a1 leeming to barton - highways...
TRANSCRIPT
March 2016
A1 Leeming to Barton Improvement
We’re upgrading a 12 mile section of the A1 between Leeming and Barton – widening it from dual carriageway to a three lane motorway. This £380 million investment started in 2014 and is around half way to being completed. The project is being carried out by contractors Carillion Morgan Sindall JV on our behalf.
What’s happening in the Catterick area?
Over the coming few months, our activities around the Catterick South Junction will require some careful phased management of traffic routes. Work happening in this area will be critical to the successful completion of the A1 Leeming to Barton improvement scheme.
What will it involve?
At all times during the work, we will maintain access from the Catterick South Junction to Catterick and the wider local road network, using various temporary diversions until our work on the new A1(M) and the local access road and is completed.
For more information
If you have any questions about the work and traffic management around the Catterick South Junction, please contact our onsite project team, who will be happy to help you:
Email: [email protected]
Tel: 01677 932 300
Phase 1 – January to March 2016What will happen during this phase of work?
� During this phase, our work will focus on the construction of a new temporary slip road on to the northbound A1.
� We will also be undertaking temporary widening works around Catterick Lane.
© Crown copyright and database rights 2016Ordnance Survey 100030649
New A1
Existing A1
Existing A1
CAT
TER
ICK
LA
NE
LE
EM
ING
LA
NE
TUN
STA
LL R
OA
D
LOW
GR
EE
N
Catterick SouthJunction
CATTERICK
Phase 1January to March 2016 N
Road open
Road closed
Road underconstruction
Phase 2 – March – May 2016What will happen during this phase of work?
� Once the temporary connection is available to use as a route on to the new northbound A1, we will use a temporary one-way traffic arrangement on the Tunstall link road, and a short section of Tunstall Road.
� Works will be taking place on Tunstall Bridge and a temporary connection on to the new southbound A1.
© Crown copyright and database rights 2016Ordnance Survey 100030649
New A1
Existing A1
Existing A1
CAT
TER
ICK
LA
NE
LE
EM
ING
LA
NE
TUN
STA
LL R
OA
D
LOW
GR
EE
N
Catterick SouthJunction
CATTERICK
Phase 2March – May 2016 N
Road open
Road closed
One way
Road underconstruction
Crown copyright 2016.
You may re-use this information (not including logos) free of charge in any format or medium, under the terms of the Open Government Licence.To view this licence:visit www.nationalarchives.gov.uk/doc/open-government-licence/write to the Information Policy Team, The National Archives, Kew, London TW9 4DU, or email [email protected] document is also available on our website at www.gov.uk/highways
Phase 3 – May 2016What will happen during this phase of work?
� During this phase, a temporary section of road will be used to divert Catterick Lane around the new Tunstall Bridge.
© Crown copyright and database rights 2016Ordnance Survey 100030649
New A1
Existing A1
Existing A1
CAT
TER
ICK
LA
NE
LE
EM
ING
LA
NE
TUN
STA
LL R
OA
D
LOW
GR
EE
N
Catterick SouthJunction
CATTERICK
Phase 3May 2016 N
Road open
Road closed
One way
Road underconstruction
Phase 4 – May to July 2016What will happen during this phase of work?
� Once we have completed work to Tunstall Bridge, and it has been opened to traffic, we will be able to start excavating the old section of Catterick Lane.
� The old Tunstall Bridge will be also demolished at that point.
© Crown copyright and database rights 2016Ordnance Survey 100030649
New A1
Existing A1
Existing A1
CAT
TER
ICK
LA
NE
LE
EM
ING
LA
NE
TUN
STA
LL R
OA
D
LOW
GR
EE
N
Catterick SouthJunction
CATTERICK
Phase 4May to July 2016 N
Road open
Road closed
One way
Road underconstruction
If you have any enquiries about this publication email [email protected] or call 0300 123 5000*. Please quote the Highways England publications code PR181/15.Highways England Leeds creative job number N150602*Calls to 03 numbers cost no more than a national rate call to an 01 or 02 number and must count towards any inclusive minutes in the same way as 01 and 02 calls.These rules apply to calls from any type of line including mobile, BT, other fixed line or payphone. Calls may be recorded or monitored.Registered office Bridge House, 1 Walnut Tree Close, Guildford GU1 4LZ Highways England Company Limited registered in England and Wales number 09346363
Phase 5 – July to December 2016What will happen during this phase of work?
� During the summer, we will move traffic on to the new section of the A1 between Sowber Hill and Catterick central junction.
� A temporary connection will be installed so that access to Catterick, Tunstall, Hackforth and the surrounding villages is maintained.
� Work will then take place on the local access road.
© Crown copyright and database rights 2016Ordnance Survey 100030649
New A1
Existing A1
CAT
TER
ICK
LA
NE
LE
EM
ING
LA
NE
TUN
STA
LL R
OA
D
LOW
GR
EE
N
Catterick SouthJunction
CATTERICK
Phase 5July to December 2016 N
Road open
Road closed
One way
Road underconstruction Existing A1
“under construction”to Local Access Road
Phase 6 – early 2017What will happen during this phase of work?
� Once we have completed work to Tunstall Bridge, and it has been opened to traffic, we will be able to start excavating the old section of Catterick Lane.
� The old Tunstall Bridge will be also demolished at that point.
© Crown copyright and database rights 2016Ordnance Survey 100030649
New A1
Existing A1
Existing A1
CAT
TER
ICK
LA
NE
LE
EM
ING
LA
NE
TUN
STA
LL R
OA
D
LOW
GR
EE
N
Catterick SouthJunction
CATTERICK
Phase 6early 2017 N
Road open
Road closed
One way
Road underconstruction
Planned work dates may be subject to change due to unforeseen circumstances, such as poor weather conditions. Any changes will be notified nearer the time via our scheme web page (detailed below). You can also sign up to
receive email alerts, which will provide you with up to date information about our work.