A Year of Progress

June 2016

URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke

Page 2: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

2

What is U-Battery?

• A source of heat and

electricity installed at the

point of use – embedded

power

• For end users, it provides

a solution to their Energy

Trilemma

Page 3: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

U-Battery: Technology and Fuel

• Reactor Building footprint projected to be equivalent

to penalty area on soccer pitch.

• TRISO fuel was first developed in the UK and has a

long and successful history of development and

deployment. Discussions have taken place with

several international vendors including BWXT. TRISO

fuel provides damage resistance to temperatures of

1600˚C – well above worse case scenarios.

• This fuel type is at a high level of Technology

Readiness and underpins our safety case.3

• High Temperature Gas Reactor technology, with each

reactor rated at 10MW(th) & 4MW(e).

• Nearly 20% U-235 enriched accident tolerant TRISO

fuel, embedded within Prismatic Block type fuel.

• Helium primary coolant transferring heat via

intermediate heat exchanger to a nitrogen Closed

Brayton Cycle secondary.

• Reactor outlet temperature of 750˚C.

• Cycle efficiency of >40% when producing electricity

through gas turbine-alternator.

Page 4: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

4

Energy Requirements served

Page 5: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

5

TRISO TRL 9 - U-Battery TRL 2System

GroupSub-System / Major Equipment TRL

Primary

System

Reactor Pressure Vessel Medium

Core Mechanical Design Low

Primary Gas Duct Medium

Intermediate Heat Exchanger Medium

Primary Gas Circulator High

Secondary

System

Recuperator High

Pre-Cooler High

Power

Conversion

Systems

Gas Turbine Medium

Compressor(s) Medium

Intercooler(s) High

Alternator High

Start-Up Motor High

Tertiary

Systems

Cooling Tower(s) High

Tertiary Coolant Pumps High

System

GroupSub-System TRL

Auxiliary

Systems

Ancillary Cooling Systems Medium

Coolant Make-Up Systems Medium

Building Services High

Start-Up and Shutdown-Systems High

Fuel Route

Systems

Dry Store Cell(s) Medium

Flasking Facility Medium

Fuelling Machine Low

Flasks Medium

Reactor and Control Rod Servicing Equipment Low

Control and

Safety

Systems

Electronic Control System Medium

Control Room and Control Equipment Medium

Fire Detection and Suppression (FDS) Systems High

Building Security Systems High

Page 6: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

Members

Project Development

Leading Members Supporting Organisations

Page 7: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

Technical and Cost Development

• Overall U-Battery Conceptual Design

Review– Design updates to find and use existing transport flask,

Excellox not possible

– Review decision between BeO and graphite moderator

– Two single units or a twin reactor unit using a single

turbine/generator

• Product Breakdown Structure Delivered

• Cost Estimate Model Developed– Atkins/Faithful and Gould Cost Estimators

• Major Component Conceptual Design

Delivered– Reactor Pressure Vessel

– Intermediate Heat Exchanger

• Interaction with partners and Tier 1

supply chain to deliver cost estimate

7

Page 8: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

8

The markets and applications vary by country.

• In UK and many other countries, the market is

for embedded generation at industrial sites.

Many sites can make use of the cogeneration

capability. Such deployment avoids significant

grid connection costs.

• In Canada, there are many remote

communities that are not connected to a

national grid currently operating diesel

generators. This is true, also, for many islands

and parts of the developing world where it

would obviate the need to build a national grid.

• In the nuclear industry, U-Batteries could be

always-on emergency generators for large

nuclear power plants.

• Desalination is a further application.

• Deployment at military sites may be attractive

Projected Markets

Page 9: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

International Interest

9

Poland

• Letter of Intent to investigate early deployment at

NCBJ site, near Warsaw

• Potential for Polish, EU structural and Euratom/EIB

funding

US

• Presented at US Nuclear Infrastructure

Conference in Oak Ridge Feb 2016

• Advanced Research Projects Agency – Energy

• NRC has initiated a programme to consider

licensing for non-LWRsJapan

• Interest of JAEA to bring expertise derived from HTTR.

• NDA signed.

Canada

• Ontario Energy Ministry/Natural Resources Canada

study executed by Hatch. In top 9/100. Study

recommended direct engagement.

• Interest in early deployment at Chalk River

UK/URENCO

• URENCO £4m for Phase 1

• Partners “sweat” equity

• Seeking matched funding from Govt.

• DECC SMR TEA and micro-reactor study

• DECC SMR Competition

Page 10: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

Funding

• Phase 1– URENCO £4m

– Partner “sweat equity”

– Matched funding sought from UK Govt.

– Potential new partners and/or from international interest

• Phase 2 and beyond– URENCO to continue assuming that we pass stage-gates

– Partners have the same choice

– Further partners may join

– UK Govt, EU or other international development funding is possible

– Both Rothschild and PWC have indicated that equity and debt funding

will be possible at this stage.

10

Page 11: A Year of Progress June 2016 - U-Battery · A Year of Progress June 2016 URENCO Cammell-Laird AMECFW WSAtkins Laing O’Rourke. 2 What is U-Battery? ... long and successful history

Summary and Conclusion

• Technology is deliverable – Development not Research.

• The market for micro-reactors is there.

• Licensing needs to be target-based, as in UK, Canada etc. NRC has seen a need to

review its processes acknowledging that its current licensing was created for large

LWRs

• Financing is simpler than large reactors because the capital cost is lower and the

construction period is much shorter.

• Much of the competition is with diesel or CCGT so the business model foresees an

organisation that allows customers to buy power - a utility. It foresees an

organisation that will maintain and re-fuel U-Batteries.

• We have a strong team and we are delivering