abb-318-wpo field or factory testing-transformer pd testing at site
TRANSCRIPT
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 1/67
© ABB Inc.May 10, 2012 | Slide 1
E397G & E408GField or Factory Testing- TransformerPD testing at Site
ABB Automation & Power World: April 23-26, 2012
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 2/67
© ABB Inc.May 10, 2012 | Slide 2
E397G & E408GField or Factory Testing- Transformer PD testing at Site
Speaker name: Dr. Poorvi Patel
Speaker title: Manager, TRES EngineeringSolutions
Company name: ABB INC
Location: St. Louis, MO
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 3/67
Content
Why Test a Transformer
Typical Factory Testing
Testing in Field
Induced Testing
Case picture
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 4/67
Why Test Transformers?Part of Manufacturers QA Process
Verifies Design Criteria
Losses, Clearances, Impedances, BIL Rating, Impulse Withstand, Thermal Design,Insulation System Design, etc.
Verifies Manufacturing Criteria
Windings, Insulation System Assembly, Core Building, Processing, Accessories, CoolingSystem, etc.
Verification of Standards CriteriaIEEE/ANSI, IEC, CSA, etc.
Verification of Customer Requirements
Special Loading Capability
Dielectric Withstand Additional Operational Characteristics
Special Requirements
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 5/67
Actual Tested Values Product Quality Indicators
Review Tested Values of Performance Parameters verses CalculatedIncludes Winding Resistance, No-load losses, Exciting current, Load losses, Impedance, Soundlevel, and Temperature measurements
Agreement between calculated and measured values confirm the qualityof design, material, manufacturing, and testing
Hence, availability of calculated values for transformer performance parameters prior to the timeof test is recommended
Significant deviations between calculated and measured values couldindicate quality issue(s) and will need to be discussed with the
manufacturer
Tolerances, for different performance parameters which are not specified byIEEE C57.12.00 should be agreed upon with the manufacturer before the order isplaced
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 6/67
Types of Tests- Factory
Preliminary Tests (Low Voltage Tests)- screening of the assembyVoltage/Turns Ratio, Polarity, and Phase Displacement
Winding Resistance
LTC Tests (If Applicable)
Wiring Tests including Current Transformers
Performance Tests (Normal Voltage Tests) – verify if the TFO meets the spec
No-load and Load Loss Measurements, Impedance, etc.Cooling Losses
Temperature Rise
Sound Tests (Load & No-load)
Dielectric Tests (Above Normal Voltage Tests)- Verify the designPower Factor, Capacitance and Insulation Resistance
Typically performed with preliminary tests
Impulse Testing (Lightning and Switching)
Applied Tests
Induced Test with PD
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 7/67
Types of Tests (cont.) -Factory
Advanced Tests (Condition Assessment)
Frequency Response Analysis (FRA)
Dielectric Frequency Response (DR)
Acoustic Tests (Sonic)
Advanced PD Analysis
Test SequenceExtent of testing depends on size and voltage class as defined by ANSI standards
Class 1 <= 69 kV
Class II > 69 kV
Exact test sequences are not fully covered by standards
Follow IEEE and IEC Standard recommendations where practical
Final test sequence should be agreed to by both parties
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 8/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 9/67
Field Testing Power Transformers - On the Rail Car orTruck
Receiving Inspection And Tests
Visual Inspection
Look for visible dent, damage, or touchup paint
Dry air pressure in the transformer tank
Impact Recorder Tape reviewHorizontal, Vertical, Longitudinal
Dew Point (Internal pressure ≈ 3.5 psi) ABB acceptance limit is 0.8% surface moisture
What about 0.5% moisture?
Core Megger1000 VDC must be 100 Meg Ohms or better
Contact OEM if Lower
SFRA- Sweep Frequency Analysis
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 10/67
Final Testing After completing the assembly and oil filling operations, finalelectrical and oil tests should be conducted.
Electrical tests include:Power factor and capacitance of windings and bushings
Maximum of .5% PF
Winding excitation test
Insulation resistance (megger)Minimum of 1000 Mohms at 100V
Winding resistance
±2% phase-to-phase variation and compare to factory values
Controls checks and calibration of temperature devicesCT ratio and polarity
Transformer Turns Ratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 11/67
Insulation Power Factor & Capacitance
MethodInsulation power factor bridge is used to measure power factor andcapacitance of winding insulation and bushings. Test voltage is typically 10 kV(max Voltage) for windings and for bushings it is determined by the bushingdesign and construction. Readings are corrected to standard temperature.Testing is highly susceptible to temperature, humidity and contamination.
WhyCheck the condition of the transformer or bushing insulation. TypicallyPF should be ≤ 0.5%. Higher PF may be due to moisture or foreigncontamination in the insulation structure or excessive contamination tobushing surfaces.
Acceptance criteria ANSI power factor limit for bushings is .5% when corrected to 20°C. ABBrecommends that the readings be compared to nameplate values. Bushingsshould be replaced when the measured power factor doubles the nameplatevalue or capacitance is in excess of 110% of the nameplate value.
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 12/67
HV Cable
Guard LV Test Lead
ApparatusGround
Ground Lead
mA & W
Test Mode: UST
C1 Test Includes
•Core insulationbetween centerconductor andtapped layer.
C1 %PF is temperaturecorrected to 20 °C
using the average ofthe apparatus andambient temperature.
Connection toParent Apparatus
Insulation Power Factor & Capacitance-Bushings
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 13/67
Electrical Tests (Low Voltage Tests) when transformer is notfilled with oil.
Power Factor and capacitance of the bushings before installing intothe transformer (if applicable) Note: Bushings that are in cratesor laying down test results may not match the nameplate values.(Some problems usually are: bad ground, crates draw moisture,straps may effect the readings.)
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 14/67
Final Testing- After completing the assembly and oil filling operations, finalelectrical and oil tests should be conducted
Electrical tests include:
Power factor and capacitance of windings and bushings
Maximum of .5% PF
Winding excitation test
Insulation resistance (megger)
Minimum of 1000 Mohms at 100V
Winding resistance
±2% phase-to-phase variation and compare to factory values
Controls checks and calibration of temperature devices
CT ratio and polarity
Transformer Turns Ratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 15/67
Winding Excitation
Method
Voltage source is applied to winding and exciting current is measured.Test is most often done with power factor bridge test set at 10 kV.Residual magnetism greatly effects readings. Demagnetization ofcored may be required for acceptable results.
WhyMaintenance test generally recognized to detect any changes in themagnetic circuit.
Acceptance criteria
This is a repeat test. All subsequent tests are compared to originalbaseline test for indications of variance. Phase A and Phase C shouldbe close.
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 16/67
Final Testing- After completing the assembly and oil filling operations, finalelectrical and oil tests should be conducted
Electrical tests include:
Power factor and capacitance of windings and bushings
Maximum of .5% PF
Winding excitation test
Insulation resistance (megger)
Minimum of 1000 Mohms at 100V
Winding resistance
±2% phase-to-phase variation and compare to factory values
Controls checks and calibration of temperature devices
CT ratio and polarity
Transformer Turns Ratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 17/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 18/67
Core Resistance (Megger)
MethodUsing Megger instruments, 1000V is applied for one minute to coreground strap. Test is sensitive to temperature, moisture andcontamination. Some transformers may be constructed such that coreground strap is not accessible.
Why
Prove insulation integrity of core from ground potential and test forinadvertent core grounds.
Acceptance criteria
Minimum acceptance criteria is ≥2000 megaohms when corrected to20°C
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 19/67
Final Testing- After completing the assembly and oil filling operations, finalelectrical and oil tests should be conducted
Electrical tests include:
Power factor and capacitance of windings and bushings
Maximum of .5% PF
Winding excitation test
Insulation resistance (megger)
Minimum of 1000 Mohms at 100V
Winding resistance
±2% phase-to-phase variation and compare to factory values
Controls checks and calibration of temperature devices
CT ratio and polarity
Transformer Turns Ratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 20/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 21/67
Final Testing- After completing the assembly and oil filling operations, finalelectrical and oil tests should be conducted
Electrical tests include:
Power factor and capacitance of windings and bushings
Maximum of .5% PF
Winding excitation test
Insulation resistance (megger)
Minimum of 1000 Mohms at 100V
Winding resistance
±2% phase-to-phase variation and compare to factory values
Controls checks and calibration of temperature devices
CT ratio and polarity
Transformer Turns Ratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 22/67
Current Transformer Ratio, Polarity
MethodRatio can be verified either by primary current injection or secondaryvoltage injection. Polarity is verified by battery polarization orbuck/boost circuits.
WhyVerify proper ratio and polarity of current transformers.
Acceptance criteriaVaried depending on relay accuracy and burden rating of the CT.
Generally ± 1% of calculated ratio.
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 23/67
Final Testing- After completing the assembly and oil filling operations, finalelectrical and oil tests should be conducted
Electrical tests include:
Power factor and capacitance of windings and bushings
Maximum of .5% PF
Winding excitation test
Insulation resistance (megger)
Minimum of 1000 Mohms at 100V
Winding resistance
±2% phase-to-phase variation and compare to factory values
Controls checks and calibration of temperature devices
CT ratio and polarity
Transformer Turns Ratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 24/67
Transformer Turns Ratio
Method
Tests are conducted using low voltage ratio bridge or three phasepower supply and voltmeters. Voltage is applied to the primarywinding and the voltage is measured on a secondary winding. Test isconducted at all tap positions. Ratio is calculated in accordance withnameplate values.
WhyTest is done to verify all internal connections and windingconfigurations are correct
Acceptance criteria
ANSI limits that are measured ratio must be ±0.5% of calculated voltageratio
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 25/67
Advanced Testing in the field
Dielectric Frequency Response- DFR
Sweep Frequency Response Analysis- SFRA
HV-testing in the field
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 26/67
Advanced Testing in the field
Dielectric Frequency Response- DFR
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 27/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 28/67
Dielectric Frequency Response
60 Hz1 mHz 1 kHz
Frequency (Hz)
Powerfactor
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 29/67
Dielectric Response of Power Transformers
Off-line diagnostics
Oil and cellulose insulation system
Dielectric properties are strongly affected bymoisture and ageing.
Dielectric response measurements can beused for diagnostic purposes.
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 30/67
Why Dielectric Response
Purpose of measurement
Diagnostic test of insulation systemMoisture content
Oil Conductivity
Diagnose defects in systemDiagnose high PF or tan
Contamination
Carbon Tracking
Resistance in core ground circuit
Quality control test of Factory and/or Field processing
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 31/67
Power Products where DFR is used
Transformer diagnostics
Power TransformersTransformer Bushings
Instrument Transformers
Cable diagnostics
XLPE cables
Oil/paper cables
Manufacturing controlling system
Trouble shooting electrical apparatus
Material chacterization
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 32/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 33/67
Advanced Testing in the field
Sweep Frequency Response Analysis- SFRA
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 34/67
What is FRA?
FRA means: Frequency Response Analysis
FRA is : “An off -line, non- destructive diagnostic technique”
FRA shows: Spectrum changes mechanical deformation
FRA is: Comparative method (two spectra are compared)
FRA is: Measurement of electrical response(from 10 Hz to 2 MHz or more).
FRA can detect mechanicalproblems without opening thetransformer.
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 35/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 36/67
When should we perform FRA?
Prevention:
After manufacturingFingerprint measurement
Create first reference
As part of a routine diagnostic protocolTo check for changes during service time
After installation or relocationTo check for transformer integrity
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 37/67
When should we perform FRA?
High probability of mechanical movements:
After unusual disturbance during shipmentTo check for damages in the active part
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 38/67
When should we perform FRA?
Diagnostic purposes:
After a major change in on-line diagnostic condition
After a transformer alarm
After a significant through-fault event
After external failures compromising the transformer condition(short circuits, close lightning impact, ...)
To compare with a sister unit in troubles
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 39/67
Typical results: FRA frequency ranges
Core influence
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 40/67
Typical results: FRA frequency ranges
Winding influence
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 41/67
Typical results: FRA frequency ranges
Leads, grounding influence
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 42/67
Advanced Testing in the field
HV-testing in the field
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 43/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 44/67
Reasons for Field Induced Test
After installation of critical HV transformers such as 500-kV
or 765-kV unitsWhen PD is indicated by DGA results (higher levels ofHydrogen gas)
When unusual sparking or popping sounds are heard frominside the unit
When oil results show corrosive sulfur or any othercontamination
After field repairs or internal inspections where the insulationis disturbed
To help determine the suitability for continued service orreplacement on older critical units such as generatortransformers at nuclear power plants
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 45/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 46/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 47/67
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 48/67
Transformer being set up for testing
Lift Vehicle
Bushing Shields
Good Weather ?
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 49/67
HV Cable Connections
Connection to HV Divider Connection to LV Bushing
d f
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 50/67
Adaption Transformer Connections
i b hi
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 51/67
PD connections to bushing tap
Connection to Bushing TapInput Quadrupole and
preamplifier
PD i i il
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 52/67
PD connections in test trailer
Computer PD Control Panel9 Channel ICM PD instrument
S d C lib i f PD
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 53/67
Setup and Calibration for PD
Connect Quadrupole and Preamplifier to HV bushingtaps
Windings rated 115-kV and above
Connect PD Calibrator to one Bushing
Inject 500-pC into Bushing Terminal
Use Spectrum Analyzer to locate minimum noiseband
Calibrate each PD Channel
Make Cross-calibration for other phases
Store calibration settings for report
S A l f N i R j i
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 54/67
Spectrum Analyzer for Noise Rejection
PD signal from Calibrator
Noise Signal
Band with best signalto noise ratio
CF
BW
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 55/67
PD M t Di l
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 56/67
PD Measurement Display
PD recording for
report
Continuous readout of PD
PD P tt Di l
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 57/67
PD Pattern Display
T i l tt f N2 b bbl i i di g
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 58/67
Typical pattern for N2 bubbles in winding
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 59/67
Conclusions
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 60/67
Conclusions
Field Induced test is an important diagnostictoolWhen the condition of the transformer issuspect
For Critical applicationsHigh Voltage Transformers (> 345 kV)
Important GSU Transformers
Transformers feeding critical loads
HVTMS standard of accuracy and safety
Tests that can be done with the HVTMS
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 61/67
Tests that can be done with the HVTMS
Induced Test with PD measurement
Applied test up to 500-kVNo-load loss test at rated frequency
Extended 110% voltage “gassing” test
Load loss test at rated frequency *
Temperature test (heat-run test)*
Extended load “gassing” test*
ABB can perform complete set of ANSI tests after on-siterepairs
* May require high MVAR capacitor bank trailer
Life Extension Options and Considerations
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 62/67
Life Extension Options and Considerations Verification: High Voltage Impulse Testing
Mobile Impulse Generator
Lightning impulse test up to 1800 kV
Switching impulse test up to 1300 kV
When required, failure localization during LI / SI test
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 63/67
Cases
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 64/67
Cases
Contact information
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 65/67
© ABB Inc.May 10, 2012 | Slide 66
Contact information
If you have further questions , please contact me at:
PRESENTER Dr. Poorvi Patel
COMPANY ABB TRES, St. Louis
CONTACT PHONE (314)-679-4838 , (636)-328-6501
CONTACT E-MAIL [email protected]
Important reminders
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 66/67
© ABB Inc.May 10, 2012 | Slide 67
Important reminders Automation & Power World 2012
Please be sure to complete the workshop evaluation
Professional Development Hours (PDHs) andContinuing Education Credits (CEUs):
You will receive a link via e-mail to print
certificates for all the workshops you have attendedduring Automation & Power World 2012.
BE SURE YOU HAVE YOUR BADGE SCANNEDfor each workshop you attend. If you do not haveyour badge scanned you will not be able to obtainPDHs or CEUs credentials.
8/12/2019 ABB-318-WPO Field or Factory Testing-Transformer PD Testing at Site
http://slidepdf.com/reader/full/abb-318-wpo-field-or-factory-testing-transformer-pd-testing-at-site 67/67