abb storm preparedness web in ar presentation

63
© ABB Slide 1 July 24, 2015 Take the wind out of the next SuperStorm Strategies for storm preparedness and quick recovery to improve grid reliability and resiliency ABB PowerED Power Education Webinar Series: July 24, 2015

Upload: roberto-eduardo-quintal-palomo

Post on 04-Sep-2015

16 views

Category:

Documents


8 download

DESCRIPTION

Redes de distribución electrica despues de la tormenta

TRANSCRIPT

  • ABBSlide 1July 24, 2015

    Take the wind out of the next SuperStormStrategies for storm preparedness and quick recovery to improve grid reliability and resiliency

    ABB PowerED Power Education Webinar Series: July 24, 2015

  • ABBSlide 3July 24, 2015

    Taking the wind out of the next SuperStormTodays experts

    Brian Friedrich, PE,

    Vice President, US Service Sales,

    ABB Inc.

    John Boggess,

    Principal Project Engineer, Power Systems Substations,

    ABB Inc.

    Craig Stiegemeier,

    Business Development and Technology Director,

    Transformer Remanufacturing and Engineering

    Services (TRES), ABB Inc.

    Parag Parikh,

    Industry Solution Executive, Power Systems Network

    Management, ABB Enterprise Software

  • ABBSlide 4July 24, 2015

    IntroductionStuff happens

    Natural disasters happen

    Hurricanes, floods, tornados

    2015 AccuWeather Atlantic Hurricane Forecast

  • ABBSlide 5July 24, 2015

    Introduction

    Space weather (geomagnetic storms)

    affect the earth and power grid system

    Solar flares, solar storms / wind

    Monitoring and forecasting space

    weather is a national priority

    Use ground and space-based

    sensors and imaging systems, past

    conditions, and numerical models.

    Able to predict space weather on

    time scale of hours to days.

    Recent activity

    June 22 G4 - severe geomagnetic storm

    June 25 enormous geomagnetic storm (2 days) Credit: NASA/SDO/AIA/LMSAL

  • ABBSlide 6July 24, 2015

    Pre-Storm

    Substation analysis and

    hardening

    Power transformer

    evaluations

    Proactive outage

    support agreements

    During the storm

    Monitoring

    Agenda

    PostStorm

    Substation first responders

    Repair parts

    Replacement equipment

    Field services

    Rapid transformer

    replacement

  • ABBSlide 7July 24, 2015

    Substation hardeningJohn Boggess,Principal Project Engineer, Power Systems Substations, ABB Inc.

  • ABBSlide 8July 24, 2015

    Storm hardening of substations

    Source: NOAA (National Oceanic and Atmospheric Administration)

    Top 5 US Costliest

    Storms

    $125B - Katrina

    (2005)

    $68B - Sandy (2012)

    $38B - Ike (2008)

    $29B - Wilma (2005)

    $27B - Andrew

    (1992)Tertiary Source: Wikipedia, for

    background purposes only

    U.S. 2012 BILLION-DOLLAR WEATHER AND CLIMATE DISASTERS

    Recent Superstorms have increased pressure on utilities and governmental agencies to harden

    critical infrastructure for improved grid system reliability during major storm events.

  • ABBSlide 9July 24, 2015

    Storm hardening of substations

    Impacts to substations can range from minor to

    catastrophic:

    Loss of HVAC system

    Loss of AC station service

    SCADA & communications failure

    Loss of DC battery system(s)

    Water damage to protection, automation &

    control equipment (i.e. control house)

    Damage to high voltage equipment from

    flooding in switchyard

    De-energization of a substation

    Fire and catastrophic loss

    Flood inundation impacts to substations

    Substation owners must evaluate the risk ofloss for specific equipment and/or systems todetermine the scope of the flood mitigation.

  • ABBSlide 10July 24, 2015

    After identifying critical substations with

    vulnerability to storm surge (as per FEMA

    FIRM maps) or high flood zones, different

    levels of flood mitigation can be

    employed.

    Storm hardening of substations

    Innovative substation solutions can

    provide early warning capabilities,

    mitigate potential outages, and reduce

    restoration times during weather events.

    Developing a flood mitigation strategy

  • ABBSlide 11July 24, 2015

    Storm hardening of substations

    Float switches can be strategically

    installed at locations throughout a

    substation. The output contacts from the

    float switches can then be hardwired into

    the substations SCADA system and monitored via status points to alert

    operations of flood events.

    Substation flood monitoring

    Multiple float switches, at different

    elevations, can notify operators of initial

    flood conditions, as well as higher water

    events at critical flood levels.

    Initial

    Critical

  • ABBSlide 12July 24, 2015

    Storm hardening of substations

    For distribution substation applications, a

    proven approach has been to combine the

    cost-effectiveness of modular equipment

    solutions with the storm hardening concept of

    elevated substations.

    At medium voltage levels, many modular

    substation designs are available that can be

    installed on elevated foundations, platforms or

    stilts.

    Elevating substation equipment

    Dedicated protection & control/bulk

    power protection enclosures

    Standby generator; aux power in storm-prone

    or remote environments

  • ABBSlide 13July 24, 2015

    Storm hardening of substations

    Elevated substations, integrated with GIS, provide reliable, reduced-footprint

    replacement solutions with environmental immunity. Based on prior installations & case studies, elevating substations with indoor GIS

    (gas-insulated switchgear) has proven to be an excellent solution to flood-prone

    substation areas.

    According to the U.S. DOE, per August 2013 Report - U.S. Energy Industry

    Response to Recent Hurricane Seasons, Common hardening activities to protect against flood damage include elevating substations and relocating facilities to areas

    less prone to flooding.

    Elevated substations

    Elevating an entire transmission substation is more challenging due to the amount of

    space required for increased electrical clearances at higher voltages.

  • ABBSlide 14July 24, 2015

    Storm hardening of substations

    Typically utilizes an enclosed cast-in-place (CIP) basement/cable vault, partially below grade, with water-proofing, sloped-floor, and sumps to manage water

    intrusion. For severe flood loading, stilt designs or breakaway walls can be

    incorporated into the foundation design per ASCE 7-10 flood loading guidelines.

    HV apparatus, protection & control, and other major equipment is located on the first floor concrete diaphragm with an elevation above projected flood levels.

    A pre-engineered metal building, with increased galvanizing and specified with HDG or stainless steel materials are used to withstand the corrosive environment.

    Excellent flexibility can be provided with SF6-to-Cable connections.

    Keys to elevated GIS substation design

  • ABBSlide 15July 24, 2015

    Completely enclosed substation

    Use of all dead-front equipment

    All connections via plug-in cables

    Storm hardening of substations

    No exposed HV/MV conductors in entire

    substation

    Superior Safety by Design solution

    Keys to enclosed substation design

  • ABBSlide 16July 24, 2015

    Storm hardening of substationsExamples of elevated and/or enclosed substations

  • ABBSlide 17July 24, 2015

    Storm hardening of substations

    Significant storm surge and flood events are relatively rare. However, recent

    superstorms have caused catastrophic property damage and loss of life.

    The U.S. DOE estimated outage costs to range from $18 to $33 billion dollars per

    year (in the last ten years). Paramount to the significant costs related to these

    power outages is their potential hindrance to emergency responders.

    Infrastructure hardening with substation upgrades at strategic locations can reduce

    the impacts of flooding & wind at critical substations during severe weather events.

    Innovative substation solutions and new technologies can improve grid storm

    hardening by detecting floods early or building substations with environmental

    immunity to withstand flooding, corrosion & wind.

    Storm & flood hardening of critical substations vulnerable to flooding can provide

    improved reliability, life cycle costs, security and most importantly public safety.

    Summary

  • ABBSlide 18July 24, 2015

    A layered approach for power equipmentCraig Stiegemeier,Business Development and Technology Director, Transformer Remanufacturing and Engineering Services (TRES), ABB Inc.

  • ABBSlide 19July 24, 2015

    A layered approach for power equipmentTransformer resiliency, geomagnetic storms and recovery transformers

    Agenda:

    Assessment of critical stations and equipment to the impact

    of regional challenges

    Storms hurricanes, tornadoes, and solar storms

    Seismic exposure

    Build in hardening or modify to improve equipment

    resiliency

    Geomagnetic storms

    Effects of geomagnetic storms on power transformers

    Impact of transformer reaction on the grid

    Ability to quickly recover from major damage

  • ABBSlide 20July 24, 2015

    Protect your grid to minimize downtimeA layered approach for power equipment

    1. Assess the asset risk to natural and physical disturbances

    2. Harden equipment against extreme environments

    3. Monitor the asset and surroundings and automate response

    to abnormalities

    4. Rapidly repair lightly damaged equipment

    5. Rapidly replace severely damaged equipment

    Strategy must flex to address a diversity of failure modes

    Assess risk, harden, monitor, automate, rapidly repair or replace

  • ABBSlide 21July 24, 2015

    Harden (new designs or modify existing equipment)Example: relocation of key equipment to less vulnerable locations

  • ABBSlide 22July 24, 2015

    Harden (new designs or modify existing equipment)

    Solid (oil free) construction reduces risk of fire

    Non-porcelain shed minimizes possible damage to people

    and equipment and increases resiliency to contamination

    High-seismic zone rated

    Take advantage of material advancements, such as dry bushings (and porcelain-free arresters)

  • ABBSlide 23July 24, 2015

    Hardening has its limitations must prepare for rapid repair or replacement of damaged equipmentTrain personnel for rapid recovery

    1. Develop trained rapid response teams

    2. Response team has access to standardized spare parts &

    systems designed for rapid installation

    3. Emergency response for storms or disasters with pre-

    established order process to expedite reaction

    4. Coordinated training with federal, state and local first

    responders

    1. Focus on field safety performance

    2. Familiarization with tools and equipment

    3. Technical support for Fusion Center

    5. Include transportation logistics supporting move of large

    equipment to critical locations

    6. Consider a life-cycle support process

  • ABBSlide 24July 24, 2015

    Geomagnetic disturbance (GMD)

    Strong solar flare activities => Sends plasma beams to earth

    Changes the magnetic field of Earth => GMD

    By NASA

  • ABBSlide 25July 24, 2015

    Change of earths magnetic field => Voltage in transmission circuits

    Transmission line / Power

    transformers / Ground

    Fraction of a volt to several volts/km

    Ground currents flow into neutrals of

    power transformers

    Magnitude of GIC in a transmission

    circuit is a function of:

    Magnitude & orientation of GMD,

    location on earth, proximity to large

    bodies of water, resistance of the

    soil, & direction / height / length of

    the transmission line

    Highest for > 500 kV transmission

    K Scale

    Mechanism of generation of Geomagnetically Induced Currents (GIC)

  • ABBSlide 26July 24, 2015

    Non linearity of the core material limits core from fully

    saturating

    DC causes part cycle saturation of the core

  • ABBSlide 27July 24, 2015

    % Imag of 1 phase Transformer under effect of DC

    Per Phase Currents

    High Peak pulseOne per Cycle

    Small mean width1/8th 1/12th of Cycle

    RMS = 15 20 % of peak

  • ABBSlide 28July 24, 2015

    VAR consumption vs. magnitude of GIC

    Utilities use this data to plan their VAR resources during GMD events

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    0 50 100 150 200 250 300 350 400

    % M

    VA R

    atin

    g

    GIC, Amps/Phase

  • ABBSlide 29July 24, 2015

    0%

    1%

    2%

    3%

    4%

    5%

    6%

    60 120 180 240 300 360 420 480 540 600 660

    % H

    arm

    on

    ic A

    mp

    litu

    de (

    % o

    f R

    ate

    d L

    oad

    Cu

    rren

    t)

    Harmonic Frequency, Hz

    Harmonic Spectrum of Magnetizing Current under different levels of GICs

    Idc = 25 Amps/Phase

    Idc = 50 Amps/Phase

    Current harmonics associated with DC / GIC

    Utilities use this data to optimize protection during GMD events

  • ABBSlide 30July 24, 2015

    -40

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    GIC

    , Am

    psA

    DC

    Low / moderate magnitudes of GIC

    sustained for several hours;

    interrupted by short duration / high peak pulses

    7 hr signature of GIC

    Signature / profile of GIC

  • ABBSlide 31July 24, 2015

    Winding Hot Spot Temperature vs Time, 1-Phase Transformer

    108

    110

    112

    114

    116

    118

    120

    122

    124

    0 5 10 15 20 25 30

    Time, Minutes

    Wdg H

    ot S

    pot Tem

    pt, D

    egre

    e C

    Idc = 50 Amps

    Idc = 30 Amps

    Idc = 20 Amps

    Effect of GIC on winding hot spot temperature

    Actual temperature rise is much lower for the short duration of high GIC peaks

    For a 2 minute duration: Rise is 3, 4, and 6 C for GIC of 20, 30, and 50 Amps

  • ABBSlide 32July 24, 2015

    Evaluation of total susceptibility of transformers to effects of GIC

    To determine which transformers:

    Are susceptible to damaging overheating

    Are susceptible to core saturation and only moderate

    overheating

    Have low level of susceptibility to either effects of GIC

    Are not susceptible to effects of GIC

    Total susceptibility to effects of GIC is determined by:

    Transformer design based susceptibility

    GIC level based susceptibility

  • ABBSlide 33July 24, 2015

    Results of GIC susceptibility study on large power transformer fleet > 500 kV

    Orange: Susceptible to both core saturation and possible damaging winding and/or structural

    parts overheating

    Yellow: Susceptible to core saturation and only moderate overheating

    Green: Low susceptibility to both core saturation and overheating

    Blue: Not susceptible to core saturation or overheating

  • ABBSlide 34July 24, 2015

    FERC Order 779

    In May 2013, FERC issued

    Order 779 which directs

    NERC to submit reliability

    standards that address the

    impact of GMD on the

    reliable operation of the

    bulk-power system

    Stage 1 operating procedures

    Stage 2 detailed assessments (planning

    studies)

    Standards project 2013-03

    (GMD mitigation) began in

    June 2013

  • ABBSlide 35July 24, 2015

    TPL 007 summary

    Requires a GMD Vulnerability Assessment of the system

    for its ability to withstand a benchmark GMD event without

    causing a wide area blackout, voltage collapse, or damage

    to transformers, once every five years. Applicability:

    Planning Coordinators, Transmission Planners

    Requires a Transformer thermal impact assessment to

    ensure that all high-side, wye grounded transformers

    connected at 200kV or higher will not overheat based on

    the Benchmark GMD Event. Applicability: Generator

    Owners, Transmission Owners

  • ABBSlide 36July 24, 2015

    GIC effects

  • ABBSlide 37July 24, 2015

    Studies needed for GIC concerns

    Geo-electric field determination

    DC system modeling

    GIC calculation

    Calculation of transformer reactive power absorption and

    harmonics

    Planning type studies with added reactive power

    absorption, considering contingencies.

    Conduct harmonics studies and determine the effects

    Identify limit violations and system issues

    Conduct thermal assessment of a portion of transformer

    fleet

    Determine mitigations and study their effects

  • ABBSlide 39July 24, 2015

    Emergency Storm Response Program

    Program focuses on power products and services for substations

    HV breakers and equipment, MV switchgear and equipment, power transformers

    Types of support - personnel and equipment

    Proactive - preplanned program for disaster support

    Research vendors now and set up blanket PO (in advance of storms) for defined

    responsibilities: scope of work, work locations, manpower requirements, equipment

    requirements, timing

    Assessments, hardening

    Reactive just had an unexpected disaster - need help now

    Work with vendors that have a quick PO, standard terms and conditions of sale

    Look for OEMs who have the drawings and schematics

    Look for vendors with full coverage areas and a network of resources

  • ABBSlide 40July 24, 2015

    First responders

    Advance team to perform initial

    assessment of substations to quickly

    identify rough work scope required

    What are the priorities

    Quick-fix versus fully restore

    Outage restoration priority changes

  • ABBSlide 41July 24, 2015

    Initial assessments

    Flooding of control cabinets as shown in a control relay from

    an 115 kV SF6 circuit breaker control cabinet

  • ABBSlide 42July 24, 2015

    Success story SuperStorm Sandy

    Reactive Quick PO with major NE utility

    Quick to site 1 day for first responders

    Team came in right after approximately 100 techs within 2 weeks as need dictated.

    Initial focus get people back on-line Band-Aids

    Work scope

    Substation overhauls (13 substations)

    Transformers, HV breakers, and MV switchgear

    Cleaning, testing, repairs, replacements

    Replacement breakers and components

    (surplus / used market)

  • ABBSlide 43July 24, 2015

    Rapid response exampleRecovery Transformer (RecX) Program

    Began before 9/11 with EPRIs Infrastructure Security Initiative (ISI)

    ABB was asked to examine feasibility of a

    fast-to-install transformer design

    DHS became involved after the project

    created a

  • ABBSlide 44July 24, 2015

    Versatile recovery transformer RecX Project

    Mobile transformers are not a new concept, but have traditionally been limited to

    less than 100 MVA and 230 kV

    Challenges and limitations

    Why are they limited?

    Large power drives physical size

    Heavy weights (hundreds of tons)

    Transportation difficulties

    Inability to fit equipment into complex

    site locations

  • ABBSlide 45July 24, 2015

    Versatile recovery transformer RecX Program

    How can we overcome these limitations?

    Size and Weight

    Separate into single-phase units

    Distributes weight

    High temperature

    insulation

    Reduces weight

    Longer lifetime

    Higher overload capacity

    Transportation

    Shipment via truck

    Rapid delivery to

    site

    Flexibility

    Transformer mounted on steel frame

    Easy lifting and setting

    Acts as transformer

    pad

    Remote cooling system

    Flex connections, easy to place

  • ABBSlide 46July 24, 2015

    Recovery Transformer (RecX) ProgramRapid deployment using truck transportation

  • ABBSlide 47July 24, 2015

    Recovery Transformer (RecX) ProgramRapid deployment Assembly using pre-configured subassemblies

  • ABBSlide 48July 24, 2015

    Recovery Transformer (RecX) ProgramRapid deployment Storage to energization: 5 days, 10 hours, 10 minutes (no overtime)

  • ABBSlide 49July 24, 2015

    Outage Lifecycle Management Enabled Storm Preparedness

    Parag Parikh,Industry Solution Executive, Power Systems Network Management, ABB Enterprise Software

  • ABBSlide 50July 24, 2015

    Challenges of grid reliability & resiliencyThe main historical issues have remained the same

    Regulatorycompliance

    OPEX + CAPEX management

    Customer engagement

    Reliability

    Health & safety

    Operational complexities

  • ABBSlide 51July 24, 2015

    Super storm Sandy constituted a strategic surprise for me and much of the

    Department of Defense. Paul Stockton

    Difficult logistics and poor

    communication between utilities,

    defense officials, state planners and first

    responders.

    Inadequate communication to

    customers, inadequate planning in

    vulnerable areas, poor visibility on the

    grid.

    Lack of attention on future black sky events worse than Sandy.

    Super stormsA Strategic Surprise for the Power Sector

  • ABBSlide 52July 24, 2015

    Changing the game from Centralized to Distributed Grid

    Centralized generation

    One-directional power flow

    Generation follows load

    Top-down operations planning

    Centralized and distributed generation

    Intermittent renewable generation

    Multi-directional power flow

    Operation based on real-time data

    Demand Response for economics and reliability

    TRADITIONAL GRID

    DISTRIBUTED GRID

    Outage Lifecycle Mgmt;

    OMS, Mobile, Analytics

    PV Solar complete

    Panel-to-Grid solutionsDistribution SCADATransformersReclosers & SwitchesWireless Infrastructure

    Asset Health

    Energy Management

    EMS SCADAMarket Operations

  • ABBSlide 53July 24, 2015

    Storm Preparedness Opportunities for Improvement

    5 of 6 major New York IOUs cited

    for inadequate communications

    capabilities during Sandy.

    During overtime workers typically

    make between 200% and 300% of

    average hourly base salary.

    AutomationRegulatory innovation

    Reducing OvertimeImproving Outage Communications

    Fault Location to identify fault

    location

    FLISR to reduce impact of an

    outage

    Damage Assessment

    automation to improve ETR

    and Restoration Plans

  • ABBSlide 54July 24, 2015

    Evolution of Outage Lifecycle

    Integrated Outage Management

    Event Management

    Outage Management System

    Proactive Distribution

    Management

    Mobile Workforce Management

    Asset Health Management

    Organizational Visibility

    Enterprise Asset Management

    Enterprise Resource Planning

    Outage Management 2.0

    Outage Management 1.0

    Historical

  • ABBSlide 55July 24, 2015

    Optimizing the Outage Lifecycle

    Connecting the Pieces

    Outage Management System

    Distribution Management System

    SCADA

    Distribution Automation

    Mobile Workforce Management

    AVL

    AMI

    DERMS

    EAM/ERP

    GIS

    CIS/CRM

    IVR

    Grid Analytics

    External Communications

  • ABBSlide 56July 24, 2015

    The lifecycle of an outage

    Prediction + Preparation

    Schedule and prioritize resources and keep

    stakeholders informed

    Assessment + Restoration

    Isolate, auto restore , deploy right crew to safely and efficiently restore remaining customers while keeping stakeholders informed

    Repair + Closeout

    Compliance, reporting and review helps build plan for next outage

    PlanningForecast, plan and prepare resources with full visibility

    and scenario-based planning

    1

    2

    3

    4

    OLM

  • ABBSlide 57July 24, 2015

    Outage Lifecycle ManagementStorm Preparedness

    Planning

    Library of storm models What-if analysis Customer notification preferences Asset Health Solution enabled asset review

    Prepare

    Projection model for impeding storm Assess resource needs and location Prepare for mutual assistance call outs and on-boarding

    Assess & Restore

    Damage Assessment and Outage Analysis Enable self-healing whenever possible Prioritize work and dispatch crew Notify stakeholder

    Closeout

    Post event analysis and reports to identify crew work, outage areas and issues

    Build data for future preparation, planning and grid hardening tasks

  • ABBSlide 58July 24, 2015

    Advanced Distribution Management System

    Common Network Model and Training Simulator

    Data Historian & Business Analytics

    SCADA

    Communication Infrastructure

    Field Devices DA Devices, Sensors and DER

    OMS Applications Trouble Call Management

    Outage Analysis

    Operations Management

    Crew Management

    Referral Work Orders

    Switch Order Management

    DMS Applications Load Flow Analysis

    Short Circuit Analysis

    Fault Detection and Location

    Automated Switching

    Overload Reduction Switching

    Volt/VAR Optimization

    Enterprise

    Integration

    GIS

    AVL

    IVR

    AMI/MDM

    Data Acquisition

    Monitoring & Event Processing

    Supervisory Control & Interlocking

    Data Archiving

    Calculation & Reports

    Human Machine Interaction

    Inter-Center Communication

    Communication Front-Ends (Protocol Conversion)

    Common Operator Graphical User InterfaceEnterprise IT Systems

    CIS

    ABB Outage Lifecycle Management & Grid Optimization Solution

    Mobile Workforce

    ManagementAsset & Work

    Management

    DRMS &

    DERMS

    IT/O

    T C

    onverg

    ence

    Asset Health Center

  • ABBSlide 59July 24, 2015

    Uses all available real-time and

    historical data on assets

    Online monitoring/sensors

    SCADA/historian

    Inspections and testing

    Work orders

    Risk of failure and criticality is

    continuously assessed

    Current picture of asset health

    always available especially during storm planning and preparation

    Drives optimal storm planning and

    maintenance decisions

    Storm PreparednessAsset Health - Risk of Failure and Criticality

    Location

  • ABBSlide 60July 24, 2015

    Storm Preparedness & RecoveryAdvanced Distribution Management System

    Assess

    System StateSystem

    AnalysisSystem

    Reliability

    System

    Restoration

    Outage

    Analysis

    FLISR

    Load Transfer

    Outage

    prediction and

    ETR generation

    Real-time power

    flow analysis to

    improve

    confidence in

    Switching

    decisions

    Real-Time

    Analysis

    Crew

    Dispatch

    Restoration

    Switching Plans

    ETR Updates

    Cold-load Pickup

    Manage field

    activities

    Normalize feeder

    configuration

    Customer

    Notification

    Fault Location

    calculation

    Self-healing Automatic

    Switching

    Minimize outage

    impact

    Reliability

    Improvement

    Prepare system

    planning and

    reliability

    enhancement

    studies

    Compare actual

    operational actions

    against simulated

    scenario

    Restoration

    Switching

    Operational

    Preparedness

    Validate and

    plan system

    control actions

    Save simulation

    for contingency

    planning

    Balance load

    Prepare switch

    order template

    Improve grid

    resiliency

    System

    Planning

    Simulation

    Case Studies

  • ABBSlide 61July 24, 2015

    Storm RecoveryDamage Assessment & ETR

    Assessment Information

    ID: 32

    Area: West

    Lat, Long: 41.876789, -

    71.3996124

    Date Assessed: 08/26/13 3:04

    PM

    Assessment Details

    Assessor Name: Tom Hill

    Hazard Level: High

    Equipment: Poles / Lines

    Customers: 5

    Critical: 1

    Emergency Onsite: Yes

    Work: Replace 3 poles. Click here to enlarge

    Move lines.

  • ABBSlide 62July 24, 2015

    Provide accurate and consistent and

    timely outage communications to

    internal and external stakeholders

    Increase customer satisfaction

    Increase situational awareness

    Support multiple communications

    channels (text, smartphone, web, etc.)

    Storm RecoveryOutage Communication

    Source: ComEd

  • ABBSlide 63July 24, 2015

    Storm Preparedness & RecoveryOutage Lifecycle Management Benefits

    Ensure compliance with regulatory requirements with

    full audit trail throughout the event.

    Same tools to be followed in blue sky days and major

    events

    Improves situational awareness, in the control room, out

    in the field and across the organization

    Improved resource planning that saves time and money

    Common data across platform ensures accurate data is

    communicated to stakeholder and customers

    Reduced outage duration and improved reliability

    leading to improved customer satisfaction

  • ABBSlide 65July 24, 2015

    Register todayDont miss these educational webinars

    ABB PowerED power education series

    Saving lives through arc flash mitigation: Leveraging technology to improve

    safety and reliability

    Sept 22 at 1-2 pm EDT

    https://attendee.gotowebinar.com/register/174811720747498497

    How secure is your substation? Physical security (Part I) - 3 strategic elements

    to protect your assets

    Oct 16 2-3 pm

    https://attendee.gotowebinar.com/register/4569042926504925441

    It's not a matter of if, but when: Physical security (Part II) - Strategies for

    recovery and repair

    Oct 28 1-2 pm EDT

    https://attendee.gotowebinar.com/register/1694434646917646594

    Smart grid optimization series sponsored by ABBs Smart Grid Center of Excellence