a4 presentation
TRANSCRIPT
• Huan Leng Chan
• Steven Cowie
• Russell Jackson
• Adam Ledger
• Ahsan Muhammad
• Oyindamola Ogunnoiki
• Oliver Peck
• Panteha Toloueinia
• Ali Youssefi
• Feature building at North end of site•Close to staff entrance•Services in place from old offices•Away from A47 road, so not noisy
• Temporary offices sited on grass area, so as not to obstruct car park or site traffic access
• CHP located in East of site, by existing unit•Can share resources between the units•Easy to connect to network, as pipe work is close by
•Effluent treatment works, consisting of 5 tanks, arranged in a horseshoe at south end of site
•As far from residential area and office/design centre building as possible (no potential smell or airborne particles)•Arranged in horseshoe shape so access for repairs etc is easier.
• Mixture of angles and curves, intended to make the building appear aesthetically eye-catching
• Low gradient roof over single story section, intended for grass to be planted – eye-catching, improved heat retention properties and reduced heat island effects
• Designed to allow lots of natural light into the design centre and open plan offices.
• Dynamic glass to limit glare• Controllable vents to make use of natural ventilation for
cooling• 2 leaf cavity wall with insulation in cavity to retain heat• Inner wall is blockwork• Outer wall is brickwork, with the front clad with wood for
aesthetics
• Open plan office area and design centre area, intended to minimize dependence on electrical lighting - Building orientation is based around these areas getting the most light
• Only rooms that don’t have direct access to natural light are supply cupboards and toilets – Electrical lighting in these rooms will be on movement sensors to minimize unneccesary energy consumption
• Steel beam with concrete slab flooring construction
• Braced where indicated by shading. Lift shaft also designed to brace against horizontal loadings
Feature Building Beam/Column Calculations
• Critical beam identified as E3-E4• Beam span at critical section is 8m• Critical beam size calculated as
762 x 267 x 173 kg/m
• Critical column identified as E4• Critical column size calculated as
203 x 203 x 71 kg/m
Foundations
Building Type of foundation
Size (B x L) (m)
Depth of foundation (m)
Number of foundations
Feature building
Shallow – Rectangular pad
2.5 x 2.0 2.0 30
CHP Shallow – Square pad
2.0 x 2.0 1.0 4
CHP building
Shallow – Square pad
1.5 x 1.5 1.5 6
Effluent treatment tank (critical)
Deep – Pile 0.3 x 0.3 10 16
Approximate Costing – Feature building
Types
Cost per unit area, excluding VAT (£/m2)
Cost, excluding VAT (£)
Minimum Maximum Minimum Maximum
Economic shell and core with heating only
466 820 738,144 1,298,880
Medium shell with heating and ventilation
728 1082 1,153,152 1,713,888
High quality shell and core with air conditioning
958 1746 1,517,472 2,765,664
Approximate Costing - Foundations
TypesType of
foundation
Cost per unit area, excluding VAT (£/m2)
Cost, excluding VAT (£)
Minimum Maximum Minimum Maximum
Feature building Rectangular pad 103 138 103,824 139,104
CHP Square pad 93 112 2,260 2,722
CHP building Square pad 93 112 6,975 8,400
-Deep foundation
TypesType of
foundation
Cost per unit area, excluding VAT (£/m2)
Cost, excluding VAT (£)
Minimum Maximum Minimum Maximum
Effluent treatment tank Deep pile 153 215 12,393 17,415
-Shallow foundation
Effluent Treatment
Objective:Design and cost for the provision of an onsite effluent treatment facility to reduce treatment costs charged by the water authority, with the potential to create a useable energy stream.
Cost Reduction
Aims
– reduce cost by
• reducing the COD and BOD discharged to the sewer system.
• collect the waste products of the process for use in the CHP plant.
The ConceptProposed System -
Preliminary Treatment – Equalisation tank
Primary Treatment – Sedimentation tank
Secondary Treatment – Upflow Anaerobic Sludge Blanket Reactor (UASB)
Other Equipment – Biogas Scrubber, Anaerobic Digester, Centrifuge
Results
From mass balance it can be deduced that the following reductions can be made:
TSS removal 84.34 %
BOD removal 87.35 %
COD removal 84.39 %
With the production of 2.88MWhr-1
Costs
Total investment required = £4,461,964Annual Saving = £2,615,762Adjusting for inflation gives a payback period of 23 months
Combined Heat and Power
Requirements:
• 4 MWhr of electricity
• 25 tonnes/hr of steam at 183°C and 7 bar
Comparison
Combined Cycle
Gas Turbine Steam Turbine
Capital Cost(£ x 106)
1.7 – 2.2 1.2 – 1.3 2 -2.4
Operation and Maintenance Cost(£ / year)
170000 84000 90000
Efficiency(%)
80 35 50
Advantages
High reliability and availabilityEase of installationFlexibility to meet different fuel needsEase of serviceLow maintenance requirementsCleaner environmental emissionsLower capital cost than combined cycle and steam CHPs
Disadvantages
Cause a lot of noise and vibrations
Lower efficiency
Maintenance requires trained and
knowledgeable workers
Cost
Capital Cost (£) 3.55 million
Operating and Maintenance Cost (£/year)
160000
Fuel Cost (£/year) 3.6 million
Cost of Power Generated (£/year) 2 million
Annual Saving (£) 1.4 million