Note: The size factor for this pump was too small to use empirical relationships to cost
the pump. Therefore, a pump was located that could meet the technical requirements of
the process was found.
A 1/3 hp self priming centrifugal pump with an optimum flow rate of 25 min
gal was
located with a cost of $450.00, including an assumed shipping and handling rate (23).
122
A-19: S-301 Flue Gas Scrubber Calculations
Note: 90% of carbon dioxide is to be removed.
Note: All gasses except carbon dioxide in flue gas are assumed to have negligible solubility in
water (57)
Note: Due to the fact that the water stream has a mass flow rate two orders of magnitude higher
than the gas stream, the scrubber was assumed to operate at a temperature of 25 °C
Amount of carbon dioxide to be removed
hr
kg
hr
kg2.48)6.53)(9.0(
Minimum flow rate
hr
kg
L
kg
g
L
kg
g
hr
kg44629)
1)(
08.1)(
1000)(2.48(
hr
kg
hr
kg49231)44629)(1.1( water flow rate
y*=87x (58)
xa=0; y*a=0
03.0;0004.0
)18
(49231
)44
(2.48* bb y
kg
kmolkg
kg
kmolkg
x
yb-yb*=0.0210
ya=0.0573
ΔyLM=0.036
Noy= Δy/ΔyLM=0.05346/0.036=1.5 transfer units
1.5*1.4 m=2.04 m tower height
S-301 Cost Calculations
Note: Separator height set to 2 m = 78.72 in
inmD
mD
mLD
LrV
i
iii
75.5849.1
)2(2
5.32
2
3
2
2
Note: int p 3125.0
for low pressure vessels with diameters between 4 and 6 ft (18).
lbstDLtDW pipi 31.2070)8.0)((
Where 3
284.0in
lb for carbon steel
PLvMP CCFC
Note: S-101 was designed as a vertical vessel
61.4448$)()(8.361
30.17089$
70684.07396.0
))ln(02297.0)ln(18255.00132.7( 2
LDC
eC
iPL
WW
v
For carbon steel FM = 1
123
CP = $21537.91
A-20: V-301 Calculations
Note: An adiabatic expansion was assumed.
Note: The enthalpy of the salts was assumed to be constant over the valve. Therefore, the
enthalpy of the water would also be constant over the valve.
kg
kJ
kg
kJ
HH fi
64.35964.359
ˆˆ
Therefore, Tf = 86oC
Ti=80 oC
Pi=30.975MPa
Tf = ?
Pf=0.11MPa
Q=0
Water @ P = 0.11 MPa, Tf = 86 oC (52)
Water @ P = 30.975 MPa, T = 80oC (52)
124
A-21: E-401 Methane Cooler Calculations
kWs
kJ
hr
Btu
hr
kJ
mol
kJ
hr
molQ
dTTThr
moldTCnQ
T
T
C
C
CHPgas
o
o
88.488.43.166685.1757199.2107.799
103661.010469.51031.3407.7992
1
4
60
500
2853
,
Note: The specific heat of the gas was assumed to be the specific heat of methane, which
is reasonable as the stream is more than 90% methane
Note: The specific heat of the methane was obtained from literature (54)
𝑄 = 4.88𝑘𝑊 = 𝑚𝐻2𝑂 4 − 1
17571.5𝑘𝐽
𝑟= 𝑚𝐻2𝑂 205.24
𝑘𝐽
𝑘𝑔− 134.19
𝑘𝐽
𝑘𝑔
𝑚𝐻2𝑂 = 247.31𝑘𝑔
𝑟
Note: The specific enthalpies of the water streams came from a literature source (49)
E-401 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
10
37.273
90140
120932ln
)90140()120932(
ln
Note: U was determined based on a conservative estimate for water-gas systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
MPa
CT o
11.0
321
MPa
CT o
99.21
5002
MPa
CT o
985.21
603
MPa
CT o
105.0
494 1
2
3
4
125
2
2
1.6
37.27310
3.16668
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
81.1694$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures greater than 600 psig:
5.1600
0198.0600
1292.08510.0
2
PPFP
22.2542$PC
126
A-22: E-402 Methane Cooler Calculations
kWhr
Btu
hr
kJ
mol
kJ
hr
molQ
dTTThr
moldTCnQ
T
T
C
C
CHPgas
o
o
14.054.47741.50363.007.799
103661.010469.51031.3407.7992
1
4
43
60
2853
,
Note: The specific heat of the gas was assumed to be the specific heat of methane, which
is reasonable as the stream is more than 90% methane
Note: The specific heat of the methane was obtained from literature (54)
𝑄 = 0.14𝑘𝑊 = 𝑚𝐻2𝑂 4 − 1
503.41𝑘𝐽
𝑟= 𝑚𝐻2𝑂 205.24
𝑘𝐽
𝑘𝑔− 134.19
𝑘𝐽
𝑘𝑔
𝑚𝐻2𝑂 = 7.09𝑘𝑔
𝑟
Note: The specific enthalpies of the water streams came from a literature source (49)
E-402 Cost Calculations
hrftF
BtuU
TUAQ
o
lm
210
Note: The log mean temperature difference was zero for this case, and therefore the
average approach temperature was used
Note: U was determined based on a conservative estimate for water-gas systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
2
2
4.2
2010
54.477
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
MPa
CT o
11.0
321
MPa
CT o
985.21
602
MPa
CT o
98.21
433
MPa
CT o
105.0
494 1
2
3
4
127
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
83.1459$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures greater than 600 psig:
5.1600
0198.0600
1292.08510.0
2
PPFP
74.2189$PC
128
A-23: E-403 Hydrogen Cooler Calculations
𝑄 = 𝑚𝐻2 2 − 3
𝑄 = 0.193𝑘𝑔
𝑟 10832
𝑘𝐽
𝑘𝑔− 4434.3
𝑘𝐽
𝑘𝑔
𝑄 = 0.34𝑘𝑊
Note: The specific enthalpies of the hydrogen streams came from a literature source (49)
𝑄 = 0.34𝑘𝑊 = 𝑚𝐻2𝑂 4 − 1
503.41𝑘𝐽
𝑟= 𝑚𝐻2𝑂 205.24
𝑘𝐽
𝑘𝑔− 134.19
𝑘𝐽
𝑘𝑔
𝑚𝐻2𝑂 = 17.3𝑘𝑔
𝑟
Note: The specific enthalpies of the water streams came from a literature source (49)
E-403 Cost Calculations
hrftF
BtuU
F
FF
FF
FFFF
T
T
TTT
TUAQ
o
o
oo
oo
oooo
lm
lm
2
1
2
12
10
37.273
90140
120932ln
)90140()120932(
ln
Note: U was determined based on a conservative estimate for water-gas systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
2
2
5.0
37.27310
22.1165
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
lm
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
MPa
CT o
11.0
321
MPa
CT o
115.0
5002
MPa
CT o
11.0
603
MPa
CT o
105.0
494 1
2
3
4
129
80.1135$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures less than than 600 psig, FP = 1
80.1135$PC
130
A-24: E-404 Hydrogen Cooler Calculations
𝑄 = 𝑚𝐻2 2 − 3
𝑄 = 0.193𝑘𝑔
𝑟 4434.3
𝑘𝐽
𝑘𝑔− 4189.8
𝑘𝐽
𝑘𝑔
𝑄 = 0.013𝑘𝑊
Note: The specific enthalpies of the hydrogen streams came from a literature source (49)
𝑄 = 47.2𝑘𝐽
𝑟= 𝑚𝐻2𝑂 4 − 1
47.2𝑘𝐽
𝑟= 𝑚𝐻2𝑂 205.24
𝑘𝐽
𝑘𝑔− 134.19
𝑘𝐽
𝑘𝑔
𝑚𝐻2𝑂 = 0.66𝑘𝑔
𝑟
Note: The specific enthalpies of the water streams came from a literature source (49)
E-404 Cost Calculations
hrftF
BtuU
TUAQ
o
lm
210
Note: The log mean temperature difference was zero for this case, and therefore the
average approach temperature was used
Note: U was determined based on a conservative estimate for water-gas systems (18).
Note: The heat transfer design equation was used to size the heat exchanger (20).
2
2
3.0
2010
77.44
ft
FhrftF
Btu
hr
Btu
TU
QA
o
o
Note: It was determined a double pipe heat exchanger worked best for this application
(18).
MPa
CT o
11.0
321
MPa
CT o
115.0
602
MPa
CT o
11.0
433
MPa
CT o
105.0
494 1
2
3
4
131
67.1046$)ln(16.0146.7 A
B eC
Where CB is the base cost of the exchanger and A is the area in ft2.
BMPP CFFC
For carbon steel: 1100
0100
0
AAaF
b
M
For pressures less than than 600 psig, FP = 1
67.1046$PC
132
A-25: P-401A/B Methane Compressor Calculations
Note: Empirical correlations were used to size and cost the compressors (Seider, 569)
Compound
hr
kgm
mol
gMW
hr
moln
yi (mol
fraction)
H2O 0.179 18 9.94 0.011
CO2 1.130 44 25.68 0.029
CO 0.094 28 3.36 0.004
CH4 11.541 16 721.31 0.806
C2H6 0.860 30 28.67 0.032
C3H8 0.445 44 10.11 0.011
H2 0.193 2 96.5 0.107
895.57 mol/hr =
14.93 mol/min
1.0
min58.4
min13.0
285000
)298(314.8min
93.1433
3
ftm
Pa
KKmol
Pammol
P
RTnV
Note: Assume ideal gas
31.1
440.27
974.35
Kmol
JKmol
J
C
Ck
v
P
Note: CP and Cv determined from a literature source (49)
11
00436.01k
k
I
O
B
IB
p
ppV
k
kP
133
hphpP
P
hpP
psikPaP
psikPaP
BC
B
o
I
B
2.1175.0
36.8
36.8
84.319022000
34.41285
75.0
Note: Screw compressors were chosen because of the low power consumption (18)
BMDP
P
B
CFFC
eC C
60.19336$))ln(79.08929.6(
For an electric motor, FD = 1
FM = 1 for carbon steel
CP = $19336.60
Thus,
The total cost for 1 compressor: $19336.60
The total cost for 2 compressors: $38673.20
134
A-26: P-402A/B Vacuum Pump Calculations
Note: No empirical relationships for determining the size and purchase cost of a vacuum
pump could be found. Therefore, a vacuum pump was located that met the necessary
technical requirements of the process.
A TorrVac B Series Rotary Vane Vacuum Pump was located with a maximum flow rate
of 21 min
3ft and a maximum vacuum of 0.5 mm Hg was located (25).
135
A-27: S-401 Hydrogen Membrane Calculations
Note: The hydrogen flux across the membrane is )(
06.02 barsm
mol (26)
Note: The area of the membrane is assumed to be 60cm-1
(26)
The maximum amount of hydrogen that could diffuse through this membrane is given by
FAtdPQ
Where time is in seconds
)22)(1000
1)(
2)(06.0)(3600)(06.0( 2
2bar
g
kg
mole
gm
hr
s
sbarm
molQ
hr
kgQ 57.0
This membrane is able to handle the 0.19 kg/hr of hydrogen produced by the process.
S-401 Cost Calculations
The cost of the membrane is approximated to be $50,000. (61)
136
Appendix B: Spread Sheets with Explanations
Team Kazaam! used spreadsheets exclusively to perform the economic analysis of the
project. The following information demonstrates how the spreadsheets were utilized to
arrive at the final economic data. All calculations were performed on a single
spreadsheet; therefore, cells referenced in figures later in this appendix can be found in
figures towards the beginning of the chapter.
B-1: Calculation of Total Bare-Module Costs
The first step in calculating the costs of the process was to determine the installed cost of
each piece of equipment, CTBM. CTBM was obtained by the following equation:
NFCC TBMPTBM
Figure 7 shows the formulas used to calculate the CTBM of each piece of equipment.
Values for CP were obtained from Appendices A and D. FTBM values were obtained from
Sieder (18). N is the number of units required.
Figure 7: Calculating the CTBM of the equipment
137
The output of this spreadsheet is shown in Figure 8.
Figure 8: Output from calculating the CTBM of the equipment
.
B-2: Calculation of Total Capital Investment
This spreadsheet was then used to calculate the total capital investment required for the
project. Figure 9 shows the formulas used to calculate CTCI; this calculation follows the
model put forth by Sieder (18).
Figure 9: Formulas used to calculate CTCI
Calculated CTBM values were initially given in 2006 dollars. To adjust this to 2010
dollars, the following equation was used.
)(O
OI
ICC
138
C is the cost in 2010 dollars. CO is the cost in 2006 dollars. It has a value of 524.2, the
PCI for December 2009, the most recent data available (62). IO has a value of 500, the
PCI for 2006 (18).
The total CTBM is the sum of the inflation adjusted CTBM, the prices of equipment
purchased at 2010 dollars and the price of the initial catalyst charge. The cost of site
preparation is 5% of the CTBM. The cost of service facilities was assumed to be zero, due
to the fact that this facility will be integrated with a nearby algae farm and coal fired
power plant. The allocated cost associated with process and cooling water facility
preparation was calculated using the following formula 96.068.0 15001000 PCAlloc SSC
Where SC has a value of 110.8 and SP has a value of 546.
The CDPI is given by the sum of the CTBM, cost of site preparation and allocated costs.
The cost of contingency funds and contractor’s fee is approximated by being 18% of the
CDPI. The CDPI and the contingency and contractor’s fee cost are summed together to
produce the CTDC.
The cost of land is approximated as 2% of the CTDC. The cost of royalties is set as zero, as
no patented processes are utilized in the design. The cost of plant startup is approximated
as 20% of CTDC. The sum of these factors together with the CTDC yields the cost of the
total permanent investment.
The working capital is the money required to run the plant for one month. This is 8.33%
of the yearly operating cost which is described in the next section. The sum of the total
permanent investment and the working capital yields the CTCI.
Figure 10 shows the output of the spreadsheet used to find CTCI.
Figure 10: Output of formulas used to calculate CTCI
139
B-3: Calculation of Yearly Operating Costs
This spreadsheet was then used to calculate the yearly operating costs required for the
project. Figure 11 shows the formulas used to calculate this cost; this calculation follows
the model put forth by Sieder (18).
Figure 11: Formulas used to calculate yearly operating costs
The cost of the feedstock was assumed to be $1/ton. The yearly cost for the utilities was
read in from Table 21. The cost of direct wages and benefits (DW&B) is based on one
operator per shift at five shifts at 2080 operator hours/year at $35/hour. The operational
direct salaries and benefits were assumed to be 15% of the DW&B. The operational
supplies were assumed to be 6% of the DW&B.
The cost of maintenance wages and benefits (MW&B) was set at 3.5% of the CTDC. The
salaries and benefits associated with maintenance were set at 25% of MW&B.
Maintenance overhead was set at 5% of MW&B.
The general plant overhead was set at 7.1% of the combined wages and salaries for
operations and maintenance (M&O-SW&B). Mechanical services costs were set at 2.4%
of the M&O-SW&B. The employee relations department amounts to 5.9% of the M&O-
SW&B. Business services account for 7.4% of the M&O-SW&B.
Depreciation was set assuming a linear depreciation of the CTDC with 10% salvage value
at the end of a 30 year plant operation. Due to the small annual sales of the process, no
general expenses were assessed. The total annual production cost is the sum of the above
values.
140
Figure 12 shows the output of the above spreadsheet.
Figure 12: Output of formulas used to calculate yearly operating costs
B-4: Calculation of NPV
This spreadsheet was then used to calculate the net present value of the plant. Figure 13
shows the formulas used to calculate this value; this calculation follows the model put
forth by Sieder (18).
Figure 13: Formulas used to calculate NPV
A one year construction time was assumed. Depreciation values were found according to
the method described in the Economic Analysis section; this depreciation is not linear
and is based on the current U.S. tax code. Linear depreciation is typically accounted for
in the calculation of COM (18). Cost of manufacture minus depreciation is the COM
minus depreciation. Sales is the annual sales revenue. Net earnings is sales minus COM
minus depreciation. Discounted cash flow is the net earnings plus depreciation. Cash flow
is given by the following equation
n
CashFlowDiscountedPV
)30.01(
where n is the number of years beyond 2010. Cumulative PV is given by the previous
year’s cumulative PV plus the PV for that year.
The full table showing the final PV and the output of the full 30 year spreadsheet is
shown in the Economic Analysis section.
141
Appendix C: Overall Mass and Energy Balances
Table 28: Flow Rates of Input Streams
Input Stream Mass Flow Rate 𝑘𝑔
𝑟
1 5240
17 630
23 23300
26 125000
36 1900
Total 156070
Table 29: Flow Rates of Output Streams
Output Stream Mass Flow Rate 𝑘𝑔
𝑟
25 23300
28 75400
30 4960
31 49300
32 560
35 170
43 1630
48 14.3
52 0.193
61 272
Total 155606.493
Table 30: Net Flow Rates of Individual Components in the Process
Component Input Flow Rate 𝑘𝑔
𝑟 Output Flow Rate
𝑘𝑔
𝑟 Net Flow
𝑘𝑔
𝑟
Algae 125 0 (125)
Air 621 548 (73.354)
Water 155000 155000 37.470
Salts 114 128 13.750
Carbon Dioxide 0 134 133.883
Carbon Monoxide 0 0.211 0.211
Methane 0 11.5 11.542
Ethane 0 0.860 0.860
Propane 0 0.445 0.445
Hydrogen 0 0.193 0.193
Total 155860 155823.209 0.000
Note: The water mass flow rate is three orders of magnitude larger than any other
component. Therefore the mass flows of the entire process can be approximated through
the mass flows of the water. The mass flows in and out of water are approximately equal
142
with the exception of the water produced in the furnace, which are four orders of
magnitude smaller than the total water flow rate.
Table 31: Overall Energy Balance
Equipment Power Consumption (kW) Annual Power Usage (kWh)
P-101A/B 165 1440000
P-102A/B 1.5 13100
P-201A/B 10.9 95400
P-202A/B 9.6 84300
P-301A/B 0.25 2190
P-401A/B 8.4 73200
P-402A/B 1.1 9810
1718000
Note: The annual power usage of P-101A/B is two orders of magnitude larger than any
other pump. Therefore the annual power usage of the entire process can be approximated
through the annual power usage of P-101A/B.
143
Appendix D: ChemCad Outputs
The following printouts were generated using ChemCAD software. The entire process
was not modeled using ChemCAD; rather, the software was generally used to double
check hand calculations to ensure their accuracy. Certain values were calculated using
ChemCAD. These values are highlighted in yellow and referenced in Process Description
section.
D-1: Pumps
ChemCAD outputs for pumps are shown in Table 32. ChemCAD was used to double
check the calculated break horsepower of each pump, shown in the line labeled
“Calculated power hp.” The hand calculated values are in the line below that labeled
“Hand calculated hp.” The line below that marked “Within 5hp?” indicates whether or
not the ChemCAD value is within 5hp of the hand calculated value. If the values are
within 5hp, then the hand calculation was assumed to be accurate. The other information
is presented to give the reader more information about the pump.
Information is not included for P-301 A/B or P-402 A/B. These pumps are commercially
purchased; thus, the power for these pumps was not calculated.
Table 32: ChemCAD outputs for pumps CHEMCAD 6.1.3
Page 1
Job Name: Date: 04/21/2010 Time: 20:39:00
Pump Summary
Equip. No. P-101 A/B P-102 A/B P-201 A/B P-301
A/B
Name
Output pressure kPa 31000.0000 110.0000 290.0000
110.0000
Efficiency 0.7500 0.7500 0.7500
0.7500
Calculated power hp 79.2513 0.1014 11.7122
0.0083
Hand calculated hp 82.3 0.073 11.94
Within 5hp? Yes No Yes
Calculated Pout kPa 31000.0000 110.0000 290.0000
110.0000
Head ft 10289.6855 2.9260 63.3385
2.9260
Vol. flow rate ft3/hr 182.2432 827.9667 4410.1313
67.6009
Mass flow rate kg/h 5184.3999 23321.9023 124470.0000
1904.1599
Cost estimation flag 1 1 1
1
Pump type 1 0 0
0
Install factor 2.8000 2.8000 2.8000
2.8000
Basic pump cost $ 844 3148 4364
5129
144
Basic motor cost $ 3583 356 649
1954
Total purchase cost $ 4427 3504 5013
7084
Total installed cost 12397 9811 14036
19834
($)
Compressor Summary
Equip. No. P-401 A/B P-402 A/B
Name
Pressure out kPa 22000.0000 115.0000
Type of Compressor 1 1
Efficiency 0.7500 0.7500
Calculated power hp 7.5796 0.2868
Hand calculated hp 11.2
Within 5hp?
Cp/Cv 1.3078 1.3923
Theoretical power hp 5.6847 0.2151
Ideal Cp/Cv 1.3015 1.3925
Calc Pout kPa 22000.0000 115.0000
Install factor 1.3000 1.3000
Basic compressor $ 37868 4973
Basic motor cost $ 464 263
Basic driver cost $ 486 26
Total purchase cost $ 38818 5262
Total installed cost 50463 6841
($)
Cost estimation flag 1 1
Calc. mass flowrate 13 0
(kg/h)
D-2: Pump Outlet Streams
ChemCAD was used to calculate the temperatures of streams 2 and 45. The rest of the
pump outlet streams are included here to demonstrate that the streams do not experience a
significant rise in temperature across the pumps. Stream 50 is shown here to have a
temperature of 769 °C; however, this value is not utilized because P-402 A/B is a
commercial vacuum pump, not a theoretical compressor as shown here. ChemCAD does
not have the appropriate settings to simulate a vacuum pump. The rest of the material is
presented to give the reader a greater understanding of the characteristics of these process
streams. ChemCAD simulation of output streams are shown in Table 33.
The schematic used to calculate both the pumps and the outlet streams are shown in
Figure 14.
Table 33: ChemCAD simulation of pump output streams CHEMCAD 6.1.3
Page 1
Job Name: Date: 04/21/2010 Time: 20:41:29
Stream No. 2 24 27+29
37
Name
- - Overall - -
145
Molar flow kmol/h 279.1532 1294.5824 6909.2426
105.6986
Mass flow kg/h 5184.4000 23321.9018 124470.0000
1904.1600
Temp C 35.0712 32.0027 25.0604
32.0030
Pres kPa 31000.0000 110.0000 290.0000
110.0000
Vapor mole fraction 0.0000 0.0000 0.0000
0.0000
Enth kJ/h -7.9866E+007 -3.6917E+008 -1.9739E+009 -
3.0142E+007
Tc C 420.1414 374.2000 374.2000
374.2000
Pc kPa 32869.7819 22118.2302 22118.2302
22118.2302
Std. sp gr. wtr = 1 1.008 1.000 1.000
1.000
Std. sp gr. air = 1 0.641 0.622 0.622
0.622
Degree API 8.8663 10.0000 10.0000
10.0000
Average mol wt 18.5719 18.0150 18.0150
18.0150
Actual dens lb/ft3 62.5232 62.0991 62.2215
62.0991
Actual vol ft3/hr 182.8063 827.9673 4410.1987
67.6009
Std liq ft3/hr 181.6187 823.6063 4395.6226
67.2449
Std vap 0 C scfh 220958.2344 1024701.4375 5468876.0000
83663.6563
- - Liquid only - -
Molar flow kmol/h 279.1532 1294.5824 6909.2426
105.6986
Mass flow kg/h 5184.4000 23321.9018 124470.0000
1904.1600
Average mol wt 18.5719 18.0150 18.0150
18.0150
Actual dens lb/ft3 62.5232 62.0991 62.2215
62.0991
Actual vol ft3/hr 182.8063 827.9673 4410.1987
67.6009
Std liq ft3/hr 181.6187 823.6063 4395.6226
67.2449
Std vap 0 C scfh 220958.2344 1024701.4375 5468876.0000
83663.6563
Cp Btu/lbmol-F 18.1855 17.9844 18.0078
17.9844
Z factor 0.3887 0.0010 0.0028
0.0010
Visc cP 0.8024 0.7946 0.9218
0.7946
Th cond Btu/hr-ft-F 0.3520 0.3557 0.3503
0.3557
Surf. tens. dyne/cm 69.8316 70.8904 72.0931
70.8903
CHEMCAD 6.1.3
Page 2
146
Job Name: Date: 04/21/2010 Time: 20:41:29
Stream No. 45 50
Name
- - Overall - -
Molar flow kmol/h 0.8697 0.0957
Mass flow kg/h 13.4880 0.1930
Temp C 500.4834 768.9864
Pres kPa 22000.0000 115.0000
Vapor mole fraction 1.000 1.000
Enth kJ/h -41519. 2038.5
Tc C -80.2268 -239.8800
Pc kPa 5563.3378 1295.9465
Std. sp gr. wtr = 1 0.300 0.070
Std. sp gr. air = 1 0.535 0.070
Degree API 340.4216 1889.9286
Average mol wt 15.5092 2.0158
Actual dens lb/ft3 3.0354 0.0017
Actual vol ft3/hr 9.7963 254.7803
Std liq ft3/hr 1.5886 0.0974
Std vap 0 C scfh 688.3771 75.7840
- - Vapor only - -
Molar flow kmol/h 0.8697 0.0957
Mass flow kg/h 13.4880 0.1930
Average mol wt 15.5092 2.0158
Actual dens lb/ft3 3.0354 0.0017
Actual vol ft3/hr 9.7963 254.7803
Std liq ft3/hr 1.5886 0.0974
Std vap 0 C scfh 688.3771 75.7840
Cp Btu/lbmol-F 14.5970 7.2554
Z factor 1.0768 1.0002
Visc cP 0.02478 0.02119
Th cond Btu/hr-ft-F 0.0799 0.2575
Figure 14: ChemCAD Pumps
147
D-3: Valve Outlet Streams
. The properties of the streams leaving the three letdown valves of the process were
simulated using ChemCAD. ChemCAD simulations of output streams are shown in Table
34. ChemCAD was used to calculate the temperature of stream 13. Streams 8 and 34 are
shown here as well; the simulated values are within 10% of the hand calculated values,
demonstrating that the hand calculated values are accurate.
The schematic used to calculate the valve outputs is shown in Figure 15.
Table 34: ChemCAD simulations of valve output streams CHEMCAD 6.1.3
Page 1
Job Name: Date: 04/21/2010 Time: 20:50:47
Stream No. 8 13 34
Name
- - Overall - -
Molar flow kmol/h 279.0179 1.1149 3.8206
Mass flow kg/h 5069.6190 18.0440 169.8160
Temp C 111.1644 23.9800 80.0000
Pres kPa 300.0000 140.0000 110.0000
Vapor mole fraction 0.02686 1.000 0.0000
Enth kJ/h -7.7541E+007 -87903. -1.3658E+006
Tc C 366.0101 -77.8064 984.3835
Pc kPa 21212.5792 5598.5001 63966.1696
Std. sp gr. wtr = 1 0.983 0.313 1.662
Std. sp gr. air = 1 0.627 0.559 1.535
Degree API 12.4558 320.8178 -46.3615
Average mol wt 18.1695 16.1839 44.4476
Actual dens lb/ft3 3.7659 0.0578 101.0561
Actual vol ft3/hr 2967.8679 688.3544 3.7047
Std liq ft3/hr 182.1394 2.0369 3.6083
Std vap 0 C scfh 220851.1875 882.5038 3024.1104
- - Vapor only - -
Molar flow kmol/h 7.4935 1.1149
Mass flow kg/h 177.9338 18.0440
Average mol wt 23.7452 16.1839
Actual dens lb/ft3 0.1408 0.0578
Actual vol ft3/hr 2785.9036 688.3544
Std liq ft3/hr 9.3846 2.0369
Std vap 0 C scfh 5931.3022 882.5038
Cp Btu/lbmol-F 8.9200 8.5563
Z factor 0.9885 0.9976
Visc cP 0.01512 0.01120
Th cond Btu/hr-ft-F 0.0188 0.0228
- - Liquid only - -
Molar flow kmol/h 271.5244 3.8206
Mass flow kg/h 4891.6841 169.8160
Average mol wt 18.0156 44.4476
Actual dens lb/ft3 59.2661 101.0561
Actual vol ft3/hr 181.9644 3.7047
Std liq ft3/hr 172.7547 3.6083
Std vap 0 C scfh 214919.8594 3024.1104
Cp Btu/lbmol-F 18.2277 25.5928
Z factor 0.0024 0.0220
148
Visc cP 0.2495 1.519
Th cond Btu/hr-ft-F 0.3931 0.2521
Surf. tens. dyne/cm 56.4453 98.1514
Figure 15: ChemCAD Valves
D-4: Heat Exchanger Duties
The duties of the ten heat exchangers used in the process were simulated using
ChemCAD; the ChemCAD output of these exchangers is found in Table 35; these values
are shown in the line labeled “Calc Ht Duty kJ/s.” Underneath that line are the hand
calculated values in the line labeled “Hand values kJ/s.” All exchangers except for E-301
and E-302 had ChemCAD calculated values within 10% of the hand values; thus, the
hand values were assumed to be accurate. The bigger discrepancy in E-301 and E-302 is
likely caused by different heat capacities of the salts; in these cases, the data used in hand
calculations were assumed to be more accurate.
The ChemCAD schematic used in this simulation is shown in Figure 16.
Table 35: ChemCAD heat exchanger outputs CHEMCAD 6.1.3
Page 1
Job Name: Date: 04/21/2010 Time: 21:52:48
Heat Exchanger Summary
Equip. No. E-101 E-102 E-201 E-
202
Name
1st Stream dp kPa 5.0000 5.0000 5.0000
5.0000
2nd Stream dp kPa 5.0000 5.0000 5.0000
5.0000
1st Stream T Out C 465.0000
2nd Stream T Out C 372.0000 43.0000
131.0000
Calc Ht Duty kJ/s 2321.4846 556.9088 84.0278
1.2704
149
Hand values kJ/s 2308 518 80
1.24
LMTD (End points) C 39.7675 31.7110 37.7404
43.2850
LMTD Corr Factor 1.0000 1.0000 1.0000
1.0000
1st Stream Pout kPa 30965.0000 105.0000 135.0000
120.0000
2nd Stream Pout kPa 30995.0000 295.0000 125.0000
135.0000
Equip. No. E-301 E-302 E-401 E-
402
Name
1st Stream dp kPa 5.0000 5.0000 5.0000
5.0000
2nd Stream dp kPa 5.0000 5.0000 5.0000
5.0000
2nd Stream T Out C 80.0000 43.0000 60.0000
43.0000
Calc Ht Duty kJ/s 40.6089 4.8854 5.0465
0.1472
Hand values kJ/s 28.3 3.8 4.9
0.14
LMTD (End points) C 150.2101 19.6421 152.0590
10.5497
LMTD Corr Factor 1.0000 1.0000 1.0000
1.0000
1st Stream Pout kPa 105.0000 105.0000 105.0000
105.0000
2nd Stream Pout kPa 30975.0020 105.0000 21985.0020
21980.0020
Equip. No. E-403 E-404
Name
1st Stream dp kPa 5.0000 5.0000
2nd Stream dp kPa 5.0000 5.0000
2nd Stream T Out C 60.0000 43.0000
Calc Ht Duty kJ/s 0.3429 0.0131
Hand values kJ/s 0.34 0.013
LMTD (End points) C 152.1790 10.9607
LMTD Corr Factor 1.0000 1.0000
1st Stream Pout kPa 105.0000 105.0000
2nd Stream Pout kPa 110.0000 105.0000
150
Figure 16: ChemCAD heat exchangers
151
Appendix E: Web Printouts
P-102A/B
152
P-301A/B
153
P-402A/B
154
Appendix F: Meeting Logs
Meeting/ Phone Log 1
Date: February 2, 2010
Members Present (name of senior design group members plus name and title of person
providing information)
Dr. Seames, Professor at University of North Dakota
Members: Kim Seamans, Zac Ronan, Kyle Kryger and Amanda Rubio
Summary of Information, that pertains to the report (costs, flow rates, sizes,
assumptions).
The meeting was very helpful in guiding us with our plant design because Dr. Seames
was well verse in the topic of algae. After we were able to give him some details about
our plant design he was able to provide some assumptions about the algae. It can be
assumed that algae is available as a slurry with 2.5% algae by mass for purchase and that
a reasonable amount of algae entering the process a day is about 3 tons/day.
Meeting/ Phone Log 2
Date: April 22, 2010
Members Present (name of senior design group members plus name and title of person
providing information)
Mike Arnold, Professor at University of Arizona, Team Kazaam
Members: Kim Seamans, Zac Ronan, Kyle Kryger and Amanda Rubio
Summary of Information that pertains to the report (costs, flow rates, sizes, assumptions).
The last meeting with Professor Arnold to review the overall reports and help us find any
discrepancies. There were some minor changes and when he was reviewing the
economic analysis he suggested that we change the interest rate for the discounted cash
flow from 15% to 30% because our product is new and inherently risky.