abb storm preparedness web in ar presentation
DESCRIPTION
Redes de distribución electrica despues de la tormentaTRANSCRIPT
-
ABBSlide 1July 24, 2015
Take the wind out of the next SuperStormStrategies for storm preparedness and quick recovery to improve grid reliability and resiliency
ABB PowerED Power Education Webinar Series: July 24, 2015
-
ABBSlide 3July 24, 2015
Taking the wind out of the next SuperStormTodays experts
Brian Friedrich, PE,
Vice President, US Service Sales,
ABB Inc.
John Boggess,
Principal Project Engineer, Power Systems Substations,
ABB Inc.
Craig Stiegemeier,
Business Development and Technology Director,
Transformer Remanufacturing and Engineering
Services (TRES), ABB Inc.
Parag Parikh,
Industry Solution Executive, Power Systems Network
Management, ABB Enterprise Software
-
ABBSlide 4July 24, 2015
IntroductionStuff happens
Natural disasters happen
Hurricanes, floods, tornados
2015 AccuWeather Atlantic Hurricane Forecast
-
ABBSlide 5July 24, 2015
Introduction
Space weather (geomagnetic storms)
affect the earth and power grid system
Solar flares, solar storms / wind
Monitoring and forecasting space
weather is a national priority
Use ground and space-based
sensors and imaging systems, past
conditions, and numerical models.
Able to predict space weather on
time scale of hours to days.
Recent activity
June 22 G4 - severe geomagnetic storm
June 25 enormous geomagnetic storm (2 days) Credit: NASA/SDO/AIA/LMSAL
-
ABBSlide 6July 24, 2015
Pre-Storm
Substation analysis and
hardening
Power transformer
evaluations
Proactive outage
support agreements
During the storm
Monitoring
Agenda
PostStorm
Substation first responders
Repair parts
Replacement equipment
Field services
Rapid transformer
replacement
-
ABBSlide 7July 24, 2015
Substation hardeningJohn Boggess,Principal Project Engineer, Power Systems Substations, ABB Inc.
-
ABBSlide 8July 24, 2015
Storm hardening of substations
Source: NOAA (National Oceanic and Atmospheric Administration)
Top 5 US Costliest
Storms
$125B - Katrina
(2005)
$68B - Sandy (2012)
$38B - Ike (2008)
$29B - Wilma (2005)
$27B - Andrew
(1992)Tertiary Source: Wikipedia, for
background purposes only
U.S. 2012 BILLION-DOLLAR WEATHER AND CLIMATE DISASTERS
Recent Superstorms have increased pressure on utilities and governmental agencies to harden
critical infrastructure for improved grid system reliability during major storm events.
-
ABBSlide 9July 24, 2015
Storm hardening of substations
Impacts to substations can range from minor to
catastrophic:
Loss of HVAC system
Loss of AC station service
SCADA & communications failure
Loss of DC battery system(s)
Water damage to protection, automation &
control equipment (i.e. control house)
Damage to high voltage equipment from
flooding in switchyard
De-energization of a substation
Fire and catastrophic loss
Flood inundation impacts to substations
Substation owners must evaluate the risk ofloss for specific equipment and/or systems todetermine the scope of the flood mitigation.
-
ABBSlide 10July 24, 2015
After identifying critical substations with
vulnerability to storm surge (as per FEMA
FIRM maps) or high flood zones, different
levels of flood mitigation can be
employed.
Storm hardening of substations
Innovative substation solutions can
provide early warning capabilities,
mitigate potential outages, and reduce
restoration times during weather events.
Developing a flood mitigation strategy
-
ABBSlide 11July 24, 2015
Storm hardening of substations
Float switches can be strategically
installed at locations throughout a
substation. The output contacts from the
float switches can then be hardwired into
the substations SCADA system and monitored via status points to alert
operations of flood events.
Substation flood monitoring
Multiple float switches, at different
elevations, can notify operators of initial
flood conditions, as well as higher water
events at critical flood levels.
Initial
Critical
-
ABBSlide 12July 24, 2015
Storm hardening of substations
For distribution substation applications, a
proven approach has been to combine the
cost-effectiveness of modular equipment
solutions with the storm hardening concept of
elevated substations.
At medium voltage levels, many modular
substation designs are available that can be
installed on elevated foundations, platforms or
stilts.
Elevating substation equipment
Dedicated protection & control/bulk
power protection enclosures
Standby generator; aux power in storm-prone
or remote environments
-
ABBSlide 13July 24, 2015
Storm hardening of substations
Elevated substations, integrated with GIS, provide reliable, reduced-footprint
replacement solutions with environmental immunity. Based on prior installations & case studies, elevating substations with indoor GIS
(gas-insulated switchgear) has proven to be an excellent solution to flood-prone
substation areas.
According to the U.S. DOE, per August 2013 Report - U.S. Energy Industry
Response to Recent Hurricane Seasons, Common hardening activities to protect against flood damage include elevating substations and relocating facilities to areas
less prone to flooding.
Elevated substations
Elevating an entire transmission substation is more challenging due to the amount of
space required for increased electrical clearances at higher voltages.
-
ABBSlide 14July 24, 2015
Storm hardening of substations
Typically utilizes an enclosed cast-in-place (CIP) basement/cable vault, partially below grade, with water-proofing, sloped-floor, and sumps to manage water
intrusion. For severe flood loading, stilt designs or breakaway walls can be
incorporated into the foundation design per ASCE 7-10 flood loading guidelines.
HV apparatus, protection & control, and other major equipment is located on the first floor concrete diaphragm with an elevation above projected flood levels.
A pre-engineered metal building, with increased galvanizing and specified with HDG or stainless steel materials are used to withstand the corrosive environment.
Excellent flexibility can be provided with SF6-to-Cable connections.
Keys to elevated GIS substation design
-
ABBSlide 15July 24, 2015
Completely enclosed substation
Use of all dead-front equipment
All connections via plug-in cables
Storm hardening of substations
No exposed HV/MV conductors in entire
substation
Superior Safety by Design solution
Keys to enclosed substation design
-
ABBSlide 16July 24, 2015
Storm hardening of substationsExamples of elevated and/or enclosed substations
-
ABBSlide 17July 24, 2015
Storm hardening of substations
Significant storm surge and flood events are relatively rare. However, recent
superstorms have caused catastrophic property damage and loss of life.
The U.S. DOE estimated outage costs to range from $18 to $33 billion dollars per
year (in the last ten years). Paramount to the significant costs related to these
power outages is their potential hindrance to emergency responders.
Infrastructure hardening with substation upgrades at strategic locations can reduce
the impacts of flooding & wind at critical substations during severe weather events.
Innovative substation solutions and new technologies can improve grid storm
hardening by detecting floods early or building substations with environmental
immunity to withstand flooding, corrosion & wind.
Storm & flood hardening of critical substations vulnerable to flooding can provide
improved reliability, life cycle costs, security and most importantly public safety.
Summary
-
ABBSlide 18July 24, 2015
A layered approach for power equipmentCraig Stiegemeier,Business Development and Technology Director, Transformer Remanufacturing and Engineering Services (TRES), ABB Inc.
-
ABBSlide 19July 24, 2015
A layered approach for power equipmentTransformer resiliency, geomagnetic storms and recovery transformers
Agenda:
Assessment of critical stations and equipment to the impact
of regional challenges
Storms hurricanes, tornadoes, and solar storms
Seismic exposure
Build in hardening or modify to improve equipment
resiliency
Geomagnetic storms
Effects of geomagnetic storms on power transformers
Impact of transformer reaction on the grid
Ability to quickly recover from major damage
-
ABBSlide 20July 24, 2015
Protect your grid to minimize downtimeA layered approach for power equipment
1. Assess the asset risk to natural and physical disturbances
2. Harden equipment against extreme environments
3. Monitor the asset and surroundings and automate response
to abnormalities
4. Rapidly repair lightly damaged equipment
5. Rapidly replace severely damaged equipment
Strategy must flex to address a diversity of failure modes
Assess risk, harden, monitor, automate, rapidly repair or replace
-
ABBSlide 21July 24, 2015
Harden (new designs or modify existing equipment)Example: relocation of key equipment to less vulnerable locations
-
ABBSlide 22July 24, 2015
Harden (new designs or modify existing equipment)
Solid (oil free) construction reduces risk of fire
Non-porcelain shed minimizes possible damage to people
and equipment and increases resiliency to contamination
High-seismic zone rated
Take advantage of material advancements, such as dry bushings (and porcelain-free arresters)
-
ABBSlide 23July 24, 2015
Hardening has its limitations must prepare for rapid repair or replacement of damaged equipmentTrain personnel for rapid recovery
1. Develop trained rapid response teams
2. Response team has access to standardized spare parts &
systems designed for rapid installation
3. Emergency response for storms or disasters with pre-
established order process to expedite reaction
4. Coordinated training with federal, state and local first
responders
1. Focus on field safety performance
2. Familiarization with tools and equipment
3. Technical support for Fusion Center
5. Include transportation logistics supporting move of large
equipment to critical locations
6. Consider a life-cycle support process
-
ABBSlide 24July 24, 2015
Geomagnetic disturbance (GMD)
Strong solar flare activities => Sends plasma beams to earth
Changes the magnetic field of Earth => GMD
By NASA
-
ABBSlide 25July 24, 2015
Change of earths magnetic field => Voltage in transmission circuits
Transmission line / Power
transformers / Ground
Fraction of a volt to several volts/km
Ground currents flow into neutrals of
power transformers
Magnitude of GIC in a transmission
circuit is a function of:
Magnitude & orientation of GMD,
location on earth, proximity to large
bodies of water, resistance of the
soil, & direction / height / length of
the transmission line
Highest for > 500 kV transmission
K Scale
Mechanism of generation of Geomagnetically Induced Currents (GIC)
-
ABBSlide 26July 24, 2015
Non linearity of the core material limits core from fully
saturating
DC causes part cycle saturation of the core
-
ABBSlide 27July 24, 2015
% Imag of 1 phase Transformer under effect of DC
Per Phase Currents
High Peak pulseOne per Cycle
Small mean width1/8th 1/12th of Cycle
RMS = 15 20 % of peak
-
ABBSlide 28July 24, 2015
VAR consumption vs. magnitude of GIC
Utilities use this data to plan their VAR resources during GMD events
0
5
10
15
20
25
30
35
40
45
50
0 50 100 150 200 250 300 350 400
% M
VA R
atin
g
GIC, Amps/Phase
-
ABBSlide 29July 24, 2015
0%
1%
2%
3%
4%
5%
6%
60 120 180 240 300 360 420 480 540 600 660
% H
arm
on
ic A
mp
litu
de (
% o
f R
ate
d L
oad
Cu
rren
t)
Harmonic Frequency, Hz
Harmonic Spectrum of Magnetizing Current under different levels of GICs
Idc = 25 Amps/Phase
Idc = 50 Amps/Phase
Current harmonics associated with DC / GIC
Utilities use this data to optimize protection during GMD events
-
ABBSlide 30July 24, 2015
-40
-30
-20
-10
0
10
20
30
40
50
GIC
, Am
psA
DC
Low / moderate magnitudes of GIC
sustained for several hours;
interrupted by short duration / high peak pulses
7 hr signature of GIC
Signature / profile of GIC
-
ABBSlide 31July 24, 2015
Winding Hot Spot Temperature vs Time, 1-Phase Transformer
108
110
112
114
116
118
120
122
124
0 5 10 15 20 25 30
Time, Minutes
Wdg H
ot S
pot Tem
pt, D
egre
e C
Idc = 50 Amps
Idc = 30 Amps
Idc = 20 Amps
Effect of GIC on winding hot spot temperature
Actual temperature rise is much lower for the short duration of high GIC peaks
For a 2 minute duration: Rise is 3, 4, and 6 C for GIC of 20, 30, and 50 Amps
-
ABBSlide 32July 24, 2015
Evaluation of total susceptibility of transformers to effects of GIC
To determine which transformers:
Are susceptible to damaging overheating
Are susceptible to core saturation and only moderate
overheating
Have low level of susceptibility to either effects of GIC
Are not susceptible to effects of GIC
Total susceptibility to effects of GIC is determined by:
Transformer design based susceptibility
GIC level based susceptibility
-
ABBSlide 33July 24, 2015
Results of GIC susceptibility study on large power transformer fleet > 500 kV
Orange: Susceptible to both core saturation and possible damaging winding and/or structural
parts overheating
Yellow: Susceptible to core saturation and only moderate overheating
Green: Low susceptibility to both core saturation and overheating
Blue: Not susceptible to core saturation or overheating
-
ABBSlide 34July 24, 2015
FERC Order 779
In May 2013, FERC issued
Order 779 which directs
NERC to submit reliability
standards that address the
impact of GMD on the
reliable operation of the
bulk-power system
Stage 1 operating procedures
Stage 2 detailed assessments (planning
studies)
Standards project 2013-03
(GMD mitigation) began in
June 2013
-
ABBSlide 35July 24, 2015
TPL 007 summary
Requires a GMD Vulnerability Assessment of the system
for its ability to withstand a benchmark GMD event without
causing a wide area blackout, voltage collapse, or damage
to transformers, once every five years. Applicability:
Planning Coordinators, Transmission Planners
Requires a Transformer thermal impact assessment to
ensure that all high-side, wye grounded transformers
connected at 200kV or higher will not overheat based on
the Benchmark GMD Event. Applicability: Generator
Owners, Transmission Owners
-
ABBSlide 36July 24, 2015
GIC effects
-
ABBSlide 37July 24, 2015
Studies needed for GIC concerns
Geo-electric field determination
DC system modeling
GIC calculation
Calculation of transformer reactive power absorption and
harmonics
Planning type studies with added reactive power
absorption, considering contingencies.
Conduct harmonics studies and determine the effects
Identify limit violations and system issues
Conduct thermal assessment of a portion of transformer
fleet
Determine mitigations and study their effects
-
ABBSlide 39July 24, 2015
Emergency Storm Response Program
Program focuses on power products and services for substations
HV breakers and equipment, MV switchgear and equipment, power transformers
Types of support - personnel and equipment
Proactive - preplanned program for disaster support
Research vendors now and set up blanket PO (in advance of storms) for defined
responsibilities: scope of work, work locations, manpower requirements, equipment
requirements, timing
Assessments, hardening
Reactive just had an unexpected disaster - need help now
Work with vendors that have a quick PO, standard terms and conditions of sale
Look for OEMs who have the drawings and schematics
Look for vendors with full coverage areas and a network of resources
-
ABBSlide 40July 24, 2015
First responders
Advance team to perform initial
assessment of substations to quickly
identify rough work scope required
What are the priorities
Quick-fix versus fully restore
Outage restoration priority changes
-
ABBSlide 41July 24, 2015
Initial assessments
Flooding of control cabinets as shown in a control relay from
an 115 kV SF6 circuit breaker control cabinet
-
ABBSlide 42July 24, 2015
Success story SuperStorm Sandy
Reactive Quick PO with major NE utility
Quick to site 1 day for first responders
Team came in right after approximately 100 techs within 2 weeks as need dictated.
Initial focus get people back on-line Band-Aids
Work scope
Substation overhauls (13 substations)
Transformers, HV breakers, and MV switchgear
Cleaning, testing, repairs, replacements
Replacement breakers and components
(surplus / used market)
-
ABBSlide 43July 24, 2015
Rapid response exampleRecovery Transformer (RecX) Program
Began before 9/11 with EPRIs Infrastructure Security Initiative (ISI)
ABB was asked to examine feasibility of a
fast-to-install transformer design
DHS became involved after the project
created a
-
ABBSlide 44July 24, 2015
Versatile recovery transformer RecX Project
Mobile transformers are not a new concept, but have traditionally been limited to
less than 100 MVA and 230 kV
Challenges and limitations
Why are they limited?
Large power drives physical size
Heavy weights (hundreds of tons)
Transportation difficulties
Inability to fit equipment into complex
site locations
-
ABBSlide 45July 24, 2015
Versatile recovery transformer RecX Program
How can we overcome these limitations?
Size and Weight
Separate into single-phase units
Distributes weight
High temperature
insulation
Reduces weight
Longer lifetime
Higher overload capacity
Transportation
Shipment via truck
Rapid delivery to
site
Flexibility
Transformer mounted on steel frame
Easy lifting and setting
Acts as transformer
pad
Remote cooling system
Flex connections, easy to place
-
ABBSlide 46July 24, 2015
Recovery Transformer (RecX) ProgramRapid deployment using truck transportation
-
ABBSlide 47July 24, 2015
Recovery Transformer (RecX) ProgramRapid deployment Assembly using pre-configured subassemblies
-
ABBSlide 48July 24, 2015
Recovery Transformer (RecX) ProgramRapid deployment Storage to energization: 5 days, 10 hours, 10 minutes (no overtime)
-
ABBSlide 49July 24, 2015
Outage Lifecycle Management Enabled Storm Preparedness
Parag Parikh,Industry Solution Executive, Power Systems Network Management, ABB Enterprise Software
-
ABBSlide 50July 24, 2015
Challenges of grid reliability & resiliencyThe main historical issues have remained the same
Regulatorycompliance
OPEX + CAPEX management
Customer engagement
Reliability
Health & safety
Operational complexities
-
ABBSlide 51July 24, 2015
Super storm Sandy constituted a strategic surprise for me and much of the
Department of Defense. Paul Stockton
Difficult logistics and poor
communication between utilities,
defense officials, state planners and first
responders.
Inadequate communication to
customers, inadequate planning in
vulnerable areas, poor visibility on the
grid.
Lack of attention on future black sky events worse than Sandy.
Super stormsA Strategic Surprise for the Power Sector
-
ABBSlide 52July 24, 2015
Changing the game from Centralized to Distributed Grid
Centralized generation
One-directional power flow
Generation follows load
Top-down operations planning
Centralized and distributed generation
Intermittent renewable generation
Multi-directional power flow
Operation based on real-time data
Demand Response for economics and reliability
TRADITIONAL GRID
DISTRIBUTED GRID
Outage Lifecycle Mgmt;
OMS, Mobile, Analytics
PV Solar complete
Panel-to-Grid solutionsDistribution SCADATransformersReclosers & SwitchesWireless Infrastructure
Asset Health
Energy Management
EMS SCADAMarket Operations
-
ABBSlide 53July 24, 2015
Storm Preparedness Opportunities for Improvement
5 of 6 major New York IOUs cited
for inadequate communications
capabilities during Sandy.
During overtime workers typically
make between 200% and 300% of
average hourly base salary.
AutomationRegulatory innovation
Reducing OvertimeImproving Outage Communications
Fault Location to identify fault
location
FLISR to reduce impact of an
outage
Damage Assessment
automation to improve ETR
and Restoration Plans
-
ABBSlide 54July 24, 2015
Evolution of Outage Lifecycle
Integrated Outage Management
Event Management
Outage Management System
Proactive Distribution
Management
Mobile Workforce Management
Asset Health Management
Organizational Visibility
Enterprise Asset Management
Enterprise Resource Planning
Outage Management 2.0
Outage Management 1.0
Historical
-
ABBSlide 55July 24, 2015
Optimizing the Outage Lifecycle
Connecting the Pieces
Outage Management System
Distribution Management System
SCADA
Distribution Automation
Mobile Workforce Management
AVL
AMI
DERMS
EAM/ERP
GIS
CIS/CRM
IVR
Grid Analytics
External Communications
-
ABBSlide 56July 24, 2015
The lifecycle of an outage
Prediction + Preparation
Schedule and prioritize resources and keep
stakeholders informed
Assessment + Restoration
Isolate, auto restore , deploy right crew to safely and efficiently restore remaining customers while keeping stakeholders informed
Repair + Closeout
Compliance, reporting and review helps build plan for next outage
PlanningForecast, plan and prepare resources with full visibility
and scenario-based planning
1
2
3
4
OLM
-
ABBSlide 57July 24, 2015
Outage Lifecycle ManagementStorm Preparedness
Planning
Library of storm models What-if analysis Customer notification preferences Asset Health Solution enabled asset review
Prepare
Projection model for impeding storm Assess resource needs and location Prepare for mutual assistance call outs and on-boarding
Assess & Restore
Damage Assessment and Outage Analysis Enable self-healing whenever possible Prioritize work and dispatch crew Notify stakeholder
Closeout
Post event analysis and reports to identify crew work, outage areas and issues
Build data for future preparation, planning and grid hardening tasks
-
ABBSlide 58July 24, 2015
Advanced Distribution Management System
Common Network Model and Training Simulator
Data Historian & Business Analytics
SCADA
Communication Infrastructure
Field Devices DA Devices, Sensors and DER
OMS Applications Trouble Call Management
Outage Analysis
Operations Management
Crew Management
Referral Work Orders
Switch Order Management
DMS Applications Load Flow Analysis
Short Circuit Analysis
Fault Detection and Location
Automated Switching
Overload Reduction Switching
Volt/VAR Optimization
Enterprise
Integration
GIS
AVL
IVR
AMI/MDM
Data Acquisition
Monitoring & Event Processing
Supervisory Control & Interlocking
Data Archiving
Calculation & Reports
Human Machine Interaction
Inter-Center Communication
Communication Front-Ends (Protocol Conversion)
Common Operator Graphical User InterfaceEnterprise IT Systems
CIS
ABB Outage Lifecycle Management & Grid Optimization Solution
Mobile Workforce
ManagementAsset & Work
Management
DRMS &
DERMS
IT/O
T C
onverg
ence
Asset Health Center
-
ABBSlide 59July 24, 2015
Uses all available real-time and
historical data on assets
Online monitoring/sensors
SCADA/historian
Inspections and testing
Work orders
Risk of failure and criticality is
continuously assessed
Current picture of asset health
always available especially during storm planning and preparation
Drives optimal storm planning and
maintenance decisions
Storm PreparednessAsset Health - Risk of Failure and Criticality
Location
-
ABBSlide 60July 24, 2015
Storm Preparedness & RecoveryAdvanced Distribution Management System
Assess
System StateSystem
AnalysisSystem
Reliability
System
Restoration
Outage
Analysis
FLISR
Load Transfer
Outage
prediction and
ETR generation
Real-time power
flow analysis to
improve
confidence in
Switching
decisions
Real-Time
Analysis
Crew
Dispatch
Restoration
Switching Plans
ETR Updates
Cold-load Pickup
Manage field
activities
Normalize feeder
configuration
Customer
Notification
Fault Location
calculation
Self-healing Automatic
Switching
Minimize outage
impact
Reliability
Improvement
Prepare system
planning and
reliability
enhancement
studies
Compare actual
operational actions
against simulated
scenario
Restoration
Switching
Operational
Preparedness
Validate and
plan system
control actions
Save simulation
for contingency
planning
Balance load
Prepare switch
order template
Improve grid
resiliency
System
Planning
Simulation
Case Studies
-
ABBSlide 61July 24, 2015
Storm RecoveryDamage Assessment & ETR
Assessment Information
ID: 32
Area: West
Lat, Long: 41.876789, -
71.3996124
Date Assessed: 08/26/13 3:04
PM
Assessment Details
Assessor Name: Tom Hill
Hazard Level: High
Equipment: Poles / Lines
Customers: 5
Critical: 1
Emergency Onsite: Yes
Work: Replace 3 poles. Click here to enlarge
Move lines.
-
ABBSlide 62July 24, 2015
Provide accurate and consistent and
timely outage communications to
internal and external stakeholders
Increase customer satisfaction
Increase situational awareness
Support multiple communications
channels (text, smartphone, web, etc.)
Storm RecoveryOutage Communication
Source: ComEd
-
ABBSlide 63July 24, 2015
Storm Preparedness & RecoveryOutage Lifecycle Management Benefits
Ensure compliance with regulatory requirements with
full audit trail throughout the event.
Same tools to be followed in blue sky days and major
events
Improves situational awareness, in the control room, out
in the field and across the organization
Improved resource planning that saves time and money
Common data across platform ensures accurate data is
communicated to stakeholder and customers
Reduced outage duration and improved reliability
leading to improved customer satisfaction
-
ABBSlide 65July 24, 2015
Register todayDont miss these educational webinars
ABB PowerED power education series
Saving lives through arc flash mitigation: Leveraging technology to improve
safety and reliability
Sept 22 at 1-2 pm EDT
https://attendee.gotowebinar.com/register/174811720747498497
How secure is your substation? Physical security (Part I) - 3 strategic elements
to protect your assets
Oct 16 2-3 pm
https://attendee.gotowebinar.com/register/4569042926504925441
It's not a matter of if, but when: Physical security (Part II) - Strategies for
recovery and repair
Oct 28 1-2 pm EDT
https://attendee.gotowebinar.com/register/1694434646917646594
Smart grid optimization series sponsored by ABBs Smart Grid Center of Excellence